CompTIA Project+ overview

  • 197 practice questions
  • 32 flashcards
  • 3 study guide topics
  • 38 key terms

What you'll study

  • Project Management Concepts33%
  • Planning and Forecasting33%
  • Executing and Delivering34%

CompTIA Project+ is an entry-level project management credential offered by CompTIA, aimed at professionals who coordinate, support, or lead projects as part of a broader technical or business role. It suits people moving into project work for the first time, team members who need to speak the language of formal project delivery, and IT staff who manage small initiatives alongside their primary responsibilities. Unlike credentialing programs that assume years of documented project leadership, Project+ is positioned as a foundational certificate, which makes it a common starting point before more advanced project management designations.

The exam is structured around three broad areas: project management concepts, including roles, constraints, and lifecycle models; planning and forecasting, covering scope, schedule, cost, and risk baselines; and executing and delivering, which addresses stakeholder communication, quality, change control, and project closure. Questions are delivered in multiple choice format.

Preparation typically combines a structured study guide or instructor-led course, a review of the current published exam objectives, and repeated practice with scenario-based questions that test judgment rather than recall. Because many items are situational, candidates benefit from mapping each practice scenario to a specific domain and process group. Candidates should confirm current item counts, time limits, pricing, and retake rules directly with CompTIA, since those administrative details were not verifiable in the source material reviewed.

Common mistakes

Answering scenario questions from personal workplace experience - picking the action that worked on their own project - instead of the action the exam's framework prescribes.

Experienced practitioners have seen informal shortcuts succeed in small organisations and unconsciously treat those as the 'correct' answer, even when the question describes a formal, governed environment.

What to do instead

Before answering, re-read the stem for governance cues ('according to the project charter', 'the organisation requires', 'the PMO standard'). If a cue exists, eliminate any answer that bypasses that artefact or approval, then choose among what remains. Drill 20 stems where your instinct and the framework diverge, and write down the rule that overrode your instinct.

Collapsing the sponsor, project manager, PMO and team into one role - e.g. picking the project manager as the person who approves the charter, authorises funding, or accepts the final deliverable.

In many real organisations the PM drafts the charter and chases signatures, so the drafting and approving steps blur together in memory. The exam keeps them strictly separate.

What to do instead

Build a one-page role matrix with columns for sponsor, PM, PMO, functional manager and team, and rows for: charter, funding, scope baseline approval, change approval above threshold, deliverable acceptance, templates and standards. Memorise the sponsor/PM/PMO column as 'authorise and fund = sponsor, plan and deliver = PM, standardise and report = PMO', then test it against past-style scenarios.

Treating project, program, portfolio and operations as interchangeable labels, and mislabelling a scenario that describes ongoing work or a group of related projects as a single project.

The words are used loosely in job titles and internal documents, so the distinguishing criteria (temporary vs ongoing, unique output vs repeated service, related vs strategically grouped) never get learned as a decision rule.

What to do instead

Apply a fixed decision order every time: does it end? (no = operations). Is the output unique? Is it one coordinated effort producing one output? (no, but related projects sharing a goal = program). Is it a collection prioritised against strategy and funding? (= portfolio). Say the order out loud on every practice question that uses these terms.

Jumping straight from the scope statement to the schedule, and being unable to distinguish a deliverable, a work package and an activity when a question asks where a task belongs.

Scheduling tools let people create tasks without ever building a WBS, so the decomposition hierarchy is never internalised. Questions that hinge on the level of the WBS look like trivia rather than process.

What to do instead

Memorise the chain deliverable > work package > activity, with the work package as the lowest level the PM controls and estimates at, and the activity as what gets sequenced and assigned. Practise by taking one familiar deliverable and decomposing it three levels deep on paper, then labelling each level.

Confusing contingency reserve, management reserve, cost baseline and project budget - for example saying the cost baseline includes management reserve, or that contingency reserve is held by the sponsor.

The four terms are near-synonyms in everyday speech and most candidates never draw the stack, so they answer by feel on questions that turn on exactly one boundary.

What to do instead

Draw the additive stack once and redraw it from memory each study session: activity cost estimates + contingency reserve (for known-unknowns, controlled by the PM) = cost baseline; cost baseline + management reserve (for unknown-unknowns, controlled by the sponsor) = project budget; budget + profit = price. Then answer reserve questions by asking 'was this risk identified in the register?'

Identifying the critical path by picking the path with the most tasks or the longest-looking chain, and failing to recompute float and the critical path after a stated delay is introduced.

Candidates memorise 'critical path = longest path' but do not connect it to zero float, and under time pressure they skip the recalculation step the question is actually testing.

What to do instead

Always compute forward pass and backward pass on a scratch grid (ES, EF, LS, LF, float) rather than eyeballing, confirm the critical path is the set of tasks with zero float, and check for more than one critical path. When a stem adds a delay, recalculate before reading the options, and remember a delay beyond float changes which path is critical.

Approving or rejecting a change request before assessing its impact, or letting a change be implemented and documented afterwards.

Stakeholders pressure teams to move fast, and the assessment step feels like bureaucracy. Candidates compress the sequence to 'request, approve, do' and pick that compressed option because it sounds efficient.

What to do instead

Memorise the fixed order as a chain and apply it mechanically: log the request, assess impact on scope, schedule, cost, quality and risk, route to the CCB or designated approver, update the baselines and change log, then communicate. On any question where an option approves or performs work before the impact assessment exists, eliminate it first.

Swapping quality assurance and quality control - describing QA as testing and inspecting the product, or QC as auditing and improving the process.

In practice the same team often does both, and the words 'quality' and 'control' carry no hint of the process-versus-product distinction.

What to do instead

Anchor on one sentence: QA is preventive and process-focused (audits, standards, checklists for how work is done); QC is detective and product-focused (inspection, testing, comparing a deliverable to acceptance criteria). On each question, ask 'is the object a process or a product?' and select accordingly.

Mismatching risk response strategies - using 'avoid' when the scenario describes reducing probability or impact, using 'share' for a threat, or applying threat strategies to an opportunity.

The strategy names overlap in plain English (avoid/mitigate both sound like 'prevent'), and candidates learn the threat list only, then guess when an opportunity appears.

What to do instead

Learn the two lists side by side and say them as pairs: threat - avoid, mitigate, transfer, accept, escalate; opportunity - exploit, enhance, share, accept, escalate. Note that 'accept' and 'escalate' are common to both, and that transfer moves financial ownership (insurance, fixed-price contract) without eliminating the risk. Sort ten practice scenarios into the five strategies before reading any options.

Choosing 'escalate to the sponsor', 'update the risk register' or 'document the issue' as the first action on a 'what should the project manager do FIRST' question.

These are safe-sounding answers that are hard to argue with, so they survive elimination by default; candidates never check whether a fact-finding or plan-review step must come before any record-keeping or escalation.

What to do instead

Use a fixed first-action ladder: gather or verify the facts, then check the plan, charter, register or contract, then act within the PM's authority, and only escalate when the decision exceeds that authority. On FIRST/NEXT questions, eliminate any option that records, reports or escalates before the situation has been assessed, then choose the earliest step in the ladder that remains.

Exam requirements can change. Confirm current details with the exam provider.

CompTIA Project+ practice

197 questions. Each one lists the choices, the correct answer, and an explanation. With JavaScript, this list opens one question at a time. The checker at the top of this page saves progress in this browser when it is available.

  1. Question 1Project Management Concepts

    Which characteristic distinguishes a project from ongoing operations?

    1. It repeats on a fixed cycle with no defined end
    2. It follows procedures that never change
    3. It is performed by a standing functional team
    4. It is temporary and produces a unique result Correct answer.

    Explanation

    A project is a temporary endeavor undertaken to create a unique product, service, or result, and it has a defined start and end. Operational work is ongoing and repetitive, sustaining the business after projects deliver the capability. The presence of a defined end date and a unique outcome is the defining distinction.

  2. Question 2Project Management Concepts

    A sponsor demands a shorter schedule without changing scope, budget, or team size. Which project dimension is most likely to suffer?

    1. Scope definition
    2. Quality Correct answer.
    3. Stakeholder register
    4. Communication channels

    Explanation

    Scope, schedule, cost, and quality are interdependent, so a change to one forces a trade-off somewhere else. Compressing the schedule while holding scope, budget, and staffing constant typically reduces quality or increases risk. The project manager should make this trade-off explicit with the sponsor.

  3. Question 3Project Management Concepts

    What is the primary purpose of a project charter?

    1. To archive the records of closed projects
    2. To authorize the project and its manager Correct answer.
    3. To list every task in the detailed schedule
    4. To record daily assignments for each team member

    Explanation

    The charter formally authorizes the existence of the project and gives the project manager authority to apply organizational resources to project activities. It captures high-level scope, objectives, and key stakeholders rather than detailed planning content. Detailed task lists and assignments come later in planning.

  4. Question 4Project Management Concepts

    A work breakdown structure decomposes project work into which of the following?

    1. Calendar dates in chronological order
    2. Accounting cost codes for each department
    3. Smaller, manageable work packages Correct answer.
    4. Individual performance goals for each team member

    Explanation

    The WBS hierarchically decomposes deliverables into progressively smaller components until the lowest level, the work package, can be estimated, scheduled, and assigned. It is deliverable-oriented rather than time-oriented. Cost accounts and schedules are built from the WBS afterward.

  5. Question 5Project Management Concepts

    Who typically provides project funding and approves major changes to a project?

    1. The quality auditor
    2. The Scrum Master
    3. The project sponsor Correct answer.
    4. The project coordinator

    Explanation

    The sponsor is the person or group that funds the project and champions it within the organization. The sponsor authorizes major scope and budget changes and helps resolve issues beyond the project manager's authority. Operational roles such as coordinator or Scrum Master support delivery but do not own funding decisions.

  6. Question 6Project Management Concepts

    When should lessons learned be captured during a project?

    1. Throughout the life cycle and at phase gates Correct answer.
    2. Only during the closing phase
    3. Only after the project has failed
    4. Only when the sponsor formally requests them

    Explanation

    Lessons learned are most valuable when captured continuously, because insights can be applied to the remainder of the same project. Phase gates and retrospectives are natural checkpoints for recording and sharing them. Collecting them only at the end limits their benefit to future work.

  7. Question 7Project Management Concepts

    Which project phase typically includes formal acceptance of deliverables and release of team resources?

    1. Initiating
    2. Closing Correct answer.
    3. Planning
    4. Executing

    Explanation

    Closing covers formal acceptance of the final deliverables, transition of the product to the customer, and release of project resources. It also includes final performance reporting and archiving of project information. Initiating and planning occur well before deliverables are accepted.

  8. Question 8Project Management Concepts

    What is the main role of a project management office (PMO)?

    1. To set project standards and governance Correct answer.
    2. To audit organizational financial statements
    3. To perform the technical work on each project
    4. To replace project managers on each project

    Explanation

    A PMO establishes and supports project management standards, methods, and governance across the organization. Depending on its type, from supportive to controlling, it may also provide templates, coaching, and portfolio oversight. It does not execute the technical work or substitute for assigned project managers.

  9. Question 9Project Management Concepts

    In a weak matrix organization, who typically holds the greatest authority over project resources?

    1. The functional manager Correct answer.
    2. The project coordinator
    3. The PMO analyst
    4. The project manager

    Explanation

    In a weak matrix, the project manager has limited authority and acts more as a coordinator or expediter. Resource decisions, priorities, and staff assignments remain with the functional manager who owns the people. Authority shifts toward the project manager as the organization moves toward a strong matrix or projectized structure.

  10. Question 10Project Management Concepts

    A task on the critical path is delayed by three days. What is the most likely effect on the project?

    1. The project finishes three days early
    2. The project finish date is delayed Correct answer.
    3. Total float on the path grows by three days
    4. The task is removed from the critical path

    Explanation

    Critical path activities have zero total float, so any delay on that path pushes the project completion date out unless the delay is recovered elsewhere. Recovery options include crashing, fast tracking, or re-sequencing remaining critical work. Non-critical paths would absorb the delay within their float.

  11. Question 11Project Management Concepts

    In a RACI matrix, what does the accountable role represent?

    1. The person who performs the work
    2. A person kept informed of progress
    3. The one person ultimately answerable Correct answer.
    4. Anyone consulted for subject matter input

    Explanation

    Accountable means the single person who ultimately answers for the work being completed correctly, and only one person should hold it per activity. Responsible is the role that performs the work, while consulted and informed describe communication relationships. Keeping accountability singular prevents diffusion of ownership.

  12. Question 12Project Management Concepts

    Midway through a project, a stakeholder requests a new feature. What should the project manager do first?

    1. Escalate to the sponsor for a decision
    2. Add the feature to the schedule right away
    3. Submit it to the change control process Correct answer.
    4. Reject the request without further review

    Explanation

    All change requests should enter the established change control process, where impact on scope, schedule, cost, and quality is assessed before a decision. Only after that analysis does the appropriate authority approve or reject the change. Immediate inclusion or outright rejection bypasses the governance the project depends on.

  13. Question 13Project Management Concepts

    Which situation best describes scope creep?

    1. The team delivers a feature ahead of schedule
    2. A formally approved change raises the cost baseline
    3. Unapproved small additions gradually expand the work Correct answer.
    4. The sponsor formally reduces the project scope

    Explanation

    Scope creep is the uncontrolled expansion of project scope through many small, unapproved additions that are never reflected in the baseline. The cumulative effect is missed deadlines and budget overruns without corresponding approvals. Legitimate change goes through integrated change control and updates the baselines.

  14. Question 14Project Management Concepts

    Purchasing insurance against a potential financial loss is an example of which risk response strategy?

    1. Avoidance
    2. Transference Correct answer.
    3. Acceptance
    4. Mitigation

    Explanation

    Transference shifts the financial impact of a threat to a third party, such as an insurer or a fixed-price vendor, without eliminating the risk itself. Avoidance removes the cause of the risk entirely, and mitigation reduces probability or impact. Acceptance simply acknowledges the risk and its consequences.

  15. Question 15Project Management Concepts

    In Scrum, who is responsible for maximizing the value of the product backlog?

    1. The product owner Correct answer.
    2. The development team lead
    3. The Scrum Master
    4. The project sponsor

    Explanation

    The product owner orders the backlog and makes prioritization decisions intended to maximize delivered value. The Scrum Master facilitates the process and removes impediments, while the development team self-organizes the delivery work. Sponsors fund the effort but do not manage backlog content.

  16. Question 16Project Management Concepts

    A Gantt chart primarily displays which of the following?

    1. Risk probability and impact scores
    2. Stakeholder influence mapped against interest
    3. Task durations and overlaps over time Correct answer.
    4. Cost baseline by accounting period

    Explanation

    A Gantt chart is a bar chart that plots scheduled activities against a time axis, making durations, sequencing, and overlaps visible. It helps stakeholders see when work occurs and where parallel activity exists. Cost, stakeholder, and risk information require different tools or charts.

  17. Question 17Project Management Concepts

    A project manager needs to determine who receives which project information and how often. Which document is most appropriate?

    1. Resource calendar
    2. Issue log
    3. Procurement statement of work
    4. Communications management plan Correct answer.

    Explanation

    The communications management plan defines stakeholders' information needs, the format and frequency of distribution, and who is responsible for each communication. It is the planning artifact that guides information flow across the project. Other documents listed serve scheduling, issue tracking, or procurement purposes.

  18. Question 18Project Management Concepts

    Which statement correctly distinguishes a risk from an issue?

    1. Risks are recorded only in the charter
    2. A risk has already happened; an issue may happen later
    3. A risk may happen later; an issue has already happened Correct answer.
    4. Both terms describe the same event

    Explanation

    A risk is an uncertain future event that could affect the project if it occurs, so it is managed proactively. An issue is a problem that has already occurred and requires resolution now. When a risk materializes, it is typically recorded as an issue and handled through issue management.

  19. Question 19Project Management Concepts

    A stakeholder has high influence over decisions and high interest in the project outcome. How should the project manager engage this stakeholder?

    1. Send them routine status reports only
    2. Engage them closely in key decisions Correct answer.
    3. Monitor them with minimal communication
    4. Route all contact through the team

    Explanation

    Stakeholders who are both influential and interested sit in the manage-closely quadrant of a power-interest grid. They need regular, substantive engagement and involvement in significant decisions that affect them. Minimal communication risks their disengagement or late objections.

  20. Question 20Project Management Concepts

    Which activity belongs to quality control rather than quality assurance?

    1. Setting quality standards for the project
    2. Writing the quality management plan
    3. Auditing processes for compliance
    4. Inspecting deliverables to find defects Correct answer.

    Explanation

    Quality control is concerned with monitoring and verifying specific deliverables to identify defects and confirm conformance to requirements. Quality assurance focuses on the processes used to build the product, such as process audits and standards definition. Control looks at outputs; assurance looks at how the work is done.

  21. Question 21Project Management Concepts

    An activity has an early start of day 6, a late start of day 11, and a duration of 4 days. What is its total float and its status?

    1. 5 days; not on the critical path Correct answer.
    2. 11 days; on the critical path
    3. 4 days; not on the critical path
    4. 0 days; on the critical path

    Explanation

    Total float equals late start minus early start, so 11 minus 6 gives 5 days of float. Any activity with a float value greater than zero is not on the critical path, because it can slip without moving the project finish. Critical activities are those whose float equals zero.

  22. Question 22Project Management Concepts

    A project has a budget at completion of 500,000, earned value of 200,000, and actual cost of 250,000. Using EAC = BAC / CPI, what is the estimate at completion?

    1. 625,000 Correct answer.
    2. 800,000
    3. 750,000
    4. 450,000

    Explanation

    The cost performance index is EV divided by AC, or 200,000 / 250,000 = 0.8, indicating the project is earning 80 cents per dollar spent. Dividing BAC by CPI gives 500,000 / 0.8 = 625,000 as the forecast total cost if performance continues. A CPI below 1.0 signals an overrun relative to the budget.

  23. Question 23Project Management Concepts

    A buyer wants the seller to carry most of the cost risk on a well-defined scope. Which contract type fits best?

    1. Cost plus fixed fee
    2. Firm fixed price Correct answer.
    3. Cost plus incentive fee
    4. Time and materials

    Explanation

    A firm fixed price contract sets a total price up front, so the seller absorbs cost overruns and benefits from savings, placing most cost risk on the seller. It works best when requirements are clear and stable enough to price accurately. Cost-reimbursable and time-and-materials arrangements leave more risk with the buyer.

  24. Question 24Project Management Concepts

    Velocity has fallen for three sprints while release scope keeps growing. Which analysis best supports a completion forecast?

    1. Extend each sprint so more work fits in
    2. Add team members to raise velocity
    3. Cancel the release and notify the sponsor
    4. Trend completed points against remaining scope Correct answer.

    Explanation

    Comparing cumulative completed story points with the remaining release scope produces an empirically based projection of the completion date. It uses actual team throughput rather than assumptions and makes the effect of scope growth visible. Changing sprint length or adding people alters the system without providing a forecast.

  25. Question 25Project Management Concepts

    Using the PERT weighted average, what is the expected duration of an activity with an optimistic estimate of 4 days, a most likely estimate of 10 days, and a pessimistic estimate of 22 days?

    1. 10 days
    2. 12 days
    3. 11 days Correct answer.
    4. 13 days

    Explanation

    The PERT weighted average is (optimistic + 4 x most likely + pessimistic) / 6. Substituting gives (4 + 40 + 22) / 6 = 66 / 6 = 11 days. The weighting of four times the most likely value pulls the result toward the realistic estimate while still reflecting uncertainty.

  26. Question 26Project Management Concepts

    Which statement describes a milestone?

    1. A task that consumes most of the project budget
    2. A summary task that groups related work
    3. A resource assigned to multiple activities
    4. A zero-duration point marking a key event Correct answer.

    Explanation

    A milestone is a significant point or event in the project with zero duration. It marks progress or a decision point rather than work that consumes time or resources.

  27. Question 27Project Management Concepts

    Which document breaks project scope into manageable work packages?

    1. Work breakdown structure Correct answer.
    2. Communication plan
    3. Project charter
    4. Risk register

    Explanation

    The work breakdown structure decomposes the total project scope into progressively smaller, manageable components called work packages. It provides the basis for estimating, scheduling, and assigning work.

  28. Question 28Project Management Concepts

    Which statement best describes a project constraint?

    1. A documented belief accepted as true
    2. A limit that restricts the team's options Correct answer.
    3. A change requested by a stakeholder
    4. A known event that may affect the project

    Explanation

    A constraint is a limitation or boundary that restricts the project team's options, such as a fixed budget, deadline, or regulatory requirement. It differs from an assumption, which is accepted as true without proof.

  29. Question 29Project Management Concepts

    Who typically funds the project and provides high-level support for it?

    1. Functional manager
    2. Project coordinator
    3. Scrum master
    4. Project sponsor Correct answer.

    Explanation

    The project sponsor provides funding, champions the project at the executive level, and supports the project manager. This role is distinct from day-to-day coordination, resource ownership, or agile facilitation.

  30. Question 30Project Management Concepts

    Which sequence represents a typical predictive project life cycle?

    1. Planning, initiating, closing, executing, monitoring and controlling
    2. Initiating, executing, planning, closing, monitoring and controlling
    3. Executing, planning, initiating, monitoring and controlling, closing
    4. Initiating, planning, executing, monitoring and controlling, closing Correct answer.

    Explanation

    A predictive life cycle generally begins with initiation, proceeds through planning and execution, uses monitoring and control throughout, and ends with closure. The phases build on one another in a logical sequence.

  31. Question 31Project Management Concepts

    What distinguishes a project from ongoing operations?

    1. A project is temporary and produces a unique result Correct answer.
    2. A project repeats the same process indefinitely
    3. A project has permanent staff
    4. A project has no defined start or end

    Explanation

    A project is temporary and creates a unique product, service, or result. Operations are ongoing and repetitive, with the goal of sustaining the business.

  32. Question 32Project Management Concepts

    Which statement is an example of a project assumption?

    1. Regulatory approval is mandatory before launch
    2. The budget is capped at 200,000
    3. The vendor will deliver hardware in two weeks Correct answer.
    4. The project must finish by 31 December of this year

    Explanation

    An assumption is something accepted as true for planning purposes without full proof, such as expecting a vendor delivery within two weeks. Constraints, by contrast, are imposed limits such as fixed dates, budgets, or mandatory approvals.

  33. Question 33Project Management Concepts

    In a functional organization, who usually has primary authority over project staff?

    1. The project manager
    2. The project sponsor
    3. The PMO director
    4. The functional manager Correct answer.

    Explanation

    In a functional organization, staff report to their functional managers, who control resources and priorities. The project manager typically has limited authority and must coordinate through those managers.

  34. Question 34Project Management Concepts

    What does resource leveling typically do?

    1. Shortens the schedule by adding resources
    2. Resolves overallocation and may extend the schedule Correct answer.
    3. Increases cost by reducing team size
    4. Removes all noncritical activities from the plan

    Explanation

    Resource leveling adjusts activity start and finish dates to resolve resource overallocation or conflicting resource demands. Because it works within resource limits, it can extend the project schedule.

  35. Question 35Project Management Concepts

    Which statement correctly distinguishes fast tracking from crashing?

    1. Fast tracking adds resources; crashing overlaps activities
    2. Fast tracking is only for agile; crashing is only for waterfall
    3. Fast tracking reduces scope; crashing increases budget
    4. Fast tracking overlaps activities; crashing adds resources Correct answer.

    Explanation

    Fast tracking compresses the schedule by performing activities in parallel that would normally be sequential. Crashing compresses the schedule by adding resources, often at increased cost.

  36. Question 36Project Management Concepts

    A project has earned value of 100,000, planned value of 120,000, and actual cost of 80,000. Which statement best describes its performance?

    1. Under budget and ahead of schedule
    2. Over budget and ahead of schedule
    3. Over budget and behind schedule
    4. Under budget and behind schedule Correct answer.

    Explanation

    The cost performance index is earned value divided by actual cost, or 100,000 / 80,000 = 1.25, which indicates spending less than planned for the work completed. The schedule performance index is earned value divided by planned value, or 100,000 / 120,000 = 0.83, which indicates less work completed than planned.

  37. Question 37Project Management Concepts

    What is the main purpose of a project kickoff meeting?

    1. To perform acceptance testing of final deliverables
    2. To close the project and release all team resources
    3. To approve the final project budget and reserves
    4. To align stakeholders on goals, scope, and roles Correct answer.

    Explanation

    A kickoff meeting brings key participants together to build shared understanding of project objectives, scope, roles, and working arrangements. It is a starting alignment activity, not a budget approval, testing, or closure event.

  38. Question 38Project Management Concepts

    Prevention and appraisal costs are best described as which type of quality cost?

    1. Costs of rework and warranty
    2. Costs incurred to avoid defects Correct answer.
    3. Failure costs
    4. Costs that are always sunk

    Explanation

    Prevention and appraisal costs are cost-of-conformance activities intended to avoid defects before and during production. Failure costs, by contrast, arise from internal or external defects after they occur.

  39. Question 39Project Management Concepts

    What is the primary responsibility of a risk owner?

    1. Funding the risk response
    2. Documenting lessons learned at project closure
    3. Approving all change requests
    4. Monitoring the risk and executing the response Correct answer.

    Explanation

    A risk owner is assigned to monitor a specific risk and carry out the agreed response if it is triggered. This keeps accountability clear and improves the effectiveness of risk response actions.

  40. Question 40Project Management Concepts

    Which information is typically found in a stakeholder register?

    1. Stakeholder names, influence, and interest Correct answer.
    2. Contract payment terms and invoices
    3. Detailed task durations and dependencies
    4. Approved budget baseline and reserves

    Explanation

    A stakeholder register identifies stakeholders and records relevant information such as contact details, influence, interest, expectations, and engagement classification. It supports stakeholder analysis and engagement planning.

  41. Question 41Project Management Concepts

    What is the primary purpose of a change control board?

    1. Review and decide on change requests Correct answer.
    2. Write the project charter
    3. Assign daily tasks to team members
    4. Perform technical testing of requested changes

    Explanation

    A change control board reviews proposed changes, assesses their impact, and decides whether to approve, reject, or defer them. It governs changes rather than performing the technical work or managing daily tasks.

  42. Question 42Project Management Concepts

    A buyer has unclear requirements and wants sellers to propose solutions. Which document is most appropriate?

    1. Request for proposal Correct answer.
    2. Purchase order
    3. Non-disclosure agreement
    4. Work performance report

    Explanation

    A request for proposal solicits sellers' proposed solutions when requirements are not fully defined. It allows the buyer to compare approaches and select the best fit.

  43. Question 43Project Management Concepts

    What is the main purpose of a sprint retrospective?

    1. Inspect team process and identify improvements Correct answer.
    2. Estimate the next sprint's backlog items
    3. Prioritize the product backlog
    4. Demonstrate completed work to stakeholders

    Explanation

    The retrospective is an agile ceremony for the team to inspect how it worked and identify process improvements. It focuses on team effectiveness rather than demonstrating product increments or prioritizing work.

  44. Question 44Project Management Concepts

    A project has stable, well-understood requirements and requires extensive regulatory documentation. Which delivery approach is best suited?

    1. Kanban
    2. Extreme programming
    3. Scrum
    4. Predictive waterfall Correct answer.

    Explanation

    Stable requirements and heavy documentation needs favor a predictive approach with sequential phases and formal baselines. Agile approaches are better suited to evolving requirements and frequent incremental delivery.

  45. Question 45Project Management Concepts

    A finish-to-start dependency has a two-day lead. What does this mean?

    1. The predecessor can finish two days after the successor starts
    2. The successor must start exactly when the predecessor finishes
    3. The successor may start two days early Correct answer.
    4. The successor must wait two full days after the predecessor finishes

    Explanation

    A lead allows the successor activity to begin before the predecessor finishes, shortening the dependency relationship by the stated amount. A lag would instead impose a waiting period after the predecessor finishes.

  46. Question 46Project Management Concepts

    Team members are polite but unclear about roles, and conflict emerges over who does what. Which team development stage is this?

    1. Performing
    2. Storming Correct answer.
    3. Forming
    4. Norming

    Explanation

    Storming is characterized by conflict as team members clarify roles, expectations, and working relationships. Forming is initial orientation, norming is agreement on norms, and performing is high-functioning collaboration.

  47. Question 47Project Management Concepts

    Which practice ensures that only approved versions of project documents and deliverables are used?

    1. Cost baseline control
    2. Quality auditing
    3. Scope validation
    4. Configuration management Correct answer.

    Explanation

    Configuration management identifies configuration items, controls changes to them, and ensures that approved versions are used. It prevents confusion caused by outdated or unauthorized versions.

  48. Question 48Project Management Concepts

    A project has eight stakeholders, including the project manager. How many communication channels exist?

    1. 28 Correct answer.
    2. 8
    3. 32
    4. 16

    Explanation

    The number of communication channels is calculated as n(n - 1) / 2, where n is the number of stakeholders. With eight stakeholders, the calculation is 8 x 7 / 2 = 28 channels.

  49. Question 49Project Management Concepts

    Which statement describes a key feature of the critical chain method?

    1. It adds buffers to protect the completion date Correct answer.
    2. It removes all resource dependencies from the network
    3. It replaces milestones with daily stand-up meetings
    4. It schedules every task at its latest start date

    Explanation

    The critical chain method accounts for both task dependencies and resource availability, then adds buffers to protect the project completion date from variability. These buffers absorb delays rather than hiding safety time inside individual tasks.

  50. Question 50Project Management Concepts

    Which description best matches a portfolio?

    1. A temporary endeavor undertaken to create a unique product
    2. A group of related projects managed together to obtain shared benefits
    3. A collection of projects and programs grouped to meet strategic business objectives Correct answer.
    4. A single project split into sequential phases with gate reviews

    Explanation

    A portfolio is the top level of the alignment hierarchy and groups projects, programs, and subsidiary portfolios so the organization can pursue strategic objectives and balance investment. Related projects managed jointly for shared benefits form a program, which is a narrower grouping.

  51. Question 51Project Management Concepts

    Who typically approves the project charter and authorizes funding for the project?

    1. The project coordinator
    2. The project manager
    3. The project sponsor Correct answer.
    4. The PMO analyst

    Explanation

    The sponsor is the senior person who champions the project, provides the financial resources, and issues or approves the charter. The project manager receives authority from that charter rather than granting it, and supporting roles do not control funding.

  52. Question 52Project Management Concepts

    Which principle requires that a work breakdown structure capture all work needed to complete the scope and nothing beyond it?

    1. The rule of seven
    2. The Pareto principle
    3. The 100% rule Correct answer.
    4. The rolling wave rule

    Explanation

    The 100% rule states that the sum of the child elements in a WBS must represent 100 percent of the parent's scope, preventing both missing work and work that is outside scope. It is the primary test of completeness for WBS decomposition.

  53. Question 53Project Management Concepts

    Which statement correctly describes the relationship between quality and grade?

    1. Quality and grade are interchangeable terms in project quality management.
    2. A high grade always means the product satisfies its requirements.
    3. Low grade can be acceptable, but low quality is never acceptable. Correct answer.
    4. Low quality can be acceptable when the grade is high enough.

    Explanation

    Grade is a category or rank based on technical characteristics, while quality is the degree to which requirements are fulfilled. A product may legitimately be a lower grade if that is what was specified, but failing to meet requirements is a quality failure regardless of grade.

  54. Question 54Project Management Concepts

    A project manager gathers raw observations such as hours logged, defects counted, and percentage of work completed. How are these observations classified?

    1. Work performance forecasts
    2. Work performance information
    3. Work performance data Correct answer.
    4. Work performance reports

    Explanation

    Work performance data is the raw output collected during execution before any analysis or contextual comparison. Once that data is analyzed against baselines it becomes work performance information, and when packaged for stakeholders it becomes work performance reports.

  55. Question 55Project Management Concepts

    Which of the following is an enterprise environmental factor rather than an organizational process asset?

    1. A standard project charter template used across the company
    2. The organization's documented procurement policies
    3. Marketplace conditions and current currency exchange rates Correct answer.
    4. A lessons-learned repository maintained by the PMO

    Explanation

    Enterprise environmental factors are conditions outside the project team's control, such as market conditions, exchange rates, culture, and available infrastructure. Organizational process assets are internal policies, templates, procedures, and repositories the team can change and reuse.

  56. Question 56Project Management Concepts

    A developer adds a feature that customers never requested and that does not appear in the requirements. How is this best described?

    1. Scope creep
    2. Gold plating Correct answer.
    3. Progressive elaboration
    4. Scope validation

    Explanation

    Gold plating is the addition of extra functionality that was not requested, typically to please the customer, and it consumes resources without approved value. Scope creep differs because it is uncontrolled change that enters through the customer or stakeholders rather than being volunteered by the team.

  57. Question 57Project Management Concepts

    A problem has already occurred and is currently affecting the project's progress. Where should the project manager record it?

    1. Change log
    2. Risk register
    3. Assumption log
    4. Issue log Correct answer.

    Explanation

    An issue log tracks problems that have already materialized and are being actively managed, including owners and resolution status. Risks are uncertain future events, assumptions are things taken as true for planning, and the change log records change requests.

  58. Question 58Project Management Concepts

    Which artifact sets clear expectations for how team members will communicate and behave with one another?

    1. The team charter Correct answer.
    2. The RACI chart
    3. The staffing management plan
    4. The resource calendar

    Explanation

    A team charter records agreed ground rules, communication norms, decision-making approaches, and behavioral expectations for the team. It is created with the team so members own the rules that govern their interaction.

  59. Question 59Project Management Concepts

    Adapting the project management approach, processes, and tools to fit a project's size, complexity, and constraints is known as what?

    1. Tailoring Correct answer.
    2. Decomposition
    3. Rolling wave planning
    4. Benchmarking

    Explanation

    Tailoring is the deliberate adjustment of processes, methods, and artifacts so the management approach fits the specific project context rather than applying every process uniformly. It is expected on every project and should be documented in the project management plan.

  60. Question 60Project Management Concepts

    What is the main purpose of holding a lessons-learned session at the end of a project phase?

    1. To capture knowledge that can improve future project performance Correct answer.
    2. To update the project schedule baseline with actual dates
    3. To assign accountability for defects found during testing
    4. To obtain formal sign-off on the phase deliverables

    Explanation

    Lessons learned capture what went well and what should change so the organization's knowledge base improves and future projects avoid repeated mistakes. Sessions held at phase ends, not only at closure, let the team apply improvements within the same project.

  61. Question 61Project Management Concepts

    How is management reserve positioned relative to the cost baseline?

    1. It is allocated to individual work packages by the team.
    2. It sits above the cost baseline and is not part of it. Correct answer.
    3. It is included inside the cost baseline as contingency.
    4. It replaces the cost baseline once risks are realized.

    Explanation

    The cost baseline consists of the work package costs plus contingency reserves for identified risks. Management reserve covers unknown-unknown work and is held outside the baseline, so using it normally requires sponsor approval and a baseline change.

  62. Question 62Project Management Concepts

    A project manager places all team members in one physical workspace for the duration of the project. What is this arrangement called?

    1. Colocation Correct answer.
    2. Virtual teaming
    3. Matrix staffing
    4. Sourcing

    Explanation

    Colocation, sometimes called a war room, places team members in the same physical location to strengthen communication, trust, and problem solving. It is a development technique used when face-to-face interaction is valuable and feasible.

  63. Question 63Project Management Concepts

    In a strong matrix organization, how does the project manager's authority typically compare with the functional manager's?

    1. The two share equal authority and the project manager reports to the functional manager.
    2. The project manager has considerable authority over the project and controls the project budget. Correct answer.
    3. The project manager has limited authority and coordinates mainly through functional managers.
    4. The functional manager controls the project budget while the project manager supplies staff.

    Explanation

    A strong matrix gives the project manager significant authority, budget control, and full-time project staff, while functional managers retain control of people and technical standards. This shift of budget and schedule authority is what distinguishes strong from weak or balanced matrices.

  64. Question 64Project Management Concepts

    A project delivers its approved scope on time and within budget, yet the sponsor stops further funding because the expected revenue increase never appeared. Which concept does this best illustrate?

    1. The project failed to realize its intended benefits Correct answer.
    2. The project's lessons learned were not documented
    3. The project scope was not verified against requirements
    4. The project's prevention costs exceeded its appraisal costs

    Explanation

    Delivering scope, schedule, and cost targets addresses output, while benefits realization concerns whether the product produced the intended business outcome. A project can be executed well and still fail to deliver the benefits described in the business case.

  65. Question 65Project Management Concepts

    A project manager evaluating vendor proposals discovers that a close relative owns one of the bidding firms. What is the most appropriate course of action?

    1. Hand the entire vendor evaluation to the relative's own account manager
    2. Score the relative's proposal lower than it deserves to remove any appearance of favoritism
    3. Say nothing so the evaluation stays unbiased and simply score the relative's proposal on merit
    4. Disclose the relationship to the appropriate parties and remove any personal influence over the evaluation Correct answer.

    Explanation

    Professional conduct requires disclosing real or apparent conflicts of interest and stepping away from decisions where personal interest could bias judgment. Transparency protects both the integrity of the selection and the project manager's credibility.

  66. Question 66Project Management Concepts

    A project manager plans the work for the upcoming phase in fine detail, while later phases are documented only at a high level and will be broken down further as each one approaches. Which technique is being applied?

    1. Rolling wave planning Correct answer.
    2. Decomposition of the work breakdown structure
    3. Fast tracking of the schedule
    4. Configuration management of deliverables

    Explanation

    Rolling wave planning is an iterative planning technique in which work close to being performed is planned in detail while work farther out is planned at a coarse level, then elaborated as more information becomes available. It is a practical expression of progressive elaboration and is common on projects with uncertain future scope.

  67. Question 67Planning and Forecasting

    A project manager is decomposing the project scope into a work breakdown structure. What is the lowest level of the WBS called?

    1. A milestone
    2. A control account
    3. A work package Correct answer.
    4. A deliverable

    Explanation

    Decomposition continues until the work is small enough to estimate, schedule, and assign to one owner; that lowest element is the work package. Control accounts sit above work packages, and milestones are schedule events rather than WBS components.

  68. Question 68Planning and Forecasting

    Which estimating technique uses the actual cost of a similar past project to estimate the current project and is typically used when detailed information is limited?

    1. Parametric estimating
    2. Bottom-up estimating
    3. Three-point estimating
    4. Analogous estimating Correct answer.

    Explanation

    Analogous estimating compares the current project with a similar completed one and adjusts for known differences, making it fast but less accurate. It is most useful early, when detailed data are unavailable.

  69. Question 69Planning and Forecasting

    Which characteristic describes a milestone in a project schedule?

    1. It has zero duration and marks a significant point Correct answer.
    2. It has a duration equal to its predecessor
    3. It requires dedicated resources
    4. It represents the longest path in the network

    Explanation

    A milestone is a significant point or event in the schedule and therefore consumes no time or resources. It is used to flag checkpoints such as approvals or phase completions.

  70. Question 70Planning and Forecasting

    Which tool displays scheduled activities as horizontal bars against a calendar timeline?

    1. Responsibility assignment matrix
    2. Resource histogram
    3. Precedence diagram
    4. Gantt chart Correct answer.

    Explanation

    A Gantt chart plots activities as bars positioned along a calendar axis, so durations and overlaps are easy to see. Precedence diagrams instead show activities as nodes connected by dependency arrows.

  71. Question 71Planning and Forecasting

    Total float is best defined as:

    1. The time between a milestone and the activity that follows it
    2. The amount of time an activity can be delayed without delaying the early start of its successor
    3. The difference between the optimistic and pessimistic duration estimates
    4. The amount of time an activity can be delayed without delaying the project finish date Correct answer.

    Explanation

    Total float measures schedule slack along a path up to the project completion date. Activities with zero total float lie on the critical path.

  72. Question 72Planning and Forecasting

    Which reserve is held by senior management for unforeseen work outside the approved scope and is not included in the cost baseline?

    1. Funding reserve
    2. Management reserve Correct answer.
    3. Quality reserve
    4. Contingency reserve

    Explanation

    Management reserve covers unknown-unknowns and is controlled above the project manager, so it sits outside the cost baseline. Contingency reserve addresses identified risks and is part of the baseline.

  73. Question 73Planning and Forecasting

    Using three-point estimating, what is the weighted (PERT) expected duration when the optimistic estimate is 4 days, the most likely is 6 days, and the pessimistic is 14 days?

    1. 7 days Correct answer.
    2. 9 days
    3. 8 days
    4. 6 days

    Explanation

    The PERT weighted average is (Optimistic + 4 x Most Likely + Pessimistic) / 6, which here is (4 + 24 + 14) / 6 = 7 days. Weighting the most likely value four times pulls the result toward the realistic case.

  74. Question 74Planning and Forecasting

    Progressive elaboration in which near-term work is planned in detail while later work is planned at a high level is called:

    1. Fast tracking
    2. Rolling wave planning Correct answer.
    3. Scope verification
    4. Decomposition

    Explanation

    Rolling wave planning defers detailed planning of future work until more information is available, while the imminent work is planned thoroughly. It is a form of progressive elaboration suited to uncertain or long projects.

  75. Question 75Planning and Forecasting

    A project network contains three paths from start to finish with durations of 9 weeks, 14 weeks, and 11 weeks. What is the total float on the 11-week path?

    1. 5 weeks
    2. 3 weeks Correct answer.
    3. 0 weeks
    4. 2 weeks

    Explanation

    The longest path, 14 weeks, is the critical path and sets the project duration. A non-critical path's float equals the critical duration minus its own duration, so 14 - 11 = 3 weeks.

  76. Question 76Planning and Forecasting

    Activity B may begin 3 days before Activity A finishes. Which dependency relationship describes this?

    1. Finish-to-start with a lead of 3 days Correct answer.
    2. Start-to-start with a lag of 3 days
    3. Finish-to-finish with a lead of 3 days
    4. Finish-to-start with a lag of 3 days

    Explanation

    A finish-to-start relationship with a lead allows the successor to start before the predecessor finishes. A lag, by contrast, inserts waiting time between the predecessor's finish and the successor's start.

  77. Question 77Planning and Forecasting

    Two activities on the critical path can each be crashed. Activity X costs $2,000 per day of schedule saved; Activity Y costs $5,000 per day of schedule saved. Each can be shortened by up to 2 days. Which is the better choice to shorten the schedule by one day?

    1. Either activity, because both are on the critical path
    2. Activity X, because it shortens the schedule at the lower cost per day Correct answer.
    3. Activity Y, because it has the larger crash cost
    4. Neither activity, because crashing never shortens a schedule

    Explanation

    Crashing adds cost to buy schedule time, so the most economical option is to crash critical-path activities with the lowest cost per unit of time saved. Activity X delivers the same one-day gain for less money.

  78. Question 78Planning and Forecasting

    Bottom-up estimating is most appropriate when:

    1. Detailed WBS information is available and high accuracy is required Correct answer.
    2. A quick order-of-magnitude figure is needed for a business case
    3. The scope is undefined and expected to change frequently
    4. Historical data from a similar project is the only input available

    Explanation

    Bottom-up estimating builds the total from detailed estimates for each work package, so it needs a mature WBS and yields high accuracy at the cost of time. It is poorly suited to early phases when scope is still vague.

  79. Question 79Planning and Forecasting

    The cost baseline for a project is normally composed of:

    1. Work package cost estimates plus management reserves
    2. Contingency reserves plus management reserves
    3. Work package cost estimates plus contingency reserves Correct answer.
    4. Management reserves plus profit margin

    Explanation

    The cost baseline is the time-phased budget used to measure performance and includes approved work package estimates plus contingency for identified risks. Management reserve is added only to form the total project budget, not the baseline.

  80. Question 80Planning and Forecasting

    A project has BAC = $200,000, EV = $80,000, and AC = $100,000. Assuming the current cost performance continues, what is the estimate to complete (ETC)?

    1. $250,000
    2. $120,000
    3. $150,000 Correct answer.
    4. $100,000

    Explanation

    CPI is EV / AC = 0.8, so EAC = BAC / CPI = $250,000. ETC is the remaining cost, EAC - AC = $150,000.

  81. Question 81Planning and Forecasting

    Which statement best describes resource leveling?

    1. It may extend the schedule because it resolves resource over-allocation Correct answer.
    2. It smooths resource usage without changing the project finish date
    3. It reduces the number of communication channels on the project
    4. It is applied only when resources are effectively unlimited

    Explanation

    Resource leveling resolves over-allocation, often by delaying activities, which can push out the critical path and finish date. Resource smoothing instead adjusts usage within existing float without moving the completion date.

  82. Question 82Planning and Forecasting

    A fixed-price contract is most suitable when:

    1. Payment is based on hours worked at an agreed rate
    2. Scope is poorly defined and likely to change
    3. Scope is well defined and requirements are stable Correct answer.
    4. The buyer will reimburse the seller for all allowable costs

    Explanation

    A fixed-price contract places cost risk on the seller, who must estimate the work accurately to protect its margin. That arrangement works only when requirements are stable enough for a firm price to be set.

  83. Question 83Planning and Forecasting

    A project spends $10,000 on training aimed at preventing defects. In cost-of-quality terms, this spending is classified as:

    1. Appraisal cost
    2. Internal failure cost
    3. External failure cost
    4. Prevention cost Correct answer.

    Explanation

    Prevention costs are investments made to keep defects from occurring, such as training, process design, and quality planning. Appraisal and failure costs address detection and correction rather than avoidance.

  84. Question 84Planning and Forecasting

    A risk has a 30% probability of occurring and would cost $50,000 if it does occur. What is its expected monetary value?

    1. $15,000 Correct answer.
    2. $35,000
    3. $20,000
    4. $50,000

    Explanation

    Expected monetary value is the probability multiplied by the financial impact, here 0.30 x $50,000 = $15,000. The figure is used to size contingency reserves and compare risks.

  85. Question 85Planning and Forecasting

    A project has 10 stakeholders who all need to communicate with one another. How many communication channels exist?

    1. 45 Correct answer.
    2. 10
    3. 20
    4. 90

    Explanation

    The number of channels is n(n - 1) / 2, where n is the number of stakeholders. For 10 people that is (10 x 9) / 2 = 45 channels.

  86. Question 86Planning and Forecasting

    A make-or-buy analysis is performed primarily to:

    1. Determine whether work should be performed internally or purchased Correct answer.
    2. Establish the project's communication channels
    3. Select the winning bidder
    4. Calculate the cost baseline

    Explanation

    Make-or-buy analysis compares the cost and capability of performing work in-house against acquiring it externally, sometimes including indirect costs and capacity constraints. The result feeds the procurement decisions in the plan.

  87. Question 87Planning and Forecasting

    Activity D has an early finish of day 15, its successor has an early start of day 18, and Activity D has a late finish of day 25. What is the free float of Activity D?

    1. 0 days
    2. 10 days
    3. 3 days Correct answer.
    4. 7 days

    Explanation

    Free float is the successor's early start minus the activity's early finish, so 18 - 15 = 3 days. Total float, by contrast, would be the late finish minus the early finish, which is 10 days.

  88. Question 88Planning and Forecasting

    A project has BAC = $400,000, EV = $200,000, and AC = $250,000. What is the to-complete performance index (TCPI) for finishing within the approved budget?

    1. 0.75
    2. 1.33 Correct answer.
    3. 2.00
    4. 1.25

    Explanation

    TCPI against BAC is (BAC - EV) / (BAC - AC), which here is $200,000 / $150,000 = 1.33. A value above 1.0 signals that remaining work must be performed more efficiently than planned.

  89. Question 89Planning and Forecasting

    In critical chain project management, the purpose of the project buffer is to:

    1. Absorb delays on non-critical feeding paths
    2. Protect the project completion date from delays on the critical chain Correct answer.
    3. Provide slack for activities performed by vendors
    4. Replace the cost contingency reserve in the baseline

    Explanation

    The project buffer is placed at the end of the critical chain and aggregates the safety removed from individual tasks, shielding the delivery date from accumulated variation. Buffers placed where feeding paths join the chain are feeding buffers.

  90. Question 90Planning and Forecasting

    A project has a base cost estimate of $80,000, identified risks with a total expected monetary value of $6,000, and a $10,000 management reserve set aside by senior management. What is the cost baseline?

    1. $86,000 Correct answer.
    2. $80,000
    3. $90,000
    4. $96,000

    Explanation

    The cost baseline includes the work estimates plus contingency for identified risks, so $80,000 + $6,000 = $86,000. Management reserve is added on top of the baseline to give the total project budget, not the baseline itself.

  91. Question 91Planning and Forecasting

    A project has BAC = $300,000, EV = $120,000, and AC = $150,000. If all remaining work is expected to be performed at the budgeted rate, what is the estimate at completion (EAC)?

    1. $300,000
    2. $360,000
    3. $330,000 Correct answer.
    4. $375,000

    Explanation

    When future work proceeds at the planned rate, EAC is AC plus the remaining budget: $150,000 + ($300,000 - $120,000) = $330,000. This forecast assumes the variance observed so far will not continue.

  92. Question 92Planning and Forecasting

    At what level of a work breakdown structure is work typically estimated, scheduled, and controlled?

    1. Planning package
    2. Control account
    3. Project phase
    4. Work package Correct answer.

    Explanation

    The work package is the lowest level of the WBS and is the point at which work can be reliably estimated, scheduled, and controlled. Higher levels aggregate multiple work packages for management reporting.

  93. Question 93Planning and Forecasting

    Which schedule component represents a significant point or event and has zero duration?

    1. Summary task
    2. Milestone Correct answer.
    3. Lag
    4. Hammock activity

    Explanation

    A milestone marks a significant point or event and has no duration. It is used to track progress and key decision points on the schedule.

  94. Question 94Planning and Forecasting

    In a RACI chart, which role is assigned to the person who ultimately answers for the work being completed?

    1. Accountable Correct answer.
    2. Responsible
    3. Consulted
    4. Informed

    Explanation

    The accountable person owns the outcome and answers for the work, although the responsible person performs it. Only one person is typically accountable for each activity.

  95. Question 95Planning and Forecasting

    Which estimating technique uses duration or cost data from a previous, similar project as the basis for a new estimate?

    1. Three-point estimating
    2. Analogous estimating Correct answer.
    3. Bottom-up estimating
    4. Parametric estimating

    Explanation

    Analogous estimating uses historical data from a comparable project and is often used when detailed information is limited. It is generally less accurate than more detailed techniques.

  96. Question 96Planning and Forecasting

    What is the schedule baseline?

    1. The original schedule before any changes, which is never updated
    2. The approved version of the schedule used to compare performance Correct answer.
    3. The current schedule after any approved changes
    4. The list of all activities before sequencing

    Explanation

    The schedule baseline is the approved version of the schedule model against which actual progress is compared. It can be changed only through formal change control.

  97. Question 97Planning and Forecasting

    A bar chart that shows activity start and finish dates along a calendar timeline is called a:

    1. Gantt chart Correct answer.
    2. Network diagram
    3. Resource histogram
    4. Precedence diagram

    Explanation

    A Gantt chart displays activities as bars against a calendar timeline, making start and finish dates easy to see. It may also show dependencies and progress.

  98. Question 98Planning and Forecasting

    A regulatory agency mandates that the project finish before a fixed date. This is best classified as a:

    1. Risk
    2. Assumption
    3. Constraint Correct answer.
    4. Dependency

    Explanation

    A constraint is a limitation or restriction that affects project execution, such as a fixed completion date. The mandated date must be planned around because it is not optional.

  99. Question 99Planning and Forecasting

    A project manager overlaps two normally sequential activities to shorten the schedule. What technique is being used, and what is the main risk?

    1. Fast tracking; it increases the risk of rework Correct answer.
    2. Resource leveling; it may extend the schedule
    3. Lead time; it eliminates the dependency between the activities
    4. Crashing; it increases cost by adding resources

    Explanation

    Fast tracking compresses the schedule by performing activities in parallel that would normally be sequential. This increases the risk of rework and coordination problems because later work may start before earlier work is complete.

  100. Question 100Planning and Forecasting

    Estimating the cost of a building at a fixed dollar amount per square meter is an example of:

    1. Bottom-up estimating
    2. Parametric estimating Correct answer.
    3. Expert judgment
    4. Analogous estimating

    Explanation

    Parametric estimating uses a statistical relationship between historical data and a measurable variable, such as cost per square meter. It can be highly accurate when the underlying data are reliable.

  101. Question 101Planning and Forecasting

    Which technique builds expert consensus through several rounds of anonymous questionnaires?

    1. Nominal group technique
    2. Brainstorming
    3. Delphi technique Correct answer.
    4. Focus group

    Explanation

    The Delphi technique collects expert opinions anonymously over multiple rounds, allowing participants to refine their views without being influenced by dominant personalities. It is useful when expert input is needed but direct discussion is impractical.

  102. Question 102Planning and Forecasting

    A project manager needs to reduce peak resource demand but must not change the project finish date. Which technique should be used?

    1. Fast tracking
    2. Resource smoothing Correct answer.
    3. Crashing
    4. Resource leveling

    Explanation

    Resource smoothing adjusts activities within their available float to even out resource demand without changing the critical path or finish date. Resource leveling, by contrast, can extend the schedule when resources are constrained.

  103. Question 103Planning and Forecasting

    A project has EV = $40,000 and PV = $50,000. What does the schedule performance index indicate?

    1. SPI = 1.25, so the project is ahead of schedule.
    2. SPI = 0.80, so the project is behind schedule. Correct answer.
    3. SPI = 0.80, so the project is over budget.
    4. SPI = 1.25, so the project is under budget.

    Explanation

    The schedule performance index is EV divided by PV, so SPI = 40,000 / 50,000 = 0.80. An SPI below 1.0 means less work was completed than planned, so the project is behind schedule.

  104. Question 104Planning and Forecasting

    A project has BAC = $150,000 and an EAC of $170,000. What is the variance at completion?

    1. -$20,000 overrun Correct answer.
    2. $320,000 unfavorable
    3. $170,000 favorable
    4. $20,000 favorable

    Explanation

    Variance at completion is BAC minus EAC, so $150,000 - $170,000 = -$20,000. A negative VAC indicates that the project is forecast to exceed its approved budget.

  105. Question 105Planning and Forecasting

    Rolling up the estimated costs of individual work packages to higher WBS levels to produce a total project cost is called:

    1. Cost baseline
    2. Reserve analysis
    3. Funding limit reconciliation
    4. Cost aggregation Correct answer.

    Explanation

    Cost aggregation sums work-package estimates up through the WBS to produce higher-level and total project cost estimates. The resulting total is then used to develop the cost baseline and funding requirements.

  106. Question 106Planning and Forecasting

    A project team identifies a known risk with an expected monetary value of $8,000. Where should this amount normally be held?

    1. Contingency reserve Correct answer.
    2. Profit margin
    3. Management reserve
    4. Activity cost estimate

    Explanation

    A contingency reserve covers known risks that have been identified and analyzed, such as a risk with an expected monetary value. It is part of the project budget but not necessarily part of the cost baseline, depending on organizational policy.

  107. Question 107Planning and Forecasting

    Which document links each requirement to its source, owner, and the deliverable that satisfies it?

    1. Traceability matrix Correct answer.
    2. Scope statement
    3. Work breakdown structure
    4. Stakeholder register

    Explanation

    A requirements traceability matrix records each requirement and links it to its origin, owner, and the deliverable or test that verifies it. This helps ensure requirements are not lost or overlooked.

  108. Question 108Planning and Forecasting

    Which technique repeatedly simulates project outcomes using random values for uncertain activity durations?

    1. Sensitivity analysis
    2. Decision tree analysis
    3. Expected monetary value analysis
    4. Monte Carlo simulation Correct answer.

    Explanation

    Monte Carlo simulation runs many iterations with randomly generated values for uncertain variables, producing a distribution of possible project outcomes. It is commonly used for schedule and cost risk analysis.

  109. Question 109Planning and Forecasting

    A buyer knows the required outcome but not the detailed solution and wants vendors to propose approaches. Which document is most appropriate?

    1. Purchase order
    2. Request for proposal Correct answer.
    3. Request for quotation
    4. Invitation for bid

    Explanation

    A request for proposal asks vendors to propose a solution and approach when the buyer knows the outcome but not the detailed method. It allows evaluation of technical approach as well as price.

  110. Question 110Planning and Forecasting

    A project manager is deciding who needs which information and how often it should be delivered. Which activity is being performed?

    1. Organizational process asset review
    2. Stakeholder engagement planning and monitoring
    3. Communication requirements analysis Correct answer.
    4. Performance reporting and distribution

    Explanation

    Communication requirements analysis determines the information needs of stakeholders, including content, format, and frequency. Its results feed the communication management plan.

  111. Question 111Planning and Forecasting

    A team plots the effect of each identified risk on the project objective as horizontal bars ordered from largest to smallest. What is this display called?

    1. Fishbone diagram
    2. Decision tree
    3. Tornado diagram Correct answer.
    4. Probability-impact matrix

    Explanation

    A tornado diagram is a type of sensitivity analysis that displays risks as horizontal bars ordered by their impact on an objective. It helps identify which risks warrant the most attention.

  112. Question 112Planning and Forecasting

    A production process requires 100 hours for the first unit, and each doubling of output reduces unit labor hours by 20%. What is the estimated labor for the fourth unit?

    1. 72 hours
    2. 60 hours
    3. 80 hours
    4. 64 hours Correct answer.

    Explanation

    A 20% reduction per doubling corresponds to an 80% learning curve. The second unit takes 80 hours, and the fourth unit takes 80% of that, or 64 hours.

  113. Question 113Planning and Forecasting

    The approved project budget is $500,000, but organizational funding is limited to $100,000 per quarter. The project manager adjusts the expenditure plan to match these limits. This is an example of:

    1. Reserve analysis for known risks
    2. Funding limit reconciliation Correct answer.
    3. Cost aggregation across work packages
    4. Value engineering of deliverables

    Explanation

    Funding limit reconciliation compares planned expenditures with funding limits and adjusts the schedule or spending plan so the project does not exceed available funding. It can affect the timing of work even when total budget is sufficient.

  114. Question 114Planning and Forecasting

    A buyer uses a time-and-materials contract for work with an uncertain scope. Which risk is most characteristic of this contract type?

    1. The buyer bears the risk of cost growth. Correct answer.
    2. The seller bears all cost risk for overruns.
    3. The buyer has no ability to direct the work.
    4. The price is fixed before work begins.

    Explanation

    In a time-and-materials contract, the buyer pays for actual hours plus materials, so cost growth from additional hours falls largely on the buyer. This type is often used when scope is uncertain, but it requires active monitoring.

  115. Question 115Planning and Forecasting

    A project can choose between two risk responses. Response A costs $10,000 and has a 40% chance of a $50,000 loss. Response B costs $20,000 and has a 10% chance of a $50,000 loss. Based on expected monetary value, which response is preferred?

    1. Response A, with an expected cost of $30,000
    2. Response B, with an expected cost of $25,000 Correct answer.
    3. Response B, with an expected cost of $20,000
    4. Response A, with an expected cost of $10,000

    Explanation

    Expected cost combines the response cost with the probability-weighted loss. Response A is $10,000 + (0.40 × $50,000) = $30,000, while Response B is $20,000 + (0.10 × $50,000) = $25,000, so Response B has the lower expected cost.

  116. Question 116Planning and Forecasting

    In a work breakdown structure, the lowest level of decomposition, at which work can be reliably estimated, scheduled, and controlled, is called a:

    1. Planning package
    2. Control account
    3. Work package Correct answer.
    4. Deliverable

    Explanation

    Decomposition stops at the work package, the smallest WBS element that can be estimated and managed as a unit. Higher aggregation points, such as control accounts, group work packages for management reporting.

  117. Question 117Planning and Forecasting

    Which three components together make up the scope baseline?

    1. Scope statement, WBS, and WBS dictionary Correct answer.
    2. WBS, WBS dictionary, and schedule baseline
    3. Requirements documentation, scope statement, and WBS
    4. Scope management plan, WBS, and requirements traceability matrix

    Explanation

    The scope baseline is the approved version of the scope statement plus its associated WBS and WBS dictionary. It is the reference used to judge scope performance and to evaluate change requests.

  118. Question 118Planning and Forecasting

    The critical path in a project schedule network is best described as:

    1. the longest path, which sets the shortest project duration Correct answer.
    2. the path the sponsor designates as highest priority
    3. the path with the lowest total estimated cost
    4. the path containing the most activities in the network

    Explanation

    The critical path is the longest total duration path through the network, so it determines the shortest possible project duration. Activities on it have zero or negative total float, and any delay to them delays the project finish.

  119. Question 119Planning and Forecasting

    A project manager estimates the cost of a new software module by comparing it to a similar module completed on a previous project. Which estimating technique is being used?

    1. Analogous estimating Correct answer.
    2. Parametric estimating
    3. Bottom-up estimating
    4. Three-point estimating

    Explanation

    Analogous estimating uses the actual cost or duration of a similar past activity or project as the basis for the new estimate. It is fast but least accurate, and it depends on genuine similarity between the items.

  120. Question 120Planning and Forecasting

    During planning, a team records that the hardware will arrive within three weeks based on a vendor's verbal promise. Where should this be documented?

    1. In the assumption log Correct answer.
    2. In the quality management plan
    3. In the project charter's budget section
    4. In the issue log

    Explanation

    An assumption log records planning assumptions and their potential impact so they can be validated and, where uncertain, analyzed as risks. Documented assumptions help the team revisit beliefs that later prove false.

  121. Question 121Planning and Forecasting

    Activity B can begin five days after Activity A starts, because the first portion of A's output is enough to start B. Which relationship and modifier describes this?

    1. Finish-to-finish with a lead of five days
    2. Start-to-start with a lag of five days Correct answer.
    3. Finish-to-start with a lag of five days
    4. Start-to-finish with a lead of five days

    Explanation

    Start-to-start means the successor can begin relative to the start of the predecessor, and a lag adds waiting time after that point. Here B starts five days after A starts, which is SS plus a five-day lag.

  122. Question 122Planning and Forecasting

    An activity has an optimistic estimate of 6 days, a most likely estimate of 9 days, and a pessimistic estimate of 18 days. Using the weighted three-point (PERT) formula, what is the expected duration?

    1. 11 days
    2. 12 days
    3. 9 days
    4. 10 days Correct answer.

    Explanation

    The weighted formula is (Optimistic + 4 x Most likely + Pessimistic) / 6, which here is (6 + 36 + 18) / 6 = 10 days. Weighting the most likely value four times pulls the result toward the realistic case.

  123. Question 123Planning and Forecasting

    The approved cost baseline for a project is $400,000, and the sponsor sets aside an additional $30,000 for unplanned scope changes. What is the total authorized project budget?

    1. $370,000
    2. $400,000
    3. $430,000 Correct answer.
    4. $30,000

    Explanation

    The project budget equals the cost baseline plus management reserve held for unplanned scope changes. Here $400,000 of approved work plus $30,000 of management reserve gives $430,000.

  124. Question 124Planning and Forecasting

    Which set of baselines forms the performance measurement baseline used for earned value analysis?

    1. Cost, procurement, and risk baselines
    2. Scope, schedule, and cost baselines Correct answer.
    3. Schedule, communications, and stakeholder baselines
    4. Scope, quality, and resource baselines

    Explanation

    The performance measurement baseline integrates the approved scope, schedule, and cost baselines so actual performance can be compared against a single reference. Management reserve is excluded from this baseline.

  125. Question 125Planning and Forecasting

    A company can make a component internally for $80,000 in setup plus $20 per unit, or buy it for $50 per unit. The project needs 2,000 units. What does the make-or-buy analysis show?

    1. Buy, saving $20,000 Correct answer.
    2. Make, saving $20,000
    3. Make, saving $40,000
    4. Buy, saving $40,000

    Explanation

    Making costs $80,000 + (2,000 x $20) = $120,000, while buying costs 2,000 x $50 = $100,000. Buying is therefore $20,000 cheaper for this quantity, although non-cost factors should also be weighed.

  126. Question 126Planning and Forecasting

    A project has a clearly defined first phase but only high-level deliverables for work scheduled a year later. Which planning approach is most appropriate?

    1. Deferring all planning until the later phase starts
    2. Replacing the WBS with a high-level milestone list
    3. Progressively elaborating the WBS as more information becomes available Correct answer.
    4. Decomposing the entire WBS to work packages before work begins

    Explanation

    Rolling wave planning elaborates near-term work in detail while leaving far-term work at a higher level until more information exists. Planning packages are later decomposed into work packages as the work approaches.

  127. Question 127Planning and Forecasting

    A RACI chart shows three different people marked "A" for the same task. What is the problem with this assignment?

    1. Only one person should be accountable for each task Correct answer.
    2. The "A" designation should be replaced by "R" in every case
    3. Multiple "A" entries guarantee the task is overstaffed
    4. The chart must designate at least one "C" for every task

    Explanation

    Accountability cannot be shared, so each task should have exactly one accountable person even if several people are responsible for doing the work. Multiple accountable parties create confusion about who makes the final decision.

  128. Question 128Planning and Forecasting

    A team determines that adding a design review costing $10,000 will likely eliminate rework estimated at $60,000. The design review is best classified as which type of quality cost?

    1. Prevention cost Correct answer.
    2. External failure cost
    3. Internal failure cost
    4. Appraisal cost

    Explanation

    Prevention costs are incurred to keep defects from occurring in the first place, and design reviews are a classic example. Spending on prevention is usually cheaper than paying for rework or field failures later.

  129. Question 129Planning and Forecasting

    A network has two paths from start to finish. Path 1 is Activity A (4 days) followed by Activity B (6 days). Path 2 is Activity A (4 days), then Activity C (3 days), then Activity D (5 days). What is the total float of Activity B?

    1. 6 days
    2. 2 days Correct answer.
    3. 0 days
    4. 5 days

    Explanation

    Path 1 has a total duration of 10 days and Path 2 has a total duration of 12 days, so Path 2 is critical. Activity B sits only on the 10-day path, giving it a total float of 12 - 10 = 2 days.

  130. Question 130Planning and Forecasting

    A project is three days behind schedule. Activity X, on the critical path, can be crashed up to 2 days at $600 per day. Activity Y, on the critical path, can be crashed 1 day at $450. Activity Z, on the critical path, can be crashed up to 3 days at $900 per day. What is the lowest additional cost to recover three days?

    1. $1,350
    2. $2,700
    3. $1,650 Correct answer.
    4. $1,800

    Explanation

    Crash the cheapest days first: one day of Y at $450 plus two days of X at $1,200 totals $1,650. Using the lowest crash cost per day for each required day minimizes the total compression cost.

  131. Question 131Planning and Forecasting

    Which statement distinguishes the critical chain method from the critical path method?

    1. It accounts for resource availability and aggregates safety into buffers Correct answer.
    2. It requires every activity to be estimated at its most likely duration
    3. It removes all buffers to shorten the reported schedule
    4. It ignores resource availability and relies only on logical dependencies

    Explanation

    The critical chain method builds the network using both dependency and resource constraints, then pools individual activity safety into project and feeding buffers. This differs from the critical path method, which considers only logical dependencies and durations.

  132. Question 132Executing and Delivering

    A project manager is preparing to move a project into the execution phase. What is the primary purpose of holding a project kickoff meeting?

    1. To baseline the schedule and cost so variances can be tracked
    2. To align team and stakeholders on goals, scope, and roles Correct answer.
    3. To archive the planning documents before execution starts
    4. To obtain the sponsor's formal signature on the project charter

    Explanation

    The kickoff brings the performing team and key stakeholders together at the start of execution so everyone shares a common understanding of objectives, scope boundaries, and who does what. Charter approval and baselining are completed earlier, during initiating and planning.

  133. Question 133Executing and Delivering

    In a RACI chart, what does the 'A' designation signify for an activity?

    1. Must be consulted before the work begins
    2. Is kept informed of task progress
    3. Is ultimately answerable for the outcome Correct answer.
    4. Performs the work on the task

    Explanation

    RACI stands for Responsible, Accountable, Consulted, and Informed. The accountable person owns the outcome and is the single point of approval, while the responsible party does the work.

  134. Question 134Executing and Delivering

    During execution, a developer reports that a required test server was never provisioned, which is now blocking testing. Where should the project manager record this?

    1. In the risk register, because it may affect the schedule
    2. In the change log, because it alters a project baseline
    3. In the lessons learned register, for future reference
    4. In the issue log, because it is already occurring Correct answer.

    Explanation

    An issue log tracks problems that have already happened and are actively affecting the project, along with owners and resolution status. The risk register is reserved for uncertain future events that have not yet occurred.

  135. Question 135Executing and Delivering

    A newly formed team begins arguing about task ownership and openly challenges the project manager's authority. Which stage of team development is this?

    1. Storming Correct answer.
    2. Performing
    3. Forming
    4. Norming

    Explanation

    In the storming stage, team members test boundaries, compete for roles, and may resist direction from the project manager. The project manager typically responds with clear ground rules and facilitated conflict resolution.

  136. Question 136Executing and Delivering

    When should lessons learned be captured on a project?

    1. Only during the project closeout phase
    2. Continuously throughout the project Correct answer.
    3. Only when a change request is approved
    4. Only after a risk response is triggered

    Explanation

    Lessons learned are most valuable when captured as events happen and reviewed at phase gates, so the knowledge can still influence the current project. Capturing them only at closure limits their usefulness to the team that generated them.

  137. Question 137Executing and Delivering

    A project manager wants to set expectations for meeting attendance, decision making, and how disagreements will be handled. Which document is most appropriate?

    1. The stakeholder engagement plan
    2. The team charter Correct answer.
    3. The resource management plan
    4. The communications management plan

    Explanation

    The team charter records ground rules, behavioral norms, and working agreements that the team commits to. Plans such as the communications or resource management plan describe organizational approaches rather than team behavioral commitments.

  138. Question 138Executing and Delivering

    Which activity is an example of quality control during execution?

    1. Training the team on the quality policy
    2. Inspecting deliverables against acceptance criteria Correct answer.
    3. Reviewing the process used to build the product
    4. Setting quality standards in the quality management plan

    Explanation

    Quality control inspects and tests actual deliverables to determine whether they meet the specified requirements. Process-focused reviews, training, and standards definition belong to quality assurance or planning.

  139. Question 139Executing and Delivering

    A project manager must deliver sensitive performance feedback to a team member. Which communication method is most appropriate?

    1. A note in the monthly status report
    2. An email with a written summary
    3. A post in the team chat channel
    4. A private face-to-face or video meeting Correct answer.

    Explanation

    Sensitive or emotionally charged messages are best delivered through rich, interactive channels that allow immediate clarification and preserve confidentiality. Written broadcast channels risk miscommunication and expose private information to others.

  140. Question 140Executing and Delivering

    A reviewer notices that the peer-review checklist omits security items, so the team updates the checklist for future reviews. Which process does this illustrate?

    1. Quality control
    2. Validate scope
    3. Quality assurance Correct answer.
    4. Perform integrated change control

    Explanation

    Quality assurance improves the processes used to build deliverables, and updating a review checklist is a process improvement. Quality control would instead be the act of inspecting a specific deliverable for defects.

  141. Question 141Executing and Delivering

    A stakeholder asks the project manager to add a feature that is not in the approved scope. What should the project manager do first?

    1. Add the feature to the backlog and build it next iteration
    2. Ask the sponsor to reject it to protect the baseline
    3. Assess the impact on scope, schedule, cost, and quality Correct answer.
    4. Send the request to the change control board for a vote

    Explanation

    Every change request follows the change control process, and the first step is documenting it and evaluating its impact across constraints. The change control board can only make an informed decision once that impact analysis exists.

  142. Question 142Executing and Delivering

    A project manager learns that several small features were added over the past month without any formal requests. What is this called?

    1. Scope validation
    2. Progressive elaboration
    3. Gold plating
    4. Scope creep Correct answer.

    Explanation

    Scope creep is uncontrolled expansion of project scope through additions that were never reviewed or approved. It erodes baselines quietly because each addition seems small on its own.

  143. Question 143Executing and Delivering

    A project team of 6 members expands to 10 members. If every member communicates with every other member, how many additional communication channels are created?

    1. 45
    2. 15
    3. 30 Correct answer.
    4. 6

    Explanation

    Channels are calculated as n(n-1)/2. Six members produce 15 channels and ten members produce 45, so the increase is 30.

  144. Question 144Executing and Delivering

    An identified risk occurs and the team executes the planned response using pre-approved funds set aside in the cost baseline for that purpose. Which funds are these?

    1. The management reserve
    2. The contingency reserve Correct answer.
    3. The cost of quality budget
    4. The project's profit margin

    Explanation

    Contingency reserves are budgeted for known risks that have been identified and analyzed, and they sit within the approved cost baseline. Management reserve covers unknown risks and requires sponsor approval to access.

  145. Question 145Executing and Delivering

    A vendor delivers a module, and the project manager verifies it against documented acceptance criteria before approving payment. What is this activity?

    1. A contract change request
    2. A seller performance evaluation
    3. Formal acceptance of the deliverable Correct answer.
    4. A procurement audit

    Explanation

    Verifying a seller's deliverable against agreed criteria and then formally accepting it is the deliverable acceptance step of procurement control. It protects the buyer by tying payment to verified conformance.

  146. Question 146Executing and Delivering

    According to Herzberg's two-factor theory, which item is a motivator rather than a hygiene factor?

    1. Recognition for achievement Correct answer.
    2. Safe working conditions
    3. Adequate salary
    4. Company policies

    Explanation

    Motivators such as recognition, achievement, and growth create genuine satisfaction and engagement. Hygiene factors such as pay, safety, and policies only prevent dissatisfaction when adequate.

  147. Question 147Executing and Delivering

    Two senior engineers disagree on a design approach, and the decision affects the critical path. Which conflict resolution approach is most appropriate?

    1. Avoiding
    2. Collaborating Correct answer.
    3. Accommodating
    4. Compromising

    Explanation

    Collaborating seeks a solution that fully satisfies both parties and is the preferred approach when the issue is important and time allows. Because the decision affects the critical path, a durable, well-supported resolution matters more than speed.

  148. Question 148Executing and Delivering

    A resource histogram shows a developer assigned to two overlapping tasks at 130 percent utilization. The project manager delays the non-critical task until the developer is available. What is the most likely result?

    1. The project end date may be extended Correct answer.
    2. The critical path gets shorter
    3. Costs definitely decrease
    4. The overallocation is resolved with no schedule impact

    Explanation

    Resource leveling resolves overallocation by adjusting task timing, which can push out the completion date when it affects critical or near-critical work. Resource smoothing, by contrast, works within existing float and protects the end date.

  149. Question 149Executing and Delivering

    A senior engineer's know-how for tuning the system exists only in her head. Which action best preserves that knowledge for the project?

    1. Storing approved design documents in the shared repository
    2. Pairing her with junior engineers and recording her techniques Correct answer.
    3. Recording a lesson learned about her at project closure
    4. Adding a risk about her availability to the risk register

    Explanation

    Tacit knowledge is personal and experience-based, so it is transferred through interaction such as pairing, mentoring, and demonstration, backed by written capture. Documents alone cannot convey know-how that has never been externalized.

  150. Question 150Executing and Delivering

    A project team spans three time zones. Which action best addresses a common virtual team challenge?

    1. Deferring all decisions to a monthly in-person meeting
    2. Agreeing on communication norms and expected response times Correct answer.
    3. Holding meetings without an agenda to keep discussion open
    4. Replacing written documentation with verbal updates

    Explanation

    Virtual teams struggle most with miscommunication and delayed responses, so explicit norms about channels, availability, and turnaround times reduce friction. Written records also compensate for the loss of informal, in-person cues.

  151. Question 151Executing and Delivering

    A team member's deliverables are consistently late. What should the project manager do first?

    1. Meet privately to identify the cause Correct answer.
    2. Escalate to the functional manager
    3. Log the delay and take no further action
    4. Reassign the work to another team member

    Explanation

    Performance problems are best addressed first through direct, private conversation to uncover the root cause, which may be unclear requirements, skill gaps, or personal issues. Only after diagnosis can the project manager choose coaching, training, reassignment, or escalation.

  152. Question 152Executing and Delivering

    At a status review, a project shows a cost performance index of 0.85 and a schedule performance index of 1.10. How should this be interpreted?

    1. Behind schedule, over budget
    2. Ahead of schedule, under budget
    3. Ahead of schedule, over budget Correct answer.
    4. Behind schedule, under budget

    Explanation

    A CPI below 1.0 means work is costing more than planned, while an SPI above 1.0 means work is progressing faster than planned. Together they indicate schedule acceleration accompanied by cost overrun.

  153. Question 153Executing and Delivering

    A control chart shows seven consecutive data points on the same side of the mean, all still inside the control limits. What should the project manager conclude?

    1. The control limits are too wide and must be recalculated
    2. The data points are measurement errors and should be discarded
    3. The process is stable because no point is outside the limits
    4. The process shows a non-random pattern that warrants investigation Correct answer.

    Explanation

    A run of seven or more points on one side of the mean signals a special-cause pattern even when every point lies within the limits. Such a run indicates a shift in the process that should be investigated before defects appear.

  154. Question 154Executing and Delivering

    An unplanned regulatory requirement emerges that was never identified as a risk, and additional funding is required. What should the project manager do?

    1. Request approval to use the management reserve Correct answer.
    2. Draw on the contingency reserve already in the cost baseline
    3. Ask the team to absorb the work with no additional funds
    4. Transfer funds from another project's budget

    Explanation

    Unknown risks are funded from management reserve, which is held outside the cost baseline and released with sponsor or senior management approval. Contingency reserve is reserved for risks that were identified during planning.

  155. Question 155Executing and Delivering

    A change request is approved and the requirements documents must be revised. Which action ensures the team works from the current version?

    1. Updating the risk register with the new requirement details
    2. Performing a quality audit of the requirements document
    3. Re-baselining the project schedule and cost baselines
    4. Using configuration management and version control Correct answer.

    Explanation

    Configuration management identifies, controls, and tracks versions of project artifacts so that everyone works from the approved current release. It also records which versions are baselined and prevents obsolete copies from circulating.

  156. Question 156Executing and Delivering

    A project has a budget at completion of $200,000, earned value of $80,000, and actual cost of $100,000. Using EAC = BAC divided by CPI, what is the estimate to complete?

    1. $120,000
    2. $100,000
    3. $170,000
    4. $150,000 Correct answer.

    Explanation

    CPI equals EV divided by AC, or 0.8, so EAC equals $200,000 divided by 0.8, which is $250,000. ETC equals EAC minus AC, or $250,000 minus $100,000, giving $150,000.

  157. Question 157Executing and Delivering

    A newly formed project team has begun arguing about who should perform which tasks, and two members openly challenge the project manager's approach. Which stage of team development is the team in?

    1. Performing
    2. Norming
    3. Forming
    4. Storming Correct answer.

    Explanation

    In the storming stage, team members test boundaries and may clash over roles, authority, and working approach. The project manager should facilitate resolution rather than avoid the conflict.

  158. Question 158Executing and Delivering

    What is the primary purpose of a project kickoff meeting?

    1. To negotiate contract terms with the selected vendor
    2. To align stakeholders on goals, scope, and roles Correct answer.
    3. To baseline the schedule and cost estimates
    4. To obtain formal sign-off on the project charter

    Explanation

    A kickoff aligns the team and stakeholders on the charter's objectives, scope, roles, and working agreements before execution begins. It is a communication event, not an approval or baselining event.

  159. Question 159Executing and Delivering

    In a RACI matrix, which role should be assigned to exactly one person for each activity?

    1. Accountable Correct answer.
    2. Consulted
    3. Informed
    4. Responsible

    Explanation

    Only one person should be accountable for each activity so that ownership is unambiguous and decisions have a clear owner. Several people may be responsible for actually doing the work.

  160. Question 160Executing and Delivering

    A team holds a 15-minute daily standup. Which content is appropriate for each member to share?

    1. A review of the risk register and budget
    2. Detailed design debates among team members
    3. Progress, today's plan, and impediments Correct answer.
    4. Performance ratings for teammates

    Explanation

    A standup is a short coordination meeting limited to progress since the last meeting, the plan for the day, and any impediments. Detailed discussion is taken offline so the meeting stays brief.

  161. Question 161Executing and Delivering

    A team posts a large, visible chart of work items and their current status in the team area. What is this practice called?

    1. Quality audit
    2. Responsibility assignment matrix
    3. Information radiator Correct answer.
    4. Control chart

    Explanation

    An information radiator is a highly visible, low-effort display that lets the team and anyone walking by see status at a glance. It supports self-management and transparency.

  162. Question 162Executing and Delivering

    A team member reports that a needed test environment is unavailable. Where should the project manager record this?

    1. Issue log Correct answer.
    2. Lessons learned register
    3. Risk register
    4. Change log

    Explanation

    An issue log records issues that have already occurred, along with an owner, status, and resolution target. It is the tool for tracking active problems to closure during execution.

  163. Question 163Executing and Delivering

    A project manager sends a status report full of technical acronyms to business stakeholders who do not use them. Which communication barrier does this illustrate?

    1. Noise
    2. Jargon Correct answer.
    3. Time zone differences
    4. Filtering

    Explanation

    Jargon is a sender-side encoding problem: terminology unfamiliar to the audience obscures the message even when the channel works perfectly. Messages should be encoded for the receiver's background.

  164. Question 164Executing and Delivering

    What is the main benefit of co-locating a project team in a shared workspace?

    1. It removes the need for status reporting
    2. It eliminates all schedule risk along the critical path
    3. It speeds informal communication and team cohesion Correct answer.
    4. It reduces the need for a project charter

    Explanation

    Co-location puts the team in the same physical space, which increases rapid informal communication and builds trust and cohesion. It is a team-development technique, not a substitute for governance.

  165. Question 165Executing and Delivering

    The project manager needs a decision that every team member will commit to, and there is time available for discussion. Which decision-making approach is most appropriate?

    1. Majority vote
    2. Consensus Correct answer.
    3. Deferring the decision to the sponsor
    4. Autocratic decision by the project manager

    Explanation

    Consensus means every member can support and commit to the decision even if it is not their first choice, which builds ownership. It requires time for discussion, which the situation allows.

  166. Question 166Executing and Delivering

    What is the purpose of a quality audit during project execution?

    1. To measure individual productivity of team members
    2. To calculate the cost of rework on the project
    3. To check that processes comply with quality standards Correct answer.
    4. To inspect finished deliverables for defects before handover

    Explanation

    A quality audit is a structured, independent review of whether processes and procedures comply with the organization's quality standards and policies. It improves the process, not the individual product.

  167. Question 167Executing and Delivering

    Who typically performs user acceptance testing?

    1. The procurement manager
    2. The development team
    3. The intended end users Correct answer.
    4. The quality assurance auditors

    Explanation

    User acceptance testing confirms that the product meets the business need and is normally performed by end users or customer representatives. Developers perform unit and integration testing instead.

  168. Question 168Executing and Delivering

    A project manager wants to focus defect-reduction effort where it will have the greatest effect. Which tool should be used?

    1. Scatter diagram
    2. Control chart
    3. Pareto chart Correct answer.
    4. Fishbone diagram

    Explanation

    A Pareto chart ranks causes by frequency, showing which few causes account for most of the defects so effort can be concentrated there. It operationalizes the 80/20 principle.

  169. Question 169Executing and Delivering

    A project manager is unable to resolve a resource conflict with a functional manager. What should the project manager do next?

    1. Escalate the issue to the sponsor or governance body Correct answer.
    2. Reassign the work to another team member
    3. Accept the delay and log it in the risk register
    4. Submit a change request to reduce scope

    Explanation

    When the project manager lacks the authority to resolve a resource conflict, the issue moves up the governance chain to the sponsor or steering committee. Escalation keeps the problem visible and actionable.

  170. Question 170Executing and Delivering

    A vendor's deliverables have failed acceptance testing twice. Which action is most appropriate?

    1. Require a corrective action plan per the contract Correct answer.
    2. Terminate the contract immediately
    3. Pay the invoice and record a lesson learned
    4. Accept the deliverables to protect the schedule

    Explanation

    The contract defines remedies for nonconformance; the project manager should formally notify the seller and require a corrective action plan while protecting the schedule. Termination is a last resort reserved for severe, uncorrected breaches.

  171. Question 171Executing and Delivering

    A new developer joins the team midway through execution. What should the project manager do first to integrate the member effectively?

    1. Assign the highest-priority critical path tasks immediately
    2. Let the team decide how the new member is introduced
    3. Provide orientation and access to key documentation Correct answer.
    4. Defer any task assignment until the next phase begins

    Explanation

    New members need orientation to the project's objectives, processes, tools, and documentation before they can contribute effectively. Onboarding is a project manager responsibility even when the team assists.

  172. Question 172Executing and Delivering

    At the end of an iteration, the team reviews what went well and what should change. What is the primary output of this retrospective?

    1. A revised risk register
    2. A prioritized set of improvement actions Correct answer.
    3. A signed change request
    4. An updated project charter

    Explanation

    The retrospective produces a small set of agreed improvements that the team commits to applying in the next iteration. Its focus is team process improvement, not project baselines.

  173. Question 173Executing and Delivering

    A sprint burn-down chart shows the remaining-work line running flat for several days and then dropping sharply. What does this most likely indicate?

    1. The team is completing work faster than planned
    2. The sprint backlog was cancelled
    3. The team has too few user stories to track
    4. Work is marked complete only at the end Correct answer.

    Explanation

    A flat line followed by a steep drop usually means tasks are updated only when fully finished, or in a batch, which conceals true progress. Daily updates give a more accurate picture of remaining work.

  174. Question 174Executing and Delivering

    The project is behind schedule on the critical path, and the sponsor approves additional funds to shorten the duration. Which technique is being applied?

    1. Scope reduction
    2. Fast tracking
    3. Resource smoothing
    4. Crashing Correct answer.

    Explanation

    Crashing adds resources or overtime to critical-path activities, accepting higher cost to shorten duration. It is used when extra funds are available and the schedule must be recovered.

  175. Question 175Executing and Delivering

    A key stakeholder who was previously neutral now actively opposes a design decision. What should the project manager do?

    1. Remove the stakeholder from the stakeholder register
    2. Meet with the stakeholder to understand the concerns Correct answer.
    3. Ignore the objection since the stakeholder is not the sponsor
    4. Direct the team to proceed and document the objection

    Explanation

    Engagement requires understanding the stakeholder's concerns and addressing them through dialogue and, if warranted, a formal change. Active opposition left unaddressed can block the project.

  176. Question 176Executing and Delivering

    A critical production defect requires an immediate fix that exceeds the project manager's authority limit. What should the project manager do?

    1. Reject the change because it was not pre-approved
    2. Wait for the next scheduled change control board meeting
    3. Implement the fix immediately without documentation or approval
    4. Apply the emergency change process and seek later approval Correct answer.

    Explanation

    Emergency change procedures allow urgent fixes to proceed under a defined, shortened approval path with after-the-fact review, preserving control and traceability. This balances speed with governance.

  177. Question 177Executing and Delivering

    A team member says that even if they work harder, the extra effort will not be reflected in their performance review or reward. According to expectancy theory, which link should the project manager repair?

    1. Valence
    2. Equity
    3. Expectancy
    4. Instrumentality Correct answer.

    Explanation

    Instrumentality is the belief that performance will lead to the expected outcome or reward. When effort is not reflected in reviews, that performance-to-outcome link is broken and motivation falls.

  178. Question 178Executing and Delivering

    Several team members routinely take technical problems directly to the sponsor instead of the project manager, and the project manager learns of decisions after the fact. Which action best addresses the root of the problem?

    1. Ask the sponsor to refuse all direct contact from team members
    2. Reassign the team members who bypassed the project manager
    3. Agree escalation rules with the team and the sponsor Correct answer.
    4. Document each occurrence in the issue log and take no further action

    Explanation

    The root cause is an unclear or unaccepted escalation path, so the project manager should agree explicit escalation and communication rules with both the team and the sponsor. Clear agreements restore the project manager's coordination role without damaging relationships.

  179. Question 179Executing and Delivering

    A normally high-performing team member has become withdrawn, and the quality of their work has dropped. Which action by the project manager best reflects emotional intelligence?

    1. Report the drop in performance to the functional manager
    2. Meet privately to understand what is happening Correct answer.
    3. Reassign the team member's work to someone else
    4. Issue a formal written performance improvement plan

    Explanation

    Emotional intelligence means noticing changes in behavior and responding with empathy, starting with a private, curious conversation before formal action. Understanding the cause comes first; corrective steps follow if needed.

  180. Question 180Executing and Delivering

    A Kanban board shows 14 items in the in-progress column, well above the agreed work-in-progress limit of 5. What is the most likely consequence?

    1. Cycle time will decrease because more work is started
    2. The team's velocity will automatically increase
    3. Cycle time will increase and items will finish later Correct answer.
    4. Quality will improve because more work is visible

    Explanation

    Exceeding a WIP limit increases multitasking, context switching, and queues, which lengthens cycle time and delays completion. WIP limits exist to keep flow smooth and finish work sooner.

  181. Question 181Executing and Delivering

    A deliverable meets every documented acceptance criterion, but the requesting stakeholder says it does not solve the business problem. What should the project manager do?

    1. Review the requirements and business need with the requester Correct answer.
    2. Ask the team to redo the work at no additional cost
    3. Approve the deliverable because it meets the documented criteria
    4. Escalate to the sponsor to compel acceptance

    Explanation

    The gap suggests the documented requirements did not capture the real business need, so the project manager should revisit both with the requester and manage any resulting change formally. Blind acceptance or escalation would not close that gap.

  182. Question 182Executing and Delivering

    What is the primary purpose of a team charter?

    1. To capture the approved cost baseline for the project
    2. To document the technical design of each deliverable
    3. To list every activity in the work breakdown structure
    4. To record the team's operating agreements and authority Correct answer.

    Explanation

    A team charter records the team's purpose, boundaries, decision authority, and agreed ways of working. It gives the team a shared reference for how it will operate and what it is empowered to decide. Design documents, cost baselines, and activity lists are separate artifacts.

  183. Question 183Executing and Delivering

    A team is unsure when a user story can be considered finished. Which artifact resolves this?

    1. The communications management plan
    2. The project schedule baseline
    3. The risk register
    4. An agreed definition of done Correct answer.

    Explanation

    A definition of done states the criteria every increment must satisfy before it is treated as complete. It removes ambiguity about when work stops and quality checks have been met. Schedule, risk, and communication artifacts do not define completion criteria for work items.

  184. Question 184Executing and Delivering

    A project manager must confirm a complex design decision with a small group in real time. Which communication method is most appropriate?

    1. A printed newsletter distributed weekly
    2. A mass email sent to the whole organization
    3. An interactive meeting or video conference Correct answer.
    4. A pull-based wiki page the group can read at leisure

    Explanation

    Interactive communication provides immediate two-way exchange and is suited to reaching agreement on complex or sensitive matters. Push and pull methods cannot deliver real-time clarification from a small group. The method should match the urgency and complexity of the message.

  185. Question 185Executing and Delivering

    On a RACI chart, how many people should be accountable for a single work item?

    1. At least two, to avoid a single point of failure
    2. As many as participate in the work
    3. Exactly one Correct answer.
    4. One for each department affected

    Explanation

    Accountability means owning the outcome, so exactly one person is assigned per work item to prevent conflicting direction. Any number of people may be responsible for doing the work, consulted for input, or informed of progress. Multiplying accountable parties blurs ownership rather than strengthening it.

  186. Question 186Executing and Delivering

    A newly formed team begins arguing about roles and openly challenges the project manager's authority. Which stage of team development does this describe?

    1. Forming
    2. Norming
    3. Storming Correct answer.
    4. Performing

    Explanation

    Storming is marked by conflict over roles, expectations, and influence as members assert themselves. The project manager should address it by clarifying roles, reinforcing ground rules, and facilitating resolution. Later stages show settled norms and productive collaboration.

  187. Question 187Executing and Delivering

    A stakeholder requests a change to an approved deliverable. What should the project manager do first?

    1. Implement the change and inform the sponsor afterward
    2. Reject the request because the baseline is approved
    3. Direct the team to work overtime to absorb the change
    4. Document the request and assess its impact Correct answer.

    Explanation

    Every change request is logged and evaluated for its effect on scope, schedule, cost, quality, and risk before a decision is made. The impact analysis informs the appropriate authority, such as the change control board or sponsor. Acting before analysis or refusing outright bypasses the governance process.

  188. Question 188Executing and Delivering

    How does resource leveling differ from resource smoothing?

    1. Leveling never affects the project finish date
    2. Leveling applies only to physical materials
    3. Leveling may extend the schedule to resolve overallocation Correct answer.
    4. Smoothing may extend the critical path

    Explanation

    Resource leveling adjusts activities to remove overallocation and can change the critical path and finish date. Resource smoothing keeps the finish date fixed by using float rather than moving critical activities. Leveling is used when resource limits are hard constraints.

  189. Question 189Executing and Delivering

    A project team spans four time zones. Which practice best supports effective collaboration?

    1. Rotating meeting times and recording decisions in writing Correct answer.
    2. Scheduling all meetings in the project manager's time zone
    3. Replacing written updates with verbal-only status calls
    4. Relying on informal hallway conversations for decisions

    Explanation

    Distributed teams need deliberate inclusion and durable records because casual contact and shared context are limited. Rotating meeting times shares the inconvenience fairly, and written decisions give everyone the same reference. Practices favoring one location or relying on memory disadvantage remote members.

  190. Question 190Executing and Delivering

    Which action reflects prevention rather than inspection in managing quality?

    1. Testing the final product against acceptance criteria
    2. Logging defects found during peer review
    3. Training team members on the agreed coding standard Correct answer.
    4. Reviewing a finished deliverable before sign-off

    Explanation

    Prevention keeps defects from being introduced, while inspection detects defects after the work is done. Training people on the standard builds quality into the process itself. Reviews, testing, and defect logging are detection activities that occur after output exists.

  191. Question 191Executing and Delivering

    A team member lacks a skill needed for an upcoming critical task. What should the project manager do first?

    1. Assess the gap and arrange training or coaching Correct answer.
    2. Log the gap and take no further action
    3. Reassign the task to the most senior developer
    4. Request a schedule extension from the sponsor

    Explanation

    Development of the team begins with identifying the specific gap and the task's demands, then choosing an intervention such as training, mentoring, or pairing. This addresses the cause rather than working around it. Reassignment and schedule changes are options only if development is not feasible.

  192. Question 192Executing and Delivering

    How does a sprint review differ from a retrospective?

    1. The review is attended only by the development team
    2. The review replaces the need for a definition of done
    3. The review inspects the product increment with stakeholders Correct answer.
    4. The review focuses on improving team processes

    Explanation

    A sprint review demonstrates the completed increment to stakeholders and gathers feedback on the product. The retrospective, by contrast, examines how the team worked and what to change. Keeping the two purposes distinct prevents process discussions from crowding out product feedback.

  193. Question 193Executing and Delivering

    A vendor invoice includes hours that do not match the approved timesheets. What should the project manager do?

    1. Terminate the contract immediately
    2. Withhold the disputed charges and resolve them with the vendor Correct answer.
    3. Approve the invoice and adjust the budget baseline
    4. Pay the invoice in full to preserve the relationship

    Explanation

    Invoices are checked against the contract and records of work performed before payment is approved. Disputed amounts are held while the discrepancy is investigated and corrected with the vendor. Paying or rebaselining the budget would formalize an error.

  194. Question 194Executing and Delivering

    A project reports a CPI of 0.85 and an SPI of 1.10. Which interpretation is most accurate?

    1. The project is under budget and behind schedule
    2. The project is over budget and behind schedule
    3. The project is under budget and ahead of schedule
    4. The project is over budget and ahead of schedule Correct answer.

    Explanation

    A CPI below 1.0 means work is costing more than planned, so the project is over budget. An SPI above 1.0 means more work has been earned than scheduled at this point, so the project is ahead of schedule. Both indices must be read independently.

  195. Question 195Executing and Delivering

    A control chart shows seven consecutive data points on one side of the mean, all within the control limits. What does this indicate?

    1. A non-random pattern signals special-cause variation Correct answer.
    2. The data should be discarded as an outlier
    3. The process is stable and needs no attention
    4. The control limits were calculated incorrectly

    Explanation

    A run of seven or more points on one side of the mean is a recognized signal of non-random, special-cause variation even when every point sits inside the limits. The process should be investigated rather than assumed stable. Control limits themselves are not invalidated by the pattern.

  196. Question 196Executing and Delivering

    Two team members disagree about an approach to a task that matters little to the project manager but a great deal to one of them. Which conflict-handling approach is most appropriate?

    1. Compromising
    2. Accommodating Correct answer.
    3. Avoiding
    4. Forcing

    Explanation

    Accommodating means yielding on an issue that is unimportant to you but important to the other party, which preserves the relationship at low cost. Forcing would spend influence on a trivial matter, and avoiding leaves the disagreement unresolved. Compromising is unnecessary when the stakes are low for one side.

  197. Question 197Executing and Delivering

    On a cumulative flow diagram, the band for work in progress widens steadily over several weeks. What does this most likely indicate?

    1. Cycle time is decreasing
    2. Work is arriving faster than it is being completed Correct answer.
    3. Throughput is rising faster than new work arrives
    4. The team has reduced its batch size

    Explanation

    The vertical thickness of the in-progress band equals the amount of work started but not finished. Steady widening means items are entering faster than they leave, so work queues up and cycle time grows. A shrinking band would indicate the opposite imbalance.

CompTIA Project+ flashcards

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Project
A temporary endeavor with a defined start and end that creates a unique product, service, or result, as distinguished from ongoing operational work.
Triple constraint
The interdependent limits of scope, schedule, and cost, with quality and risk affected, that a project manager balances; changing one typically impacts the others.
Project charter
A document that authorizes the project, names the project manager, and states high-level scope, objectives, and constraints, formally starting the project.
Stakeholder
Any person or group that can affect or be affected by the project, such as sponsors, customers, users, and vendors; each should be identified and analyzed.
Functional organization
An organizational structure in which staff report to functional managers and the project manager holds little formal authority, relying on coordination and influence.
Projectized organization
A structure in which staff report primarily to the project manager, who holds high authority over resources and budget, often with co-located teams.
Strong matrix
A matrix structure in which the project manager holds greater authority than functional managers and typically controls budget and resource assignments.
RACI chart
A responsibility assignment matrix labeling each task as Responsible, Accountable, Consulted, or Informed, with exactly one person Accountable per task.
PMO
A project management office that standardizes processes, supplies templates and governance, and may support, control, or directly direct projects across the organization.
Phase gate review
A checkpoint at the end of a project phase where deliverables are reviewed and a go or no-go decision is made before work continues.
Lessons learned
Documented knowledge from a project covering what worked, what failed, and recommendations, captured during phases and at project close for reuse.
Work breakdown structure
A hierarchical decomposition of total project scope into manageable work packages, forming the basis of the scope baseline and of cost and schedule estimates.
Scope baseline
The approved scope statement, work breakdown structure, and WBS dictionary; changing any of these components requires formal change control.
Critical path
The longest path through the network diagram; it determines the shortest project duration, and its activities carry zero or negative total float.
Total float
The amount of time an activity can be delayed without delaying the project finish date; critical path activities have zero total float.
PERT estimate
A weighted three-point estimate calculated as (Optimistic + 4 times Most Likely + Pessimistic) divided by 6, used to reduce estimating bias.
Contingency reserve
Time or budget set aside for identified risks that have known response plans; it is included within the approved project cost baseline.
Management reserve
Budget held outside the cost baseline for unidentified unknown-unknown risks; drawing on it typically requires sponsor or senior management approval.
Resource leveling
A scheduling technique that adjusts activity start and finish dates based on resource constraints, often extending the project duration or changing the critical path.
Resource smoothing
A scheduling technique that shifts activities within their available float so resource demand stays level, normally without changing the critical path.
Risk register
A document listing identified risks with probability, impact, score, owner, and planned response; it is updated continuously throughout the project.
Estimate at completion
A forecast of final project cost; when current cost performance is expected to continue, EAC equals budget at completion divided by cost performance index.
Change control board
A group that reviews, approves, defers, or rejects change requests against defined criteria; its decisions protect the approved project baselines.
Issue log
A record of open issues with owners, status, and due dates; it tracks problems already occurring rather than uncertain future risks.
Tuckman stages
The team development sequence of forming, storming, norming, performing, and adjourning, moving from orientation through conflict to productivity and release.
Quality assurance
The executing process of auditing processes and work to confirm they meet quality standards, focusing on preventing defects rather than inspecting them out later.
Quality control
The monitoring process of inspecting deliverables and measuring results against quality standards in order to identify and correct defects.
Formal acceptance
The customer's documented approval that a deliverable meets its requirements, which then triggers payment or transition to the next phase.
Smoothing
A conflict resolution approach that de-emphasizes differences and emphasizes common ground, giving up part of the concern to maintain harmony.
Collaborating
A conflict resolution approach that fully addresses both parties' concerns to reach consensus; considered most effective when sufficient time exists.
Transition plan
A document describing how deliverables, knowledge, and support responsibilities move from the project team to the operations or receiving organization.
Kickoff meeting
A meeting that communicates project goals, roles, and the plan to the team and stakeholders, marking the beginning of project execution.

CompTIA Project+ study guide

Project Management Concepts

Core distinctions

A project is a temporary, unique effort that creates a defined product, service, or result. Operations are ongoing and repetitive. Programs group related projects; portfolios group projects, programs, and operations to meet strategic goals. A common trap is labeling routine, indefinite work as a project.

Constraints and lifecycle

Projects balance scope, schedule, cost, quality, resources, and risk; changing one usually affects others. Process groups are initiating, planning, executing, monitoring/controlling, and closing. Predictive, iterative, and adaptive approaches all use these groups, though the amount of upfront planning varies.

People and authority

The sponsor funds the project, approves the charter, and removes organizational barriers. The project manager plans and coordinates day-to-day work. The team performs the work. The charter authorizes the project and the PM. Organizational structure affects authority: functional organizations give the PM little authority, matrix organizations share it, and projectized organizations give the PM high authority. A PMO supports or governs projects.

Artifacts and terms

Know the charter, stakeholder register, business case, issue log, and lessons register. A risk is uncertain and future-oriented; an issue is already happening. An assumption is believed true but unconfirmed; a constraint is a limit.

Traps

Do not confuse sponsor and PM accountability, and do not say the PM approves the charter. Lessons learned are captured throughout the project, not only at closure.

Rule of thumb

If work repeats indefinitely with no defined end, classify it as operations. A new PM lacking formal authority should locate the approved charter and engage the sponsor before directing work.

Planning and Forecasting

Scope and schedule

Planning creates the scope baseline: scope statement, WBS, and WBS dictionary. Decompose work until packages can be estimated and assigned. Scheduling means defining activities, sequencing dependencies, estimating durations, and developing the schedule. The critical path is the longest path through the network and determines the shortest possible project duration; its activities have zero float. Float is how long an activity can slip without delaying the project. Fast tracking overlaps activities and adds risk; crashing adds resources and usually adds cost.

Cost and reserves

Estimating methods include analogous (quick, less accurate), parametric (unit rates), and bottom-up (detailed, more accurate). Contingency reserve covers known risks; management reserve covers unknown risks and is typically controlled by the sponsor.

Forecasting with earned value

PV is planned value, EV earned value, and AC actual cost. SV = EV - PV; CV = EV - AC; SPI = EV / PV; CPI = EV / AC. Negative variances and indexes below 1 are unfavorable. A common forecast is EAC = BAC / CPI when current cost performance continues. Also know ETC = EAC - AC, VAC = BAC - EAC, and TCPI = (BAC - EV) / (BAC - AC).

Risk and supporting plans

Use the risk register, probability/impact analysis, and responses: avoid, mitigate, transfer, accept, exploit, enhance, share, and accept. Quality planning sets standards; communications planning sets who needs what and when; procurement planning addresses make-or-buy.

Traps

Do not call the critical path the shortest path. Do not use management reserve for known risks. CPI above 1 means under budget, not over budget.

Worked example

BAC = 100,000; EV = 40,000; AC = 50,000. CPI = 0.8, so EAC = 100,000 / 0.8 = 125,000. The project is over budget and forecast to finish at 125,000.

Executing and Delivering

Executing work

Execution includes directing and managing project work, developing the team, performing quality assurance, managing communications and stakeholder engagement, conducting procurements, and implementing risk responses. The PM coordinates work, removes impediments, and keeps baselines current through change control.

Change control

Any change to scope, schedule, cost, or quality should go through integrated change control: document the request, assess impacts, obtain approval from the change control board or delegated authority, update plans and baselines if approved, and communicate the decision. Gold plating means adding unrequested features; it is not scope validation. Scope creep is uncontrolled scope expansion.

Quality and team

Quality assurance is process-focused: are we using the right processes? Quality control is product-focused: are the outputs correct? Team development includes motivation and conflict management. Conflict often arises from schedules, priorities, and resources. Collaboration/problem-solving is usually best; forcing may suit emergencies; compromise, smoothing, and avoiding have narrower uses. Address conflict early and directly.

Monitoring, acceptance, and closure

Track work performance, the issue log, risk triggers, and procurement performance. Validate deliverables against customer acceptance criteria. Closure includes final acceptance, contract closure, releasing the team, archiving records, capturing lessons learned, and handing off benefits. Transition is not optional.

Traps

Do not approve changes verbally without impact analysis. Do not confuse quality assurance with quality control. Do not treat closure as only a final report, and do not ignore procurement close-out.

Rule of thumb

When a stakeholder requests a new feature mid-project, do not simply add it. Log the request, analyze scope, schedule, cost, and risk impacts, route it through change control, and update the baseline only if approved.

CompTIA Project+ cheat sheet

Quick reference

Project Management Concepts

  • A project is temporary and produces a unique product, service, or result; operations are ongoing and repetitive.

  • Triple constraint: scope, schedule, and cost, with quality at the center - changing one constraint generally requires adjusting at least one other.

  • The project charter authorizes the project and the project manager's authority; it is issued by the sponsor, not written or approved by the project manager alone.

  • Authority spectrum: functional < weak matrix < balanced matrix < strong matrix < projectized.

  • In a functional organization the project manager typically acts as coordinator or expediter with little formal authority over resources.

  • RACI rule: only one person is Accountable per task; multiple people may be Responsible, Consulted, or Informed.

  • Project phases may run sequentially (predictive) or overlap/iterate (adaptive); exiting a phase normally requires a gate or phase-end review.

  • A PMO may be supportive (templates, training, best practice), controlling (compliance required), or directive (project managers report to it).

  • Lessons learned are captured at phase gates and at project close, not only at the end of the project.

Quick reference

Planning and Forecasting

  • WBS rule: decompose deliverables, not activities; the lowest level is the work package, and the 100% rule requires all scope to be represented.

  • PERT weighted estimate = (O + 4M + P) / 6; simple triangular estimate = (O + M + P) / 3.

  • PERT standard deviation = (P − O) / 6; variance = ((P − O) / 6) squared.

  • The critical path is the longest path through the network and sets the shortest project duration; total float on the critical path equals zero.

  • Total float = LS − ES = LF − EF; free float = ES of the successor − EF of the activity.

  • The cost baseline is the approved, time-phased budget that includes contingency reserves but excludes management reserves.

  • Contingency reserve covers known-unknown risks; management reserve covers unknown-unknowns and sits outside the cost baseline.

  • Resource leveling can extend the schedule or change the critical path; resource smoothing uses only float and does not change the finish date.

  • EVM forecasting: CPI = EV / AC, SPI = EV / PV, EAC = BAC / CPI when current cost performance continues, and VAC = BAC − EAC.

Quick reference

Executing and Delivering

  • Tuckman sequence: forming, storming, norming, performing, adjourning; storming is a normal stage and is worked through rather than avoided.

  • Conflict approaches ranked by durable outcome: collaborating, compromising, smoothing or forcing, with avoiding as a last resort.

  • Change flow: submit request, log it, assess impact, obtain CCB decision, update baselines, implement, verify, then communicate.

  • Only approved changes modify baselines; unapproved change requests are not implemented.

  • Quality assurance is process-focused and preventive during execution; quality control is product-focused and detective on deliverables.

  • The issue log records problems that have already occurred; the risk register records uncertain future events.

  • Acceptance criteria belong in the scope statement and WBS dictionary and are defined before the work is performed.

  • A phase gate is a go/no-go decision point, while a kill point is a decision to terminate the project early.

  • Closeout includes formal acceptance, contract closure, resource release, and archival of lessons learned.

CompTIA Project+ key terms

Project

A temporary effort with a defined start and end that produces a unique product, service, or result. Projects are progressively elaborated and finish when objectives are met or the effort is terminated.

Related: Project Life Cycle, Project Charter, Deliverable
Project Life Cycle

The sequence of phases a project moves through, from initiation and planning to execution and closure. The number and names of phases vary by organization and project type.

Related: Phase Gate, Project, Milestone
Project Charter

A document issued by the sponsor that formally authorizes the project, states high-level objectives and constraints, and names the project manager with authority to apply organizational resources.

Related: Project Sponsor, Project, Triple Constraint
Stakeholder

Any person or group who can affect, be affected by, or perceives themselves to be affected by the project. Stakeholders include sponsors, customers, team members, vendors, and regulators.

Related: Project Sponsor, RACI Chart
Project Sponsor

The executive who funds and champions the project, approves the charter and major changes, and helps remove obstacles that sit beyond the project manager's authority.

Related: Project Charter, Stakeholder, Management Reserve
Triple Constraint

The interlinked limits of scope, schedule, and cost, balanced against quality. Changing one typically forces an adjustment in at least one of the others.

Related: Scope Creep, Cost Baseline, Change Control Board (CCB)
Matrix Organization

An organizational structure where staff report both to a functional manager and to one or more project managers. Authority is shared, so negotiation and clear role definitions matter.

Related: RACI Chart, Project Management Office (PMO)
Project Management Office (PMO)

A group that sets and supports project management standards, templates, tools, and governance across an organization. A PMO may also coach project managers, oversee portfolios, or run projects directly.

Related: Matrix Organization, Phase Gate
Deliverable

Any measurable, verifiable output or outcome that must be produced to complete a project or phase, such as a report, a software module, or a completed training session.

Related: Milestone, Validate Scope
Milestone

A significant point or event in the project with zero duration, used to mark completion of a major deliverable or phase and to track high-level progress.

Related: Deliverable, Phase Gate, Critical Path
Phase Gate

A review held at the end of a project phase where sponsors or governance decide whether to continue, revise, pause, or cancel the work based on predefined criteria.

Related: Project Life Cycle, Project Management Office (PMO)
Lessons Learned

Knowledge captured during and after a project about what worked, what failed, and what should change next time. It is documented and stored so future teams can reuse it.

Related: Project Closure, Issue Log
Work Breakdown Structure (WBS)

A hierarchical breakdown of total project scope into smaller, manageable components ending in work packages that can be estimated, scheduled, assigned, and controlled.

Related: Scope Baseline, Deliverable
Scope Baseline

The approved project scope statement, work breakdown structure, and WBS dictionary. It is the reference used to detect and evaluate proposed scope changes.

Related: Work Breakdown Structure (WBS), Scope Creep, Change Control Board (CCB)
Scope Creep

Uncontrolled expansion of a project's scope through extra features or unrequested work that is accepted without corresponding approval and adjustments to schedule, budget, and resources.

Related: Scope Baseline, Triple Constraint
Network Diagram

A graphical view of project activities and their logical dependencies, used to determine sequence, identify the critical path, and calculate float for each activity.

Related: Critical Path, Float
Critical Path

The longest sequence of dependent activities through the network, which determines the shortest possible project duration. Activities on it typically have zero float.

Related: Float, Network Diagram, Resource Leveling
Float

The amount of time an activity can be delayed without delaying a successor or the project finish date. Also called slack; critical path activities have none.

Related: Critical Path, Resource Leveling
Three-Point Estimating

An estimating technique that uses optimistic, most likely, and pessimistic values, often averaged with a weighted formula, to account for uncertainty and produce a more realistic estimate.

Related: Analogous Estimating, Contingency Reserve
Analogous Estimating

Estimating duration or cost for current work by comparing it with similar past projects. It is fast and inexpensive but generally less accurate than detailed estimating techniques.

Related: Three-Point Estimating, Cost Baseline
Cost Baseline

The approved, time-phased project budget used to measure and monitor cost performance. It excludes management reserve and changes only through formal change control.

Related: Contingency Reserve, Management Reserve, Cost Performance Index (CPI)
Contingency Reserve

Time or money set aside for identified risks that have been analyzed and accepted. It is part of the cost baseline and is controlled by the project manager.

Related: Management Reserve, Risk Register
Management Reserve

Funds or time held for unforeseen work within project scope, known as unknown unknowns. Using it usually requires sponsor or governance approval, and it sits outside the cost baseline.

Related: Contingency Reserve, Cost Baseline
Risk Register

A living document listing identified risks with their probability, impact, score, owner, and planned response, updated as risks change throughout the project.

Related: Risk Response Strategies, Contingency Reserve
Resource Leveling

Adjusting start and finish dates to resolve resource over-allocation or to keep resource use within limits. It often extends the schedule and can change the critical path.

Related: Critical Path, Float
RACI Chart

A responsibility assignment matrix that marks each person's role for a task as Responsible, Accountable, Consulted, or Informed, clarifying who does the work and who decides.

Related: Stakeholder, Matrix Organization
Earned Value (EV)

The budgeted value of work actually completed at a point in time. It lets you compare planned progress with actual performance in both cost and schedule terms.

Related: Cost Performance Index (CPI), Schedule Performance Index (SPI), Estimate at Completion (EAC)
Cost Performance Index (CPI)

Cost performance index, calculated as earned value divided by actual cost. A value above 1.0 means work is costing less than planned; below 1.0 means overspending.

Related: Earned Value (EV), Estimate at Completion (EAC)
Schedule Performance Index (SPI)

Schedule performance index, calculated as earned value divided by planned value. A result above 1.0 indicates progress ahead of schedule; below 1.0 indicates the work is behind.

Related: Earned Value (EV), Critical Path
Estimate at Completion (EAC)

A forecast of the project's total cost based on current performance. A common formula divides budget at completion by the cost performance index.

Related: Cost Performance Index (CPI), Earned Value (EV)
Change Control Board (CCB)

A group of stakeholders authorized to review, approve, reject, or defer change requests and to decide how approved changes will affect project baselines.

Related: Scope Baseline, Issue Log
Issue Log

A record of current problems affecting the project, including owner, status, and resolution plans. Unlike risks, issues have already happened and need action now.

Related: Risk Register, Lessons Learned
Risk Response Strategies

Planned approaches for handling threats and opportunities: avoid, mitigate, transfer, accept, or escalate for threats, and exploit, enhance, share, or accept for opportunities.

Related: Risk Register, Contingency Reserve
Quality Assurance

Process-oriented work that evaluates and improves the methods and standards used to build deliverables, aiming to prevent defects before they occur.

Related: Quality Control, Validate Scope
Quality Control

Product-oriented work that inspects and tests deliverables against requirements and quality standards, identifying defects so they can be corrected through rework.

Related: Quality Assurance, Validate Scope
Validate Scope

The process of formally obtaining customer or sponsor acceptance of completed deliverables, typically through inspection and sign-off, before closing a phase or the project.

Related: Quality Control, Project Closure
Project Closure

The final phase in which deliverables are handed over, contracts are closed, resources are released, final reports and lessons learned are completed, and stakeholder acceptance is confirmed.

Related: Lessons Learned, Validate Scope
Tuckman's Team Stages

The typical progression of a team through forming, storming, norming, performing, and adjourning. Leaders adjust their style at each stage to build trust and productivity.

Related: Project Life Cycle, RACI Chart

CompTIA Project+ study plan

8 weeks · About 7 hours per week

Week 1

Project Management Concepts & Executing and Delivering

  • Map the project lifecycle phases, process groups, and their primary artifacts onto a single one-page diagram

  • Define in your own words the responsibilities of the project manager, sponsor, project team, and key stakeholders

  • Contrast predictive, agile, and hybrid delivery approaches with one concrete project example of each

  • Distinguish the triple constraints and explain how a change to one affects the others in three written scenarios

  • Build a 40-card vocabulary deck covering foundational project management terms

Your checkpoint

One-page lifecycle and roles reference sheet plus a 40-card deck, self-quizzed to at least 80% accuracy

Week 2

Project Management Concepts & Planning and Forecasting

  • Draft a project charter for a sample three-month project including objectives, success criteria, and high-level constraints

  • Decompose that project into a work breakdown structure down to work packages of eight hours or less

  • Sequence activities into a network diagram and label the critical path

  • Estimate durations for ten activities using three-point estimating and record the assumptions

  • Complete 30 practice questions on project fundamentals and log every miss by objective

Your checkpoint

Sample project packet containing charter, WBS, and network diagram with the critical path explicitly labeled

Week 3

Planning and Forecasting

  • Build a bottom-up cost estimate and roll it into a time-phased cost baseline for the sample project

  • Create a risk register with ten risks, each scored by probability and impact with a planned response

  • Outline a procurement plan identifying make-or-buy decisions, contract types, and vendor selection criteria

  • Draft a quality management plan naming standards, metrics, and control activities

  • Classify ten stakeholders on a power-interest grid and assign an engagement strategy to each

Your checkpoint

Consolidated planning document with budget baseline, risk register, procurement outline, quality plan, and stakeholder grid

Week 4

Executing and Delivering

  • Run a mock project kickoff and produce an agenda, meeting minutes, and an action item log

  • Apply the stages of team development and five conflict resolution modes to written team scenarios

  • Design a communication plan that matches information needs, frequency, and channel to each audience

  • Score at least 70% on a timed 50-question mixed-domain quiz and categorize errors by domain

Your checkpoint

Kickoff artifact set (agenda, minutes, action log, communication plan) plus a scored 50-question quiz with an error breakdown

Week 5

Executing and Delivering

  • Process five change requests through a formal change control workflow including impact analysis and change board decision

  • Triage eight issue log entries, assigning owners, priority, and escalation paths

  • Convert three risk register entries into executed responses and update them with triggers and residual risk

  • Interpret a quality control finding and document the corresponding corrective action

  • Explain how configuration management and version control protect project deliverables

Your checkpoint

Change control log and issue log containing documented decisions for thirteen total scenarios

Week 6

Planning and Forecasting & Executing and Delivering

  • Compute PV, EV, AC, CV, SV, CPI, SPI, EAC, ETC, and VAC across six worked scenarios

  • Forecast a project's completion cost and date from performance data and state the assumptions behind the forecast

  • Compare agile planning artifacts such as backlog, burndown, and velocity against predictive baselines

  • Write a one-page status recommendation explaining schedule and cost trends to a sponsor audience

  • Rebuild notes on any domain 2 objective still scoring below 75% on practice sets

Your checkpoint

Earned value worksheet of twelve problems solved at 85% or higher accuracy plus a one-page status forecast memo

Week 7

Project Management Concepts & Planning and Forecasting & Executing and Delivering

  • Identify your five weakest objectives from tracked practice data and rebuild study notes for each

  • Work 30 cross-domain scenario questions at a pace of 90 seconds per question

  • Teach back three core concepts aloud without notes in under five minutes each

  • Review closure activities including lessons learned, deliverable transition, and resource release

  • Reattempt all previously missed questions and confirm each is now explainable

Your checkpoint

Remediation log of five weak objectives, each retested to 80% or higher accuracy

Week 8

Executing and Delivering & Project Management Concepts & Planning and Forecasting

  • Complete two full-length timed practice exams and tag every missed question by domain and objective

  • Re-study each missed item until you can justify the correct answer and reject each distractor

  • Recite all key formulas and definitions from memory during a 15-minute self-audit

  • Confirm exam-day logistics including scheduling, identification, and testing environment requirements

Your checkpoint

Two timed practice exam scores at 85% or higher plus a one-page formula and definitions sheet written entirely from memory

Milestones

Week 2: Charter, WBS, and network diagram complete; 30-question fundamentals set scored at 70% or higher

Week 4: Timed 50-question mixed set scored at 70% or higher, with all domain 1 objectives marked as understood or flagged for remediation

Week 6: Earned value worksheet at 85% or higher accuracy and no more than two unresolved weak objectives remaining

Week 8: Two full-length timed exams at 85% or higher with every missed question re-explained correctly without notes

CompTIA Project+ exam day

Your checklist

Government-issued photo ID with signature

Bring an unexpired, original (not photocopied) ID. The name must match your exam registration exactly. Confirm the accepted ID list with CompTIA/Pearson VUE before test day - requirements differ between test centers and online proctoring, and a mismatch is the most common reason people are turned away.

Second form of identification

Some test centers ask for a secondary ID (e.g., a credit card or employee badge). This is not universal - check with your chosen delivery provider whether a second ID is required for your appointment.

Appointment confirmation and registration/order number

Screenshot or print the confirmation email showing your appointment time, exam code (PK0-005), and delivery method. Useful if the check-in desk cannot locate your booking.

Your CompTIA/Pearson VUE account credentials

Know the username and password tied to your certification account so you can log in, complete any pre-exam steps, and later retrieve your score report and certificate status.

Online-proctored setup tested in advance

If testing from home, run the provider's system test on the same computer, camera, microphone, and network you will use on exam day. Confirm browser version, permissions, and that no VPN or corporate firewall will block the session.

A quiet, private, well-lit room with a cleared desk

Online proctoring typically requires a closed door, no other people, no second monitors, and nothing on the desk except allowed items. Unplug or cover extra screens and remove papers, books, and phones from the room.

Plan to arrive or log in early

Aim to arrive at the test center or start the online check-in well before your slot - commonly 15–30 minutes. Late arrivals may be refused entry or lose the fee. Confirm the exact grace period with the provider.

Travel, parking, and building-access logistics

Know the route, parking options, and which entrance/floor the test center is on. For early-morning slots, verify the building is open at that hour.

Leave study materials, notes, and wearables at home or outside the exam room

Cram sheets, phones, smart watches, and earbuds are not permitted in the testing room. Don't plan on reviewing notes in the waiting area unless the provider explicitly allows it.

Light snack and water for afterward

Scheduled breaks are generally not available during the exam, so eat and hydrate before you check in rather than counting on a mid-exam pause. Confirm any break or accommodation policy with the provider.

A one-page objectives review, not new material

In the final hours, skim the official exam objective domains and your own summary of weak areas. Learning a brand-new topic the night before reliably costs more in confidence than it gains in points.

A realistic time plan for 90 questions in 90 minutes

That is roughly one minute per question with no slack, so plan to answer, flag only genuinely uncertain items, and leave time to sweep flagged questions before the clock ends.

Plan the day

Final 72 hours

Stop introducing new topics. Re-read the official exam objectives and mark any objective you cannot explain in one sentence; spend remaining study time only on those gaps. Do one or two timed practice sets under exam conditions - 90 questions in 90 minutes - and review your misses for the reasoning error, not just the right answer.

Final 72 hours

Verify logistics: confirm your appointment date, time, exam code, and delivery method; run the online system test if applicable; check the test center address and parking. If you need to reschedule, do it now rather than inside any late-change window - confirm the reschedule deadline and any fee with the provider.

Final 72 hours

Protect sleep. Two normal nights beat one long cram session; shift your bedtime earlier now so an early slot does not leave you foggy.

24 hours before

Do a light pass only: domain list, formulas/terminology you keep confusing, and the question-type format (multiple choice, multiple response, drag-and-drop style items where more than one selection may be required). Then stop studying.

24 hours before

Lay out ID, confirmation printout, and clothing (layers help with variable room temperature). Prepare food and coffee so the morning has no decisions. Set two alarms.

24 hours before

For online proctoring: clear the desk, close the door to the room, charge the laptop, and confirm the camera and microphone work. Note your check-in window - confirm with the provider how early you may launch the session.

Morning of

Eat a normal meal, hydrate, and avoid heavy caffeine if you are already anxious. Do not cram in the car or at the check-in desk; a last-minute contradictory fact does more harm than good.

Morning of

Arrive or begin check-in early with your ID ready. Expect ID verification, a photo, a rules/NDA acknowledgement, and possibly a locker or room scan for your belongings - confirm the specifics with your provider.

During the test

Read the whole question stem before the answer choices, especially on 'which is BEST' or 'which is FIRST' items. Look for the qualifier word and eliminate options that are correct in general but wrong for the scenario's phase or constraint.

During the test

Answer every question. There is no credit for unanswered items, so if time is tight, select your best choice and move on. Flag only items where new information later in the exam might genuinely change your mind, and revisit them in a final sweep.

During the test

For multi-select items, count what the stem asks for (e.g., 'choose two') and confirm you have exactly that number selected. For ordering/sorting-style items, re-check the sequence end to end before submitting.

After the test

Read the score report carefully: you receive a pass/fail result plus a scaled score and a breakdown of performance by domain. Keep the report - the domain breakdown tells you exactly where to focus if you need to retake, and it feeds your continuing-education planning if you passed.

Rules to check

  • Bring valid, unexpired government-issued photo ID with a signature, and make sure the name matches your registration exactly. Exact ID acceptance criteria vary by delivery method - confirm with CompTIA/Pearson VUE in advance rather than assuming.

  • Treat the exam content as confidential. You will typically be asked to accept a non-disclosure agreement at check-in; do not reproduce, discuss, or post actual exam questions afterward.

  • Do not bring unauthorized materials into the testing room - no notes, phones, smart watches, or earbuds. Online sessions usually include a room scan; test-center sessions usually require belongings to be stored. Confirm allowed items with the provider.

  • The clock generally runs continuously, and scheduled breaks are typically not offered. If you need a break or other accommodation, request it in advance through the provider's accommodation process - it cannot usually be arranged on the day.

  • Understand the scoring model: results are reported on a scaled range rather than a raw percentage, with a set passing threshold, so your practice-test percentages are not directly comparable to the real score. Confirm the current passing score and exam length on the official CompTIA page before test day.

  • Your provisional pass/fail result is usually shown at the end of the exam, but official confirmation and certification records may update later. Do not treat the on-screen result as final documentation until your account reflects it.

  • If something goes wrong - connectivity loss, a proctor disconnect, a hardware failure - stop and follow the provider's incident process immediately rather than restarting on your own. Cases opened the same day are far easier to resolve, and confirm the appeal/retake policy with the provider.

  • Arriving late, or failing ID verification, can result in being denied entry or losing your exam fee. Know the provider's late-arrival and reschedule/cancellation deadlines and fees, and confirm them yourself before your appointment.

CompTIA Project+ FAQ

How many CompTIA Project+ practice questions are available?

The practice set has 197 CompTIA Project+ questions. Each one includes the choices, the correct answer, and an explanation, and the set is free to read with no signup.

How many CompTIA Project+ flashcards are available?

The flashcard set has 32 CompTIA Project+ cards. Each card shows the term and its definition.

Which topics does the CompTIA Project+ study material cover?

The CompTIA Project+ study material covers Project Management Concepts, Planning and Forecasting, and Executing and Delivering.

What format facts does the catalog list for the CompTIA Project+ exam?

The catalog lists these item types: multiple choice for the CompTIA Project+ exam.