C&G 2079-11 F-Gas Category I Practice Test

C&G 2079-11 F-Gas Category I overview

  • 200 practice questions
  • 32 flashcards
  • 5 study guide topics
  • 37 key terms

What you'll study

  • F-gas and ODS regulations, legal duties and environmental impact20%
  • Refrigerant safety, cylinder handling, PPE and risk assessment20%
  • Leak checking, containment, record keeping and reporting obligations20%
  • Installation, commissioning, pressure testing and evacuation of RAC systems20%
  • Servicing, maintenance, refrigerant recovery, recycling and decommissioning20%

City & Guilds 2079-11 (F-Gas and ODS Regulations, Category I) is a UK vocational qualification for technicians who handle fluorinated greenhouse gases and ozone-depleting substances in refrigeration, air conditioning and heat pump work. Category I is the widest category, aimed at engineers who carry out the full range of activities - installation, commissioning, servicing, leak checking, recovery and decommissioning - rather than the narrower task sets covered by the lower categories.

Assessment is commonly split between a written or multiple-choice theory paper and a practical assessment in which candidates demonstrate handling skills on real equipment. The syllabus is organised around themes including the F-gas and ODS regulations, legal duties and environmental impact; refrigerant safety, cylinder handling, PPE and risk assessment; leak checking, containment, record keeping and reporting obligations; installation, commissioning, pressure testing and evacuation; and servicing, maintenance, recovery, recycling and decommissioning.

Preparation should combine a careful read of the current F-gas and ODS regulations with hands-on practice: recovery procedures, evacuation and vacuum testing, leak detection methods, and accurate record keeping. Because the regulations are revised periodically, always study against the current official version rather than older training notes.

Please note: the City & Guilds qualification page for 2079 returned a '404 Page Not Found' error when checked, so figures such as question count, exam duration, pass mark, fee, retake rules and certificate validity are not published on this page. Confirm them with City & Guilds or your approved training centre before booking.

Common mistakes

Converting refrigerant charge into CO2-equivalent incorrectly - for example quoting a leak as '0.8 kg of R-410A' and stopping there, or multiplying by the wrong GWP (using R-22's 1810 for an HFC blend).

Candidates memorise GWP values as isolated numbers and never rehearse the two-step calculation (kg × GWP ÷ 1000 = tonnes CO2e), and they mix up single-component and blend figures under exam pressure.

What to do instead

Drill the formula tonnes CO2e = kilograms × GWP ÷ 1000 until it is automatic, and for every practice question write the refrigerant, its GWP and the CO2e total on the same line. Check the current F-gas GWP table rather than recalling from memory.

Describing the HFC phase-down as a ban on using or servicing R-410A, or stating that reclaimed refrigerant is treated the same as virgin gas under the quota.

News headlines and shorthand talk of 'F-gas bans' blur the distinction between the CO2e quota on placing gas on the market and the separate servicing restrictions that apply only above specific charge and GWP thresholds.

What to do instead

Learn the three separate mechanisms as a list: the phase-down quota (measured in tonnes CO2e placed on the market), the servicing ban on virgin high-GWP gas above a charge threshold, and the rules on reclaimed or recycled gas. Revise the thresholds and dates from the regulation text, not from memory.

Connecting a regulator to a refrigerant or nitrogen cylinder without first checking the hydrostatic test date, valve condition and whether the cylinder has a correct valve cap fitted.

Candidates focus on the task they are about to do and treat the cylinder as a passive object; test-date stamps are small, faint and easily overlooked, and exam scenarios rarely remind you to look.

What to do instead

Adopt a fixed pre-use sequence you can recite: check the test date is in date, check the valve and thread are undamaged, confirm the correct regulator and hose for that gas, secure the cylinder upright, then open the valve slowly. Practise this order until it is a habit.

Treating an A2L refrigerant such as R-32 or R-454B as if it were non-flammable - no ignition-source control, no gas detection, no consideration of room volume or lower flammability limit.

A2L is 'lower flammability' and many candidates remember only that it is 'not as bad as A3', which collapses into 'not flammable' in their notes and in their answers.

What to do instead

Keep a three-way comparison in your revision: A1 non-flammable, A2L lower flammability with a slow flame speed, A3 higher flammability. For A2L, always state ignition-source exclusion, ventilation or room-volume checks, leak detection and appropriate tooling as part of the answer.

Recording a leak check as simply 'checked, no leaks' without the date, refrigerant type, charge size, method used, result and the engineer's name and certification number.

Candidates answer the technical question and treat the paperwork as an afterthought, so they recall that a record exists but not which fields make it compliant.

What to do instead

Memorise the record as a checklist of fields - equipment identifier, date, refrigerant and charge, CO2e, check method, result, any repair and follow-up date, engineer and company details. Write the list out from memory in every revision session until it is complete in one pass.

Applying a single leak-check interval to every system, such as stating that all equipment must be checked every 12 months regardless of charge size or leak-detection fitment.

The frequency table is a set of thresholds with exceptions, and candidates often remember one row of it and generalise; hermetic sealed systems and fitted leak-detection systems add further variations.

What to do instead

Build a table from memory with the charge bands in tonnes CO2e, the corresponding interval, and two modifiers: hermetically sealed equipment and the presence of a functioning leak-detection system. Test yourself by covering the intervals column and reconstructing it, then check against the regulation.

Using a vacuum as the leak test - pulling the system down to roughly -1 bar gauge, seeing the gauge hold, and declaring the system leak-free.

A standing vacuum test is quick, requires no nitrogen, and appears to prove the circuit is sound, so candidates conflate 'holds vacuum' with 'pressure-tight' and skip the pressure test entirely.

What to do instead

Separate the two tests explicitly in your answers: a pressure test with oxygen-free nitrogen proves strength and tightness under positive pressure, and evacuation removes moisture and non-condensables. Never describe vacuum decay as a substitute for a pressure test.

Pressure-testing a system with compressed air or oxygen, or connecting an unregulated nitrogen cylinder directly to the circuit and letting full cylinder pressure into it.

Candidates know nitrogen is the right gas but do not internalise why, so under a scenario requiring an alternative they reach for the workshop air line, and they underestimate how high a full nitrogen cylinder's pressure is.

What to do instead

State the reason, not just the rule: oxygen supports combustion and oil in the circuit can ignite, and compressed air introduces moisture. Always specify oxygen-free nitrogen through a regulator set to the test pressure, with the pressure increased in stages and never above the manufacturer's figure.

Recovering refrigerant into a disposable cylinder or filling a recovery cylinder without weighing it against the 80% maximum fill limit.

Recovery is often taught as a plumbing exercise and the cylinder constraint is treated as a minor detail, so candidates picture any empty cylinder as suitable and forget that liquid expansion leaves no headroom.

What to do instead

Link the rule to the risk: liquid refrigerant expands with temperature and a cylinder without headroom can rupture hydraulically. Before every recovery, state the tare weight, the cylinder's capacity, the 80% figure and the fact that only dedicated, in-test recovery cylinders are used.

Recording the recovered quantity as a rough estimate, or failing to account for refrigerant left in oil, in the receiver or isolated in a part of the circuit during decommissioning.

Candidates treat recovery as done when the machine stops pulling gas, forgetting that residual refrigerant in compressor oil, liquid lines and isolated sections still counts and must be captured and recorded.

What to do instead

Answer with a sequence: isolate and recover from each section in turn, use a recovery machine capable of pulling a deep vacuum, account for gas dissolved in oil, weigh recovered refrigerant, and record the amount against the original charge with any discrepancy explained.

Exam requirements can change. Confirm current details with the exam provider.

C&G 2079-11 F-Gas Category I practice

200 questions. Each one lists the choices, the correct answer, and an explanation. With JavaScript, this list opens one question at a time. The checker at the top of this page saves progress in this browser when it is available.

  1. Question 1F-gas and ODS regulations, legal duties and environmental impact

    What does the abbreviation GWP stand for in F-gas regulations?

    1. Greenhouse weight percentage
    2. Gas warming property
    3. Global warming potential Correct answer.
    4. General warming pressure

    Explanation

    GWP is a relative measure of how much heat a greenhouse gas traps in the atmosphere compared with carbon dioxide over a set period, usually 100 years. It is used to convert the mass of an F-gas into tonnes of CO2 equivalent for regulatory thresholds.

  2. Question 2F-gas and ODS regulations, legal duties and environmental impact

    Which of the following refrigerants is an ozone-depleting substance controlled by ODS regulations?

    1. R-410A
    2. R-22 Correct answer.
    3. R-134a
    4. R-32

    Explanation

    R-22 is a hydrochlorofluorocarbon containing chlorine, so it depletes stratospheric ozone and falls under ODS controls. R-134a, R-410A and R-32 are HFCs or HFC blends with no chlorine and are controlled as F-gases, not as ODS.

  3. Question 3F-gas and ODS regulations, legal duties and environmental impact

    Which legislation is the main UK control on ozone-depleting substances such as CFCs and HCFCs?

    1. The F-gas Regulation and its quota system
    2. The COSHH Regulations and safety data sheets
    3. The Pressure Systems Safety Regulations
    4. The ODS Regulation Correct answer.

    Explanation

    The retained ODS Regulation controls production, use, recovery and destruction of ozone-depleting substances. The F-gas Regulation deals with fluorinated greenhouse gases, not the ozone-depleting CFCs and HCFCs themselves.

  4. Question 4F-gas and ODS regulations, legal duties and environmental impact

    For stationary refrigeration equipment containing 5 tCO2e or more but less than 50 tCO2e, what is the maximum interval between statutory leak checks?

    1. Every six months
    2. Every twelve months Correct answer.
    3. Every three months
    4. Every month

    Explanation

    The regulation sets a 12-month maximum interval for equipment at or above 5 tCO2e and below 50 tCO2e. More frequent checks apply at larger charge sizes, and intervals are halved where a certified leak detection system is fitted.

  5. Question 5F-gas and ODS regulations, legal duties and environmental impact

    For how long must an operator keep records of F-gas leak checks, repairs and gas quantities?

    1. At least one year
    2. At least five years Correct answer.
    3. Only until the next service
    4. At least ten years

    Explanation

    Records must be kept for at least five years and made available to the regulator on request. They provide an audit trail for leak checks, repairs, gas recovery and charge changes.

  6. Question 6F-gas and ODS regulations, legal duties and environmental impact

    What is the correct legal approach for F-gas recovered from refrigeration equipment during service?

    1. Pour it down a drain
    2. Recover it for recycling or destruction Correct answer.
    3. Release it slowly to atmosphere
    4. Burn it in an open fire

    Explanation

    F-gases must not be vented to atmosphere; recovered gas must be handled by certified personnel and sent for recycling, reclamation or destruction. This prevents emissions of high-GWP gases and keeps the gas traceable.

  7. Question 7F-gas and ODS regulations, legal duties and environmental impact

    Which of these substances is a fluorinated greenhouse gas controlled by the F-gas Regulation?

    1. Carbon dioxide (R-744)
    2. Ammonia (R-717)
    3. Propane (R-290)
    4. R-134a Correct answer.

    Explanation

    R-134a is an HFC and is a fluorinated greenhouse gas listed as an F-gas. Ammonia, carbon dioxide and propane are natural refrigerants and are not controlled as F-gases.

  8. Question 8F-gas and ODS regulations, legal duties and environmental impact

    What does ODP measure?

    1. Its pressure in a cylinder
    2. Its ozone-destroying ability Correct answer.
    3. Its toxicity to humans
    4. Its flammability rating

    Explanation

    ODP compares a substance's ozone-destroying effect with that of CFC-11, which is assigned an ODP of 1. It is separate from GWP, which measures climate impact.

  9. Question 9F-gas and ODS regulations, legal duties and environmental impact

    A system contains 10 kg of R-410A with a GWP of 2088. What is the charge expressed in tonnes of CO2 equivalent?

    1. 2.09 tCO2e
    2. 208.8 tCO2e
    3. 0.21 tCO2e
    4. 20.88 tCO2e Correct answer.

    Explanation

    Multiply the mass in kilograms by the GWP and divide by 1000: 10 × 2088 ÷ 1000 = 20.88 tCO2e. This figure determines which leak-check frequency and record-keeping duties apply.

  10. Question 10F-gas and ODS regulations, legal duties and environmental impact

    Equipment has a charge of 60 tCO2e. How often must statutory leak checks be carried out?

    1. Every three months
    2. Every two years
    3. Every six months Correct answer.
    4. Every twelve months

    Explanation

    At 50 tCO2e or more but below 500 tCO2e, leak checks are required at least every six months. A certified leak detection system would allow the interval to be doubled to twelve months.

  11. Question 11F-gas and ODS regulations, legal duties and environmental impact

    A system containing 600 tCO2e has a fixed leak detection system installed and operating. What is the maximum interval between manual leak checks?

    1. Every three months
    2. Every twelve months
    3. Every month
    4. Every six months Correct answer.

    Explanation

    At 500 tCO2e or more a leak detection system is mandatory, and manual checks must be at least every six months when it is fitted. Without a detection system the interval is three months.

  12. Question 12F-gas and ODS regulations, legal duties and environmental impact

    Who is legally permitted to carry out leak checks on stationary F-gas refrigeration equipment?

    1. A certified F-gas handler Correct answer.
    2. A general building contractor
    3. Any competent maintenance technician
    4. The equipment owner without certification

    Explanation

    Leak checking is a regulated activity that must be done by personnel holding the appropriate F-gas certificate, normally through a certified employer. General maintenance staff without F-gas certification cannot perform it.

  13. Question 13F-gas and ODS regulations, legal duties and environmental impact

    What must happen before refrigeration equipment containing F-gas is permanently decommissioned?

    1. The refrigerant must be vented to speed up the process
    2. The equipment must be painted and resold
    3. The circuit must be flushed with water
    4. A certified person must recover the refrigerant Correct answer.

    Explanation

    The operator must ensure refrigerant is recovered before dismantling or disposal, and the recovery must be done by certified personnel. Venting is prohibited and water flushing does not remove the legal duty.

  14. Question 14F-gas and ODS regulations, legal duties and environmental impact

    What is the main environmental concern associated with HFC refrigerants?

    1. They are all highly toxic
    2. They destroy stratospheric ozone
    3. They cause acid rain
    4. They have high global warming potential Correct answer.

    Explanation

    HFCs generally have zero ozone-depletion potential but can have very high GWP, so leaks contribute significantly to climate change. Toxicity and acid rain are not the regulatory reason HFCs are controlled.

  15. Question 15F-gas and ODS regulations, legal duties and environmental impact

    What is the ozone-depletion potential of most HFC refrigerants?

    1. Negative
    2. Greater than 1
    3. Between 0.5 and 1
    4. Zero Correct answer.

    Explanation

    HFCs contain no chlorine or bromine, so their ODP is zero and they do not directly destroy stratospheric ozone. They are controlled because of their global warming potential.

  16. Question 16F-gas and ODS regulations, legal duties and environmental impact

    Which information must be recorded for equipment containing 5 tCO2e or more of F-gas?

    1. Only the equipment serial number
    2. The date of the last service and the technician's name
    3. The gas type and charge, checks and repairs Correct answer.
    4. The purchase price of the gas and its supplier

    Explanation

    Records must show the gas type and charge, leak checks, repairs and gas recovered or added. These records must be kept for at least five years.

  17. Question 17F-gas and ODS regulations, legal duties and environmental impact

    What is the operator's duty when a leak of F-gas is detected?

    1. Wait until the next scheduled maintenance visit
    2. Seal the leak with tape and record it as repaired
    3. Top up the charge and keep the system running
    4. Repair it promptly and verify the repair Correct answer.

    Explanation

    The operator must arrange repair as soon as practicable and then check that the repair has been effective, normally within one month. Simply topping up or delaying repair breaches the leak-control duty.

  18. Question 18F-gas and ODS regulations, legal duties and environmental impact

    Which is a legal requirement for a business that installs or services F-gas equipment?

    1. It must be a member of a trade association
    2. It must hold a company F-gas certificate Correct answer.
    3. It must sell only natural refrigerants
    4. It must employ at least ten engineers

    Explanation

    Companies carrying out regulated F-gas activities must hold the relevant company certification and use certified personnel. Trade association membership and company size are not legal conditions.

  19. Question 19F-gas and ODS regulations, legal duties and environmental impact

    Which statement correctly distinguishes GWP from ODP?

    1. Both measure the same environmental effect
    2. GWP measures ozone destruction and ODP measures climate change
    3. GWP measures climate impact; ODP measures ozone destruction Correct answer.
    4. ODP applies only to HFCs and GWP only to CFCs

    Explanation

    GWP compares a gas's heat-trapping effect with CO2, while ODP compares its ozone-destroying effect with CFC-11. A gas can have a high GWP and zero ODP, as most HFCs do.

  20. Question 20F-gas and ODS regulations, legal duties and environmental impact

    What must appear on a label for an F-gas container placed on the market?

    1. The gas, its GWP and CO2e mass Correct answer.
    2. The date of manufacture and the test pressure
    3. The cylinder colour code and the tare weight
    4. The supplier's name, address and telephone number

    Explanation

    Containers must be labelled to say they contain fluorinated greenhouse gases, with the GWP and the quantity expressed in CO2 equivalent. This supports traceability and safe handling.

  21. Question 21F-gas and ODS regulations, legal duties and environmental impact

    Under the HFC phase-down, what percentage of the baseline is the 2030 target for placing HFCs on the market?

    1. 21% Correct answer.
    2. 100%
    3. 63%
    4. 45%

    Explanation

    The phase-down steps reduce the HFC quota from the baseline to 21% by 2030. The 45% step applies from 2021 and the 63% step from 2018.

  22. Question 22F-gas and ODS regulations, legal duties and environmental impact

    A system contains 3 kg of R-404A with a GWP of 3922. What is the charge in tCO2e and the minimum leak-check frequency?

    1. 117.7 tCO2e and every 3 months
    2. 11.77 tCO2e and every 6 months
    3. 11.77 tCO2e and every 12 months Correct answer.
    4. 1.18 tCO2e and every 12 months

    Explanation

    3 × 3922 ÷ 1000 = 11.766 tCO2e, which is at least 5 but below 50 tCO2e, so checks are due every 12 months. The six-month interval starts at 50 tCO2e.

  23. Question 23F-gas and ODS regulations, legal duties and environmental impact

    A switchgear unit contains 0.5 kg of SF6 with a GWP of 22,800. What is the CO2 equivalent charge?

    1. 0.0114 tCO2e
    2. 1.14 tCO2e
    3. 114 tCO2e
    4. 11.4 tCO2e Correct answer.

    Explanation

    0.5 × 22,800 ÷ 1000 = 11.4 tCO2e. This exceeds 5 tCO2e, so leak checks and records are required for the equipment.

  24. Question 24F-gas and ODS regulations, legal duties and environmental impact

    What is the correct fate of R-22 recovered from an old refrigeration system in the UK?

    1. It may be reused indefinitely in any refrigeration system
    2. It may be topped up with HFCs and kept in service
    3. It may be vented to atmosphere if the system is outdoors
    4. It must be recovered and destroyed by an approved process Correct answer.

    Explanation

    R-22 is an HCFC controlled as an ODS, and the UK no longer permits its use for maintenance, so recovered R-22 must be destroyed by an approved facility. Mixing it with HFCs would also create an illegal and unrecorded refrigerant.

  25. Question 25F-gas and ODS regulations, legal duties and environmental impact

    In F-gas law, what does 'placing on the market' mean?

    1. Operating the equipment after installation
    2. Installing the equipment at the end user's site
    3. Recovering gas during decommissioning
    4. Supplying or making it available to another party Correct answer.

    Explanation

    Placing on the market covers supplying or making available the product or gas to another party, whether paid for or free. It is distinct from installing, operating or decommissioning the equipment.

  26. Question 26F-gas and ODS regulations, legal duties and environmental impact

    Which of these actions is prohibited under F-gas legislation when handling a refrigerant that contains HFCs?

    1. Returning recovered refrigerant to a certified reclamation facility
    2. Releasing the refrigerant into the atmosphere after servicing Correct answer.
    3. Storing recovered refrigerant in a suitably rated recovery cylinder
    4. Recycling refrigerant on site for reuse in the same equipment

    Explanation

    The F-gas Regulation bans the deliberate release of fluorinated greenhouse gases into the atmosphere, including during servicing, maintenance and disposal. Recovered gas must be recovered, and then recycled, reclaimed or destroyed by suitably qualified arrangements.

  27. Question 27F-gas and ODS regulations, legal duties and environmental impact

    Which of these refrigerants is controlled as an ozone-depleting substance?

    1. R-744
    2. R-22 Correct answer.
    3. R-134a
    4. R-410A

    Explanation

    R-22 is HCFC-22, a hydrochlorofluorocarbon that contains chlorine and therefore has a measurable ozone-depletion potential. Its production and use are controlled under the ODS Regulation, and it is not an HFC.

  28. Question 28F-gas and ODS regulations, legal duties and environmental impact

    In F-gas legislation, who is the 'operator' of stationary refrigeration equipment?

    1. The business controlling its technical operation Correct answer.
    2. The wholesaler that supplied the original refrigerant charge
    3. The manufacturer that assembled and supplied the compressor
    4. The technician who carries out the scheduled leak checks

    Explanation

    The operator is the natural or legal person who has actual control over the day-to-day technical functioning of the equipment. Legal duties such as leak checks, record keeping and repair therefore sit with the operator, not with the servicing contractor.

  29. Question 29F-gas and ODS regulations, legal duties and environmental impact

    For how long must an operator keep the F-gas records for stationary refrigeration equipment?

    1. 5 years Correct answer.
    2. 3 years
    3. 10 years
    4. 1 year

    Explanation

    Records of leak checks, repairs, refrigerant added and recovery must be retained for at least five years. They must be made available to the competent authority on request.

  30. Question 30F-gas and ODS regulations, legal duties and environmental impact

    Above which charge, in tonnes of CO2 equivalent, does stationary refrigeration equipment first become subject to statutory leak checks?

    1. 500 tCO2e
    2. 1 tCO2e
    3. 5 tCO2e Correct answer.
    4. 50 tCO2e

    Explanation

    The leak-check obligation starts at a charge of 5 tonnes CO2 equivalent. Below that threshold the equipment must still be operated so as to avoid leakage, and gas must still be recovered, but periodic statutory checks are not required.

  31. Question 31F-gas and ODS regulations, legal duties and environmental impact

    A leak on a commercial refrigeration system has just been repaired. Within what period must the follow-up leak check be carried out?

    1. Before the system is restarted
    2. Within seven days of the repair
    3. By the next scheduled annual check
    4. Within one month of the repair Correct answer.

    Explanation

    After a leak has been repaired, the operator must ensure a follow-up check is carried out within one month to confirm the repair has been effective. The repair itself must be completed without undue delay.

  32. Question 32F-gas and ODS regulations, legal duties and environmental impact

    A firm wants to start installing and servicing split air-conditioning units containing HFCs. What authorisation does the firm itself need?

    1. A personal certificate held by the managing director
    2. A company certificate covering the relevant activities Correct answer.
    3. A waste carrier registration for recovered refrigerant
    4. A refrigerant purchase licence issued by the supplier

    Explanation

    Businesses that install, service, maintain or decommission F-gas equipment must hold a company certificate covering those activities. The technicians who actually handle the refrigerant must separately hold the appropriate personal qualification.

  33. Question 33F-gas and ODS regulations, legal duties and environmental impact

    Under the ODS Regulation, what is the position on using recycled HCFC-22 to service existing refrigeration equipment?

    1. It is allowed if the equipment was installed before 2000
    2. It is allowed for a further ten years under a phase-out quota
    3. It is allowed provided the technician records the quantity used
    4. It is prohibited, including the use of recycled or reclaimed material Correct answer.

    Explanation

    The use of virgin and recycled HCFCs for servicing and maintenance was banned once the phase-out took effect. Recovered R-22 must therefore be recovered and then destroyed or reclaimed for feedstock-type uses permitted by the Regulation, not used to recharge systems.

  34. Question 34F-gas and ODS regulations, legal duties and environmental impact

    Which GWP values must be used when calculating the CO2 equivalent charge of an F-gas system?

    1. The values given in the latest IPCC assessment report
    2. The values published by the refrigerant manufacturer on the cylinder
    3. The highest value published for any blend component
    4. The values listed in the Annexes to the F-gas Regulation Correct answer.

    Explanation

    Calculations must use the GWP values set out in the Annexes to the Regulation, which are based on the IPCC Fourth Assessment Report 100-year values. Using a different published figure can change the CO2 equivalent charge and therefore the applicable obligations.

  35. Question 35F-gas and ODS regulations, legal duties and environmental impact

    Which detail must be shown on the label of a new stationary refrigeration unit charged with an HFC?

    1. The charge in tonnes of CO2 equivalent and the GWP Correct answer.
    2. The date of the next scheduled leak check
    3. The name of the technician who carried out commissioning
    4. The pressure test certificate number

    Explanation

    Equipment containing F-gases must be labelled with the refrigerant designation and, where required, the charge expressed in CO2 equivalent together with the GWP. The label must be legible and durable and must remain on the equipment.

  36. Question 36F-gas and ODS regulations, legal duties and environmental impact

    Equipment has an automatic leak detection system fitted. How often must the system itself be checked for correct operation?

    1. Every five years
    2. Only when a leak alarm is triggered
    3. At least every 12 months Correct answer.
    4. Every three months

    Explanation

    Where a leak detection system is installed, the operator must ensure it is checked for proper functioning at least once every 12 months. The detection system allows the leak-check interval for the equipment itself to be extended, so its reliability matters.

  37. Question 37F-gas and ODS regulations, legal duties and environmental impact

    The HFC phase-down baseline is calculated from the average annual HFC placed on the market during which period?

    1. 2015 to 2018
    2. 2005 to 2008
    3. 1990 to 1995
    4. 2009 to 2012 Correct answer.

    Explanation

    The baseline is the average quantity of HFCs placed on the market each year over 2009 to 2012, expressed in CO2 equivalent. Future annual limits are then set as percentages of that baseline.

  38. Question 38F-gas and ODS regulations, legal duties and environmental impact

    Since 1 January 2015, which equipment could no longer be placed on the market if it contained HFCs with a GWP of 150 or more?

    1. Domestic refrigerators and freezers Correct answer.
    2. Transport refrigeration units for lorries
    3. Stationary fire protection systems
    4. Industrial process chillers over 500 kW

    Explanation

    Placing domestic refrigerators and freezers containing HFCs with a GWP of 150 or more on the market has been prohibited since 1 January 2015. The ban applies to the equipment being placed on the market, not to equipment already in service.

  39. Question 39F-gas and ODS regulations, legal duties and environmental impact

    The HFC quota system under the F-gas Regulation applies directly to which activity?

    1. Exporting HFC-containing equipment to another country
    2. Charging a new split unit with pre-filled HFC
    3. Importing bulk HFCs into the country for sale Correct answer.
    4. Servicing a refrigeration system with reclaimed HFC

    Explanation

    The quota limits the total CO2 equivalent of bulk HFCs that producers and importers may place on the market each year. Companies must be registered and hold sufficient quota before such bulk supply can lawfully take place.

  40. Question 40F-gas and ODS regulations, legal duties and environmental impact

    From 1 January 2017, new cars could only be placed on the market if their mobile air-conditioning system used a refrigerant with what maximum GWP?

    1. 750 or less
    2. 150 or less Correct answer.
    3. Zero
    4. 75 or less

    Explanation

    Mobile air-conditioning in new vehicles has been restricted to refrigerants with a GWP of no more than 150 since 1 January 2017. This is why R-134a, with a GWP of 1430, was replaced by R-1234yf in new car platforms.

  41. Question 41Refrigerant safety, cylinder handling, PPE and risk assessment

    Which type of glove is appropriate when handling refrigerant cylinders and making connections?

    1. Low-temperature insulating gloves Correct answer.
    2. Heavy duty leather rigging gloves
    3. General purpose cotton handling gloves
    4. Disposable nitrile examination gloves

    Explanation

    Liquid refrigerant boils at a very low temperature, so contact with skin, a cold valve or escaping liquid can cause cryogenic burns. Gloves designed for low-temperature work provide thermal insulation while remaining flexible enough to handle valves and gauges.

  42. Question 42Refrigerant safety, cylinder handling, PPE and risk assessment

    What eye protection should be worn where there is a risk of liquid refrigerant spraying during a task?

    1. Tinted welding goggles
    2. Standard safety spectacles with side shields
    3. Chemical splash goggles and a face shield Correct answer.
    4. Prescription glasses on their own

    Explanation

    A refrigerant splash can cause severe cold burns to the eye and surrounding skin. Goggles seal around the eye to stop liquid reaching it, and a face shield protects the rest of the face from a sudden release.

  43. Question 43Refrigerant safety, cylinder handling, PPE and risk assessment

    How should refrigerant cylinders be kept in a workshop?

    1. Laid horizontally on racking to save space
    2. In a sealed cupboard to keep them dry
    3. Upright, secured, in a well ventilated area Correct answer.
    4. Stacked no more than three high on the floor

    Explanation

    Cylinders are stored upright so that the valve stays at the top and liquid cannot enter the valve or regulator. They must be restrained to prevent falling and kept in a ventilated place so any leakage disperses rather than accumulating.

  44. Question 44Refrigerant safety, cylinder handling, PPE and risk assessment

    What is the purpose of the valve protection cap fitted to a refrigerant cylinder?

    1. It shields the valve from impact damage Correct answer.
    2. It seals the valve thread to prevent leaks
    3. It shows the cylinder has been inspected
    4. It allows the cylinder to be lifted by crane

    Explanation

    The cap is a mechanical guard, not a pressure seal. If a cylinder falls, an unguarded valve can be sheared off and release the full charge violently, so the cap must be in place whenever the cylinder is in storage or transit.

  45. Question 45Refrigerant safety, cylinder handling, PPE and risk assessment

    Why is refrigerant vapour a particular hazard in low-lying areas such as pits and basements?

    1. It rises quickly and collects at ceiling level
    2. It reacts with concrete to form a toxic gas
    3. It is lighter than air and disperses slowly
    4. It is heavier than air and can accumulate Correct answer.

    Explanation

    Most refrigerant vapours are denser than air, so they sink and pool in the lowest part of a space. In a basement or pit this can produce an oxygen-deficient atmosphere at the exact place where an engineer is working.

  46. Question 46Refrigerant safety, cylinder handling, PPE and risk assessment

    What is the correct first aid for skin that has been splashed with liquid refrigerant?

    1. Flush with lukewarm water and get medical help Correct answer.
    2. Apply a hot compress and cover with a dressing
    3. Wash with solvent then apply a sterile dressing
    4. Rub the area briskly to restore circulation

    Explanation

    Liquid refrigerant causes cold burns by freezing tissue, so the affected area should be flushed gently with lukewarm water to rewarm it slowly. Rubbing damages frozen tissue, and medical assessment is needed because the depth of a cold burn is not always obvious at first.

  47. Question 47Refrigerant safety, cylinder handling, PPE and risk assessment

    What is the main purpose of a risk assessment for a refrigerant task?

    1. To identify hazards and decide on controls Correct answer.
    2. To show that the work can be completed quickly
    3. To provide a written record for the client file
    4. To confirm that the engineer holds a qualification

    Explanation

    A risk assessment is a structured look at what could cause harm and how likely that is, followed by a decision on the controls needed. The written record exists to communicate and review those decisions, not to satisfy paperwork.

  48. Question 48Refrigerant safety, cylinder handling, PPE and risk assessment

    Which document should be consulted first for hazard, first aid and handling information on a particular refrigerant?

    1. The refrigerant pressure-enthalpy chart
    2. The cylinder test certificate
    3. The manufacturer's safety data sheet Correct answer.
    4. The site emergency evacuation plan

    Explanation

    The safety data sheet is the supplier's formal summary of the hazards of the substance, together with first aid, handling, storage and exposure information. It should be available before the refrigerant is used and kept where workers can reach it.

  49. Question 49Refrigerant safety, cylinder handling, PPE and risk assessment

    When recovering liquid refrigerant into a recovery cylinder, what is the maximum fill level by weight?

    1. 80% of its capacity by weight Correct answer.
    2. 50% of its capacity by weight
    3. 95% of its capacity by weight
    4. 100% of its capacity by weight

    Explanation

    Liquid refrigerant expands as it warms, so a cylinder filled to capacity could become hydraulically full and rupture. Filling to about 80% leaves an ullage space for expansion, and the cylinder must be weighed during filling.

  50. Question 50Refrigerant safety, cylinder handling, PPE and risk assessment

    Which practice is acceptable when a refrigerant cylinder needs to be warmed to speed up transfer?

    1. Placing it beside a space heater running at full output
    2. Wrapping it in an unregulated heat mat
    3. Playing a blowtorch over the cylinder base
    4. Using a warm water bath at a controlled temperature Correct answer.

    Explanation

    Warming raises the cylinder pressure, but the heat must be gentle and controlled. A warm water bath with a thermometer keeps the cylinder within its permitted temperature, while flames and uncontrolled heaters can overpressure it.

  51. Question 51Refrigerant safety, cylinder handling, PPE and risk assessment

    How should refrigerant cylinders be carried in a service van?

    1. In the cab, secured with a seat belt, to prevent theft
    2. Stacked in a closed locker to keep them out of sunlight
    3. Upright and secured, with the load space ventilated Correct answer.
    4. Lying flat in the load space with the valve caps fitted

    Explanation

    Cylinders carried upright with the valve uppermost and restrained cannot roll or fall and are less likely to discharge liquid into the valve. Ventilation of the load space means that a leaking cylinder cannot build up a dangerous concentration during the journey.

  52. Question 52Refrigerant safety, cylinder handling, PPE and risk assessment

    Why does a basement plant room present a higher risk from a refrigerant leak than a ground floor room?

    1. Refrigerant reacts with damp basement air to form acid
    2. Pressure relief valves discharge more readily underground
    3. Basements are always warmer than the rest of the building
    4. Vapour can collect there and displace breathing air Correct answer.

    Explanation

    Because refrigerant vapour is denser than air, it drains into low spaces and cannot easily escape. In a basement the concentration can rise until oxygen is displaced to a level that causes rapid loss of consciousness.

  53. Question 53Refrigerant safety, cylinder handling, PPE and risk assessment

    In the hierarchy of risk control, which measure should be considered first?

    1. Training staff in the task
    2. Providing written safe systems of work
    3. Eliminating the hazard Correct answer.
    4. Issuing suitable personal protective equipment

    Explanation

    The hierarchy starts with removing the hazard altogether, then substituting something less hazardous, then engineering controls, then administrative measures, with personal protective equipment last. Controls at the top of the hierarchy protect everyone and do not depend on individual behaviour.

  54. Question 54Refrigerant safety, cylinder handling, PPE and risk assessment

    Before starting work on a system containing a flammable A2L refrigerant, which precaution applies?

    1. Purge the system with oxygen before brazing
    2. Remove ignition sources and use gas detection Correct answer.
    3. Work alone to reduce the number of people exposed
    4. Increase the charge to improve leak detection

    Explanation

    A2L refrigerants are mildly flammable, so any source of ignition in the work area must be controlled and a suitable gas detector used to warn of a release. The risk assessment must also consider ventilation and the quantity of charge present.

  55. Question 55Refrigerant safety, cylinder handling, PPE and risk assessment

    What must be done to pipework that has contained refrigerant before brazing it?

    1. Open the circuit and let it vent while brazing
    2. Loosen the valve caps so pressure can escape
    3. Recover the refrigerant and purge with nitrogen Correct answer.
    4. Blow through with compressed air from the workshop line

    Explanation

    Refrigerant must be recovered first so that no residual gas can decompose into toxic products when heated or cause a pressure rise. A nitrogen purge then keeps oxygen away from the inside of the pipe while it is hot.

  56. Question 56Refrigerant safety, cylinder handling, PPE and risk assessment

    A workplace exposure limit for a refrigerant is normally stated as an average concentration over which period?

    1. An eight hour reference period Correct answer.
    2. A four hour working shift
    3. A one hour sampling period
    4. A fifteen minute working period

    Explanation

    A long-term workplace exposure limit is expressed as a time-weighted average over an eight hour reference period, reflecting a normal working shift. Some substances also have a short-term limit averaged over fifteen minutes for peak exposures.

  57. Question 57Refrigerant safety, cylinder handling, PPE and risk assessment

    Liquid refrigerant splashes into an engineer's eye. What should be done first?

    1. Wipe the eye with a dry tissue to remove the liquid
    2. Irrigate with clean water for at least 15 minutes Correct answer.
    3. Ask the engineer to blink rapidly for two minutes
    4. Apply an eye ointment and cover the eye with a pad

    Explanation

    Immediate and prolonged irrigation with clean water is the priority because it removes the refrigerant and warms the frozen tissue. Medical help must then be arranged even if the eye appears to recover, because cold burns can worsen over time.

  58. Question 58Refrigerant safety, cylinder handling, PPE and risk assessment

    A refrigerant cylinder is dropped and its valve is visibly bent. What is the correct action?

    1. Transfer the contents to another cylinder indoors
    2. Quarantine it, label it and report it as damaged Correct answer.
    3. Straighten the valve and use the cylinder as normal
    4. Return it to the vehicle and continue the job

    Explanation

    A bent valve may be cracked or partly sheared and could fail without warning, so the cylinder must be taken out of use. It should be isolated, clearly labelled as damaged and returned to the supplier for assessment rather than handled further.

  59. Question 59Refrigerant safety, cylinder handling, PPE and risk assessment

    What is the preferred way to move a large refrigerant cylinder up a short flight of steps?

    1. Drag it by the valve cap with a strap
    2. Use a trolley or get a second person to help Correct answer.
    3. Roll it up the steps on its side
    4. Lift it alone using a firm grip on the valve

    Explanation

    Cylinders are heavy and awkward, so mechanical aids or a team lift should be used wherever the load cannot be handled safely by one person. The valve and cap must never be used as lifting or pulling points.

  60. Question 60Refrigerant safety, cylinder handling, PPE and risk assessment

    What must a risk assessment for lone working on refrigeration plant address?

    1. How help will be summoned if the engineer is injured Correct answer.
    2. Only whether the engineer has a mobile phone
    3. Whether the client will sign the job sheet
    4. The cost of the call-out and travel time

    Explanation

    Lone workers cannot rely on a colleague to raise the alarm, so the assessment must cover how an emergency is detected and how assistance reaches them. It should also consider the nature of the task, the site's communication coverage and any check-in arrangements.

  61. Question 61Refrigerant safety, cylinder handling, PPE and risk assessment

    A large refrigerant leak occurs in a basement plant room while you are working there. What is the correct immediate sequence of actions?

    1. Ventilate the room, then search for the leak source
    2. Raise the alarm, evacuate, then isolate and ventilate Correct answer.
    3. Isolate the leak, then ventilate, then evacuate if needed
    4. Continue working while monitoring the gas detector

    Explanation

    Life safety comes first: warn others, get out of the contaminated space and call for help, then deal with the plant only if it is safe to do so. Isolation and ventilation reduce the hazard for those who subsequently enter, and no one should re-enter without suitable protection.

  62. Question 62Refrigerant safety, cylinder handling, PPE and risk assessment

    Why is the tare weight marked on a refrigerant cylinder important when filling by weight?

    1. It gives the date of the last periodic inspection
    2. It confirms that the cylinder is safe to transport by road
    3. It shows the maximum pressure the cylinder can hold
    4. It allows the refrigerant content to be calculated Correct answer.

    Explanation

    The tare weight is the empty weight of the cylinder, so subtracting it from the total on the scales gives the mass of refrigerant inside. This is how the fill is controlled to stay within the permitted limit for the cylinder.

  63. Question 63Refrigerant safety, cylinder handling, PPE and risk assessment

    At what oxygen level in air is an oxygen depletion monitor in a plant room normally set to alarm?

    1. 19.5% by volume Correct answer.
    2. 17.0% by volume
    3. 20.9% by volume
    4. 23.5% by volume

    Explanation

    Normal air contains about 20.9% oxygen by volume, and an alarm set at 19.5% gives warning before impairment occurs. Setting the alarm at the normal level would cause constant nuisance alarms, while 17% is already low enough to affect judgement and coordination.

  64. Question 64Refrigerant safety, cylinder handling, PPE and risk assessment

    Which control most reduces the risk from a slow refrigerant leak in a basement plant room?

    1. Mechanical ventilation interlocked with gas detection Correct answer.
    2. Fitting a leak alarm that sounds in the plant room
    3. Supplying engineers with full face respiratory protection
    4. Displaying warning signs on the plant room door

    Explanation

    An engineering control that removes the hazard at source ranks above alarms, signs and personal protection in the hierarchy of control. Extract ventilation at low level, started automatically by detection, keeps the concentration down whether or not anyone is wearing protective equipment.

  65. Question 65Refrigerant safety, cylinder handling, PPE and risk assessment

    When charging a system with a flammable refrigerant, why should equipment and cylinders be bonded and earthed?

    1. To stop the cylinder from becoming magnetised
    2. To improve the accuracy of the charging scales
    3. To prevent static sparks that could ignite the gas Correct answer.
    4. To reduce the pressure inside the recovery cylinder

    Explanation

    Flowing refrigerant and uncharged pipework can accumulate static electricity, and a spark has enough energy to ignite a flammable refrigerant. Bonding and earthing give a continuous path to earth so that charge cannot build up during charging operations.

  66. Question 66Refrigerant safety, cylinder handling, PPE and risk assessment

    Which items of personal protective equipment are essential when transferring liquid refrigerant between cylinders?

    1. Steel-toe boots and a high-visibility vest
    2. A high-visibility vest and a cotton dust mask
    3. Insulating gloves and a face shield Correct answer.
    4. A disposable paper dust mask and safety glasses

    Explanation

    Liquid refrigerant is at a very low temperature and can cause cold burns and eye damage if it sprays or splashes. Insulating gloves protect the hands, and a face shield protects the eyes and face during transfer. The risk assessment and safety data sheet should confirm the final PPE selection for the task.

  67. Question 67Refrigerant safety, cylinder handling, PPE and risk assessment

    What should be fitted to a refrigerant cylinder when it is not connected for use?

    1. The valve protection cap or guard Correct answer.
    2. A spare pressure gauge fitted to the outlet
    3. A locking chain wrapped around the valve
    4. A plastic dust bag tied over the valve

    Explanation

    The valve protection cap or guard is designed to protect the valve from impact during storage and handling. A damaged valve can release refrigerant rapidly and turn the cylinder into a projectile. The cap or guard should be replaced whenever the cylinder is disconnected.

  68. Question 68Refrigerant safety, cylinder handling, PPE and risk assessment

    A refrigerant cylinder label shows a flame pictogram. What does this indicate about the contents?

    1. The contents are toxic if inhaled
    2. The gas is flammable Correct answer.
    3. The contents are stored under vacuum
    4. The contents are corrosive to copper

    Explanation

    The flame pictogram is the hazard symbol for a flammable substance. It warns that the refrigerant can ignite if it mixes with air and meets an ignition source. It does not by itself indicate toxicity, corrosiveness or that the cylinder is under vacuum.

  69. Question 69Refrigerant safety, cylinder handling, PPE and risk assessment

    How should refrigerant cylinders be stored in a workshop?

    1. In a sealed cupboard so that leaks are contained
    2. Lying flat under a workbench to save space
    3. Next to a space heater to stop valves freezing
    4. Upright and secured, in a well-ventilated area Correct answer.

    Explanation

    Cylinders should be stored upright and secured so they cannot fall, in an area with good ventilation to disperse any leakage. Heat sources must be avoided because they raise cylinder pressure and can lead to relief valve discharge. A sealed cupboard is unsuitable because leaking refrigerant could accumulate.

  70. Question 70Refrigerant safety, cylinder handling, PPE and risk assessment

    What is the safest way to move a refrigerant cylinder across a workshop floor?

    1. Use a cylinder trolley and secure the cylinder to it Correct answer.
    2. Roll the cylinder on its side while guiding it by hand
    3. Carry it by the valve guard with both hands
    4. Drag it by a strap attached to the valve

    Explanation

    A cylinder trolley with a securing strap keeps the cylinder upright and under control during movement. Manual carrying or rolling exposes the valve to impact and increases the risk of muscle strain. The valve guard is not a lifting handle.

  71. Question 71Refrigerant safety, cylinder handling, PPE and risk assessment

    When should a risk assessment for a refrigerant task be reviewed?

    1. When the task or conditions change Correct answer.
    2. Once every five years regardless of changes
    3. Only after an accident has occurred
    4. Only when a new employee joins the company

    Explanation

    A risk assessment is a living document and must be reviewed whenever the task, equipment, personnel or working conditions change. It should also be reviewed after an incident or near miss. A fixed five-year interval alone is not sufficient if circumstances change.

  72. Question 72Refrigerant safety, cylinder handling, PPE and risk assessment

    A person becomes dizzy after breathing refrigerant vapour in a plant room. What should be done first?

    1. Give them a hot drink and tell them to rest
    2. Lay them flat and apply a cold compress
    3. Ask them to breathe into a paper bag
    4. Move them to fresh air and call for help Correct answer.

    Explanation

    The priority is to remove the person from exposure to the vapour and obtain medical help. Rescuers should only enter the area if it is safe to do so and should use appropriate respiratory protection if needed. Food, drink and home remedies should not delay removal from exposure.

  73. Question 73Refrigerant safety, cylinder handling, PPE and risk assessment

    Before using a face shield for refrigerant work, what should you check?

    1. That it carries the refrigerant hazard label
    2. That it is clean, undamaged and fits correctly Correct answer.
    3. That it is stored in a sealed plastic bag
    4. That it has a current calibration certificate

    Explanation

    PPE must be inspected before use to confirm it is clean, free from cracks or scratches and fits the wearer correctly. Damaged PPE may fail when it is needed, so it should be replaced. Calibration certificates and hazard labels apply to instruments and containers, not face shields.

  74. Question 74Refrigerant safety, cylinder handling, PPE and risk assessment

    How should you deal with an unlabelled refrigerant cylinder found in a workshop?

    1. Compare the pressure with a generic chart
    2. Rely on the colour of the cylinder shoulder
    3. Quarantine it and have the contents analysed Correct answer.
    4. Smell the gas escaping from the valve

    Explanation

    An unlabelled cylinder must not be used because its contents and safe handling requirements are unknown. It should be isolated and identified by a competent person using analysis or other reliable means. Smell, colour and pressure alone cannot reliably identify a refrigerant.

  75. Question 75Refrigerant safety, cylinder handling, PPE and risk assessment

    Which gas should be used to pressure-test a refrigerant system?

    1. Oxygen-free nitrogen Correct answer.
    2. Carbon dioxide from a fire extinguisher
    3. Compressed air from a workshop compressor
    4. Oxygen from a welding cylinder

    Explanation

    Oxygen-free nitrogen is dry and inert, making it suitable for pressure testing without contaminating the system. Compressed air can introduce moisture or oil, and oxygen can support combustion and react dangerously with system oil. Carbon dioxide is not a suitable test gas for refrigerant systems.

  76. Question 76Refrigerant safety, cylinder handling, PPE and risk assessment

    A refrigerant cylinder has a leaking pressure relief device. What is the correct action?

    1. Paint over the relief device so that the leak is sealed
    2. Warm the cylinder gently until the relief valve reseats
    3. Keep people away, ventilate the area and seek advice Correct answer.
    4. Fit a brass blanking cap over the relief device to stop the leak

    Explanation

    The pressure relief device is a safety feature and must never be blocked or altered. A leaking relief device indicates that the cylinder is under abnormal pressure or is faulty, so the area should be ventilated and people kept away while expert help is obtained. The cylinder should be treated as defective.

  77. Question 77Refrigerant safety, cylinder handling, PPE and risk assessment

    A plant room has no permanent ventilation and is reached by a fixed ladder. Which risk assessment finding is most significant for refrigerant work?

    1. The plant room door may be the wrong colour
    2. The access ladder may need a new coat of paint
    3. The floor may be slightly uneven near the door
    4. A refrigerant leak could accumulate and displace oxygen Correct answer.

    Explanation

    Refrigerant vapour is heavier than air and can collect in low-lying spaces with poor ventilation, displacing oxygen. This creates a serious risk of asphyxiation for anyone entering the plant room. The other findings are minor cosmetic or housekeeping issues by comparison.

  78. Question 78Refrigerant safety, cylinder handling, PPE and risk assessment

    You arrive to recover refrigerant and find the plant room much hotter than expected and a strong smell of refrigerant. What is the correct action?

    1. Continue quickly so the exposure time is reduced
    2. Open a window and carry on with the recovery
    3. Increase the recovery rate to finish sooner
    4. Stop work, withdraw, and reassess the risks Correct answer.

    Explanation

    A strong smell of refrigerant and unexpectedly hot conditions are changes that invalidate the original risk assessment. Work should stop, the area should be withdrawn from and the risks reassessed before any further activity. Continuing or speeding up the job increases the chance of exposure or ignition.

  79. Question 79Refrigerant safety, cylinder handling, PPE and risk assessment

    A recovery cylinder has no visible test date. What should you do?

    1. Use it if it feels unusually light when empty
    2. Quarantine it until its test status is confirmed Correct answer.
    3. Use it only for flammable A2L refrigerants
    4. Mark the current date on the cylinder and use it

    Explanation

    A cylinder without a confirmed test date must not be used because its pressure integrity is unknown. It should be quarantined and its test status confirmed by a competent person before any filling. Adding a date yourself does not make the cylinder safe.

  80. Question 80Refrigerant safety, cylinder handling, PPE and risk assessment

    A refrigerant cylinder left in direct summer sunlight has become hot and its internal pressure has risen noticeably. What is the correct action?

    1. Move the cylinder to a shaded, well-ventilated area and let it cool Correct answer.
    2. Continue using the cylinder, because cylinders are designed to withstand high ambient temperatures
    3. Lay the cylinder on its side in the shade so that the pressure drops
    4. Vent refrigerant to atmosphere until the pressure falls back to normal

    Explanation

    Refrigerant cylinders should be kept out of direct sunlight and away from other heat sources, because rising temperature raises internal pressure and can cause the relief device to lift or the cylinder to fail. The correct response is to remove the heat source, moving the cylinder to a shaded, well-ventilated place and allowing it to cool naturally. Refrigerant must never be deliberately vented to reduce pressure, and a hot cylinder should not be used until it has cooled.

  81. Question 81Leak checking, containment, record keeping and reporting obligations

    For how long must an operator keep records relating to equipment containing fluorinated greenhouse gases?

    1. Ten years
    2. Five years Correct answer.
    3. Three years
    4. One year

    Explanation

    Records for equipment subject to leak checks must be kept for at least five years. This allows the regulator to verify leak checks, gas movements and servicing history. The five-year period applies to each record entry.

  82. Question 82Leak checking, containment, record keeping and reporting obligations

    At what minimum CO2 equivalent charge does equipment first become subject to leak checks and record keeping under the F-gas rules?

    1. 5 tonnes CO2e Correct answer.
    2. 1 tonne CO2e
    3. 50 tonnes CO2e
    4. 10 tonnes CO2e

    Explanation

    The general threshold is 5 tonnes CO2 equivalent. Equipment below that charge is outside the routine leak-check and record-keeping regime. Hermetically sealed equipment has a separate 10-tonne threshold.

  83. Question 83Leak checking, containment, record keeping and reporting obligations

    What is the standard leak-check interval for equipment containing between 5 and 50 tonnes CO2e when no automatic leak detection system is fitted?

    1. Every 6 months
    2. Every 3 months
    3. Every 12 months Correct answer.
    4. Every 24 months

    Explanation

    For the 5–50 tonnes CO2e band the standard interval is at least once every 12 months. The interval can be extended to 24 months only where a qualifying leak detection system is installed. More frequent checks apply above 50 tonnes.

  84. Question 84Leak checking, containment, record keeping and reporting obligations

    At what CO2e charge does it become mandatory to install an automatic leak detection system?

    1. 50 tonnes CO2e
    2. 500 tonnes CO2e Correct answer.
    3. 250 tonnes CO2e
    4. 100 tonnes CO2e

    Explanation

    Automatic leak detection is mandatory for equipment containing 500 tonnes CO2e or more. The system allows the leak-check interval to be doubled. It must also be checked for correct operation at least every 12 months.

  85. Question 85Leak checking, containment, record keeping and reporting obligations

    After a leak has been repaired, within what period must a follow-up leak check be carried out?

    1. Within 24 hours Correct answer.
    2. Within one month
    3. Within 14 days
    4. Within 7 days

    Explanation

    A repair must be verified by a follow-up leak check within 24 hours. This confirms that the repair has been effective. The result of the follow-up check must be recorded.

  86. Question 86Leak checking, containment, record keeping and reporting obligations

    At what CO2e charge does hermetically sealed equipment first become subject to periodic leak checks?

    1. 10 tonnes CO2e Correct answer.
    2. 50 tonnes CO2e
    3. 100 tonnes CO2e
    4. 5 tonnes CO2e

    Explanation

    Hermetically sealed equipment is exempt below 10 tonnes CO2e. From 10 tonnes upwards it must be leak checked, initially every 12 months for the 10–100 tonne band. This is a higher starting threshold than for other equipment.

  87. Question 87Leak checking, containment, record keeping and reporting obligations

    Who is permitted to carry out a periodic leak check on F-gas refrigeration equipment?

    1. Only the original equipment manufacturer
    2. A person holding the appropriate F-gas qualification Correct answer.
    3. Any site employee who has been shown the procedure
    4. The equipment owner, provided they hold insurance

    Explanation

    Leak checking is a certified activity, so the person carrying it out must hold the appropriate F-gas qualification. Company certification is also required for the undertaking carrying out the work. The equipment owner cannot simply authorise an unqualified employee.

  88. Question 88Leak checking, containment, record keeping and reporting obligations

    When must an operator make F-gas records available to the regulator?

    1. Never, because records are confidential
    2. Only after a refrigerant leak has been reported
    3. On request by the competent authority Correct answer.
    4. Only when the equipment is decommissioned

    Explanation

    Operators must make their F-gas records available to the competent authority on request. The records support verification of leak checks, gas movements and compliance. Confidentiality does not override this legal duty.

  89. Question 89Leak checking, containment, record keeping and reporting obligations

    What is the standard leak-check interval for equipment containing 50 to 500 tonnes CO2e without an automatic leak detection system?

    1. Every 6 months Correct answer.
    2. Every 12 months
    3. Every 3 months
    4. Every 24 months

    Explanation

    The 50–500 tonne CO2e band requires checks at least every 6 months. If a qualifying automatic leak detection system is fitted, the interval may be extended to 12 months. The 6-month interval is the baseline.

  90. Question 90Leak checking, containment, record keeping and reporting obligations

    What is the leak-check interval for equipment rated at 500 tonnes CO2e or more when a compliant automatic leak detection system is fitted?

    1. Every 12 months
    2. Every 3 months
    3. Every 6 months Correct answer.
    4. Every 24 months

    Explanation

    At 500 tonnes CO2e and above, a leak detection system is mandatory. With a compliant system, checks are required at least every 6 months rather than every 3 months. The system itself must be checked at least every 12 months.

  91. Question 91Leak checking, containment, record keeping and reporting obligations

    What interval applies to equipment in the 5–50 tonnes CO2e band when a compliant automatic leak detection system is installed?

    1. Every 12 months
    2. Every 18 months
    3. Every 6 months
    4. Every 24 months Correct answer.

    Explanation

    Installing a compliant leak detection system doubles the standard interval. For the 5–50 tonne band, the standard 12 months therefore becomes 24 months. The system must be checked at least every 12 months.

  92. Question 92Leak checking, containment, record keeping and reporting obligations

    An R-410A system contains 25 kg of refrigerant. R-410A has a GWP of 2088. Which leak-check interval applies if no leak detection system is fitted?

    1. Every 24 months
    2. Every 6 months Correct answer.
    3. Every 12 months
    4. Every 3 months

    Explanation

    25 kg × 2088 = 52,200 kg CO2e, or 52.2 tonnes CO2e. This falls in the 50–500 tonne band, so checks are required every 6 months. Always convert the charge to CO2e before selecting the interval.

  93. Question 93Leak checking, containment, record keeping and reporting obligations

    A hermetically sealed unit contains 120 tonnes CO2e and has no leak detection system. What leak-check interval applies?

    1. Every 3 months
    2. Every 6 months Correct answer.
    3. Every 12 months
    4. Every 24 months

    Explanation

    For hermetically sealed equipment, the 10–100 tonne band is checked every 12 months and the 100 tonne-plus band every 6 months. At 120 tonnes CO2e the unit is above 100 tonnes, so the 6-month interval applies. A compliant detection system would extend it to 12 months.

  94. Question 94Leak checking, containment, record keeping and reporting obligations

    How often must an automatic leak detection system itself be checked to confirm it is functioning correctly?

    1. Every 3 months
    2. Every 6 months
    3. Every 12 months Correct answer.
    4. Every 24 months

    Explanation

    A leak detection system must be checked for correct operation at least once every 12 months. If it is not checked, the operator cannot rely on it to extend the leak-check interval. The check should be recorded.

  95. Question 95Leak checking, containment, record keeping and reporting obligations

    Which item must be recorded when refrigerant is added to a system after a leak?

    1. The name of the site security guard
    2. The colour of the recovery cylinder
    3. The quantity and type of refrigerant added Correct answer.
    4. The wholesale price of the refrigerant

    Explanation

    Records must show the quantity and type of gas added during maintenance, servicing or because of leakage. This allows the regulator to see gas losses and confirm that leaks are being addressed. The date and reason for the addition should also be traceable.

  96. Question 96Leak checking, containment, record keeping and reporting obligations

    Which activity requires the undertaking carrying it out to hold an F-gas company certificate?

    1. Preparing a quotation for a new cold room
    2. Changing a room thermostat
    3. Cleaning the external condenser fins
    4. Carrying out leak checks on refrigeration equipment Correct answer.

    Explanation

    Leak checking is one of the certificated activities, along with installation, maintenance, servicing, repair and decommissioning. The undertaking must hold company certification and the operative must hold a personal qualification. Non-refrigerant tasks such as cleaning or quoting are not certificated activities.

  97. Question 97Leak checking, containment, record keeping and reporting obligations

    Which information must appear on the label of equipment containing fluorinated greenhouse gases?

    1. Installer's home address
    2. Date of last insurance inspection
    3. Electricity meter reading
    4. Refrigerant type and CO2e charge Correct answer.

    Explanation

    The label must identify the refrigerant and state the quantity expressed as tonnes CO2e. It may also state the GWP of the gas. This helps anyone servicing the equipment to identify the charge and its climate impact.

  98. Question 98Leak checking, containment, record keeping and reporting obligations

    A refrigeration system has three independent circuits, each containing 10 kg of R-410A (GWP 2088). How should the leak-check threshold be applied?

    1. Aggregate to 62.6 tonnes CO2e; check every 6 months
    2. Aggregate to 62.6 tonnes CO2e; check every 3 months
    3. Assess each circuit separately; check every 6 months
    4. Assess each circuit separately; check every 12 months Correct answer.

    Explanation

    Where equipment contains multiple circuits, each circuit is assessed separately for the CO2e thresholds. Each 10 kg R-410A circuit is 10 × 2088 = 20,880 kg CO2e, or about 20.9 tonnes. That places each circuit in the 5–50 tonne band, so the 12-month interval applies.

  99. Question 99Leak checking, containment, record keeping and reporting obligations

    A system contains 30 kg of R-404A (GWP 3922) and 5 kg is added after a leak is repaired. Which leak-check interval applies, and what must be recorded about the addition?

    1. Every 3 months; record the supplier name
    2. Every 6 months; record gas quantity and type Correct answer.
    3. Every 24 months; record the refrigerant cost
    4. Every 12 months; record only the repair date

    Explanation

    30 kg × 3922 = 117,660 kg CO2e, or 117.7 tonnes, which falls in the 50–500 tonne band and requires 6-monthly checks. The 5 kg added must be recorded as the quantity and type of refrigerant added. The record should also show the date and reason for the addition.

  100. Question 100Leak checking, containment, record keeping and reporting obligations

    An operator of a 300 tonnes CO2e system has a leak detection system fitted, but the last functional check was 18 months ago. What leak-check interval must be used?

    1. Every 3 months
    2. Every 6 months Correct answer.
    3. Every 24 months
    4. Every 12 months

    Explanation

    The extended interval is only available if the leak detection system is checked at least every 12 months. An 18-month gap means the system cannot be relied upon for the extension. The operator must therefore revert to the standard 6-month interval for the 50–500 tonne band.

  101. Question 101Leak checking, containment, record keeping and reporting obligations

    An operator runs a plant containing 700 tonnes CO2e. Which statement about annual F-gas reporting is correct?

    1. Annual operator report required
    2. Report only after a leak
    3. Report only on decommissioning
    4. Records kept; available on request Correct answer.

    Explanation

    Annual F-gas reporting to the regulator is imposed on producers, importers, exporters and undertakings that destroy F-gases. Operators of large equipment must keep records for at least five years and make them available to the competent authority on request. A 700-tonne plant therefore has record-keeping duties but not an annual operator report.

  102. Question 102Leak checking, containment, record keeping and reporting obligations

    A leak is found and the equipment cannot be repaired. What must the operator do?

    1. Continue operating until the next check
    2. Increase the leak-check frequency to every 3 months
    3. Recover the refrigerant and decommission Correct answer.
    4. Top up the refrigerant and record the top-up

    Explanation

    If a leak cannot be repaired, the equipment must not simply be kept running with repeated top-ups. The operator must ensure the refrigerant is recovered and the equipment is decommissioned. The gas recovery and decommissioning must be recorded.

  103. Question 103Leak checking, containment, record keeping and reporting obligations

    What record must be kept when a piece of F-gas equipment is decommissioned?

    1. Building energy rating
    2. Undertaking identity and certificate number Correct answer.
    3. Resale value of the equipment
    4. Name of the refrigerant supplier's driver

    Explanation

    Records must identify the undertaking that installed, serviced, maintained or decommissioned the equipment, including its certificate number where applicable. The quantity of refrigerant recovered must also be recorded. This provides an audit trail for the gas.

  104. Question 104Leak checking, containment, record keeping and reporting obligations

    By what date must producers and importers normally submit their annual F-gas report for the previous calendar year?

    1. 30 April
    2. 30 June
    3. 31 March Correct answer.
    4. 31 January

    Explanation

    Producers and importers must report their previous calendar year activities by 31 March. This is an annual reporting obligation separate from operator record keeping. Late or missing reports can lead to enforcement action.

  105. Question 105Leak checking, containment, record keeping and reporting obligations

    Which detail about leak checks must be included in an operator's records?

    1. Cost of replacement filters
    2. Weather conditions during checks
    3. Engineer travel time to site
    4. Leak-check dates and results Correct answer.

    Explanation

    Records must include the dates and results of leak checks carried out on the equipment. This demonstrates that the required checks were done and whether any leak was found. Records must be kept for at least five years.

  106. Question 106Leak checking, containment, record keeping and reporting obligations

    For how long must an operator keep the F-gas records for a stationary refrigeration system?

    1. Five years Correct answer.
    2. Ten years
    3. One year
    4. Three years

    Explanation

    The F-gas rules require records to be kept for at least five years. During that period the records must be made available to the regulator on request.

  107. Question 107Leak checking, containment, record keeping and reporting obligations

    What is the maximum interval between periodic leak checks for equipment containing more than 5 but less than 50 tonnes CO2e when no automatic leak detection system is fitted?

    1. Twelve months Correct answer.
    2. Six months
    3. Twenty-four months
    4. Thirty-six months

    Explanation

    Equipment in the 5 to 50 tonnes CO2e band has a default leak-check interval of twelve months. A longer interval is allowed only where a compliant automatic leak detection system is fitted.

  108. Question 108Leak checking, containment, record keeping and reporting obligations

    An operator finds a leak during a scheduled leak check. What is the operator required to do?

    1. Replace the equipment within twelve months
    2. Repair the leak without undue delay Correct answer.
    3. Top up the refrigerant and continue running
    4. Wait until the next scheduled check to repair it

    Explanation

    A detected leak must be repaired without undue delay so that further emissions are prevented. Adding refrigerant without repairing the leak does not satisfy the containment duty.

  109. Question 109Leak checking, containment, record keeping and reporting obligations

    Who is responsible for keeping the F-gas records for a stationary refrigeration system?

    1. The equipment manufacturer
    2. The technician who last serviced the system
    3. The refrigerant supplier
    4. The operator of the equipment Correct answer.

    Explanation

    The operator of the equipment is responsible for keeping the required F-gas records. A technician may complete entries, but the legal record-keeping duty remains with the operator.

  110. Question 110Leak checking, containment, record keeping and reporting obligations

    After a leak on an F-gas system has been repaired, when must the follow-up leak check be carried out?

    1. Before the next scheduled annual check
    2. Within one month of the repair Correct answer.
    3. Only if the system loses charge again
    4. Within three months of the repair

    Explanation

    A follow-up check must be carried out within one month after the repair to confirm that the repair has been effective. This is separate from the next routine scheduled leak check.

  111. Question 111Leak checking, containment, record keeping and reporting obligations

    Which detail about the undertaking carrying out a leak check must be included in the operator's records?

    1. Its name and certificate number Correct answer.
    2. The home address of the technician
    3. The equipment's warranty expiry date
    4. The purchase price of the refrigerant

    Explanation

    Records must identify the undertaking that performed the leak check, including its name and certificate number. This shows that the work was carried out by a competent certified business.

  112. Question 112Leak checking, containment, record keeping and reporting obligations

    To whom must an operator submit an annual F-gas report?

    1. The local fire service
    2. The environmental regulator Correct answer.
    3. The refrigerant supplier
    4. The equipment manufacturer

    Explanation

    Annual F-gas reports are submitted to the environmental regulator, which enforces the F-gas rules. They are not sent to equipment manufacturers or refrigerant suppliers.

  113. Question 113Leak checking, containment, record keeping and reporting obligations

    What is the effect on the leak-check interval if an automatic leak detection system is fitted but is not functioning correctly?

    1. The interval is doubled because a system is fitted
    2. The default interval applies until it works Correct answer.
    3. The extended interval can still be used until the next service
    4. The equipment must be shut down immediately

    Explanation

    The longer leak-check interval is allowed only while a compliant automatic leak detection system is operating correctly. If the system is faulty, the shorter default interval applies until it is repaired and functioning.

  114. Question 114Leak checking, containment, record keeping and reporting obligations

    Equipment contains 400 tonnes CO2e and has a compliant automatic leak detection system. What is the maximum interval between leak checks?

    1. Twenty-four months
    2. Six months
    3. Three months
    4. Twelve months Correct answer.

    Explanation

    For equipment from 50 up to 500 tonnes CO2e, the default interval is six months, but a compliant leak detection system allows twelve months. The three-month interval applies only at 500 tonnes CO2e or more without leak detection.

  115. Question 115Leak checking, containment, record keeping and reporting obligations

    A system contains 100 kg of R-134a, which has a GWP of 1430. What is the charge in tonnes CO2e and the leak-check interval if no automatic leak detection is fitted?

    1. 1,430 tonnes CO2e; every 3 months
    2. 14.3 tonnes CO2e; every 12 months
    3. 143 tonnes CO2e; every 6 months Correct answer.
    4. 143 tonnes CO2e; every 12 months

    Explanation

    The charge is 100 × 1430 ÷ 1000 = 143 tonnes CO2e. That falls in the 50 to 500 tonnes band, so without leak detection the interval is six months.

  116. Question 116Leak checking, containment, record keeping and reporting obligations

    What must be recorded when refrigerant is recovered from a system during service?

    1. The ambient temperature at the time
    2. The quantity recovered Correct answer.
    3. The name of the gas supplier's driver
    4. The colour of the recovery cylinder

    Explanation

    The operator's records must include the quantity of refrigerant recovered, together with the type of gas involved. Cylinder colour and weather conditions are not required record items.

  117. Question 117Leak checking, containment, record keeping and reporting obligations

    An operator has ten separate small refrigeration units on one site, each containing 4 tonnes CO2e. What leak-check obligation applies?

    1. No periodic leak checks are required Correct answer.
    2. Only the largest unit needs annual checks
    3. All ten units together need annual checks
    4. Each unit must be checked every 6 months

    Explanation

    The 5 tonnes CO2e containment threshold is applied to each piece of equipment separately, not to the total charge on a site. Because each unit is below 5 tonnes CO2e, periodic leak checks are not required for them.

  118. Question 118Leak checking, containment, record keeping and reporting obligations

    At what charge must stationary refrigeration equipment be fitted with an automatic leak detection system?

    1. 1,000 tonnes CO2e or more
    2. 500 tonnes CO2e or more Correct answer.
    3. 5 tonnes CO2e or more
    4. 50 tonnes CO2e or more

    Explanation

    Automatic leak detection is mandatory for stationary equipment containing 500 tonnes CO2e or more. Lower thresholds trigger record keeping and periodic leak checks, but not mandatory leak detection.

  119. Question 119Leak checking, containment, record keeping and reporting obligations

    A system contains 200 kg of R-404A, which has a GWP of 3922. No automatic leak detection is fitted. What is the charge in tonnes CO2e and the maximum leak-check interval?

    1. 392 tonnes CO2e; every 6 months
    2. 784 tonnes CO2e; every 6 months
    3. 78.4 tonnes CO2e; every 12 months
    4. 784 tonnes CO2e; every 3 months Correct answer.

    Explanation

    The charge is 200 × 3922 ÷ 1000 = 784.4 tonnes CO2e. At 500 tonnes CO2e or more and without leak detection, the maximum interval is three months.

  120. Question 120Leak checking, containment, record keeping and reporting obligations

    Equipment contains exactly 50 tonnes CO2e and has no automatic leak detection system. What is the maximum interval between leak checks?

    1. Six months Correct answer.
    2. Twenty-four months
    3. Three months
    4. Twelve months

    Explanation

    The twelve-month band covers 5 tonnes up to but not including 50 tonnes CO2e. Exactly 50 tonnes CO2e falls in the 50 to 500 tonnes band, which requires checks every six months without leak detection.

  121. Question 121Installation, commissioning, pressure testing and evacuation of RAC systems

    Which gas should be used to pressure test a refrigeration system?

    1. Carbon dioxide
    2. Dry nitrogen Correct answer.
    3. Oxygen
    4. Compressed air

    Explanation

    Dry nitrogen is inert and does not react with refrigerant oil or introduce moisture into the system. It is the accepted test medium for RAC pipework and systems.

  122. Question 122Installation, commissioning, pressure testing and evacuation of RAC systems

    Why is dry nitrogen passed through copper pipework while it is being brazed?

    1. To cool the joint quickly after brazing
    2. To remove moisture from the copper surface
    3. To prevent oxide scale forming inside the pipe Correct answer.
    4. To increase the internal pressure during brazing

    Explanation

    Nitrogen displaces oxygen inside the pipe, preventing copper oxide scale from forming on the hot inner surface. Scale can later block filters, valves and compressor suction.

  123. Question 123Installation, commissioning, pressure testing and evacuation of RAC systems

    According to EN 378, what strength test pressure is normally applied to a system with a maximum allowable pressure of PS?

    1. 0.5 × PS
    2. 2.5 × PS
    3. 1.0 × PS
    4. 1.43 × PS Correct answer.

    Explanation

    EN 378 specifies a strength pressure test at 1.43 times the maximum allowable pressure (PS). A separate tightness test is normally carried out at a lower pressure.

  124. Question 124Installation, commissioning, pressure testing and evacuation of RAC systems

    Why must oxygen never be used for pressure testing a refrigeration system?

    1. It can explode on contact with oil Correct answer.
    2. It has too low a cylinder pressure
    3. It reacts chemically with nitrogen
    4. It is too expensive for large systems

    Explanation

    Oxygen supports combustion vigorously, and refrigerant oil can ignite in its presence. A pressure test with oxygen therefore creates a serious explosion risk.

  125. Question 125Installation, commissioning, pressure testing and evacuation of RAC systems

    Where should the vacuum gauge be connected during evacuation of a system?

    1. At the compressor discharge
    2. At the vacuum pump inlet
    3. At the refrigerant cylinder
    4. At the far end of the system Correct answer.

    Explanation

    A gauge at the far end of the system measures the actual vacuum reached in the pipework. A gauge at the pump inlet can read lower because of pressure drop in the hoses.

  126. Question 126Installation, commissioning, pressure testing and evacuation of RAC systems

    What is the main purpose of triple evacuation?

    1. To clean the compressor oil
    2. To increase system pressure for testing
    3. To remove moisture and air Correct answer.
    4. To remove refrigerant from the system

    Explanation

    Repeated evacuation with nitrogen breaks up moisture and dilutes non-condensable gases so they can be drawn out. It is more effective than a single long evacuation.

  127. Question 127Installation, commissioning, pressure testing and evacuation of RAC systems

    What is the function of the gas ballast on a vacuum pump?

    1. To measure the vacuum level
    2. To cool the pump oil
    3. To increase the pump's ultimate vacuum
    4. To stop moisture in the pump oil Correct answer.

    Explanation

    The gas ballast admits a small amount of air to help carry condensable vapour through the pump. This reduces moisture contamination of the pump oil.

  128. Question 128Installation, commissioning, pressure testing and evacuation of RAC systems

    What effect do non-condensable gases have on a refrigeration system?

    1. Higher evaporator capacity
    2. Higher discharge pressure Correct answer.
    3. Lower discharge pressure
    4. Lower compressor current

    Explanation

    Non-condensables collect in the condenser and raise the condensing pressure. This increases compressor load and power use and reduces capacity.

  129. Question 129Installation, commissioning, pressure testing and evacuation of RAC systems

    A nitrogen pressure test shows a small pressure drop after the ambient temperature falls. What is the correct action?

    1. Open the system to atmosphere to equalise
    2. Assume a leak and dismantle the joint
    3. Correct the reading for temperature and allow stabilisation Correct answer.
    4. Immediately add more nitrogen to restore the original pressure

    Explanation

    Pressure changes with temperature, so a fall in ambient can lower the gauge reading without a leak. The test should be allowed to stabilise and the reading corrected for temperature.

  130. Question 130Installation, commissioning, pressure testing and evacuation of RAC systems

    A small pressure drop is found during a nitrogen strength test. Which method is suitable for locating the leak?

    1. Apply soap solution to joints Correct answer.
    2. Fill the system with water and look for bubbles
    3. Pressurise with oxygen and look for flames
    4. Use compressed air and listen for noise

    Explanation

    A soap solution applied to joints will produce bubbles at a leak while the system is under nitrogen pressure. It introduces no moisture or oxygen into the system.

  131. Question 131Installation, commissioning, pressure testing and evacuation of RAC systems

    How should a zeotropic refrigerant blend be charged into a system?

    1. As a vapour from the top of the cylinder
    2. As a liquid from the cylinder Correct answer.
    3. As a gas through the suction line only
    4. After heating the cylinder with a flame

    Explanation

    Zeotropic blends fractionate, so they must be charged as liquid to keep the cylinder composition correct. The liquid is usually fed into the liquid line or throttled into the suction.

  132. Question 132Installation, commissioning, pressure testing and evacuation of RAC systems

    What must be checked before starting a three-phase compressor after installation?

    1. That the refrigerant charge is 20% over
    2. That the suction valve is closed and stays closed
    3. That the phase rotation gives the correct direction Correct answer.
    4. That the oil separator is removed

    Explanation

    A three-phase compressor can run backwards if the phase sequence is wrong, which can damage it. Phase rotation must be checked before first start.

  133. Question 133Installation, commissioning, pressure testing and evacuation of RAC systems

    When purging nitrogen through pipework during brazing, which precaution is required?

    1. Seal both ends completely
    2. Use a regulator and low flow Correct answer.
    3. Use oxygen instead of nitrogen
    4. Use full cylinder pressure

    Explanation

    A regulator and low flow provide a safe purge without overpressurising the pipe. Full cylinder pressure can damage the pipework or blow out the purge.

  134. Question 134Installation, commissioning, pressure testing and evacuation of RAC systems

    What vacuum level is commonly required for evacuation of a refrigeration system?

    1. 500 microns Correct answer.
    2. 1000 microns
    3. 10,000 microns
    4. 0 microns

    Explanation

    A vacuum of 500 microns (about 0.67 mbar) is a common target for RAC systems. It shows that moisture and non-condensables have been largely removed.

  135. Question 135Installation, commissioning, pressure testing and evacuation of RAC systems

    After evacuation, the vacuum pump is isolated and the gauge reading rises slowly. What does this indicate?

    1. The gauge is faulty only
    2. A leak or moisture remains Correct answer.
    3. The pump is too large
    4. The system is fully dehydrated

    Explanation

    A standing vacuum test isolates the pump; a slow rise can be caused by vapour from moisture or by air entering through a leak. The source must be found before charging.

  136. Question 136Installation, commissioning, pressure testing and evacuation of RAC systems

    How should a pressure relief valve on a RAC system be arranged?

    1. It must be capped and sealed
    2. It must discharge into the compressor suction
    3. It must discharge to a safe location outdoors Correct answer.
    4. It must be plugged if the system is small

    Explanation

    Relief valves must be able to discharge safely without creating a hazard to people or property. They must never be blocked, capped or plugged.

  137. Question 137Installation, commissioning, pressure testing and evacuation of RAC systems

    What harm can moisture cause inside a refrigeration system?

    1. Lower discharge temperature
    2. Increased oil viscosity only
    3. Improved compressor lubrication
    4. Acid and ice formation Correct answer.

    Explanation

    Moisture can react with refrigerant oil and refrigerant to form acids, and it can freeze at the expansion device. Both effects damage the system.

  138. Question 138Installation, commissioning, pressure testing and evacuation of RAC systems

    What is a likely result of overcharging a refrigeration system with refrigerant?

    1. Lower suction pressure
    2. High discharge pressure Correct answer.
    3. Increased subcooling to zero
    4. Reduced power consumption

    Explanation

    Excess refrigerant raises condensing pressure and can cause liquid to reach the compressor. This increases power use and risks compressor damage.

  139. Question 139Installation, commissioning, pressure testing and evacuation of RAC systems

    Why must refrigerant pipework be adequately supported?

    1. To increase the refrigerant charge
    2. To improve the brazing quality
    3. To prevent vibration and joint stress Correct answer.
    4. To allow the pipe to sag for drainage

    Explanation

    Supports carry the weight of the pipe and reduce vibration, protecting brazed joints and the system. Unsuitable support can lead to cracks and leaks.

  140. Question 140Installation, commissioning, pressure testing and evacuation of RAC systems

    During commissioning, what does the superheat reading indicate?

    1. The compressor oil level
    2. The pressure relief setting
    3. Evaporator outlet state Correct answer.
    4. The amount of non-condensables

    Explanation

    Superheat is the difference between the actual suction temperature and the saturation temperature. It shows whether liquid is fully evaporated before the compressor.

  141. Question 141Installation, commissioning, pressure testing and evacuation of RAC systems

    For how long should a pressure test be held before a result is accepted?

    1. Until the gauge stops moving for one second
    2. Long enough to stabilise per EN 378 Correct answer.
    3. A minimum of 24 hours
    4. Exactly 5 minutes in all cases

    Explanation

    The test must be long enough for the pressure and temperature to stabilise and for any leak to show. EN 378 gives the required test procedure and observation period.

  142. Question 142Installation, commissioning, pressure testing and evacuation of RAC systems

    What information must be recorded after commissioning a system containing an F-Gas refrigerant?

    1. Only the installer's name
    2. Refrigerant type and amount Correct answer.
    3. The customer's bank details
    4. The colour of the pipework

    Explanation

    F-Gas records must include the refrigerant type and charge quantity, along with leak checks and servicing. This allows the operator to comply with leak-check obligations.

  143. Question 143Installation, commissioning, pressure testing and evacuation of RAC systems

    Why should the vacuum pump be isolated before it is switched off?

    1. To increase the pump speed
    2. To allow refrigerant to escape
    3. To stop oil entering the system Correct answer.
    4. To prevent the pump overheating

    Explanation

    If the pump is stopped without isolation, the vacuum in the system can draw oil from the pump into the pipework. An isolation valve prevents this.

  144. Question 144Installation, commissioning, pressure testing and evacuation of RAC systems

    Why must pressure gauges used for strength testing be calibrated?

    1. To ensure the test pressure is accurate Correct answer.
    2. To increase the test pressure automatically
    3. To make them read lower than actual pressure
    4. To allow them to be used with oxygen

    Explanation

    An inaccurate gauge can cause the system to be under-tested or over-pressurised. Calibration confirms the displayed pressure is reliable.

  145. Question 145Installation, commissioning, pressure testing and evacuation of RAC systems

    Why must suction pipe insulation have an effective vapour barrier?

    1. To increase heat gain into the pipe
    2. To reduce the need for pipe supports
    3. To stop condensation and ice Correct answer.
    4. To allow UV degradation of the insulation

    Explanation

    A vapour barrier stops water vapour from reaching the cold pipe surface. Without it, condensation and ice can form and damage the insulation.

  146. Question 146Installation, commissioning, pressure testing and evacuation of RAC systems

    Which gas is used to pressurise a refrigeration system for a strength pressure test?

    1. Oxygen from a welding cylinder
    2. Compressed air from a workshop compressor
    3. Oxygen-free nitrogen Correct answer.
    4. Carbon dioxide from a beverage cylinder

    Explanation

    Oxygen-free nitrogen is inert, dry and does not support combustion, so it is safe for strength and tightness testing. It will not react with refrigerant oil or introduce moisture.

  147. Question 147Installation, commissioning, pressure testing and evacuation of RAC systems

    Where should the vacuum gauge be connected to obtain a true reading of the vacuum in a refrigeration system?

    1. Close to the system, on the system side of the valve Correct answer.
    2. At the vacuum pump inlet, where the hose is connected
    3. On the top of the refrigerant charging cylinder
    4. At the far end of the vacuum hose, near the pump

    Explanation

    A gauge at the pump measures pressure at the pump, not in the system, and hose pressure drop can make the reading misleading. The gauge should be connected to a service port on the system, isolated from the pump, so it shows the true system vacuum.

  148. Question 148Installation, commissioning, pressure testing and evacuation of RAC systems

    What is the purpose of a tightness test after a successful strength test?

    1. To confirm the joints are leak-free at a lower pressure Correct answer.
    2. To measure the running current of the compressor
    3. To prove the system can withstand the strength test pressure
    4. To remove moisture from the refrigerant circuit

    Explanation

    The strength test proves the system can withstand a high internal pressure without bursting. The tightness test then uses a lower pressure and sensitive detection methods to show that joints and components do not leak.

  149. Question 149Installation, commissioning, pressure testing and evacuation of RAC systems

    Which sequence is correct for commissioning a new RAC system?

    1. Evacuate, strength test, leak test, charge
    2. Leak test, charge, strength test, evacuate
    3. Charge, leak test, evacuate, strength test
    4. Strength test, leak test, evacuate, charge Correct answer.

    Explanation

    The correct order is strength test, tightness test, evacuation and charging. Evacuation must follow pressure testing to remove nitrogen, air and moisture before refrigerant is introduced.

  150. Question 150Installation, commissioning, pressure testing and evacuation of RAC systems

    Before a strength pressure test, what should be done with components that are not rated for the test pressure, such as low-pressure switches?

    1. Warm them with a heat gun before testing
    2. Isolate or remove and plug the connections Correct answer.
    3. Leave them connected so their operation is proved
    4. Adjust them to their maximum setting before the test

    Explanation

    Components such as low-pressure switches may have a lower pressure rating than the test pressure and can be damaged. They should be isolated, removed or replaced with suitable plugs before the test.

  151. Question 151Installation, commissioning, pressure testing and evacuation of RAC systems

    Why should evacuation be carried out from both the high-pressure and low-pressure sides where valves permit?

    1. To ensure all sections, including traps, are evacuated Correct answer.
    2. To keep the vacuum pump oil cool during operation
    3. To reduce the amount of refrigerant left in the system
    4. To allow the compressor to run during evacuation

    Explanation

    Evacuating from both sides prevents isolated pockets of air or moisture in traps, coils and pipe sections. It also gives a shorter path for vapour to leave the system.

  152. Question 152Installation, commissioning, pressure testing and evacuation of RAC systems

    What effect does contaminated or moisture-laden vacuum pump oil have on evacuation?

    1. It has no effect on evacuation time
    2. It improves the ultimate vacuum achieved
    3. It reduces the achievable vacuum Correct answer.
    4. It increases the pumping speed of the pump

    Explanation

    Vacuum pump oil seals clearances and helps the pump achieve a deep vacuum. Moisture or contamination raises the oil's vapour pressure, so the achievable vacuum is poorer and evacuation takes longer.

  153. Question 153Installation, commissioning, pressure testing and evacuation of RAC systems

    After evacuation, the pump is isolated and the system is left standing. What is the purpose of this standing vacuum test?

    1. To allow refrigerant to boil out of the oil
    2. To confirm the vacuum is held Correct answer.
    3. To cool the compressor before charging
    4. To check the pressure relief valve setting

    Explanation

    In a standing vacuum test the pump is isolated and the system is observed. A rise in pressure can indicate a leak, moisture or outgassing, so the vacuum should remain stable for the specified period.

  154. Question 154Installation, commissioning, pressure testing and evacuation of RAC systems

    What information should be recorded after a successful pressure test?

    1. Test pressure, gas used, hold time and result Correct answer.
    2. Only the printed name of the technician who did the test
    3. Only the date on which the pressure test was completed
    4. The refrigerant charge weight recorded on the cylinder

    Explanation

    Pressure test records should allow the test to be repeated and verified, so they include the test pressure, test gas, hold time, ambient temperature and result. The date and technician are also recorded, but they are not sufficient on their own.

  155. Question 155Installation, commissioning, pressure testing and evacuation of RAC systems

    Before starting a compressor after evacuation and charging, what should be checked at the oil sight glass?

    1. That the oil level is correct and the oil is clear Correct answer.
    2. That the oil is bright red in colour
    3. That the oil is hot to the touch
    4. That the oil level is above the top of the sight glass

    Explanation

    The oil sight glass should show the correct level and clear oil, indicating adequate lubrication and no obvious moisture or contamination. Foaming or a very high level can indicate overcharging or refrigerant in the oil.

  156. Question 156Installation, commissioning, pressure testing and evacuation of RAC systems

    How should a low-pressure cut-out be checked during commissioning?

    1. By checking the control circuit voltage only
    2. By raising the discharge pressure until the switch trips
    3. By slowly reducing suction pressure to its set point Correct answer.
    4. By disconnecting it and running the compressor

    Explanation

    A low-pressure cut-out is commissioned by reducing the suction pressure slowly and confirming that it opens at the set point and resets correctly. This proves the switch protects the compressor against low suction pressure.

  157. Question 157Installation, commissioning, pressure testing and evacuation of RAC systems

    Why should open pipe ends be capped or taped during installation?

    1. To prevent the pipes from bending during handling
    2. To exclude moisture, dirt and air Correct answer.
    3. To stop refrigerant from escaping from the pipes
    4. To make the brazing process easier

    Explanation

    Open pipe ends must be capped or taped to keep moisture, dirt and air out of the circuit. Contaminants can cause corrosion, ice formation and acid in the system.

  158. Question 158Installation, commissioning, pressure testing and evacuation of RAC systems

    A technician proposes to use the system's own compressor to evacuate the circuit. Why is this unacceptable?

    1. It will remove too much oil from the crankcase
    2. It cannot produce the required rotation direction
    3. It will raise the system pressure above atmospheric
    4. It is not a vacuum pump and may overheat Correct answer.

    Explanation

    A refrigeration compressor is designed to pump vapour against a pressure difference, not to create a deep vacuum. Running it at very low suction pressure can overheat it and cause loss of lubrication and damage.

  159. Question 159Installation, commissioning, pressure testing and evacuation of RAC systems

    Why is a vacuum decay test not a substitute for a pressure leak test?

    1. Small outward leaks may go undetected Correct answer.
    2. A vacuum test requires the compressor to run continuously
    3. A vacuum test uses nitrogen; a pressure test uses oxygen
    4. A vacuum test is always more accurate than a pressure test

    Explanation

    A vacuum test draws air inward, so small outward leaks may not be detected, and it does not prove mechanical strength. A pressure test is required to verify strength and to detect leaks with the system under positive pressure.

  160. Question 160Installation, commissioning, pressure testing and evacuation of RAC systems

    After prolonged evacuation, the system will not pull below the required vacuum. What is the most appropriate action?

    1. Charge the system and check performance
    2. Add more refrigerant oil to improve sealing
    3. Investigate for leaks or moisture Correct answer.
    4. Increase the pressure gauge range and retest

    Explanation

    If the required vacuum cannot be reached, there is likely a leak, moisture, a faulty pump, hose or gauge. The correct action is to investigate and continue evacuation before charging.

  161. Question 161Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What is the maximum permitted fill level by weight for a refrigerant recovery cylinder?

    1. 70% of the cylinder water capacity
    2. 80% of the cylinder water capacity Correct answer.
    3. 90% of the cylinder water capacity
    4. 60% of the cylinder water capacity

    Explanation

    Recovery cylinders must not be filled above 80% of their water capacity by weight. The remaining vapour space allows liquid refrigerant to expand as it warms without generating hydraulic pressure that could rupture the cylinder.

  162. Question 162Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Which recovery method removes refrigerant from a system most quickly?

    1. Vapour recovery with the system compressor running
    2. Liquid recovery through the liquid line valve Correct answer.
    3. Vapour recovery through the suction service valve
    4. Recovery through a Schrader core without a depressor

    Explanation

    Liquid recovery transfers dense liquid through the liquid line valve, so the recovery machine moves a much greater mass of refrigerant per unit time. Once liquid recovery slows, the remaining vapour is recovered through the suction side.

  163. Question 163Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What is the main purpose of a refrigerant recovery machine?

    1. To recharge a system with new refrigerant from a supply cylinder
    2. To clean refrigerant to virgin specification
    3. To pressure-test a system for leaks
    4. To move refrigerant from a system into a recovery cylinder Correct answer.

    Explanation

    A recovery machine is designed to draw refrigerant out of a system and discharge it into a recovery cylinder. It does not restore refrigerant to virgin specification or recharge the system.

  164. Question 164Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What should be checked before starting recovery from a system into a recovery cylinder?

    1. Confirm the recovery cylinder is suitable and not overfull Correct answer.
    2. Weigh the system refrigerant charge and write it on the service record
    3. Connect the recovery machine to the liquid line only
    4. Open both service valves fully and start the system compressor

    Explanation

    Before recovery begins, the cylinder must be suitable for the refrigerant and have enough empty volume for the charge. This prevents overfilling and avoids mixing incompatible refrigerants.

  165. Question 165Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Which personal protective equipment is essential when transferring liquid refrigerant?

    1. A dust mask and cotton overalls
    2. Ear defenders and steel toe boots
    3. Safety goggles and suitable gloves Correct answer.
    4. A face shield and insulating mat

    Explanation

    Liquid refrigerant can cause cold burns and severe eye damage, so goggles and suitable gloves are the minimum protection. Additional protection may be needed for large charges or flammable refrigerants.

  166. Question 166Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What must happen to refrigerant recovered from a system that is being decommissioned?

    1. It can be discharged into a sealed drain
    2. It may be vented to atmosphere if the system is being scrapped
    3. It must be recovered and not vented Correct answer.
    4. It may be burned in the site incinerator

    Explanation

    Recovered refrigerant must never be vented to atmosphere; it is sent to a licensed reclaimer or destroyed by an approved route. Decommissioning does not remove the legal duty to contain the refrigerant.

  167. Question 167Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Which instrument confirms that a system has reached the required evacuation level?

    1. A refrigerant identifier
    2. A calibrated micron gauge Correct answer.
    3. A manifold gauge set
    4. A leak detector

    Explanation

    A micron gauge measures absolute pressure at very low levels and shows whether the required vacuum has been reached. Manifold gauges are not accurate enough for deep vacuum measurement.

  168. Question 168Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What must be done before removing refrigerant-containing components from a decommissioned system?

    1. Brazing the pipework closed and then opening all service valves
    2. Running the compressor to pump the charge into the receiver
    3. Recovering the refrigerant and isolating the electrical supply Correct answer.
    4. Closing the liquid valve and leaving the charge in the system

    Explanation

    Before any component is removed, the refrigerant must be recovered and the electrical supply isolated and locked off. This prevents refrigerant release and accidental start-up.

  169. Question 169Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Before cutting into the pipework of a decommissioned R290 system, what is the essential final step?

    1. Recover the charge, purge with nitrogen and confirm a safe atmosphere Correct answer.
    2. Close the service valves and leave the remaining charge inside the pipework
    3. Fill the pipework with water to displace any remaining refrigerant
    4. Run the compressor briefly to push the residual gas outdoors

    Explanation

    R290 is a flammable refrigerant, so the system must be recovered and purged with nitrogen, then checked with a gas detector before hot work. Residual gas in oil or pipework can create a flammable atmosphere.

  170. Question 170Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    During vapour recovery, how should the recovery cylinder normally be managed?

    1. Kept cooler than the system to help the vapour condense Correct answer.
    2. Inverted so that the valve is at the bottom
    3. Warmed with a heat blanket to raise its internal pressure
    4. Filled to 90% to reduce the number of cylinder changes

    Explanation

    Cooling the recovery cylinder lowers its internal pressure and helps refrigerant vapour condense, which speeds recovery and protects the machine. Heating the cylinder or overfilling it has the opposite effect.

  171. Question 171Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why is a filter drier fitted in the circuit of a recovery machine?

    1. To prevent refrigerant from condensing inside the recovery machine
    2. To remove moisture and acid from the recovered refrigerant Correct answer.
    3. To increase the recovery rate by lowering suction pressure
    4. To measure the amount of refrigerant passing through the circuit

    Explanation

    A filter drier on the recovery circuit traps moisture and acidic breakdown products so they do not enter the recovery machine or the storage cylinder. It does not measure or control the recovery rate.

  172. Question 172Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What does a standing vacuum test show after a system has been evacuated?

    1. That the system holds vacuum without a rise indicating leak or moisture Correct answer.
    2. That the recovery machine has reached its maximum suction pressure
    3. That the vacuum pump oil has been changed recently enough
    4. That the refrigerant charge is correct for the system volume

    Explanation

    A standing vacuum test checks that the system holds a vacuum after evacuation. A steady rise in pressure can indicate a leak or moisture that is boiling off under vacuum.

  173. Question 173Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why is oxygen-free nitrogen used rather than oxygen for pressure testing a refrigeration system?

    1. Oxygen can ignite oil and cause an explosion Correct answer.
    2. Oxygen reacts with refrigerant to form a toxic gas
    3. Oxygen cannot be regulated to a stable test pressure
    4. Oxygen leaves a corrosive residue inside the pipework

    Explanation

    Oxygen-free nitrogen is inert and does not support combustion. Oxygen under pressure can ignite compressor oil and cause an explosion if it contacts oil.

  174. Question 174Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    When recovering refrigerant from a system fitted with a receiver, which sequence is normally used?

    1. Recover both at the same time through one hose
    2. Recover vapour first, then switch to liquid
    3. Recover only vapour and leave the liquid in the receiver
    4. Recover liquid first, then switch to vapour Correct answer.

    Explanation

    Liquid recovery is carried out first because liquid transfers quickly and reduces the system charge rapidly. Vapour recovery then removes the remainder.

  175. Question 175Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    How should a recovery cylinder be identified after refrigerant has been recovered into it?

    1. Attach the recovery machine serial number to the valve
    2. Label it with the refrigerant type, quantity and date Correct answer.
    3. Write the system pressure on the cylinder shoulder
    4. Mark it with the colour of the original system only

    Explanation

    Every recovery cylinder must be labelled with the refrigerant type, the quantity recovered and the date. This prevents mixing and allows safe handling and transport.

  176. Question 176Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why should a system be evacuated from both the high and low sides where possible?

    1. To make the pressure test with nitrogen more accurate
    2. To remove air and moisture from all parts of the circuit Correct answer.
    3. To allow the vacuum pump to run at a lower ultimate vacuum
    4. To prevent the recovery machine from overloading during charging

    Explanation

    Evacuating from both high and low sides removes air and moisture from the whole circuit, including parts that may be isolated by valves during single-side evacuation. It also reduces evacuation time.

  177. Question 177Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why is nitrogen purging required when brazing pipework on a refrigeration system?

    1. To cool the pipe quickly after the joint is made
    2. To flush any remaining refrigerant out of the pipe
    3. To prevent oxidation and scale forming inside the pipe Correct answer.
    4. To increase the brazing temperature at the joint

    Explanation

    Nitrogen displaces oxygen while brazing, preventing oxidation that forms scale inside the pipework. Scale can later block filters, valves and compressors.

  178. Question 178Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What should be done if a recovery cylinder reaches its fill limit during a recovery job?

    1. Open the cylinder valve to release vapour and continue
    2. Continue until the cylinder pressure stops rising
    3. Stop recovery and change to an empty suitable cylinder Correct answer.
    4. Cool the cylinder with ice and continue past the limit

    Explanation

    Recovery cylinders must never exceed 80% fill, so recovery stops and the charge is transferred to another suitable empty cylinder. Releasing vapour or cooling the cylinder does not make overfilling acceptable.

  179. Question 179Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    How should oil drained from a decommissioned compressor be handled?

    1. Burn it in the site boiler as a fuel supplement
    2. Treat it as hazardous waste and use a licensed contractor Correct answer.
    3. Pour it into the drainage system with plenty of water
    4. Return it to the refrigerant cylinder and send for recycling

    Explanation

    Compressor oil can contain refrigerant, acids and other contaminants, so it is classified as hazardous waste. It must be handled and disposed of through a licensed waste contractor.

  180. Question 180Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    A refrigerant identifier shows that recovered R410A contains 5% R32. What is the correct action?

    1. Use it in an R32 system without further testing
    2. Add virgin R410A to dilute the R32 and reuse it
    3. Vent the mixture slowly to atmosphere because the charge is small
    4. Label it contaminated and send for reclaim or destruction Correct answer.

    Explanation

    Recovered refrigerant that contains another refrigerant is contaminated and cannot be reused as R410A. It must be labelled and sent to a licensed reclaimer or destroyed.

  181. Question 181Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why are Schrader cores often removed during evacuation?

    1. To allow the manifold gauge to read a positive pressure
    2. To reduce flow restriction and achieve a deeper vacuum Correct answer.
    3. To keep the vacuum pump oil from becoming contaminated
    4. To prevent the vacuum pump from drawing in refrigerant vapour

    Explanation

    Schrader cores and valve depressors restrict flow; removing them during evacuation lowers the ultimate vacuum and shortens evacuation time. They must be refitted afterwards.

  182. Question 182Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What does recycling refrigerant mean compared with reclaiming it?

    1. Burning the refrigerant to recover its chemical components
    2. Storing refrigerant in a cylinder without any treatment
    3. Cleaning to virgin refrigerant specification with laboratory analysis and certification
    4. On-site cleaning to remove oil and moisture without full analysis Correct answer.

    Explanation

    Recycling cleans refrigerant on site, typically by removing oil and moisture, but it does not restore it to virgin specification. Reclaiming involves laboratory analysis and certification to a recognised standard.

  183. Question 183Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Which precaution is essential when recovering an A2L refrigerant?

    1. Recover only the liquid and leave the vapour in the system
    2. Use flammable-rated equipment and remove all ignition sources Correct answer.
    3. Vent the charge outdoors before connecting the recovery machine
    4. Use standard recovery equipment because A2L refrigerants cannot burn

    Explanation

    A2L refrigerants are mildly flammable, so recovery equipment must be suitable for flammable refrigerants and all ignition sources must be controlled. Standard equipment and venting are not acceptable.

  184. Question 184Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why must a vacuum pump used on a flammable refrigerant be suitable for the application?

    1. The vacuum pump will overheat because the refrigerant is flammable
    2. The pump oil will react chemically with the refrigerant
    3. The pump may not be rated for flammable atmospheres Correct answer.
    4. The pump will remove the refrigerant too quickly and cause frosting

    Explanation

    A vacuum pump used on a flammable refrigerant must be rated for the atmosphere, because a leak from the pump could be ignited by its motor or switchgear. Standard pumps may not be protected.

  185. Question 185Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What is the correct disposal route for R22 recovered during decommissioning?

    1. Release it slowly outdoors because R22 has low global warming potential
    2. Send it to a licensed reclaimer or high-temperature incinerator Correct answer.
    3. Store it indefinitely in a sealed cylinder without labelling
    4. Use it to purge pipework before brazing new joints

    Explanation

    R22 is an ozone-depleting substance, so recovered R22 must go to a licensed reclaimer or be destroyed by an approved high-temperature process. Venting or unapproved burning is prohibited.

  186. Question 186Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Which type of glove is appropriate when there is a risk of contact with liquid refrigerant?

    1. Cotton general-purpose work gloves
    2. Leather rigger's gloves
    3. Cryogenic-rated impervious gloves Correct answer.
    4. Disposable latex examination gloves

    Explanation

    Liquid refrigerant can cause severe cold burns, so hands must be protected by gloves made for cryogenic service that resist penetration by liquid. General work gloves, leather, or thin latex gloves do not provide reliable insulation or liquid resistance.

  187. Question 187Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Which container is suitable for holding refrigerant recovered from a system?

    1. A plastic drum with a sealed cap
    2. A refillable cylinder designed for recovery Correct answer.
    3. A disposable original refrigerant cylinder
    4. Any steel container with a tight lid

    Explanation

    Recovered refrigerant must be put into a refillable recovery cylinder that is designed, tested, and marked for that duty. Disposable cylinders must not be refilled, and improvised containers are unsafe and illegal for refrigerant recovery.

  188. Question 188Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why must recovered refrigerant never be released to atmosphere?

    1. It increases the recovery machine discharge pressure
    2. It prevents moisture from entering the recovery circuit
    3. It reduces the weight of the recovery cylinder
    4. It has ozone-depleting or global-warming effects Correct answer.

    Explanation

    Released refrigerants can deplete stratospheric ozone or contribute to global warming, which is why regulations require recovery. Releasing them also wastes a resource that can be reclaimed and reused.

  189. Question 189Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    After refrigerant has been recovered from a decommissioned system, what record must be kept?

    1. The refrigerant type and amount Correct answer.
    2. The ambient temperature during recovery
    3. The colour code of the recovery cylinder
    4. The manufacturer of the recovery machine

    Explanation

    Records must show the type and quantity of refrigerant recovered so that the movement of controlled substances can be traced. This supports legal compliance and helps the reclaim or disposal operator handle the charge correctly.

  190. Question 190Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Which recovery method is most suitable for quickly transferring a large liquid refrigerant charge from a system with a receiver?

    1. Push-pull liquid recovery Correct answer.
    2. Gravity draining through a Schrader valve
    3. Vacuum-assisted vapour recovery
    4. Vapour recovery only through the suction line

    Explanation

    Push-pull recovery uses the pressure difference between the system and the recovery cylinder to move liquid refrigerant, then returns vapour to the system. It is much faster than vapour recovery for large liquid charges, provided the hoses and valves are set correctly.

  191. Question 191Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why should service valves not be closed on a liquid-filled section of pipework during decommissioning?

    1. The refrigerant will change colour
    2. The system will lose all its lubricant
    3. Trapped liquid can rupture the pipework Correct answer.
    4. The service valves will seize open

    Explanation

    Liquid refrigerant expands significantly when it warms, and a closed section can become hydraulically full. The resulting pressure rise can distort or rupture pipework, valves, or fittings, so sections must remain open to a safe volume or be recovered first.

  192. Question 192Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why should recovery hoses be purged before use?

    1. To cool the recovery cylinder
    2. To raise the hose pressure rating
    3. To lubricate the recovery compressor
    4. To remove air and moisture Correct answer.

    Explanation

    Hoses can hold air and moisture, and these contaminants would enter the recovery cylinder or the system. Purging with a small amount of the refrigerant displaces them and helps keep the recovered charge clean.

  193. Question 193Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What should be done if two different refrigerants are accidentally mixed in a recovery cylinder?

    1. Treat the mixture as waste for reclamation Correct answer.
    2. Vent the mixture slowly to atmosphere
    3. Return the mixture to the first system
    4. Use it in any system with a similar refrigerant

    Explanation

    Mixed refrigerants cannot be separated on site and must not be charged into equipment because the composition is unknown. The cylinder should be labelled as mixed waste and sent to a specialist for analysis, reclamation, or destruction.

  194. Question 194Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    After evacuating a system that contained moisture, what should be done with the vacuum pump oil?

    1. Filter it and reuse it
    2. Replace it with fresh oil Correct answer.
    3. Top it up with refrigerant oil
    4. Leave it until the next service

    Explanation

    Vacuum pump oil absorbs moisture and other contaminants during evacuation, which reduces its ability to achieve a deep vacuum. The oil should be replaced with fresh oil, and the old oil disposed of as hazardous waste.

  195. Question 195Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Before dismantling a decommissioned refrigeration system, what electrical safety step is required?

    1. Disconnect only the control circuit
    2. Ask the site operator to switch it off
    3. Remove the fuses and keep them in your pocket
    4. Isolate the supply and lock it off Correct answer.

    Explanation

    The electrical supply must be isolated at the source and locked off so that the system cannot be re-energised while work is in progress. A formal lockout arrangement protects the technician and anyone else on site.

  196. Question 196Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    Why is a decommissioned system often left with a slight positive pressure of oxygen-free nitrogen?

    1. To make the pipework easier to move
    2. To show the refrigerant has been removed
    3. To keep the compressor lubricated
    4. To prevent air and moisture ingress Correct answer.

    Explanation

    A small nitrogen pressure keeps air and moisture from entering the open pipework during storage or transport. It also gives a visible indication that the system has been made inert rather than left open.

  197. Question 197Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What is the purpose of the oil separator fitted to some recovery machines?

    1. To increase the recovery speed
    2. To remove carried-over lubricating oil Correct answer.
    3. To filter the refrigerant vapour
    4. To cool the recovery compressor

    Explanation

    Oil carried over with refrigerant can contaminate the recovery cylinder and reduce machine performance. An oil separator removes much of that oil so the recovered refrigerant is cleaner and the recovery machine is protected.

  198. Question 198Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    A recovery cylinder has a water capacity of 12 litres and is used for R410A, whose liquid density is about 1.06 kg/L. What is the maximum recommended fill weight at 80% of water capacity?

    1. 15.3 kg
    2. 10.2 kg Correct answer.
    3. 8.0 kg
    4. 12.7 kg

    Explanation

    The maximum fill weight is found from water capacity × 0.8 × liquid density: 12 × 0.8 × 1.06 = 10.176 kg, approximately 10.2 kg. Using 80% leaves room for liquid expansion and is a standard safety limit.

  199. Question 199Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    When recovering refrigerant from a system with a burnt-out compressor, which precaution is most important?

    1. Mix the recovered refrigerant with fresh refrigerant
    2. Recover the refrigerant as a vapour only
    3. Use a separate cylinder and filter the charge Correct answer.
    4. Vent the refrigerant through the suction line

    Explanation

    A burnout can leave acid, particulate matter, and sludge in the refrigerant, so a separate recovery cylinder and suitable filtration protect the recovery machine and prevent contamination of other charges. The recovered refrigerant should then be reclaimed or disposed of rather than reused directly.

  200. Question 200Servicing, maintenance, refrigerant recovery, recycling and decommissioning

    What is the correct action if the refrigerant in a decommissioned system cannot be identified?

    1. Mix it with R410A for reuse
    2. Vent it and flush with nitrogen
    3. Treat it as waste for analysis Correct answer.
    4. Charge it into a similar system

    Explanation

    An unidentified refrigerant must not be charged into equipment or mixed with a known refrigerant. It should be recovered, labelled as unknown, and sent for analysis or specialist disposal.

C&G 2079-11 F-Gas Category I flashcards

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

CO2e formula
Tonnes CO2e equals charge in kilograms multiplied by GWP, then divided by 1,000; this sets leak-check and record thresholds.
GWP definition
Global warming potential compares the climate impact of one kilogram of a gas with one kilogram of carbon dioxide over a stated horizon.
ODP definition
Ozone depletion potential compares a substance's ozone-destroying effect with CFC-11, which is assigned a reference value of one.
R-22 status
R-22 is an HCFC controlled as an ozone-depleting substance; virgin supplies are phased out and recovered material faces separate restrictions.
Operator responsibility
The operator must prevent leaks, arrange certified leak checks and recovery, keep records for five years, and ensure only certified competent persons work on the equipment.
Environmental impact
F-gas releases increase global warming; ODS releases also deplete ozone; leakage reduces efficiency and raises energy-related indirect emissions.
Record retention period
F-gas records, including charge, leak checks, recovery and servicing, must be kept for at least five years and made available to inspectors.
Deliberate venting ban
Deliberate release of F-gases or ODS to atmosphere is prohibited; refrigerant must be recovered, recycled, reclaimed or destroyed through authorised routes.
A2L refrigerant
A2L refrigerants have lower flammability than A3 but still require ignition control, ventilation, leak detection and flammable-refrigerant procedures.
A3 refrigerant
A3 refrigerants are highly flammable and require strict ignition-source exclusion, ventilation, and equipment designed and labelled for flammable refrigerant use.
Asphyxiation hazard
Refrigerant vapour is denser than air and can displace oxygen in pits, basements or plant rooms, causing dizziness, unconsciousness or death.
Thermal decomposition
Heated refrigerant or refrigerant exposed to flame can form hydrogen fluoride and other toxic, corrosive products, requiring evacuation and respiratory protection.
Liquid refrigerant frostbite
Liquid refrigerant contacting skin causes rapid frostbite; impermeable cold-protective gloves and eye protection are required, and liquid must not be trapped against skin.
Recovery cylinder fill limit
Recovery cylinders must not be filled above their maximum permitted weight, commonly 80% of water capacity, leaving vapour space for expansion.
Cylinder valve protection
Valve caps or guards remain fitted during transport, cylinders are secured upright, and cylinders are never lifted by the valve.
Risk assessment hierarchy
Controls are applied in order: eliminate exposure, substitute safer options, use engineering controls, adopt safe systems of work, then PPE.
PPE for refrigerant work
Typical PPE includes safety glasses or goggles, chemical-resistant gloves and safety footwear; risk assessment may add flame-retardant clothing and respiratory protection.
Cylinder heat exposure
Cylinders must be kept away from flames, heaters and direct sun because heat raises pressure and can cause relief-valve release, rupture or fire.
Leak check threshold
Periodic leak checks apply from 5 tonnes CO2e; charge in kilograms multiplied by GWP and divided by 1,000 determines the threshold.
Leak detection system effect
A verified automatic leak detection system halves the required leak-check frequency in the 50–500 and 500-plus tonnes CO2e bands.
Leak record content
Leak records identify equipment, refrigerant, charge, CO2e, check date, findings, repairs, technician and leak-detection system verification.
Leak repair verification
After a leak repair, the repaired area is rechecked and the result recorded; repeated leaks may trigger additional containment or replacement duties.
Containment measures
Containment includes minimising joints, protecting pipework from corrosion and vibration, using correct materials and avoiding unnecessary refrigerant charge.
Nitrogen pressure test
Oxygen-free nitrogen with a pressure regulator is used for strength testing; oxygen or compressed air with refrigerant oil can cause fire or explosion.
Triple evacuation
Triple evacuation breaks vacuum with nitrogen between stages to remove moisture and non-condensables, followed by a standing vacuum test.
Vacuum gauge placement
Vacuum is measured at the system with a calibrated electronic gauge, not at the pump, and the pump is isolated before the standing test.
Commissioning charge record
Commissioning records include actual charge by weight, refrigerant type, CO2e, date, equipment identity and adjustments to superheat or subcooling.
Pressure test safety
The test area is barricaded, pressure is increased in stages, and a pressurised system is never left unattended during testing.
Recovery versus recycling
Recovery removes refrigerant from a system; recycling cleans it on site; reclamation reprocesses it to a specification and requires laboratory analysis.
Decommissioning recovery
Before dismantling, all refrigerant is recovered, the quantity recorded, the system labelled, and refrigerant and components disposed of through authorised routes.
Reclaimed refrigerant analysis
Reclaimed refrigerant must meet a published specification and be supported by laboratory analysis before it is returned to equipment.
Recovery cylinder labelling
Recovery cylinders are labelled with refrigerant identity, owner, date, gross weight and tare weight; mixtures are clearly identified as mixtures.

C&G 2079-11 F-Gas Category I study guide

F-Gas and ODS Regulations: Scope, Numbers and Thresholds

Two regimes, one toolkit

Two legal regimes overlap on a refrigeration job. The F-gas Regulation (retained Regulation (EU) 517/2014 and its amendments) controls fluorinated greenhouse gases - HFCs, PFCs and SF6 - through a CO2-equivalent phase-down, placing-on-market bans, leak control, certification and labelling. The ODS Regulation (EC 1005/2009) controls ozone-depleting substances: CFCs such as R-12 and HCFCs such as R-22, including blends that contain an HCFC (for example R-408A and R-409A).

The one calculation you must own

Tonnes CO2e = charge (kg) × GWP ÷ 1000. Keep a small GWP table in your head: R-134a 1430, R-32 675, R-407C 1774, R-410A 2088, R-404A 3922, R-744 1. These are Fourth Assessment Report values; if a question supplies a different GWP, use the supplied one.

Traps that appear in questions

  • Thresholds are always in tonnes CO2e, never in kilograms of charge.
  • R-22 is an ODS, not an F-gas: it may not be used to service equipment, and recovered R-22 can only be destroyed.
  • The phase-down is measured in CO2e placed on the market, not in cylinder numbers.
  • Certification is required for both the individual technician and the company; they are separate obligations.
  • A blend containing an HCFC stays under ODS rules even though part of it is an HFC.

Worked example

A split system holds 4.0 kg of R-410A. 4.0 × 2088 ÷ 1000 = 8.35 t CO2e. That exceeds 5 t but is below 50 t, so the operator needs leak checks at least every 12 months (24 months with a verified fixed leak detection system) and a written record for each check.

Legal Duties, Operator Responsibility and Environmental Impact

Who is legally responsible

The "operator" is the person or organisation with operational control of the equipment - in practice the end user, not the contractor. Operators must prevent leakage, arrange leak checks and keep records, use only certified personnel and companies, ensure leak detection systems are fitted and verified where required, and recover refrigerant before dismantling or disposal. Technicians must hold a valid F-gas certificate at the right category, work to the required standard, avoid deliberate release, and refuse to vent gas even when instructed.

Environmental impact

The two harms are different and are measured differently. ODS deplete stratospheric ozone, measured by ODP: CFC-12 is the reference at 1.0, and R-22 is 0.055 - small but real, which is why virgin HCFC was withdrawn from service use. F-gases do not attack ozone but are potent greenhouse gases; GWP and atmospheric lifetime together describe the climate damage. R-404A's GWP of 3922 means it is nearly 4000 times more warming than the same mass of CO2.

Traps

  • "A small leak is acceptable." No - the regulation prohibits intentional release and requires every feasible precaution to prevent leakage.
  • Purging, blowing through a line or venting residual pressure during recovery is an offence however small the charge.
  • The duty sits with the operator, but a technician who releases gas can also be prosecuted.
  • Environmental impact of ODS is not measured by GWP alone; questions mix ODP and GWP deliberately.

Rule of thumb

One kilogram of R-410A (GWP 2088) released equals about 2.1 t CO2e - roughly the annual tailpipe emissions of an average UK petrol car. One kilogram, one car, one year: that single comparison explains why repeated top-ups without repair are treated so seriously.

Refrigerant Safety: Classification, Asphyxiation, Pressure and Decomposition

Classification

ASHRAE 34 / ISO 817 give each refrigerant a toxicity letter (A = lower toxicity, B = higher) and a flammability number (1 = none, 2L = lower flammability, 2, 3 = higher). R-410A, R-134a, R-407C and R-744 are A1; R-32 and R-1234yf are A2L; R-290 propane is A3; ammonia R-717 is B2L. Know where your refrigerant sits before you plan the job.

The four main hazards

Asphyxiation: most halocarbons are heavier than air, so they collect in cellars, pits and plant rooms and displace oxygen with no warning smell. Ammonia, by contrast, is lighter than air and rises. Pressure: R-410A runs roughly 60% higher pressures than R-22, so hoses, gauges and recovery equipment must be rated for it and never mixed with R-22 kit. Cold burns: liquid refrigerant boils at around -40 °C on skin, causing instant frostbite and eye damage. Decomposition: a flame or hot surface on refrigerant produces hydrogen fluoride and carbonyl fluoride, so never braze or solder a charged line.

Traps

  • A2L does not mean "will not burn"; treat it as flammable for ignition sources, hot work and charge limits.
  • A leak in a basement does not disperse - ventilate and use a calibrated detector before entering.
  • Compressed air plus refrigerant and oil can form an explosive mixture; oxygen must never be used for purging or testing.
  • Frostbite from a liquid spill is worse under a watch or ring.

Rule of thumb

Any space below ground, without through-ventilation, or with no second exit is treated as a confined space: test the atmosphere, ventilate, and post a second person at the access point before anyone enters.

Cylinder Handling, Storage, Transport and Filling Limits

Before you move it

Check the label and confirm the refrigerant identity, the tare weight, the last periodic inspection date, the valve condition, and whether it is a dedicated recovery cylinder. Never rely on colour alone: colours differ between suppliers and countries, and an unlabelled or unidentifiable cylinder should be refused. Non-refillable "disposable" cylinders must not be placed on the market for HFCs.

Moving and storing

Secure the cylinder to a trolley or pallet, valve cap fitted, kept upright, never rolled, dragged or lifted by the valve. Store upright in a ventilated, dry area away from heat, direct sunlight and ignition, ideally below about 50 °C, and segregate flammable refrigerants from oxidisers. In a vehicle the cylinder is secured, ventilated and never carried in the passenger compartment.

Filling: weigh, never guess

Cylinder pressure reflects temperature and blend composition, not how full the cylinder is. Always fill on scales. Liquid fill must not exceed 80% of the cylinder's water capacity, which leaves a vapour space for expansion - a 12 kg cylinder therefore takes a maximum of 9.6 kg of liquid. Overfilling hydraulically locks the cylinder, and a modest temperature rise can then rupture it.

Traps

  • Judging charge or fill level from the pressure gauge.
  • Mixing two refrigerants in one recovery cylinder, which turns both into unidentifiable waste.
  • Using a cylinder that is out of test or has a damaged valve.
  • Filling a recovery cylinder to its nominal capacity rather than to 80%.

Worked example

A chiller holds 30 kg of R-410A. The recovery cylinders available hold 15 kg of liquid each, so usable capacity per cylinder is 15 × 0.8 = 12 kg. You need three cylinders, not two.

Risk Assessment and PPE Selection

The assessment

Five steps: identify the hazards, decide who may be harmed and how, evaluate the risks and decide on controls, record the significant findings, and review and update. It must be task-specific, completed before work starts, and reviewed whenever the task, the equipment, the people or the environment change. A site induction or a generic method statement is not a risk assessment.

The hierarchy of control

Eliminate the hazard, substitute something safer (a lower-GWP or lower-pressure refrigerant, a factory-sealed unit), apply engineering controls (ventilation, fixed gas detection, guarding, mechanical lifting), then administrative controls (permits, procedures, training, supervision), and only then PPE. PPE protects the individual; it does not reduce the hazard and must never be the primary control.

Typical PPE for this work

Chemical splash goggles plus a face shield when coupling hoses or charging; low-temperature gloves that are loose enough to pull off if liquid gets inside; safety footwear; hearing protection in plant rooms; a calibrated refrigerant detector; respiratory protection for ammonia; flame-retardant coveralls and a hot-work permit for brazing.

Traps

  • A question that offers PPE as the first or only control is almost always wrong.
  • Jewellery, watches and rings trap liquid refrigerant against skin.
  • Lone working, emergency arrangements and rescue plans are frequently forgotten.
  • The assessment is not "done once" - it is reviewed.

Worked example

Recovering 12 kg of R-404A from a rooftop condensing unit: obtain access and permit, isolate and lock off, assess wind and weather, barricade the area below, don PPE, set the recovery machine and correctly rated cylinder on scales, and check oxygen level and refrigerant concentration before and during the work.

Leak Checking, Containment, Records and Reporting

Frequency thresholds

Leak checks are triggered by tonnes CO2e, not by charge weight: 5 t or more - every 12 months; 50 t or more - every 6 months; 500 t or more - every 3 months. Each frequency halves (24, 12 and 6 months) where a fixed leak detection system is installed and verified, and that detection system must itself be checked at least every 12 months. Hermetically sealed, factory-labelled equipment below 10 t CO2e is exempt from periodic checks, but leaks found must still be repaired.

Methods

Direct methods include an electronic detector, soap solution, UV dye and standing vacuum tests. Indirect methods include F-gas monitoring, pressure and performance checks, and visual inspection for oil traces. A confirmed leak must be repaired as soon as practicable - normally within 14 days - and a follow-up check must verify the repair within one month.

Records

Records are kept by the operator for at least five years and must show: the refrigerant type and quantity, quantities added and recovered, the date and result of every leak check, and the name, certificate number and company of the person who did the work. They must be produced on request to the regulator.

Traps

  • Using kilograms instead of CO2e to decide frequency.
  • Forgetting that verifying the leak detection system is a separate annual task.
  • Records showing repeated top-ups with no leak check in between - a classic enforcement trigger.
  • Assuming there is no reporting duty: records must be available for inspection, and company certification and waste transfer notes must be traceable.

Worked example

20 kg of R-407C (GWP 1774) = 35.5 t CO2e. That is above 5 t and below 50 t, so quarterly checks are not required: 12-monthly, or 24-monthly with a verified fixed detection system.

Installation, Commissioning, Pressure Testing and Evacuation

Pressure testing

Use oxygen-free nitrogen (OFN) only, fed through a regulator, with the system isolated and relief devices protected. Never use oxygen, compressed air or refrigerant to pressure-test: oxygen plus oil can explode, and testing with refrigerant proves nothing while creating a release. Test to the pressure specified by the manufacturer or system design - commonly 1.0 times the maximum allowable pressure for a tightness test - allow the pressure to stabilise, and record the pressure alongside the ambient temperature so you can correct for temperature drift before declaring a leak.

Evacuation and dehydration

Evacuate with a two-stage vacuum pump and read the vacuum at the furthest point with an electronic vacuum gauge, not with manifold gauges. A typical target is 500 microns (about 0.67 mbar) absolute, held for a decay test; a triple evacuation with nitrogen breaks is the reliable way to remove moisture. A vacuum that holds demonstrates dryness and gross tightness - it is not a substitute for the pressure test.

Charging and commissioning

Charge by weight from scales. Zeotropic blends such as R-407C and R-404A must be charged as liquid, because vapour charging fractionates the blend and shifts its composition and performance. Record the OFN test, the vacuum results, the final charge, and all control settings.

Traps

  • Using refrigerant to "blow through" or pressure-test a system.
  • Reading vacuum from manifold gauges - they are not accurate enough.
  • Vapour-charging a zeotropic blend.
  • Condemning a system as leaking when the overnight pressure drop was simply a fall in ambient temperature.

Rule of thumb

A pressure that varies with temperature is not evidence of a leak; a pressure that keeps falling after correcting to a reference temperature is.

Servicing, Recovery, Recycling and Decommissioning

Service work

Leak check before and after the work. Recover the charge to a dedicated cylinder before breaking into the circuit, replace filter driers whenever the system is opened, purge with OFN while brazing, evacuate, recharge by weight, and update the record. Never simply top up a system to "get it running" - the leak still has to be found and repaired.

Recovery

Recover into an evacuated, weighed, dedicated cylinder using a recovery machine, or push-pull for large charges. Do not exceed the 80% liquid fill limit, and use the machine's final pull-down stage to remove residual vapour. Recovery is mandatory for every F-gas and ODS before the circuit is opened or the equipment is dismantled or scrapped. Venting is prohibited.

Recycling versus reclaiming

Recycling is cleaning recovered refrigerant by separating oil and moisture, suitable for reuse - normally in the same equipment or by the same owner. Reclaiming is reprocessing to a published specification with laboratory analysis, and only reclaimed refrigerant may be used in another owner's equipment or sold on. Recovered ODS such as R-22 can only be destroyed.

Decommissioning

Recover all refrigerant and record the quantity, cap or remove components, send the equipment for WEEE-compliant disposal, and give the operator a decommissioning record. Label every cylinder of recovered or contaminated gas with the refrigerant, quantity, date and its waste status.

Traps

  • Calling a filtered recovery "reclaimed".
  • Mixing gases in one cylinder.
  • Assuming a small system may be vented.
  • Forgetting the waste transfer documentation for recovered gas.

Worked example

A 30 kg R-410A chiller: required cylinder liquid capacity is 30 ÷ 0.8 = 37.5 kg, so at least three 15 kg cylinders are needed.

C&G 2079-11 F-Gas Category I cheat sheet

Quick reference

F-gas and ODS Regulations

  • UK F-gas controls cover HFCs, PFCs and SF6; ODS controls cover CFCs, HCFCs, halons and other ozone-depleting substances.

  • Category I certification permits work on all RAC equipment, including leak checking, charging, recovery, recycling and decommissioning.

  • CO2e = refrigerant charge (kg) × GWP ÷ 1,000; this value determines leak-check frequency and record thresholds.

  • Common GWPs: R-134a 1430, R-32 675, R-410A 2088, R-404A 3922, R-407C 1774; CO2 has GWP 1.

  • HCFC R-22 has ODP 0.055 and GWP 1810; virgin HCFC supply for refrigeration is phased out under ODS rules.

  • F-gas equipment must be labelled with refrigerant type, charge in kg and CO2e, and GWP; labels must remain legible and maintained.

  • Deliberate venting of F-gas or ODS is prohibited; recovered refrigerant must be recycled, reclaimed or destroyed by authorised routes.

  • Certified companies and personnel must be registered; records of certification and refrigerant transactions support compliance checks.

Quick reference

Legal Duties and Environmental Impact

  • The operator is legally responsible for leak prevention, periodic checks, record keeping, recovery and use of certified personnel.

  • F-gas leakage adds to global warming; ODS leakage also depletes stratospheric ozone and increases UV reaching the surface.

  • A 1 kg release of R-410A has a CO2e of about 2.09 tonnes; a 1 kg release of R-404A is about 3.92 tonnes.

  • Leakage lowers system efficiency and capacity, raising energy use and indirect CO2 emissions over the equipment life.

  • Records must be kept for at least five years and produced to an enforcement officer on request.

  • Only competent, certified persons may install, service, leak check or recover controlled refrigerants; company certification is separate from personal certification.

  • Penalties for breaches include improvement notices, prohibition notices, fines and prosecution under environmental and F-gas legislation.

  • Environmental harm from ODS includes ozone depletion; from F-gases includes long atmospheric lifetime and high GWP.

Quick reference

Refrigerant Safety

  • ASHRAE safety groups: A1 lower toxicity/no flame propagation; A2L lower flammability; A3 higher flammability; B classes higher toxicity.

  • R-32, R-454B and R-1234yf are A2L; R-290 (propane) and R-600a (isobutane) are A3; R-410A and R-134a are A1.

  • Refrigerant vapour is denser than air and can accumulate in pits, basements and plant rooms, displacing oxygen.

  • Liquid refrigerant at atmospheric pressure boils near -30 to -50 °C and causes frostbite on contact with skin or eyes.

  • Refrigerant exposed to flames or high temperature can decompose to hydrogen fluoride, carbonyl fluoride and other toxic products.

  • Oxygen-free nitrogen is the only acceptable pressure-test gas for RAC systems; oxygen and air can form explosive mixtures with oil.

  • Never mix refrigerants; mixed refrigerant cannot be returned to original specification and may produce unexpected pressures and temperatures.

  • A refrigerant leak in a confined space requires evacuation, ventilation and appropriate respiratory protection before entry.

Quick reference

Cylinder Handling, PPE and Risk Assessment

  • Recovery cylinders must be approved for the refrigerant, within test date, undamaged and fitted with correct valve and dip tube.

  • Cylinder fill limit is by weight and commonly 80% of water capacity; overfilling can cause hydraulic rupture or relief-valve release.

  • Cylinders are stored upright, secured, valve-protected, away from heat, ignition sources and direct sunlight.

  • Cylinder colour codes and UN labels identify contents; never rely on colour alone-check the valve label and markings.

  • PPE selection follows risk assessment: safety glasses, chemical gloves, safety footwear, and flame-retardant or respiratory protection where required.

  • Risk assessment hierarchy: eliminate exposure, substitute safer refrigerant, engineer controls, adopt safe system of work, then PPE.

  • Cylinder transport requires valve caps, restraint, ventilation and segregation from oxidisers and flammable gases.

  • A cylinder that has been heated or damaged must be treated as hazardous and isolated; do not attempt to move it if pressure is rising.

Quick reference

Leak Checking, Containment, Record Keeping and Reporting

  • CO2e thresholds: 5–50 t check every 12 months; 50–500 t every 6 months; ≥500 t every 3 months.

  • Hermetically sealed equipment below 10 t CO2e is exempt from periodic leak checks but still subject to leak prevention and record duties.

  • A verified automatic leak detection system halves the required check frequency for the 50–500 t and ≥500 t bands.

  • Leak detection systems must be verified at least every 12 months and records of verification retained.

  • Records include equipment ID, refrigerant, charge, CO2e, check date, findings, repairs, technician and leak-detection verification.

  • Leaks must be repaired as soon as practicable; repaired areas require follow-up checks and records.

  • Containment measures include minimising joints, protecting pipework, controlling vibration, using correct materials and avoiding unnecessary charge.

  • Reporting obligations include records of refrigerant purchases, recovery, recycling, reclamation and destruction, retained for five years.

Quick reference

Installation, Commissioning, Pressure Testing and Evacuation

  • Installation must follow manufacturer instructions, EN 378 principles and applicable building, electrical and refrigerant safety standards.

  • Pressure testing uses oxygen-free nitrogen with a regulated source; test pressure must not exceed component or system design limits.

  • Pressure tests are increased in stages and held at each stage; test pressure, duration, gas and result are recorded.

  • Never use oxygen, compressed air or refrigerant to pressure test; oil and oxygen can ignite.

  • Triple evacuation uses nitrogen breaks between vacuum stages to remove moisture and non-condensables.

  • Final vacuum is commonly 500 microns (0.67 mbar) or manufacturer's specification; a standing vacuum test confirms no rise.

  • Charge refrigerant by weight using a calibrated scale; record actual charge and adjust superheat/subcooling to commissioning data.

  • Commissioning checks include electrical safety, rotation, controls, safety devices, leak test, insulation and documentation.

Quick reference

Servicing, Maintenance, Recovery, Recycling and Decommissioning

  • Service work begins with system identification, refrigerant check, risk assessment, isolation and recovery of refrigerant where required.

  • Recovery removes refrigerant; recycling cleans it on site; reclamation reprocesses to specification with laboratory analysis.

  • Recovery cylinders must be labelled with refrigerant, owner, date and gross/tare weights; mixed refrigerants are labelled as mixtures.

  • Recovered refrigerant must not be vented; it is recycled, reclaimed, destroyed or returned to an authorised processor.

  • Before brazing, recover refrigerant and purge with nitrogen; refrigerant or oil exposed to flame forms toxic decomposition products.

  • Decommissioning includes recovery of all refrigerant, recording quantity, disconnecting, labelling, removing components and authorised disposal.

  • Compressor oil may contain dissolved refrigerant; do not drain or open until pressure is released and refrigerant recovered.

  • After servicing, leak test, evacuate, recharge by weight, record work and verify safety controls before return to service.

C&G 2079-11 F-Gas Category I key terms

Fluorinated greenhouse gas (F-gas)

A synthetic gas containing fluorine that traps heat in the atmosphere, used in refrigeration and air conditioning. Common examples include HFCs, HFOs, PFCs and SF6.

Related: Global warming potential (GWP), CO2 equivalent (CO2e), Ozone-depleting substance (ODS)
Ozone-depleting substance (ODS)

A substance such as CFC or HCFC that destroys stratospheric ozone when released. Their use in new refrigeration equipment is banned or tightly restricted.

Related: Ozone depletion potential (ODP), Fluorinated greenhouse gas (F-gas)
Global warming potential (GWP)

A number showing how much one kilogram of a gas contributes to global warming over 100 years compared with carbon dioxide, which has a GWP of 1.

Related: CO2 equivalent (CO2e), Fluorinated greenhouse gas (F-gas)
Ozone depletion potential (ODP)

A relative score for how strongly a substance destroys ozone in the stratosphere, with CFC-11 set at 1.0. Lower values indicate less ozone damage.

Related: Ozone-depleting substance (ODS)
CO2 equivalent (CO2e)

The mass of refrigerant multiplied by its GWP, giving a common unit for comparing climate impact. It is used in F-gas records, leak thresholds and carbon reporting.

Related: Global warming potential (GWP), Refrigerant charge
Company F-gas certification

Legal approval for a business to carry out F-gas activities such as installation, servicing or recovery. It requires competent staff, written procedures and proper record keeping.

Related: F-gas competence certificate, Competent person
F-gas competence certificate

A personal qualification showing that a technician has passed the required assessment to handle fluorinated refrigerants legally and safely. Category I covers the widest range of activities.

Related: Company F-gas certification, Competent person
Refrigerant charge

The amount of refrigerant contained in a system, usually stated on the nameplate in kilograms. Charge size determines leak-check frequency and CO2e reporting.

Related: CO2 equivalent (CO2e), Leak check frequency
Leak check frequency

The legally required interval for inspecting an F-gas system for leaks, based on its CO2e charge. Larger charges need more frequent checks and automatic leak detection.

Related: CO2 equivalent (CO2e), Leak detection system, Reportable leak
Leak detection system

Fixed or portable equipment that senses escaping refrigerant and raises an alarm. Fixed systems are mandatory for some large F-gas charges and must be tested regularly.

Related: Leak check frequency
Reportable leak

A leak that must be recorded, repaired and rechecked under F-gas rules. The threshold and repair deadline depend on charge size and system type.

Related: Leak check frequency, Refrigerant logbook
Hermetically sealed system

A factory-sealed refrigeration circuit with no service valves or accessible connections. It is treated differently for leak checks because its charge is small and release risk is lower.

Related: Leak check frequency, Refrigerant charge
Refrigerant logbook

A record of refrigerant added, recovered, leak checks, repairs and cylinder movements. It provides an audit trail for legal compliance and environmental reporting.

Related: F-gas register, Reportable leak
F-gas register

A formal record listing equipment containing F-gases, charge sizes, CO2e, leak checks and repairs. It must be kept available for inspection by the regulator.

Related: Refrigerant logbook, CO2 equivalent (CO2e)
Containment

Practical measures that prevent refrigerant from escaping, such as tight joints, regular leak checks, proper recovery and prompt repair of faults.

Related: Leak check frequency, Recovery
Risk assessment

A documented process that identifies hazards, evaluates who could be harmed and sets controls before work starts. It must cover refrigerant, pressure, electricity and confined spaces.

Related: Personal protective equipment (PPE), Asphyxiation risk
Personal protective equipment (PPE)

Clothing and equipment worn to reduce exposure to hazards, such as safety glasses, gloves, boots and breathing protection. It is the last line of defence after engineering controls.

Related: Risk assessment, Safety data sheet (SDS)
Safety data sheet (SDS)

A supplier document giving hazard, handling, first-aid, storage and disposal information for a refrigerant or chemical. It must be consulted before using an unfamiliar product.

Related: Personal protective equipment (PPE), Risk assessment
Asphyxiation risk

The danger that escaping refrigerant displaces oxygen in a confined space, causing dizziness, unconsciousness or death. Work areas must be ventilated and gas detection used where needed.

Related: Risk assessment, A2L refrigerant
A2L refrigerant

A refrigerant classification for lower-flammability gases such as R32. A2L refrigerants burn weakly but still require ignition-source control, ventilation and leak detection.

Related: Risk assessment, Leak detection system
Refrigerant cylinder

A pressure vessel designed to store and transport refrigerant. It must be within test date, correctly labelled, upright and protected from heat and impact.

Related: Cylinder hydrostatic test, Cylinder valve
Cylinder hydrostatic test

A periodic pressure test confirming that a refrigerant cylinder remains safe to use. The test date is stamped on the cylinder; out-of-date cylinders must not be filled.

Related: Refrigerant cylinder, Recovery cylinder
Cylinder valve

The manual valve at the top of a refrigerant cylinder that controls flow. It must be opened slowly, kept clean and closed before moving or storing the cylinder.

Related: Refrigerant cylinder
Pressure test

A test that pressurises a system with dry nitrogen or inert gas to prove strength and tightness. Oxygen-free nitrogen is used; oxygen and refrigerant mixtures must never be used.

Related: Leak test (nitrogen), Evacuation
Leak test (nitrogen)

A tightness check using dry nitrogen and a pressure gauge or bubble solution, often after brazing. It must be done before evacuation and charging.

Related: Pressure test, Evacuation
Evacuation

Removing air and moisture from a refrigeration circuit with a vacuum pump to a specified low pressure. Proper evacuation prevents ice, acid and poor performance.

Related: Triple evacuation, Micron gauge
Triple evacuation

A dehydration method that pulls a vacuum, breaks it with dry nitrogen, and repeats the cycle three times. It removes moisture and non-condensable gases more reliably than a single evacuation.

Related: Evacuation, Micron gauge
Micron gauge

A vacuum instrument that measures very low absolute pressure in microns. It is used to confirm that evacuation has reached the required level before charging.

Related: Evacuation, Triple evacuation
Commissioning

The process of checking, adjusting and documenting a newly installed system so it operates safely and efficiently. It includes pressure testing, evacuation, charging and performance checks.

Related: Pressure test, Evacuation
Recovery

Removing refrigerant from a system into a suitable container without releasing it to the atmosphere. Recovery is required before service, repair or decommissioning.

Related: Recovery cylinder, Recycling, Decommissioning
Recycling

Cleaning recovered refrigerant on site by removing oil, moisture and particles so it can be reused in the same or similar equipment. It does not restore the refrigerant to virgin specification.

Related: Recovery, Reclamation
Reclamation

Reprocessing recovered refrigerant to a specified standard, usually by an off-site specialist, with analysis and certification. Reclaimed refrigerant can be used as a replacement product.

Related: Recycling, Recovery
Decommissioning

Permanently taking a refrigeration system out of service. It includes recovering all refrigerant, isolating utilities, removing the equipment and recording the final refrigerant fate.

Related: Recovery, Refrigerant logbook
Recovery cylinder

A cylinder specifically used to receive recovered refrigerant. It must be clearly labelled, not overfilled, and have a valid test date.

Related: Recovery, Cylinder hydrostatic test
Nitrogen purge

Passing dry nitrogen through a pipe while brazing to stop oxidation inside the system. It prevents scale and contamination that damage compressors and valves.

Related: Pressure test, Evacuation
Pressure relief valve

A safety device that opens automatically to release excess pressure from a refrigerant circuit or vessel. It protects against rupture and must never be blocked or capped.

Related: Pressure test, Risk assessment
Competent person

Someone with the training, knowledge and experience to carry out a task safely and legally. In F-gas work, competence must be demonstrated through recognised certification.

Related: F-gas competence certificate, Company F-gas certification

C&G 2079-11 F-Gas Category I study plan

8 weeks · About 7 hours per week

Week 1

F-gas and ODS regulations, legal duties and environmental impact

  • List the core legal duties of a certified F-gas operative and state which activities are restricted to certified personnel and certified companies

  • Explain global warming potential and ozone depletion potential, then rank the main refrigerant families (HFCs, HFOs, CO2, ammonia, hydrocarbons, CFCs/HCFCs) by environmental impact

  • Convert refrigerant charge weights into CO2-equivalent tonnes using GWP values and apply the resulting thresholds to real system examples

  • Identify the environmental consequences of refrigerant venting and the correct legal route for disposing of recovered ODS and F-gas

  • Summarise the penalties, enforcement routes and record-retention periods that apply to non-compliance

Your checkpoint

A one-page GWP-to-CO2e conversion table with five worked examples plus 15 self-written questions on legal duties, scored at 80% or better

Week 2

F-gas and ODS regulations, legal duties and environmental impact & Leak checking, containment, record keeping and reporting obligations

  • Build a leak-check frequency matrix from CO2e band, system type and whether a leak detection system is fitted

  • State the statutory intervals for re-checking after a leak is repaired and for verifying that a repaired leak is sealed

  • Complete a compliant F-gas equipment record for a fictitious system, including charge history, leak checks and repairs

  • Describe who must be notified, in what form and within what timeframe when a reportable leak occurs

  • Explain the labelling, containment and record-transfer duties that apply when a system changes hands

Your checkpoint

A leak-check schedule matrix covering five system sizes plus a fully completed sample equipment record and leak report

Week 3

Installation, commissioning, pressure testing and evacuation of RAC systems

  • Plan the installation sequence for a split and a small packaged system, listing the isolation, brazing, pipework and electrical checks required at each stage

  • Calculate strength-test and tightness-test pressures for R410A, R32 and R134a systems and distinguish when each test is mandatory

  • Specify the correct test gas, regulator, gauge class and test duration, and state why oxygen and air must never be used

  • Write an evacuation and dehydration procedure including triple evacuation, vacuum hold test and micron-level acceptance criteria

  • Draft a commissioning checklist covering charge verification, superheat/subcool, safety controls and handover documentation

Your checkpoint

A written commissioning procedure with calculated test pressures and vacuum targets for three refrigerants, plus 15 pressure and vacuum calculation problems solved correctly

Week 4

Installation, commissioning, pressure testing and evacuation of RAC systems & Servicing, maintenance, refrigerant recovery, recycling and decommissioning

  • Explain why pipework is nitrogen-purged during brazing and describe the checks that detect a poor purge

  • Select and justify test instruments, stating the accuracy, calibration and range requirements for pressure and vacuum measurement

  • Compare vapour, liquid and push-pull recovery methods and select the right one for a given system and refrigerant state

  • Calculate the maximum fill weight for a recovery cylinder from its water capacity and the refrigerant density, applying the 80% fill limit

  • Identify the hazards and controls for recovering a flammable refrigerant from a system containing residual charge

Your checkpoint

A timed 40-question mixed paper across domains 1, 3 and 4, completed in 60 minutes with a score of 75% or better and an error log in your own words

Week 5

Servicing, maintenance, refrigerant recovery, recycling and decommissioning

  • Distinguish recovery, recycling, reclaiming and destruction, and state which processes a Cat I operative may carry out on site

  • Write a decommissioning procedure for a system containing ODS, including pump-down, isolation, oil handling and cylinder labelling

  • Describe how recovered refrigerant is documented, stored, transported and consigned for destruction or reclaim

  • Explain the risks of mixing refrigerant types and the checks that prevent cross-contamination of recovery cylinders

  • Outline the correct handling and disposal routes for contaminated oil, filter driers and contaminated components

Your checkpoint

A written recovery and decommissioning procedure plus 12 scenario questions on recovered-refrigerant handling, scored at 80% or better

Week 6

Refrigerant safety, cylinder handling, PPE and risk assessment

  • Classify the main refrigerants by ASHRAE safety group and state the practical consequence of each class for working methods

  • Select appropriate PPE for a given task and explain the limitations of each item, including glove type and eye protection during liquid contact

  • Complete a five-step risk assessment and a dynamic on-site assessment for a live plant room job

  • Describe safe cylinder handling, storage, inspection and transport requirements, including valve protection and temperature limits

  • Identify asphyxiation, flammability, pressure-release, freeze-burn and electrical hazards and specify a control for each

Your checkpoint

Two completed risk assessments - one for an A2L system and one for an A3 system - plus a PPE selection matrix covering five different tasks

Week 7

Refrigerant safety, cylinder handling, PPE and risk assessment & Leak checking, containment, record keeping and reporting obligations

  • Work through scenario questions that combine safety decisions with leak-checking and record-keeping duties

  • Re-test every goal from weeks 1 to 6 and rank the weakest six by mock-question error rate

  • Practise explaining legal and technical points aloud in the concise style required by written exam answers

  • Review the error log and rewrite every missed question with the correct reasoning

Your checkpoint

A 60-question mixed bank across all five domains scored at 80% or better, with a dated error log showing each weak area and the action taken

Week 8

F-gas and ODS regulations, legal duties and environmental impact & Refrigerant safety, cylinder handling, PPE and risk assessment & Leak checking, containment, record keeping and reporting obligations & Installation, commissioning, pressure testing and evacuation of RAC systems & Servicing, maintenance, refrigerant recovery, recycling and decommissioning

  • Sit two full-length timed mock papers under exam conditions and record the score for each domain

  • Revisit the three lowest-scoring domain areas and close each gap with targeted revision

  • Memorise the key numbers - leak-check intervals, CO2e thresholds, test pressures, vacuum limits, cylinder fill limits - and self-test them from memory

  • Confirm the practical tasks and documentation you can perform confidently, and list anything still needing supervised practice

Your checkpoint

Two completed timed mock papers at 85% or better, with a final one-page revision sheet of key figures and a written list of remaining weak points

Milestones

Week 2: Can state the leak-check interval and post-repair re-check timing for any given charge size and system type without notes, and produce a compliant equipment record unaided

Week 4: Scores 75% or better on a timed 40-question paper covering domains 1, 3 and 4, and can calculate a strength-test pressure and a recovery cylinder fill limit correctly

Week 6: Produces a complete risk assessment in under 20 minutes and correctly assigns the safety group and required controls for six named refrigerants

Week 8: Achieves 85% or better on two full timed mocks with no single domain below 70%, and has no unresolved items on the error log

C&G 2079-11 F-Gas Category I exam day

Your checklist

Photo ID

Bring current photo identification (passport or photocard driving licence are the usual choices). Confirm with the provider which forms of ID it accepts and whether the name must match the booking exactly, as centres can refuse entry without valid ID.

Safety footwear and eye protection

Bring your own safety boots and safety glasses or goggles. Workshop rules usually require them for every practical task, including brazing, pressure testing and refrigerant handling. Confirm with the provider whether boots, glasses, gloves and coveralls are supplied or must be brought.

Overalls and hand protection

Loose-fitting overalls and suitable gloves protect against frostbite from liquid refrigerant, brazing sparks and oil. Confirm with the provider whether leather brazing gloves and cryogenic-rated gloves are provided or whether you must supply them.

Confirmation of booking and arrival details

Re-check the assessment date, start time, site address, parking, site access and signing-in procedure. Confirm with the provider if any of these are unclear, and note a contact number in case of delay.

Equipment list from the centre

Ask the provider in advance what is supplied: brazing set, pressure regulators, manifold gauges, vacuum pump and gauge, recovery machine, recovery cylinders, leak detector, charging scales and hand tools are normally centre equipment. Knowing this stops you turning up with prohibited or unnecessary items.

Copy of the assessment plan and unit outcomes

Read the practical task list before the day so you know the sequence of activities you will be asked to demonstrate, such as pipework fabrication, pressure testing, evacuation, charging, recovery, leak testing and record keeping.

Refreshed knowledge of record keeping and labelling

Be ready to explain and complete refrigerant records: what is logged, who keeps it, how long it is retained, and how equipment and cylinders are labelled. Assessment often checks paperwork as well as practical skill.

Revision of key procedures and numbers

Reread pressure testing with oxygen-free nitrogen, evacuation and dehydration, recovery cylinder filling limits, and safe charging methods. Know the reasons behind each step, because the assessor may ask you to explain as well as perform.

Notebook and pen

Useful for recording readings and making notes during practical tasks. Confirm with the provider whether notes are allowed in the assessment area or whether all recording must be on centre paperwork.

Refreshments, medication and personal needs

Practical assessments are long and physical. Bring water and any medication you may need, and tell the provider in advance about any medical condition, injury or additional support need that affects safe participation.

Travel and time buffer

Plan to arrive with time to spare. Brazing and pressure testing cannot be rushed, and lateness may mean you are not assessed. Check traffic, parking and public transport in advance.

Plan the day

Final 72 hours

Confirm the booking, site access, ID requirements and what PPE and tools the centre supplies. Re-read the assessment plan and list the practical tasks you will perform, then spend revision time on the areas you are least confident in: pressure testing, evacuation, charging, recovery and refrigerant records.

Final 72 hours (practical rehearsal)

Walk through each procedure mentally in the correct order, including the safety checks before and after: risk assessment, isolation, checking cylinder types and connections, purging hoses, weighing in and out, and leaving the work area safe and tidy. Practise explaining why each step is done.

Final 24 hours

Pack your bag with ID, PPE, overalls and any personal items. Confirm your travel plan and set an alarm. Keep revision light and focused on key safety points and record-keeping rather than trying to learn new material. Get a full night's sleep.

Morning of the assessment

Eat properly and arrive early enough to sign in, store your belongings and read any site safety information. Put on your PPE before entering the workshop. Listen carefully to the assessor's briefing and ask about anything you genuinely do not understand before work starts.

Start of the practical

Carry out and verbalise your risk assessment, check the equipment and work area, and confirm the task sequence with the assessor. Work steadily rather than fast, keep your bench organised, and record readings as you take them.

During the practical tasks

Follow the procedure in order: fabricate and assemble as required, pressure test with oxygen-free nitrogen, evacuate, charge by the correct method, leak test, recover refrigerant and complete the records. Handle refrigerant safely, avoid venting, and keep cylinders upright, secured and within filling limits.

During the written or online test

Read each question fully before answering, watch for negative wording such as 'not' or 'except', and flag questions you want to revisit. Answer every question, as there is usually no penalty for a reasoned attempt.

At the end of the day

Tidy the work area, return tools and cylinders, and make sure your paperwork is complete and legible. Ask the assessor or centre staff about results, feedback and the resit process if you are unsure what happens next.

Rules to check

  • Bring valid photo ID. The centre can refuse to assess you if identification is missing or does not match the booking, so confirm the accepted forms with the provider before the day.

  • Follow all site safety rules, including wearing the required PPE at all times in the workshop, obeying fire and emergency procedures, and using equipment only as instructed.

  • Work only on equipment you have been authorised to touch. Isolate and make safe before starting, do not vent refrigerant to atmosphere, and never leave brazing or pressure-testing operations unattended.

  • Treat the assessment as a real job. The assessor observes your working practices as well as your results, so communicate clearly, keep the area tidy and complete the paperwork accurately.

  • You may ask the assessor to clarify instructions or repeat the brief, but the assessor cannot give you answers or guide your technique. If something is genuinely ambiguous, ask before you begin the task.

  • Mobile phones and other personal devices should be switched off and stored away during assessment unless the provider says otherwise. Confirm the centre's policy on devices, notes and recording.

  • Breaks and timings vary between centres and assessment sessions. Confirm with the provider in advance how breaks are handled and whether the assessment can be paused.

  • Results, pass criteria and resit arrangements are set by the awarding organisation and the centre. Confirm with the provider how and when you will receive your result and what the appeals or resit process involves.

C&G 2079-11 F-Gas Category I FAQ

How many C&G 2079-11 F-Gas Category I practice questions are available?

The practice set has 200 C&G 2079-11 F-Gas Category I questions. Each one includes the choices, the correct answer, and an explanation, and the set is free to read with no signup.

How many C&G 2079-11 F-Gas Category I flashcards are available?

The flashcard set has 32 C&G 2079-11 F-Gas Category I cards. Each card shows the term and its definition.

Which topics does the C&G 2079-11 F-Gas Category I study material cover?

The C&G 2079-11 F-Gas Category I study material has 5 sections, including F-Gas and ODS Regulations: Scope, Numbers and Thresholds, Legal Duties, Operator Responsibility and Environmental Impact, and Refrigerant Safety: Classification, Asphyxiation, Pressure and Decomposition.

What format facts does the catalog list for the C&G 2079-11 F-Gas Category I exam?

The catalog lists these item types: multiple choice and practical assessment for the C&G 2079-11 F-Gas Category I exam.