NCCCO Mobile Crane Practice Test

NCCCO Mobile Crane Operator Certification

NCCCO Mobile Crane overview

  • 199 practice questions
  • 32 flashcards
  • 6 study guide topics
  • 40 key terms

What you'll study

  • Site and Equipment Inspection12%
  • Crane Setup and Configuration15%
  • Crane Operation33%
  • Load Chart Use and Capacity Determination25%
  • Communication and Hand Signals5%
  • Safety, Standards, and Operator Responsibilities10%

NCCCO Mobile Crane Operator certification is a professional credential for people who run telescopic boom and lattice boom mobile cranes on construction, industrial, and utility sites. It is issued by the National Commission for the Certification of Crane Operators (NCCCO). This page is an independent study resource and is not affiliated with, endorsed by, or sponsored by NCCCO - always confirm current requirements in the official candidate handbook.

The credential has two parts. Written exams are computer-based and multiple choice, and they are taken separately for each crane type and configuration - typically fixed cab, swing cab, and lattice boom. The practical exam is a hands-on test in which you demonstrate a pre-shift inspection, setup, and controlled load handling in front of a NCCCO practical examiner. Certification runs on a five-year cycle and must be renewed.

The written content splits roughly into site and equipment inspection, setup and configuration, operation, load chart use and capacity determination, communication and hand signals, and safety and operator responsibilities. Load charts and machine operation carry the most weight, so build your study time around them.

Preparation works best as a mix of hands-on seat time and deliberate chart drills: work through actual capacity problems for your crane's configuration, learn to apply notes and deductions, and rehearse hand signals and the practical sequence until they are automatic.

Common mistakes

The candidate reads a capacity out of the boom-length/radius table using an estimated or 'eyeballed' radius instead of walking off the actual operating radius from the crane's center of rotation to the center of gravity of the load, and does not re-check radius after booming up or telescoping.

Candidates carry over the habit of measuring distance to the boom tip or to the edge of the load, and they forget that radius changes the moment the boom angle changes or the load swings. Exam distractors are built from the value one column over from the correct radius.

What to do instead

Practice a fixed procedure: mark center of rotation, drop a plumb line from the hoist line at the load's center of gravity, measure horizontally, then re-measure after any boom movement. In chart questions, first write down radius, boom length, and configuration before touching the table.

The candidate compares the bare load weight to the chart capacity and forgets to add the weight of rigging, hook block, and any boom-mounted attachments (jib, auxiliary head, stowed extension) to get gross load.

The load weight is the only number written on the lift paperwork, so it feels like the whole load. Deduction items are invisible at the moment of the calculation and are usually small enough that the candidate assumes they don't matter.

What to do instead

Before opening the chart, write a deduction list (hook block, slings/shackles, spreader beam, jib/attachment, personnel platform) and total it. Compare gross load to chart capacity, never net load. For chart questions, scan the notes for stated deduction requirements first.

The candidate uses a chart page or column that does not match the actual machine configuration - full outriggers when the beams are only mid-extended, 'on rubber' values when set on outriggers, or the highest value in the table instead of the column for the actual swing area and boom-mounted equipment.

Modern load charts have multiple pages per boom length and separate structural and stability limits, and candidates grab the first number they find. Under exam time pressure, the largest number on the page looks like the answer.

What to do instead

Establish configuration before looking at the chart: outrigger state, boom length, swing area, attachments, counterweight. Then read only the matching page and the matching column; where two limits apply, use the lower one. In questions, eliminate any answer derived from a configuration the stem did not describe.

The candidate accepts a setup on unverified ground - no mats or undersized pads, near a trench, backfill, or a slope - or does not confirm the crane is level on the bubble level before the lift, then uses full-capacity chart values.

Setup errors are invisible in a written question and the candidate focuses on the lift itself. Out-of-level and soft-foot conditions feel like a 'field judgment' issue rather than a capacity issue.

What to do instead

Treat level and ground bearing as part of the capacity calculation: level the crane per the manufacturer's tolerance, size mats to the outrigger float pressure, and confirm the ground can carry it (compaction, voids, utilities, excavations). In questions, any scenario with soft ground, slope, or missing pads should push you toward derating or refusing the setup.

The candidate performs a box-checking walkaround that misses the items most likely to fail the machine: wire rope defects (broken wires, kinks, birdcaging, core protrusion, corrosion), a missing or expired annual/comprehensive inspection, hydraulic leaks, or damaged anti-two-block components.

Routine inspections become a fast loop around the machine once a candidate is experienced, and the exam asks about specific removal criteria and inspection intervals rather than general 'check the crane'.

What to do instead

Study inspection as a component-by-component list with criteria: rope condition against the manufacturer's removal criteria, hook latch and throat opening, sheave wear, outrigger beam and pad condition, and the date/documentation for the periodic inspection. Know what the operator must find and document versus what grounds the machine.

The candidate skips the start-of-shift function test of operational aids and limit devices - anti-two-block, boom angle/radius indicator, level indicator, rated capacity limiter/load moment indicator - or cannot say what to do when one is malfunctioning.

These devices are treated as automatic, so testing them feels redundant. Candidates also blur the categories of operational aid versus safety device, and therefore misjudge whether the lift can proceed.

What to do instead

Make the test a physical ritual before every lift and learn the categories: which devices must be functional to lift, which require a documented derating or a controlled procedure if failed, and which prohibit operation entirely. On the exam, a stem describing an inoperative limit device is usually testing whether you stop.

The candidate confuses hand signals that look similar - raising versus lowering the boom, raising versus lowering the load, and standard stop versus emergency stop - or does not know that the operator must obey a stop signal from anyone on the site.

Signals are learned visually and fade without practice, and the one-hand/two-hand distinctions are easy to mix under exam pressure. The 'stop from anyone' rule is often learned as site folklore rather than as a hard requirement.

What to do instead

Drill the signals physically in pairs of opposites (boom up/boom down, load up/load down, extend/retract, raise/lower boom with load) and be able to describe each in words. Memorize that stop is obeyed from anyone, that emergency stop is distinct, and that unclear signals mean stop.

The candidate starts a lift without a communication plan - no qualified signalperson identified, no agreed radio channel or backup method, signalperson not in continuous view, or the operator continues the lift when a signal is ambiguous or the radio drops out.

Communication failures are procedural, not technical, so candidates underrate them. In practice the lift 'usually works,' which trains the operator to tolerate unclear signals.

What to do instead

Brief before the lift: who signals, hand signals versus radio, channel and test, line of sight, tagline handlers, and who has authority to stop. If communication is lost or a signal is unclear, stop and re-establish - answer exam questions with the stop-and-verify option, not the 'continue slowly' option.

The candidate side-loads the boom, drags or breaks a load out with the hoist line out of plumb, swings too fast, or ignores wind acting on the boom and the load's sail area.

These are habits formed to save time on site and are not obviously 'wrong' until something fails. Wind and side load are absent from the numbers the candidate is used to checking.

What to do instead

Keep the hoist line plumb over the load's center of gravity, break the load free before hoisting, control swing with taglines and smooth starts/stops, and check the manufacturer's wind limits and the load's sail area before lifting. On questions, any option that pulls sideways, jerks, or ignores wind is a distractor.

The candidate works near energized power lines without confirming the voltage and required minimum approach distance, treats the distance as applying only to the boom, or proceeds without a dedicated spotter, barriers, or a de-energizing/grounding decision.

Candidates memorize a single number instead of the voltage-based table, and they picture the boom tip as the only contact risk rather than the load, rigging, and taglines.

What to do instead

Learn the approach-distance table by voltage range and apply it to every part of the crane, the load, and the rigging. Know the hierarchy: de-energize and ground, or maintain the distance with a spotter and warned/barricaded zone, and know when the utility must be involved. In questions, missing voltage information usually means the lift cannot be planned yet.

Exam requirements can change. Confirm current details with the exam provider.

NCCCO Mobile Crane practice

199 questions. Each one lists the choices, the correct answer, and an explanation. With JavaScript, this list opens one question at a time. The checker at the top of this page saves progress in this browser when it is available.

  1. Question 1Site and Equipment Inspection

    Who is required to perform the shift inspection of a mobile crane before it is used?

    1. The site superintendent for the project
    2. The operator assigned to run the crane Correct answer.
    3. The crane owner's maintenance technician
    4. The rigging crew foreperson on shift

    Explanation

    A competent person, normally the assigned operator, must inspect the crane before each shift it is used. The inspection covers controls, safety devices, wire rope, and the items listed in the operator's manual. Any defect affecting safe operation must be corrected before the crane is put to work.

  2. Question 2Site and Equipment Inspection

    What is the primary purpose of the latch on a crane hook?

    1. To show that the hook has been load tested
    2. To keep slings and rigging from slipping off the hook Correct answer.
    3. To let the hook swivel freely under load
    4. To increase the hook's rated load capacity

    Explanation

    The latch keeps slings, shackles, and other attachments from slipping off the hook when the line goes slack or the load shifts. It is not a load-bearing component and does not change the hook's rated capacity. A hook with a missing or broken latch is removed from service.

  3. Question 3Site and Equipment Inspection

    What is the minimum portable fire extinguisher rating required on a mobile crane?

    1. 20 BC
    2. 10 ABC
    3. 5 BC Correct answer.
    4. 2 A

    Explanation

    Mobile cranes must carry a portable fire extinguisher rated at least 5 BC. Class BC units are effective on the energized electrical and flammable-liquid fires most common around crane operations. A higher rating is acceptable; a lower one is not.

  4. Question 4Site and Equipment Inspection

    Which hand signal tells the crane operator to stop?

    1. Both arms extended forward, palms up, raised and lowered
    2. Arm extended, palm down, moved back and forth horizontally Correct answer.
    3. One arm extended out with hand open, moved in a circle
    4. Arm extended upward with fist closed, moved in small circles

    Explanation

    The standard stop signal is the arm extended with the palm down, moved back and forth horizontally. Standard signals must be used consistently by every signal person so the meaning is never in doubt. Any signal person may give the stop signal at any time.

  5. Question 5Site and Equipment Inspection

    Why is a tag line used when handling a load?

    1. To increase the lifting capacity of the crane
    2. To measure how far the load has traveled
    3. To control load rotation and swinging without touching the load Correct answer.
    4. To add a second point of support to the load

    Explanation

    A tag line lets a worker outside the fall zone steady and guide the load as it moves. It does not support any of the load weight or change the crane's capacity. Workers must never wrap a tag line around a hand or body.

  6. Question 6Site and Equipment Inspection

    What does the anemometer mounted on a crane measure?

    1. The hydraulic pressure in the boom circuit
    2. The radius from the crane to the load
    3. The angle of the boom above horizontal
    4. The wind speed at the crane Correct answer.

    Explanation

    An anemometer measures wind speed so the operator can compare it with the manufacturer's limit and stop lifting when that limit is reached. Wind limits are found in the operator's manual and load chart notes. Boom angle and radius are shown by separate indicators.

  7. Question 7Site and Equipment Inspection

    When must rigging slings be inspected for damage?

    1. Only when the annual crane inspection is done
    2. Once each month by a qualified person
    3. Before each use, by the person using them Correct answer.
    4. Only after a load has been dropped

    Explanation

    Slings must be inspected before each use by the person who will use them, in addition to documented periodic inspections. Frequent inspection catches cuts, broken wires, and stretched links before a load is committed. Damaged slings are tagged out and removed from service.

  8. Question 8Site and Equipment Inspection

    A running wire rope of 6x19 classification must be removed from service when it shows:

    1. Two randomly distributed broken wires within one full lay
    2. Six broken wires randomly distributed in one lay Correct answer.
    3. Any single broken wire found anywhere along the rope
    4. Two broken wires in a single strand within one full lay

    Explanation

    For 6x19 and 6x37 running ropes, removal is required at 6 randomly distributed broken wires in one lay, or 3 broken wires in one strand in one lay. Isolated single wires are recorded and watched but do not by themselves require removal. These criteria apply to running ropes, not to rotation-resistant or standing ropes.

  9. Question 9Site and Equipment Inspection

    What is the main purpose of placing crane mats under outrigger floats?

    1. To keep the floats from scratching the pavement
    2. To raise the crane so the boom can reach higher
    3. To spread the outrigger load over a larger ground area Correct answer.
    4. To shorten the time needed to set up the crane

    Explanation

    Mats increase the area over which each outrigger force acts, reducing soil pressure and helping prevent settlement or punch-through. They do not change the crane's load chart or allow longer boom. Mat size and type are chosen from the actual ground bearing capacity.

  10. Question 10Site and Equipment Inspection

    For power lines rated up to 50 kV, the minimum required clearance between any part of the crane or load and the line is:

    1. 10 feet Correct answer.
    2. 20 feet
    3. 15 feet
    4. 4 feet

    Explanation

    The clearance table requires 10 feet for lines rated up to 50 kV, with greater distances as voltage rises. The clearance applies to the crane, boom, load line, and load. A signal person or dedicated spotter is used when the operator cannot see the clearance.

  11. Question 11Site and Equipment Inspection

    What does the anti-two-block device on a crane do?

    1. It prevents the hook block from contacting the boom tip Correct answer.
    2. It limits the crane to a preset load moment
    3. It stops the boom from being lowered too far
    4. It locks the outriggers while lifting

    Explanation

    The anti-two-block device senses when the hook block or headache ball approaches the boom tip and stops the hoist before the parts contact. Contact would part the hoist line and drop the load. The device must be functional before lifting begins.

  12. Question 12Site and Equipment Inspection

    A polyester web sling has a deep cut across its width. What is the correct action?

    1. Use it, but only for loads under half its rated capacity
    2. Use it only if the cut is shorter than one inch
    3. Wrap the cut area with tape before use
    4. Remove it from service and tag or destroy it Correct answer.

    Explanation

    Web slings with cuts, snags, burns, or holes must be removed from service no matter how much of the sling appears intact. Cutting load-bearing fibers reduces strength unpredictably, and the rated capacity no longer applies. Damaged slings are tagged and destroyed so they cannot return to service.

  13. Question 13Site and Equipment Inspection

    When installing wire rope clips to form an eye, the clip saddle must be placed:

    1. Against the short dead end of the rope
    2. Against the live, load-bearing end of the rope Correct answer.
    3. On the side of the rope that faces the load
    4. Alternating between the live and dead ends

    Explanation

    The saddle, the wide part of the clip, goes on the live load-bearing end, and the U-bolt straddles the dead end. Reversing this crushes the live rope and greatly reduces splice efficiency. Clips are spaced and torqued per the manufacturer, then retorqued after the first load.

  14. Question 14Site and Equipment Inspection

    In a correctly installed wedge socket, the live end of the wire rope should:

    1. Run in a straight line from the socket pin Correct answer.
    2. Be bent sharply around the wedge to lock it
    3. Pass around the wedge and exit the socket barrel
    4. Be secured with at least two wire rope clips

    Explanation

    The live end must leave the socket in line with the pin so the load pulls straight through the wedge. A side-loaded live end can let the wedge work loose. The dead-end tail is left long enough beyond the socket to meet the manufacturer's requirement.

  15. Question 15Site and Equipment Inspection

    A sheave groove is worn so badly that the wire rope bottoms out in the groove. What is required?

    1. Replace the sheave before further use Correct answer.
    2. Install a larger-diameter rope on the crane
    3. Fill the groove with weld and grind it smooth
    4. Continue using it if the rope is new

    Explanation

    When the rope bottoms out, the sheave pinches and abrades the strands and can flatten the rope. A sheave worn beyond the manufacturer's limits must be replaced, not repaired by welding. Groove diameter is checked during periodic inspection.

  16. Question 16Site and Equipment Inspection

    A screw-pin shackle shows wear at the bow measuring more than 10 percent of the original dimension. What should be done?

    1. Swap the pin for a new one and continue
    2. Use it only in a vertical, non-side-loaded hitch
    3. Return it to service after a visual check
    4. Remove it from service Correct answer.

    Explanation

    Wear exceeding 10 percent of the original bow or pin dimension is a removal criterion for shackles, along with cracks, nicks, and bent pins. The worn shackle is tagged out and destroyed so it cannot be reused. Pin replacement does not correct body wear.

  17. Question 17Site and Equipment Inspection

    What does the boom angle indicator on a mobile crane show?

    1. The angle of the outrigger beams to the ground
    2. The angle between the boom and the crane's axis
    3. The angle between the boom and horizontal Correct answer.
    4. The angle of the load line away from vertical

    Explanation

    The boom angle indicator shows the boom's angle above horizontal. That angle, with boom length, is used to determine radius and read the load chart. It indicates angle only and does not itself limit the load.

  18. Question 18Site and Equipment Inspection

    During inspection you find a crack in a load-bearing weld on the boom. The crane should be:

    1. Marked with paint and monitored for growth
    2. Operated only with the boom fully retracted
    3. Operated at reduced capacity until the next annual inspection
    4. Removed from service until repaired per the manufacturer Correct answer.

    Explanation

    Cracks in structural welds or boom sections can propagate quickly once the boom is loaded. The crane is removed from service until the manufacturer or a qualified person approves and completes a repair. Reduced capacity or monitoring does not make a cracked boom safe.

  19. Question 19Site and Equipment Inspection

    Which tire condition requires the crane to be taken out of service?

    1. Tread depth that is slightly uneven across the tire
    2. Cords or fabric visible through the tread Correct answer.
    3. Mud packed into the tread grooves
    4. A small amount of sidewall scuffing

    Explanation

    Tires with cord or fabric showing, deep cuts, bulges, or improper inflation are unsafe because a blowout during a lift can upset the crane. Tires and rims are part of the shift inspection. Cosmetic scuffing or packed mud does not by itself condemn a tire.

  20. Question 20Site and Equipment Inspection

    Crane load charts assume the crane is level. Unless the manufacturer specifies otherwise, the crane must be leveled to within:

    1. 0.5 percent of level
    2. 3 percent of level
    3. 1 percent of level Correct answer.
    4. 5 percent of level

    Explanation

    The setup requirements call for the crane to be leveled within 1 percent of level grade, unless the manufacturer requires a tighter tolerance. An out-of-level crane swings the load, side-loads the boom, and no longer matches the load chart. Level is verified with a bubble level or inclinometer on the crane.

  21. Question 21Site and Equipment Inspection

    The load moment indicator fails during setup on a lift that is about to begin. What is the correct action?

    1. Stop operation until the LMI is repaired and recalibrated Correct answer.
    2. Continue if the operator calculates loads manually
    3. Continue at 50 percent of charted capacity
    4. Continue if a second person watches the boom

    Explanation

    The LMI is a required operating aid, and the crane must be taken out of service when it is not functioning. Work resumes only after repair and recalibration by a qualified person. Manual calculations or reduced capacity do not substitute for a functioning LMI.

  22. Question 22Site and Equipment Inspection

    A crane is used in severe service. What is the minimum interval for its documented inspection?

    1. Every six months
    2. Annually
    3. Monthly Correct answer.
    4. Quarterly

    Explanation

    Cranes in severe service, such as high-cycle or harsh-environment use, must receive documented inspections at least monthly. All cranes still receive the annual periodic inspection. The severity of use determines whether the shorter interval applies.

  23. Question 23Site and Equipment Inspection

    For rotation-resistant wire rope, the crane must be removed from service when the rope shows:

    1. Two broken wires in 6 rope diameters Correct answer.
    2. Two broken wires in 30 rope diameters
    3. One broken wire in 30 rope diameters
    4. One broken wire in 6 rope diameters

    Explanation

    Rotation-resistant ropes have stricter criteria because broken wires concentrate and the rope can fail with less visible damage. Removal is required at 2 randomly distributed broken wires in 6 rope diameters or 4 in 30 rope diameters. Different criteria apply to standard 6x19 and 6x37 running ropes.

  24. Question 24Site and Equipment Inspection

    If the required power line clearance cannot be maintained, work may proceed only after:

    1. A dedicated signal person is posted beside the line to warn the operator
    2. The operator has completed an electrical hazard awareness course
    3. A warning flag has been attached to the boom tip by the rigger
    4. The line is de-energized and visibly grounded Correct answer.

    Explanation

    When the table clearance cannot be kept, the line must be de-energized and visibly grounded at the site, or the utility must confirm the line is isolated, before the crane works near it. Training, flags, and spotters do not make contact safe. Encroachment procedures must be documented in the lift plan.

  25. Question 25Crane Setup and Configuration

    What is the primary purpose of placing cribbing under a mobile crane's outrigger floats?

    1. To level the crane regardless of how uneven the ground is
    2. To spread the concentrated outrigger force over a larger area of ground Correct answer.
    3. To reduce the amount of counterweight needed for the lift
    4. To lengthen the effective reach of the outrigger beam

    Explanation

    Cribbing or mats increase the contact area beneath a float so the same force produces a lower bearing pressure on the soil. The goal is to keep that pressure below what the ground can support without settlement. Cribbing does not correct an out-of-level crane; the crane must already be level before lifting.

  26. Question 26Crane Setup and Configuration

    Before making a lift, a mobile crane on outriggers must be leveled to what standard?

    1. Leveling is unnecessary once all outriggers are fully extended
    2. Within 5 percent of level in any direction
    3. Within the manufacturer's stated tolerance, commonly about 1 percent of grade Correct answer.
    4. Within 10 degrees of level in any direction

    Explanation

    Load charts assume the crane is level within a small tolerance, typically around 1 percent of grade, because even a slight tilt changes radius and loads the outriggers unevenly. The manufacturer's published tolerance governs, and the level indicator must be checked before the lift. Full outrigger extension does not by itself make a crane level.

  27. Question 27Crane Setup and Configuration

    With boom length held constant, what happens to a crane's rated capacity as the working radius increases?

    1. Rated capacity depends only on the boom angle and not on radius
    2. Rated capacity decreases Correct answer.
    3. Rated capacity stays the same until the boom is nearly horizontal
    4. Rated capacity increases because the boom is steeper

    Explanation

    A larger radius increases the overturning moment produced by the load, so the charted capacity is reduced to keep the crane within its stability and structural limits. Boom angle and radius are directly related for a fixed boom length, but the chart itself is organized by radius. Capacity therefore falls as radius grows.

  28. Question 28Crane Setup and Configuration

    On a mobile crane, boom angle is measured from what reference?

    1. The crane's longitudinal axis
    2. Horizontal to the centerline of the boom Correct answer.
    3. The tip of the boom to the load line
    4. The vertical centerline of the boom

    Explanation

    Boom angle is the angle between horizontal and the centerline of the boom, so a horizontal boom reads zero degrees and a vertical boom reads ninety. This value is used with boom length to determine radius. Angle indicators must be set for the actual boom being used.

  29. Question 29Crane Setup and Configuration

    How must the counterweight on a mobile crane be set for a lift?

    1. It must be varied according to the weight of the load being lifted
    2. It must be removed any time the boom is swung over the side
    3. It must always be the maximum weight the crane can physically carry
    4. It must match the configuration on which the selected load chart rating is based Correct answer.

    Explanation

    Each load chart is published for a specific counterweight configuration, and the chart is invalid if the actual counterweight differs. The operator confirms the counterweight matches the chart before picking. Counterweight is not adjusted lift by lift according to load weight.

  30. Question 30Crane Setup and Configuration

    For a normal lift using the outrigger chart, how should the outrigger beams be positioned?

    1. Extended only on the side toward which the load will swing
    2. Left retracted whenever the boom works over the rear
    3. Fully extended with the floats set on firm, prepared bearing Correct answer.
    4. Extended halfway to reduce tail swing

    Explanation

    Load charts are normally published for fully extended outriggers, and capacities depend on that stance. Partial extension is only permitted when a chart specifically covers it. Setting only some beams also creates unequal loading and voids the rating.

  31. Question 31Crane Setup and Configuration

    How close may an outrigger float be placed to the top edge of an unshored excavation?

    1. On the excavated spoil pile beside the hole, for extra height
    2. Directly over the opening on steel plates spanning the excavation
    3. Directly at the edge, so the crane can work at the shortest radius
    4. Far enough back that the excavation slope cannot undermine the float's support Correct answer.

    Explanation

    An excavation removes lateral support from the soil beside it, so the ground near the edge may not carry the outrigger load. The float must be set back beyond the zone of influence of the slope, and a qualified person should confirm the setback or provide shoring. Spoil piles and plates spanning the opening are not acceptable substitutes.

  32. Question 32Crane Setup and Configuration

    What primarily determines the required size of the pad placed under an outrigger float?

    1. The length of the outrigger beam
    2. The weight of the load being lifted alone
    3. The crane's travel speed on the site
    4. The allowable ground bearing pressure at the setup location Correct answer.

    Explanation

    Pad area is selected so the outrigger force divided by the contact area stays below the soil's allowable bearing pressure. Softer ground or higher float loads require larger pads or mats. Load weight alone is not enough, because the crane's own weight also reaches the outriggers.

  33. Question 33Crane Setup and Configuration

    One outrigger float of a crane carries 48,000 lb and rests on a 4 ft by 4 ft pad. What bearing pressure does that pad apply to the ground?

    1. 3,000 pounds per square foot Correct answer.
    2. 12,000 pounds per square foot
    3. 48,000 pounds per square foot
    4. 750 pounds per square foot

    Explanation

    The pad area is 4 ft times 4 ft, or 16 square feet. Dividing the 48,000 lb reaction by 16 square feet gives 3,000 pounds per square foot. That value is then compared with the allowable soil bearing pressure for the site.

  34. Question 34Crane Setup and Configuration

    Wind at the boom tip is rising and approaching the manufacturer's limit for the lift. What should the operator do?

    1. Add counterweight to counteract the wind force
    2. Raise the boom to reduce the wind's effect on the crane
    3. Stop the lift and follow the manufacturer's procedure for securing the crane Correct answer.
    4. Continue as long as the load is under half of chart capacity

    Explanation

    Manufacturers publish maximum permissible wind speeds because wind loads on the boom and load can exceed the chart's allowances regardless of load weight. When the limit is reached, lifting stops and the boom is handled as the manufacturer directs. Reducing load weight does not reduce the wind area of the boom.

  35. Question 35Crane Setup and Configuration

    During boom assembly, when must the connecting pins between boom sections be fully driven and secured with their retainers?

    1. Only when the boom is fitted with a jib
    2. After the first test lift has been completed
    3. After the boom has been raised to working angle
    4. Before the boom is raised, using the retainers specified by the manufacturer Correct answer.

    Explanation

    Boom sections must be positively pinned and retained before any raising occurs, because a partially pinned joint can separate under the boom's own weight as it lifts. Retainers are required to prevent pins from walking out in service. Pins are never left to be installed later.

  36. Question 36Crane Setup and Configuration

    A jib is erected and the load chart contains a separate rating for jib work. How is capacity determined?

    1. The jib rating is used, along with any counterweight and boom configuration that rating requires Correct answer.
    2. Capacity increases because the jib shortens the working radius
    3. The main boom chart applies unchanged
    4. The anti-two-block device may be bypassed to gain boom angle

    Explanation

    Jib ratings are published separately because a jib adds weight and offset to the boom tip and changes structural limits. The operator selects the jib chart and matches the counterweight, boom length, and offset called for by that chart. Safety devices remain functional in every configuration.

  37. Question 37Crane Setup and Configuration

    What must be done with the area swept by the crane's rotating counterweight?

    1. It must be barricaded or kept clear of personnel while the crane is operating Correct answer.
    2. It only needs to be clear during the first lift of the shift
    3. It only needs marking when the boom is over the front
    4. It should be covered with plywood to prevent damage to the deck

    Explanation

    Tail swing is a crushing hazard because the operator cannot see the entire rear swing path from the cab. The swing radius is barricaded or controlled so no one can enter it. The hazard exists for every swing, not only the first lift or one direction.

  38. Question 38Crane Setup and Configuration

    A crane must be set up on ground that slopes. What is the correct approach?

    1. Set the outriggers on the slope and check the level indicator only while swinging
    2. Lower the outriggers until the tires just touch the ground
    3. Prepare a level, stable pad with matting or cribbing so the crane is within the manufacturer's tolerance Correct answer.
    4. Extend the uphill outriggers farther than the downhill outriggers

    Explanation

    The crane must be level before lifting, so the ground itself is built up or cut down and matted rather than relying on outrigger stroke. Unequal beam extension individually changes the stance and invalidates the chart. Level is verified on the indicator before the load is applied.

  39. Question 39Crane Setup and Configuration

    Site conditions prevent fully extending the outrigger beams. How should the lift proceed?

    1. Use the fully extended chart and deduct 10 percent from the capacity
    2. Restrict the lift to boom angles above 60 degrees
    3. Use the load chart published for the outrigger extension that is actually achieved Correct answer.
    4. Compensate by installing additional counterweight

    Explanation

    Manufacturers publish separate ratings for mid-extend or non-fully-extended stances because the stability envelope changes. The chart matching the actual beam extension must be used. Arbitrary deductions and added counterweight are not substitutes for a published rating.

  40. Question 40Crane Setup and Configuration

    What is required of the rated capacity limiter before a lift is made?

    1. It must be switched off when working near power lines
    2. It must be set for the crane's actual configuration and checked as functioning before the lift Correct answer.
    3. It needs calibration only once, at the factory
    4. It must be set by the rigger at the start of each shift

    Explanation

    The rated capacity limiter computes allowable load from the boom length, angle, radius, and configuration, so it must be set to the configuration actually in use. It is verified for function as part of the pre-lift inspection. It is never disabled to complete a lift.

  41. Question 41Crane Setup and Configuration

    What is the purpose of a boom-mounted anemometer on a mobile crane?

    1. To verify outrigger float pressure
    2. To record the weight of each load lifted
    3. To indicate wind speed at the boom so it can be compared with the manufacturer's limit Correct answer.
    4. To measure the slope of the setup ground

    Explanation

    Wind speed at the boom tip can be significantly higher than at ground level, so the anemometer gives the operator the value used against the manufacturer's wind limit. When the limit is reached, lifting stops. The device does not measure ground conditions, outrigger pressure, or load weight.

  42. Question 42Crane Setup and Configuration

    Before an outrigger is set, what should the ground beneath it be checked for?

    1. Drainage grates only
    2. Underground utilities, voids, uncompacted fill, and previous excavations Correct answer.
    3. The color and texture of the surface soil
    4. Whether the surface has been painted or marked

    Explanation

    An outrigger concentrates a large force on a small area, so hidden voids, buried utilities, or loose backfill can collapse and drop the float. Site drawings, utility locates, and a visual survey are used before setup. Surface appearance alone gives no information about subsurface support.

  43. Question 43Crane Setup and Configuration

    A crane is to be set up on an elevated concrete slab. What is required?

    1. Nothing, provided the slab appears to be in good condition
    2. Spreading the load with a single layer of plywood under each float
    3. Only that all outriggers be fully extended
    4. Verification by a qualified person that the slab can carry the outrigger loads, with shoring if needed Correct answer.

    Explanation

    Elevated slabs are designed for distributed floor loads, not for the concentrated point loads an outrigger applies. A qualified person evaluates the slab and specifies shoring or load spreading as necessary. Plywood alone does not provide the required structural capacity.

  44. Question 44Crane Setup and Configuration

    What is the rule about working beneath a boom that is being assembled or disassembled?

    1. It is permitted if all workers wear hard hats
    2. It is permitted once the boom is pinned at both ends
    3. Workers must stay out from under the boom, which is supported on stands or blocking Correct answer.
    4. It is required so workers can guide the connecting pins

    Explanation

    A boom being assembled is supported only by the crane's cylinders or by temporary stands, and a loss of hydraulic pressure can drop it. Personnel stay clear and the boom is lowered onto suitable supports before work continues. Hard hats and pinning do not protect against a falling boom.

  45. Question 45Crane Setup and Configuration

    An outrigger float applies 60,000 lb to the ground and the soil is rated for 2,000 pounds per square foot. What contact area must the cribbing provide at the soil surface?

    1. At least 4 square feet
    2. At least 30 square feet Correct answer.
    3. No additional area beyond the float itself
    4. At least 15 square feet

    Explanation

    Required area equals force divided by allowable pressure, so 60,000 lb divided by 2,000 pounds per square foot is 30 square feet. The cribbing must also be thick enough for the load to spread across that full area, roughly at 45 degrees through the material. A pad smaller than this will exceed the soil's capacity.

  46. Question 46Crane Setup and Configuration

    Working radius for load chart purposes is measured from what point to what point?

    1. From the front bumper of the carrier to the load
    2. From the boom tip to the hook block
    3. From the boom pivot pin to the boom tip
    4. From the crane's center of rotation to the center of gravity of the load Correct answer.

    Explanation

    Radius is a horizontal distance measured from the crane's axis of rotation to the vertical line through the load's center of gravity. This is why the rigging height and load position affect the radius that must be used. Measuring along the boom or from the carrier gives a different, incorrect value.

  47. Question 47Crane Setup and Configuration

    After the outriggers are set on compacted fill, the crane drifts out of level as the load comes onto the hook. What is the correct action?

    1. Increase engine speed so the outriggers hold pressure
    2. Continue if the level indicator is still close to center
    3. Stop, land the load, and reset the outriggers with adequate support before continuing Correct answer.
    4. Swing to the high side to compensate for the tilt

    Explanation

    Movement during loading means the ground or blocking is yielding, which shifts load onto other outriggers and changes the stability condition the chart assumed. The lift must stop and the setup be rebuilt on adequate support. Continuing or compensating by swinging keeps the crane outside its rated condition.

  48. Question 48Crane Setup and Configuration

    A light but very large, solid load presents a big sail area, and the site is near the chart's wind limit. How does this affect the lift?

    1. Capacity is unaffected because the chart is based on weight alone
    2. The chart's wind allowance covers any shape of load
    3. The lift should simply be made at a longer radius
    4. Wind force on the load's sail area can overload the boom even though the load weight is below chart capacity Correct answer.

    Explanation

    Load charts account for wind on the boom and a limited allowance for the load, but a large sail area catches far more wind than a compact load of the same weight. The added force increases boom loading and can also cause the load to drift. Operators must consider sail area and stop when the manufacturer's wind limit is reached.

  49. Question 49Crane Setup and Configuration

    If the ground beneath an outrigger is softer than the bearing pressure assumed for the setup, what is the likely consequence?

    1. The float settles, tilting the crane and transferring load to other outriggers, which can lead to tipping Correct answer.
    2. The rated capacity of the crane increases
    3. There is no effect, because outrigger floats are made of steel
    4. Swing speeds become faster and more consistent

    Explanation

    Bearing pressure that exceeds the soil's capacity causes settlement under the float. The crane then tilts, the load shifts onto the remaining outriggers, and the machine can progress toward a tipping failure. This is why pad size and ground preparation are treated as part of the lift plan.

  50. Question 50Crane Setup and Configuration

    A mobile crane with outriggers is being set up for a lift on a firm, prepared surface. How level must the crane be before the lift is made?

    1. Level enough that the crane does not creep or walk while swinging.
    2. Within the manufacturer's specified tolerance. Correct answer.
    3. Leveled only when the load exceeds 75 percent of the chart capacity.
    4. Within 5 degrees of horizontal, which is the industry-wide maximum.

    Explanation

    Load charts are based on the crane being level, so the machine must be brought within the tolerance stated in the manufacturer's operating manual, commonly 1 percent or less. Out-of-level setups shift load between the outriggers and reduce the tipping margin, which the chart does not reflect. A crane that merely feels stable or does not creep is not necessarily within tolerance.

  51. Question 51Crane Setup and Configuration

    Before jacking a crane on its outriggers, how must the outrigger float be attached to the outrigger cylinder?

    1. Bolted to the ground pad so it cannot slide when loaded.
    2. It may be left loose on the jack cylinder when the beam is fully extended.
    3. Pinned to the cylinder with the pin secured by its keeper. Correct answer.
    4. Chained to the beam so it can pivot freely during jacking.

    Explanation

    The float is connected to the jack cylinder with a pin, and that pin must be fully driven and its keeper or clip installed so the float cannot separate under load. A float that is merely resting on the cylinder can slip off as the crane is jacked, causing a sudden drop. Securing the float to the ground pad is not a substitute for a positive, retained connection to the cylinder.

  52. Question 52Crane Setup and Configuration

    A crane's load chart contains separate ratings for different counterweight configurations, and the counterweight installed on the machine does not match the chart the operator is using. What is the correct action?

    1. Deduct the missing counterweight from the crane's rated capacity.
    2. Select the load chart that matches the counterweight installed. Correct answer.
    3. Proceed when the load is less than half of the capacity on the chart in use.
    4. Use the chart with the greatest capacity, since counterweight affects only stability.

    Explanation

    Rated capacities are valid only for the exact configuration, including counterweight, that the chart was published for. Using a chart for a heavier or lighter counterweight than what is on the machine yields an unverified rating. The operator must use the chart that corresponds to the configuration actually assembled, or bring the machine into the configuration the chart assumes.

  53. Question 53Crane Setup and Configuration

    A crane is set up on four outriggers and lifts a load with the boom swung over one corner. Which outrigger carries the greatest share of the load?

    1. Either front outrigger, because they carry the weight of the boom.
    2. The outrigger diagonally opposite the boom tip.
    3. The outrigger at the corner the boom is swung over. Correct answer.
    4. All four outriggers, in equal shares, when the crane is level.

    Explanation

    The crane would tip about a line joining two outriggers, and the load moment about that line is greatest at the corner under the boom. The outrigger on the loaded corner therefore takes the largest reaction, while the diagonally opposite float may take very little. This is why ground conditions under the loaded corner are the most critical part of the setup.

  54. Question 54Crane Setup and Configuration

    Two cranes are to make a tandem lift of a load that neither crane can handle alone. What capacity limit applies to each crane?

    1. 100 percent of the chart capacity, provided the load is shared equally between the two cranes.
    2. 50 percent of the chart capacity, regardless of how the load is shared.
    3. The full chart capacity plus a 10 percent allowance for unequal load sharing.
    4. 75 percent of the chart capacity for its configuration. Correct answer.

    Explanation

    For multi-crane lifts, each crane's share of the load must not exceed 75 percent of its rated capacity for the configuration, which leaves margin for unequal load sharing and for the effects of the other crane. The lift must be planned and directed by a qualified person, with the load distribution determined in advance. Assuming an exactly equal share is not acceptable, because the share changes as the load moves.

  55. Question 55Crane Operation

    A signal person holds an arm extended horizontally outward with the fingers closed and the thumb pointing up. What does this signal tell the operator to do?

    1. Raise the boom Correct answer.
    2. Extend the boom
    3. Lower the boom
    4. Stop all movement

    Explanation

    In the standard hand signal set, an arm extended outward with a closed fist and the thumb pointing up means raise the boom. The mirror-image signal with the thumb pointing down means lower the boom. Operators must respond only to the signals defined in the standard signal chart.

  56. Question 56Crane Operation

    What is the purpose of the anti-two-block device on a mobile crane?

    1. It limits the maximum load that can be placed on the hook.
    2. It prevents the boom from being lowered below a set angle.
    3. It keeps the upper works level while the crane swings.
    4. It stops hoisting before the load block contacts the boom tip. Correct answer.

    Explanation

    Two-blocking occurs when the load block or hook comes into contact with the boom tip or sheave, which can part the hoist rope and damage the boom. The anti-two-block device senses this condition and interrupts the hoist-up function. It is an operational aid and does not replace the operator's judgment.

  57. Question 57Crane Operation

    Why are outrigger floats or timber mats placed under the outrigger pads of a mobile crane?

    1. To raise the crane's published lifting capacity
    2. To shorten the time required to set up the crane
    3. To keep the outrigger beams from bending
    4. To spread the outrigger load over a larger ground area Correct answer.

    Explanation

    Mats and floats increase the bearing area through which the outrigger force passes into the ground. A larger area lowers the ground bearing pressure beneath that outrigger, reducing the chance of settlement or punch-through. They do not change the crane's rated capacity.

  58. Question 58Crane Operation

    How should an operator treat overhead power lines near a lift area?

    1. As insulated and safe to contact at any distance
    2. As de-energized whenever no arcing or sparking is visible
    3. As safe to approach within 5 feet if the load is non-conductive
    4. As energized and potentially lethal at all times Correct answer.

    Explanation

    Lines cannot be assumed to be de-energized or insulated based on appearance, and electricity can arc across an air gap before physical contact occurs. The operator must assume every line is energized and keep the crane, boom, rope, and load outside the required approach distance for the line's voltage. Only the utility can confirm a line is de-energized and grounded.

  59. Question 59Crane Operation

    With boom length held constant, lowering the boom angle increases the operating radius. What happens to the crane's rated capacity as a result?

    1. It increases
    2. It stays the same
    3. It decreases Correct answer.
    4. It is limited only by the hoist line pull

    Explanation

    Rated capacity on a mobile crane is tied to load radius, and capacity falls as radius grows. Lowering the boom moves the load farther from the center of rotation, which increases the overturning moment and reduces the chart value. The operator must re-check the chart whenever radius changes.

  60. Question 60Crane Operation

    What does a load moment indicator do for the crane operator?

    1. It records the operating hours of the crane.
    2. It warns when the load approaches the crane's rated capacity. Correct answer.
    3. It automatically controls the speed of the swing.
    4. It measures the weight of the crane's counterweight.

    Explanation

    A load moment indicator senses boom angle, length, and load to compute the percentage of rated capacity in use. It gives the operator a warning as capacity is approached and typically locks out functions at the limit. It is an aid and does not relieve the operator of reading the load chart.

  61. Question 61Crane Operation

    What should the operator confirm before swinging a suspended load?

    1. That the swing path is clear of personnel and obstructions Correct answer.
    2. That the hoist clutch is disengaged
    3. That the swing brake is fully applied throughout the swing
    4. That the load is raised to the maximum permissible height

    Explanation

    Swinging moves the load through an arc that may pass over workers, structures, or equipment. The operator verifies the path is clear and that the load is high enough to clear obstacles without excessive height. Tag lines are used where needed to control rotation.

  62. Question 62Crane Operation

    Under what condition do the capacities printed in a mobile crane's load chart apply?

    1. When the crane is traveling with the load close to the ground
    2. When the crane is level and set up as the manufacturer specifies Correct answer.
    3. When the boom is fully retracted regardless of setup
    4. When the ground slopes slightly toward the load being lifted

    Explanation

    Load charts are calculated for a crane that is level and configured exactly as the manufacturer's operating notes require, including outrigger extension and counterweight. Any deviation, such as slope, partial outrigger extension, or missing counterweight, invalidates the chart values. The operator must confirm the setup matches the chart's assumptions before lifting.

  63. Question 63Crane Operation

    A load chart shows 24,000 lb capacity at the planned radius. The hook block, slings, and shackles together weigh 1,500 lb. What is the heaviest load that may be lifted?

    1. 21,000 lb
    2. 24,000 lb
    3. 25,500 lb
    4. 22,500 lb Correct answer.

    Explanation

    Chart capacity covers everything suspended from the boom tip, so the weight of the hook block and rigging must be deducted first. Subtracting 1,500 lb from 24,000 lb leaves 22,500 lb of usable load weight. The gross load, not the payload alone, must stay within the chart value.

  64. Question 64Crane Operation

    What is the effect of adding parts of line to the hoist reeving?

    1. It increases lifting capacity but reduces hoist line speed. Correct answer.
    2. It increases both lifting capacity and hoist line speed.
    3. It reduces lifting capacity but increases hoist line speed.
    4. It has no effect on either capacity or line speed.

    Explanation

    Each additional part of line shares the load, so the pull required on the drum falls and the allowable load rises. Because the load must travel only a fraction of the rope length pulled, the load moves more slowly for a given drum speed. Reeving must match the parts of line called for by the load chart.

  65. Question 65Crane Operation

    How does boom deflection under load affect the actual load radius?

    1. It makes the actual radius smaller than the geometric radius.
    2. It makes the actual radius larger than the geometric radius. Correct answer.
    3. It makes the actual radius equal to the boom length.
    4. It leaves the radius unchanged because the boom is rigid.

    Explanation

    Under load, the boom bends downward, which moves the tip farther from the center of rotation than the geometry of boom angle and length would predict. The resulting radius exceeds the nominal value, and capacity must be read at that larger radius. This is why charts include a deduction for boom deflection and why heavy lifts at long radii deserve extra margin.

  66. Question 66Crane Operation

    Why do mobile crane load charts list different capacities for over-the-side and over-the-rear operations?

    1. The boom is structurally stronger over the rear quadrant.
    2. The hoist is more powerful when the boom points over the rear.
    3. The operator's visibility differs between the two quadrants.
    4. The crane's stability and structural limits change with boom position. Correct answer.

    Explanation

    The tipping axis and the way loads are carried into the carrier differ by quadrant, and the boom's structural limits can vary as well. As a result, the weakest link in each quadrant sets a different chart value. The operator must know which quadrant the chart used and keep the boom within it for the entire lift.

  67. Question 67Crane Operation

    When is it appropriate to engage a crane's swing lock?

    1. Only when the crane is stationary and not handling a suspended load, per the manufacturer Correct answer.
    2. Whenever a swinging load needs to be brought to a quick stop
    3. During every pick made over the side of the carrier
    4. To hold the boom steady while a load is being lifted

    Explanation

    The swing lock is a parking-type device that pins the upper works when the crane is not in operation. Engaging it while the crane is swinging or while a load is suspended can damage the swing mechanism or impose shock loads. The swing brake, not the lock, is used to control and stop a swing.

  68. Question 68Crane Operation

    An outrigger begins to sink into soft ground while a load is suspended. What is the correct response?

    1. Raise the boom to reduce the radius and continue.
    2. Add counterweight to hold the crane down on the high side.
    3. Stop, land the load, and reset the crane with proper blocking. Correct answer.
    4. Continue the lift but reduce the swing speed.

    Explanation

    Settlement under an outrigger changes the crane's level and can shift the tipping axis or induce side loads on the boom. The lift must be stopped and the load landed before any correction is made. The crane is then reset on adequate blocking or mats sized for the ground bearing pressure.

  69. Question 69Crane Operation

    Wind speed rises above the limit stated in the manufacturer's operating notes for the load being handled. What should the operator do?

    1. Complete the lift quickly before the wind increases further.
    2. Add counterweight to improve stability against the wind.
    3. Stop the lift and secure the crane as the manufacturer directs. Correct answer.
    4. Increase the boom angle to lower the load faster.

    Explanation

    Manufacturers set wind limits based on the sail area of the load and the crane's ability to resist the resulting forces. Above those limits, the load can be pushed off the planned radius and the boom can be overloaded. The lift must be stopped and the boom and load secured per the operating notes.

  70. Question 70Crane Operation

    The operator loses sight of the signal person, or the signal received is unclear. What should the operator do?

    1. Continue the movement at reduced speed.
    2. Sound the horn and keep moving.
    3. Stop until communication is restored. Correct answer.
    4. Follow the last signal that was given.

    Explanation

    The operator may act only on signals that are clearly understood, and must stop when communication breaks down. Continuing on an assumed signal risks moving a load into people or obstructions. Work resumes only after clear communication is re-established, using a backup method such as radio if needed.

  71. Question 71Crane Operation

    What is the effect of operating a mobile crane that is out of level?

    1. Capacity increases on the low side of the crane.
    2. The load moment indicator compensates and keeps capacity accurate.
    3. There is no effect as long as all outriggers are fully extended.
    4. Load radius changes and the load tends to swing to the low side, reducing stability. Correct answer.

    Explanation

    Out-of-level conditions tilt the center of rotation, so the actual radius differs from the planned radius and the load tends to run downhill. This shifts the tipping axis toward the load and adds side loads the boom was not designed for. Load charts assume a level crane, so capacity is no longer assured.

  72. Question 72Crane Operation

    A jib is erected and being used for a lift. How should the operator determine capacity?

    1. Use the jib load chart and deduct the hook block, rigging, and jib per the notes. Correct answer.
    2. Use the main boom chart and deduct only the weight of the jib.
    3. Add the jib weight to the load and use the main boom chart unchanged.
    4. Reduce the main boom chart capacity by half.

    Explanation

    When a jib is in use, the crane is configured differently and the main boom chart no longer describes it. The jib chart must be used, with deductions for the hook block, rigging, and any jib-related components as the notes specify. Using the wrong chart is a common cause of overloading.

  73. Question 73Crane Operation

    How does increasing boom length affect capacity when the load radius is held constant?

    1. Capacity is unaffected by boom length.
    2. Capacity generally decreases. Correct answer.
    3. Capacity depends only on hoist line speed.
    4. Capacity generally increases.

    Explanation

    A longer boom at the same radius must operate at a lower angle and carries the load through a longer, heavier structure. Both structural limits and the added boom weight reduce the allowable load. This is why charts are published for each boom length and why the shortest boom that does the job is preferred.

  74. Question 74Crane Operation

    How is the load radius measured on a mobile crane?

    1. From the front bumper horizontally to the edge of the load
    2. From the nearest outrigger float to the boom tip
    3. From the center of rotation horizontally to the load's center of gravity Correct answer.
    4. From the boom hinge pin horizontally to the hook

    Explanation

    Radius is the horizontal distance from the crane's center of rotation to the vertical line through the load's center of gravity. Measuring to the hook or to the near edge of the load gives a shorter, unsafe figure. Because the load's center of gravity may be offset from the hook, the larger of the two distances governs.

  75. Question 75Crane Operation

    An outrigger float measuring 2 ft by 2 ft carries 16,000 lb. Ignoring the weight of the mat, what is the approximate ground bearing pressure under that float?

    1. 8,000 psf
    2. 2,000 psf
    3. 4,000 psf Correct answer.
    4. 16,000 psf

    Explanation

    Ground bearing pressure equals force divided by the bearing area. The float area is 2 ft times 2 ft, or 4 square feet, so 16,000 lb divided by 4 sq ft gives 4,000 psf. A larger mat would increase the area and lower the pressure proportionally.

  76. Question 76Crane Operation

    Why is dragging or pulling a load sideways with the boom considered hazardous?

    1. The boom is designed mainly for loads in its own plane and can fail under side bending. Correct answer.
    2. It increases the hoist line speed beyond the drum rating.
    3. It disables the load moment indicator for the rest of the shift.
    4. It reduces the load radius and overloads the outrigger nearest the load.

    Explanation

    Boom strength calculations assume the load hangs essentially in the plane of the boom. Side loading introduces bending and torsion that the boom is not rated for, and the load may also swing out and increase radius unexpectedly. Side pulls should be avoided, and any that are permitted must be within the manufacturer's stated limits.

  77. Question 77Crane Operation

    The chart allows 30,000 lb at the planned radius. The hook block, slings, and shackles weigh 900 lb. What is the heaviest payload that may be lifted?

    1. 29,100 lb Correct answer.
    2. 30,900 lb
    3. 30,000 lb
    4. 28,500 lb

    Explanation

    The chart value applies to the gross load, which includes the hook block and all rigging below the boom tip. Deducting 900 lb of rigging from 30,000 lb leaves 29,100 lb of payload. The gross load must remain at or below the chart value at the actual radius.

  78. Question 78Crane Operation

    In a tandem lift, what primarily determines how much of the load each crane carries?

    1. The hoist line speed of each crane
    2. The rated capacity of each crane at its working radius
    3. The boom length selected by each operator
    4. The position of the load's center of gravity relative to each hook Correct answer.

    Explanation

    A suspended load behaves like a beam on two supports, so each crane carries a share proportional to the load's center of gravity location. Moving the center of gravity toward one hook shifts load onto that crane, and that crane may become overloaded even if the total weight is within the combined capacity. The lift plan must keep each crane's share within its chart.

  79. Question 79Crane Operation

    Why does a rapid swing with a long boom and a low boom angle create a serious overloading risk?

    1. The hoist line speed doubles, causing the load to be lifted too high.
    2. The outriggers lift off the ground and the crane levels itself.
    3. The load moment indicator stops updating during the swing.
    4. The load swings outward, increasing radius while dynamic forces add to the effective load. Correct answer.

    Explanation

    When the upper works accelerates or decelerates, the suspended load lags and swings out from the boom tip, so the actual radius becomes greater than the static value. The swing also adds dynamic forces that behave like extra weight. Together these can push the crane past its rated capacity, so swings are made smoothly and the load is kept under control with tag lines.

  80. Question 80Crane Operation

    During a lift, a rigger who is not the designated signal person sees the suspended load drifting toward a worker. What may the rigger do?

    1. Signal the operator only after notifying the lift director by radio.
    2. Nothing, because only the designated signal person may signal the operator.
    3. Warn the worker but leave the crane controls to the designated signal person.
    4. Give a stop signal, which the operator must obey. Correct answer.

    Explanation

    Anyone on the site who sees a hazard may give a stop signal, and the operator must stop the operation immediately and not resume until it is safe. The stop signal is never restricted to the designated signal person. Safety takes priority over normal signal protocol.

  81. Question 81Crane Operation

    The voltage of an overhead power line near the lift path cannot be determined. How should the operator proceed?

    1. Assume the line is de-energized because there is no arcing or humming at the moment.
    2. Ask the utility for the voltage during the lift and use a reduced clearance until then.
    3. Use the clearance listed for the lowest voltage, since unknown lines are usually distribution lines.
    4. Treat the line as energized and keep the greatest clearance required in the table. Correct answer.

    Explanation

    An unknown line must be treated as energized at the highest voltage in the applicable clearance table, which yields the largest required distance. Arcing, humming, or appearance gives no reliable indication of whether a line is energized or at what voltage. Clearance must be established before the lift begins, not negotiated during it.

  82. Question 82Crane Operation

    What is the purpose of an anti-two-block device on a mobile crane?

    1. It stops hoisting before the hook block reaches the boom tip. Correct answer.
    2. It limits the maximum boom angle the crane can reach.
    3. It prevents the crane from tipping backward when the boom is raised quickly without a load.
    4. It restricts swing speed when the boom is fully extended.

    Explanation

    Two-blocking occurs when the hook block or headache ball is pulled up against the boom tip, which can part the hoist rope and drop the load. The anti-two-block device senses the approach and interrupts the hoist function before contact occurs. It protects the rope and boom tip, not the crane's stability or swing.

  83. Question 83Crane Operation

    On a typical mobile crane load chart, what generally determines the rated capacity at short radii compared with long radii?

    1. Boom strength governs at short radii; stability governs at long radii. Correct answer.
    2. Stability governs at short radii and boom strength governs at long radii.
    3. Hydraulic system pressure governs at all radii regardless of boom length.
    4. The same limiting factor applies at all radii, so the capacity line is straight.

    Explanation

    Close in, the crane has a large resistance to overturning, so the structural strength of the boom and other components sets the limit. As radius grows, the overturning moment from the load increases until tipping becomes the controlling condition. This is why capacity falls off rapidly at long radii rather than in a straight line.

  84. Question 84Crane Operation

    A crane's load chart states that capacities apply only with all outrigger beams fully extended. A wall prevents one beam from being extended more than halfway. What is the correct action?

    1. Relocate so all beams can be fully extended, as the chart requires. Correct answer.
    2. Proceed if the outrigger float is set on a solid steel plate.
    3. Use the over-the-side chart, which already accounts for partial beam extension.
    4. Reduce the load by 25 percent to account for the shorter beam.

    Explanation

    Published capacities apply only when the crane is set up exactly as the chart specifies, including full outrigger beam extension. Operating with a partially extended beam changes the machine's geometry and support, so no chart value can be relied on. The lift must be made from a setup that matches the chart.

  85. Question 85Crane Operation

    Why are crane mats or pads placed under outrigger floats?

    1. To spread outrigger force over a larger area, reducing ground pressure. Correct answer.
    2. To provide a level reference for the boom angle indicator.
    3. To raise the crane so the boom can reach a higher hook height.
    4. To keep the floats from rotating during a swing.

    Explanation

    The float concentrates a large force into a small footprint, and the mat increases the contact area so the pressure on the soil drops below what the ground can carry. Without adequate bearing area the float can sink, tilt the crane, and shift load onto other components. The mat does not change the crane's reach or its instruments.

  86. Question 86Crane Operation

    A load resting on the ground is picked with slack in the slings and pulled free suddenly. Why is this more dangerous than a smooth lift of the same load?

    1. The slings shorten under rapid loading, which reduces the load radius.
    2. The outriggers lift off the ground only during slow, steady lifts.
    3. The load chart capacity increases during a sudden pick, so the crane is at less risk.
    4. The sudden release creates dynamic force that can briefly far exceed the load's static weight. Correct answer.

    Explanation

    When a load breaks free, the crane absorbs the energy of the sudden acceleration, producing a dynamic force well above the weight shown on the chart. This shock load can exceed the rated capacity, overstress the boom, or part the hoist rope even though the static weight appeared acceptable. Loads should be broken free gradually so the crane is never subjected to impact.

  87. Question 87Crane Operation

    A lift is planned at a radius that falls between two listed radii, and the operator cannot confirm that interpolation is permitted for this chart. The chart lists 30,000 lb at 20 ft and 24,000 lb at 25 ft. What capacity should be used?

    1. 27,000 lb, the average of the two listed values.
    2. 24,000 lb, the capacity listed for the next longer radius. Correct answer.
    3. Any value between 24,000 lb and 30,000 lb, selected by the operator.
    4. 30,000 lb, because the planned radius is closer to 20 ft than to 25 ft.

    Explanation

    Capacity never increases as radius grows, so the value listed for the next longer radius is always at or below the true capacity at the planned radius. Using it is conservative and valid even when interpolation is not authorized. Averaging or rounding toward the shorter radius could allow an overload.

  88. Question 88Crane Operation

    What is the main purpose of a tag line on a freely suspended load?

    1. To measure the load radius from the center of rotation of the crane.
    2. To keep the hoist rope from contacting the boom during a swing.
    3. To increase the crane's rated capacity by sharing part of the load weight.
    4. To control rotation and swing of the load without touching it. Correct answer.

    Explanation

    A tag line lets a rigger restrain and steer a load that would otherwise spin or drift in the wind, without putting hands on the load. Control of rotation matters because a turning load can strike structures or personnel and can add side load to the boom. The tag line carries no lifting load.

  89. Question 89Crane Operation

    Where should the operator find the rated capacities for traveling with a load (pick and carry)?

    1. By using the chart values listed for the smallest radius shown.
    2. In the same stationary load chart used for set lifts from outriggers.
    3. By subtracting 10 percent from the stationary chart capacity.
    4. In the manufacturer's pick-and-carry or travel chart. Correct answer.

    Explanation

    Traveling with a suspended load involves different support conditions, tire or track loading, and dynamic effects, so manufacturers publish separate travel or pick-and-carry ratings. Those ratings are often far lower than the stationary capacities at the same radius. The operator must use the chart that matches the actual configuration.

  90. Question 90Crane Operation

    With boom length held constant, what happens to the load radius as the boom is lowered?

    1. The radius stays the same because the boom length is unchanged.
    2. The radius decreases in proportion to the boom angle.
    3. The radius increases. Correct answer.
    4. The radius changes only if the load is lifted off the ground.

    Explanation

    Radius is the horizontal distance from the center of rotation to the load line, so lowering the boom swings the tip farther out horizontally and the radius grows. Because capacity falls as radius increases, booming down under load raises the load moment. The boom length does not fix the radius; the boom angle does.

  91. Question 91Crane Operation

    A crane is holding a load at a given radius and the operator telescopes the boom outward without specific manufacturer approval. Why is this hazardous?

    1. The boom angle increases automatically, which reduces the load moment.
    2. Extending the boom raises the hook, which unloads the crane and reduces the moment.
    3. Extending the boom increases the radius and the boom's own weight effect, raising the load moment. Correct answer.
    4. Telescoping does not change capacity as long as the radius stays the same.

    Explanation

    Extending the boom under load pushes the load line farther out and also moves the additional boom section's weight outward, both of which increase the overturning moment. The chart value that applied before telescoping no longer describes the machine. Unless the manufacturer specifically permits telescoping under load, the boom must be extended before the lift.

  92. Question 92Crane Operation

    When traveling with a suspended load is permitted by the manufacturer, which practice applies?

    1. Rely on the swing brake to hold the boom over the side during travel.
    2. Use the maximum travel speed so the load is not suspended for long.
    3. Carry the load as high as possible to clear obstacles along the travel route.
    4. Keep the load low, travel slowly, and use the travel chart for that configuration. Correct answer.

    Explanation

    Carrying a load low reduces the pendulum swing and the chance of the load striking something or adding side load to the boom. Slow travel limits dynamic forces, and the travel chart governs because the machine's support and geometry differ from a set lift. The boom position must match what the manufacturer specifies.

  93. Question 93Crane Operation

    Why must the hook on the crane's load block be fitted with a working latch?

    1. It keeps slings and fittings from slipping off the hook when the line goes slack. Correct answer.
    2. The latch increases the hook's rated capacity.
    3. It centers the load directly under the boom tip.
    4. It prevents the hook block from two-blocking against the boom tip.

    Explanation

    When the hoist line goes slack, slings can jump or slide off an open hook, and the load drops when tension returns. The latch closes the throat so the rigging stays captured. A latch does not add strength to the hook or affect two-blocking.

  94. Question 94Crane Operation

    What does a boom hoist limiting device (boom stop) do?

    1. It prevents the boom from being lowered below the chart's minimum radius.
    2. It limits swing speed when the boom is at a high angle.
    3. It stops the boom from being raised past its maximum permitted angle. Correct answer.
    4. It stops the hoist when the hook approaches the boom tip.

    Explanation

    Raising the boom beyond its permitted maximum angle can damage the boom or tip the machine backward, so the boom hoist limiting device interrupts the boom hoist function at that limit. It acts on boom elevation, not on the load hoist. Its setting is tied to the boom length and configuration.

  95. Question 95Crane Operation

    A hoist is reeved with 6 parts of line and the line pull is 10,000 lb, giving a theoretical 60,000 lb lifting force. What limits the maximum load the crane may lift?

    1. The load weight alone, since the reeving determines all other limits.
    2. The 10,000 lb single-line pull of the hoist drum.
    3. The crane's rated capacity for that radius and configuration, less deductions. Correct answer.
    4. The 60,000 lb reeving capacity, provided the rope is in new condition.

    Explanation

    Reeving determines how much force the hoist can apply to the load line, but the crane's structure, hydraulics, and stability set the actual lifting limit at each radius. The load chart already incorporates those limits, and the weight of the hook block and rigging must be deducted from it. The reeving figure is a capability of the hoist, not a permission to lift that much.

  96. Question 96Crane Operation

    A crane must be set up near the edge of an open excavation. What is the primary concern?

    1. The boom must be kept pointing away from the excavation to avoid magnetic interference.
    2. The counterweight must hang over the excavation to shorten the load radius.
    3. Soil under the outrigger may be undermined, so floats must be set back from the edge. Correct answer.
    4. The excavation makes the crane's level indicator read incorrectly.

    Explanation

    An excavation removes lateral support from the soil, and an outrigger loaded near a slope or edge can cause the side of the cut to fail. The required setback depends on soil type, depth, and any shoring or engineering guidance. Placing floats close to an unsupported edge is a ground failure risk, not a crane capacity question.

  97. Question 97Crane Operation

    Before making a lift, how does the operator check that the hoist brake will hold?

    1. By raising the load a few inches, holding it, and confirming it does not drift down. Correct answer.
    2. By running the hoist at full speed with the load still on the ground.
    3. By lowering the load to the ground and watching the hoist rope for slack.
    4. By swinging the load and observing whether the boom stops.

    Explanation

    A brief hold with the load just clear of the ground confirms that the brake stops and holds the load before it is committed to the lift. Any downward drift indicates a brake problem that must be corrected first. The test is done at a low height so a failure has limited consequences.

  98. Question 98Crane Operation

    Two loads weigh the same. Which presents the greater wind-related risk during the lift?

    1. The load with the smaller surface area, because it swings faster.
    2. The load with the larger exposed surface area, which catches more wind. Correct answer.
    3. Neither, because wind effect depends only on the weight of the load.
    4. The load made of denser material, regardless of its shape.

    Explanation

    Wind force depends on the exposed area of the load, so a bulky, flat-sided load catches far more wind than a compact one of the same weight. The resulting force can push the load out of position, spin it, or add side load to the boom. Equal weight does not mean equal wind exposure.

  99. Question 99Crane Operation

    Why must the crane's counterweight be kept exactly as specified for the load chart being used?

    1. Extra counterweight always makes the crane safer, so charts allow any amount.
    2. Charts are based on a specific counterweight; changing it invalidates them. Correct answer.
    3. Counterweight affects only travel speed, not lifting capacity.
    4. Counterweight must be removed before any lift to keep the rear axle loaded.

    Explanation

    Rated capacities are calculated for a defined machine configuration that includes a specific counterweight. Adding counterweight improves rear stability but can overstress the boom, chassis, or swing components, and removing it reduces stability. Either way the chart no longer describes the crane, so the ratings cannot be used.

  100. Question 100Crane Operation

    Why should the load's center of gravity be positioned directly below the hook before lifting?

    1. Otherwise the capacity shown on the load chart must be doubled.
    2. Otherwise the load tilts and may shift, changing the radius or shocking the crane. Correct answer.
    3. Otherwise the anti-two-block device will not function during the lift.
    4. Otherwise the swing brake cannot hold the load steady.

    Explanation

    A load hanging off-center tilts until its center of gravity lines up under the hook, and during that movement it can shift, swing, or drop into a different radius. The result is a sudden change in load moment or a shock load on the rope and boom. Rigging should be arranged so the load picks level.

  101. Question 101Crane Operation

    When should hoist rope be removed from service?

    1. At the end of every shift, regardless of the rope's condition.
    2. When the rope becomes shiny from running over the sheaves.
    3. Only when the rope breaks completely and the load drops.
    4. When broken wires, corrosion, or damage exceed the removal criteria for that rope. Correct answer.

    Explanation

    Rope is condemned when inspection shows deterioration beyond the removal criteria established for its construction, such as broken wires in a strand, heavy corrosion, kinking, or crushing. These conditions reduce strength well before visible failure occurs. Inspection intervals and criteria come from the manufacturer and applicable standards.

  102. Question 102Crane Operation

    What is the boom angle indicator used for?

    1. To measure the weight of the hook block and rigging.
    2. To show the crane's outrigger load at each corner of the chassis.
    3. To indicate wind speed at the boom tip during the lift.
    4. To set the boom angle needed to reach a required radius. Correct answer.

    Explanation

    Boom angle combines with boom length to establish the load radius, so the indicator lets the operator place the boom where the planned radius is achieved and verify it against the chart. It is a setup and monitoring aid, not a load or wind instrument. The operator still confirms radius by measurement where required.

  103. Question 103Crane Operation

    Why is a lift made directly over one corner of the crane, over an outrigger, usually restricted to a lower capacity?

    1. Because the swing brake is ineffective when the boom is over a corner.
    2. The load concentrates on the nearest outrigger, so stability is more limiting. Correct answer.
    3. Because the load moment indicator is bypassed over an outrigger.
    4. Because the load line rubs against the outrigger beam in that position.

    Explanation

    Over a corner, the load is supported nearer to a single outrigger and the resisting base for overturning is reduced compared with a lift over the side or rear. Manufacturers publish separate ratings for over-the-corner operation to reflect that condition. Using the over-the-side rating for a corner lift can overload the machine.

  104. Question 104Crane Operation

    A lift will use radio communication between the operator and the signal person. What should be done before the lift starts?

    1. Confirm a shared, clear channel, test the radios, and agree on stop signals. Correct answer.
    2. Have the signal person transmit continuous voice instructions throughout the lift.
    3. Allow other crews to share the channel so everyone hears the lift plan.
    4. Use the radio only if hand signals fail during the lift.

    Explanation

    Radio must be established as the communication method before the lift, on a channel dedicated to that lift so instructions are not confused with other traffic. The equipment is tested and the stop and emergency signals are agreed in advance. Unreliable communication is a valid reason to stop the lift.

  105. Question 105Crane Operation

    During a lift, who is permitted to give a stop signal to the crane operator?

    1. Only the lift director or site supervisor
    2. Only the designated signal person
    3. Only the person who rigged the load
    4. Anyone who sees a condition that requires the lift to stop Correct answer.

    Explanation

    Any person who observes a hazard is permitted to give the stop signal, and the operator must obey it immediately. The designated signal person normally directs the lift, but the stop signal is a universal safety override available to everyone on the site.

  106. Question 106Crane Operation

    What is the purpose of the anti-two-block device on a crane?

    1. It prevents the boom from being lowered below a set angle
    2. It automatically applies the swing brake when a load is raised
    3. It limits how much weight the hoist drum can pull
    4. It interrupts hoisting before the load block contacts the boom tip Correct answer.

    Explanation

    The anti-two-block device senses when the load block approaches the boom tip and stops the hoist-up function (and on some cranes the boom-lower function) before the parts contact. Two-blocking can break hoist rope, damage the boom tip, and drop the load.

  107. Question 107Crane Operation

    At a minimum, how many wraps of wire rope must remain on the hoist drum when the load is at its lowest point?

    1. Two full wraps Correct answer.
    2. One half wrap
    3. Enough to reach the bottom of the drum flange
    4. Five full wraps

    Explanation

    Manufacturer instructions and crane standards require at least two full wraps of rope to remain on the drum at all times. Those wraps provide the friction that anchors the rope end, so running them off can allow the rope to pull free under load.

  108. Question 108Crane Operation

    How should the operator establish the weight of a load before making a lift?

    1. Read it from the rated capacity limiter after the load is lifted
    2. Estimate it from the physical size of the load
    3. Take the actual weight from shipping papers, markings, or another reliable source Correct answer.
    4. Ask the rigger for a rough guess

    Explanation

    The load chart can only be applied correctly when the actual load weight is known before the lift. Weight must come from documentation, markings, or direct determination, because an underestimated load can put the crane over capacity without warning.

  109. Question 109Crane Operation

    Who is responsible for inspecting the crane at the start of each shift?

    1. The site safety officer
    2. The manufacturer's service technician
    3. The lift director
    4. The crane operator Correct answer.

    Explanation

    The operator performs the shift inspection of the crane before putting it into service, checking items such as fluid levels, rope condition, and safety devices. Defects found in that inspection must be corrected or reported before the crane is used.

  110. Question 110Crane Operation

    The load chart shows a capacity of 14,000 lb at the planned radius. The slings, shackles, and lifting beam below the hook weigh 1,200 lb. What is the heaviest load that may be lifted?

    1. 14,000 lb
    2. 15,200 lb
    3. 12,800 lb Correct answer.
    4. 13,000 lb

    Explanation

    Chart capacities are gross values, so the weight of all rigging below the hook must be deducted to find the net load that may be lifted. Here 14,000 lb minus 1,200 lb leaves 12,800 lb of available load weight.

  111. Question 111Crane Operation

    Load radius on a crane is measured as the horizontal distance from:

    1. The nearest outrigger float to the center of the hook
    2. The front bumper to the nearest edge of the load
    3. The boom pivot point to the hook, measured along the boom
    4. The center of rotation to the center of gravity of the load Correct answer.

    Explanation

    Rated capacities are published against radius measured horizontally from the crane's center of rotation to the center of gravity of the load. Measuring to the edge of the load or along the boom would give a shorter distance than the chart assumes and overstate capacity.

  112. Question 112Crane Operation

    For overhead power lines rated 50 kV or less, what minimum clearance must be maintained between the crane, load, and rigging, unless the utility confirms a different distance?

    1. 20 ft
    2. 15 ft
    3. 5 ft
    4. 10 ft Correct answer.

    Explanation

    The crane standard's clearance table requires a minimum of 10 ft for lines rated up to 50 kV. Higher voltages require progressively greater clearances, and the utility must be consulted if the required distance cannot be maintained.

  113. Question 113Crane Operation

    A crane's published load chart assumes the outriggers are fully extended, but the setup area is too narrow to extend them fully. What should be done?

    1. Use the manufacturer's load chart for the configuration actually achieved Correct answer.
    2. Reduce the chart rating by a fixed 10 percent
    3. Set the crane on its tires and use the same chart
    4. Proceed, because the outriggers still carry part of the load

    Explanation

    Each load chart applies only to the configuration it was published for, including outrigger extension and beam position. If full extension cannot be achieved, a chart for the actual configuration must be used, or the lift cannot be made as planned.

  114. Question 114Crane Operation

    A load with a large sail area is to be lifted while the wind is gusting. What governs the operator's wind limit?

    1. The judgment of the signal person on the ground
    2. The wind rating stamped on the rigging hardware
    3. The manufacturer's published wind limit for the boom and load configuration Correct answer.
    4. Any wind speed below 30 mph

    Explanation

    Wind limits are set by the manufacturer and vary with boom length, boom configuration, and the sail area of the load. When gusts approach that limit, or when the load cannot be controlled, the lift must be stopped.

  115. Question 115Crane Operation

    The rated capacity limiter alarms while the operator is hoisting. What is the correct response?

    1. Increase engine speed to raise the load faster
    2. Bypass the limiter to finish the lift
    3. Stop the movement and reduce the load or the radius before continuing Correct answer.
    4. Continue hoisting slowly while watching the display

    Explanation

    The rated capacity limiter warns that the crane is approaching or exceeding its rated capacity for the current configuration. The operator must stop, then reduce the load weight or the radius so the lift is back within the chart before proceeding.

  116. Question 116Crane Operation

    When two cranes share a single lift, how is the operation directed?

    1. One designated person directs both operators Correct answer.
    2. Each rigger signals the operator nearest to them
    3. The two signal persons work independently of each other
    4. Each operator follows his or her own judgment

    Explanation

    A multi-crane lift requires one designated person to direct both operators so the load is shared as planned. Independent direction can cause one crane to take more than its intended share of the load.

  117. Question 117Crane Operation

    Why should the operator decelerate the swing gradually instead of releasing the swing control abruptly?

    1. To keep the swing brake from overheating
    2. To reduce fuel consumption during the lift
    3. To control load swing and side loading of the boom Correct answer.
    4. To reduce wear on the turntable bearing

    Explanation

    An abrupt stop lets the suspended load keep moving, producing swing and side load on the boom and potentially shocking the crane. Gradual deceleration keeps the load under control and within the assumptions of the load chart.

  118. Question 118Crane Operation

    At the same working radius, why is the rated capacity lower when a longer boom is used?

    1. The hook block weighs more when the boom is long
    2. The outriggers carry less of the crane's weight with a long boom
    3. The load line is shorter with a long boom
    4. The longer, heavier boom leaves less strength and stability available for the load Correct answer.

    Explanation

    A longer boom adds weight and changes the structural and stability limits of the crane, so less capacity remains for the load at the same radius. This is why a separate chart column or row exists for each boom length.

  119. Question 119Crane Operation

    A lift is planned right at the chart limit at a 30 ft radius. When the load comes off the ground, the boom deflects under load. What is the effect, and what must be done?

    1. Radius is unchanged because the chart is based on the boom pivot
    2. Radius increases, so the lift must be replanned or the load reduced Correct answer.
    3. Boom deflection affects only lattice booms and may be ignored
    4. Radius decreases, so capacity rises and the lift remains safe

    Explanation

    Boom deflection under load increases the actual working radius beyond the no-load radius that was measured. A lift planned at the chart limit can therefore exceed capacity once the load is applied, so it must be replanned with margin or the load reduced.

  120. Question 120Crane Operation

    A load and rigging weighing 10,200 lb will be picked at a 20 ft radius, where the chart shows 22,000 lb, and set at a 38 ft radius, where the chart shows 9,500 lb. How should the lift be evaluated?

    1. Not acceptable, because the boom must be re-rated for the shorter length
    2. Acceptable, because capacity is set by the pick radius only
    3. Not acceptable, because the load exceeds the capacity at the setting radius Correct answer.
    4. Acceptable, because the 20 ft capacity is 22,000 lb

    Explanation

    The lift must be rated at the greatest radius the load will reach during the entire operation, which here is the 38 ft setting radius. Since 10,200 lb exceeds the 9,500 lb available at that radius, the lift as planned is over capacity.

  121. Question 121Load Chart Use and Capacity Determination

    When using a load chart, which items must be subtracted from the gross chart capacity to find the net load the crane may lift?

    1. The counterweight and outrigger floats bolted to the crane
    2. Hook block, slings, and all rigging below the boom tip Correct answer.
    3. Only the slings and shackles attached to the load itself
    4. Only the weight of the hook block and the headache ball

    Explanation

    Chart values are gross capacities, meaning everything suspended below the boom tip counts as load. Subtract the hook block, slings, spreader bars, and any other lifting attachments to obtain the allowable net load weight. Counterweight and outrigger floats are part of the crane's configured machine weight, not deducted load.

  122. Question 122Load Chart Use and Capacity Determination

    Load radius for a mobile crane is measured from the crane's center of rotation to what point?

    1. The nearest outrigger float, measured to the load's closest corner
    2. The front bumper, measured horizontally to the nearest edge of the load
    3. The vertical line through the load's center of gravity Correct answer.
    4. The tip of the boom, measured along the boom centerline

    Explanation

    Radius is the horizontal distance from the crane's center of rotation to the vertical line passing through the center of gravity of the suspended load. It is measured with the load hanging free, not along the boom or from a bumper. Boom deflection and load swing must be accounted for when determining the true radius.

  123. Question 123Load Chart Use and Capacity Determination

    A load chart lists one capacity for operation on fully extended outriggers and a lower capacity for operation on rubber. Which configuration normally permits the higher capacity, and why?

    1. Equal, because the chart is based only on boom strength
    2. On rubber, because the tires cushion shock and spread the load
    3. On rubber, because the crane can roll closer to the load
    4. On outriggers fully extended, because the stance is widest Correct answer.

    Explanation

    Extending the outriggers fully widens the crane's support base and removes load from the tires and suspension, which raises the stability-limited ratings. On-rubber ratings are lower because the tires and suspension become the support system. The applicable chart must match the configuration actually used.

  124. Question 124Load Chart Use and Capacity Determination

    The actual working radius is 27 ft. The chart lists 9,800 lb at 25 ft and 8,600 lb at 30 ft. Which capacity applies?

    1. The lower capacity listed at 30 ft Correct answer.
    2. The 9,800 lb value listed at 25 ft
    3. The 30 ft value plus a 10 percent allowance
    4. The average of the two listed capacities

    Explanation

    Capacities may not be interpolated upward between chart radii. When the actual radius falls between two listed radii, use the capacity for the next longer radius, which is the lower, conservative value. Here the 8,600 lb rating at 30 ft governs.

  125. Question 125Load Chart Use and Capacity Determination

    At the same radius, which boom gives the greater capacity?

    1. The 100 ft boom, because it reaches a greater height
    2. The 100 ft boom, because it has more lifting points
    3. Both are equal, since the radius is identical
    4. The 60 ft boom Correct answer.

    Explanation

    At equal radius, a shorter boom carries less of its own weight at a given reach and deflects less, so its rating is higher. Longer booms reduce capacity because boom weight and deflection act against the crane. The chart shows a separate rating for each boom length at each radius.

  126. Question 126Load Chart Use and Capacity Determination

    Before making a lift, the crane must be set up so that it is:

    1. Resting on its tires with the outriggers retracted
    2. Positioned with the boom pointing uphill on any slope
    3. Turned so the counterweight faces the load
    4. Level within the manufacturer's tolerance Correct answer.

    Explanation

    Charts are published on the assumption that the crane is level within the manufacturer's stated tolerance. An out-of-level crane swings the load and changes the load's effective radius and the machine's stability. Leveling must be verified at the carrier with a spirit level before lifting.

  127. Question 127Load Chart Use and Capacity Determination

    The chart capacity at the working radius is 24,000 lb. The hook block weighs 1,200 lb and the slings weigh 300 lb. What is the heaviest load that may be lifted?

    1. 25,500 lb
    2. 22,500 lb Correct answer.
    3. 22,800 lb
    4. 24,000 lb

    Explanation

    Gross chart capacity must cover the load plus all suspended rigging. Subtract the hook block and sling weights: 24,000 minus 1,200 minus 300 equals 22,500 lb. Deducting only part of the rigging would overload the crane.

  128. Question 128Load Chart Use and Capacity Determination

    Which document provides the rated lifting capacities for a specific crane at various radii, boom lengths, and configurations?

    1. The crane's most recent annual inspection report
    2. The manufacturer's load chart for that crane Correct answer.
    3. The general OSHA crane standard tables for that crane type
    4. The site rigging plan prepared by the lift director

    Explanation

    Rated capacities come from the crane manufacturer's load chart, which is machine-specific and configuration-specific. General regulatory tables and site plans do not replace the manufacturer's ratings. The chart in use must correspond to the crane's serial number and installed configuration.

  129. Question 129Load Chart Use and Capacity Determination

    A jib is stowed on the side of the boom and will not be used for the lift. How does the stowed jib affect capacity?

    1. It has no effect on capacity because it is not in use
    2. It replaces the hook block deduction in the chart
    3. Its weight, per the chart notes, must be deducted from boom capacity Correct answer.
    4. Capacity must be taken from the jib chart even though the jib is stowed

    Explanation

    A stowed attachment rides on the boom and therefore adds to the weight the boom must carry. Chart notes typically require deducting stowed jib or attachment weight from the boom capacity. The boom chart still governs, but the deduction reduces the usable capacity.

  130. Question 130Load Chart Use and Capacity Determination

    Which statement about parts of line is correct?

    1. It reduces boom deflection at long radii
    2. It has no effect on line pull or line speed
    3. It increases the crane's chart capacity in direct proportion
    4. It reduces line pull but not the crane's chart capacity Correct answer.

    Explanation

    Additional parts of line divide the load among more rope lines, lowering the pull on the hoist and the load on the wire rope. Chart capacity is set by structure and stability, so reeving changes do not raise the rated capacity. Reeving also reduces line speed.

  131. Question 131Load Chart Use and Capacity Determination

    A chart lists separate ratings for lifting over the front, over the rear, and over the side. The planned lift will swing over the side. Which rating applies?

    1. The highest rating shown anywhere on the chart
    2. The rating for the quadrant where the boom will work Correct answer.
    3. The over-the-front rating, because the boom is strongest there
    4. The average of the front and side ratings

    Explanation

    Charts publish different ratings for different working areas because structure and stability vary around the machine. The rating for the quadrant in which the boom will actually operate governs the lift. Where the lift swings through more than one quadrant, the lowest applicable rating governs.

  132. Question 132Load Chart Use and Capacity Determination

    Why can the actual radius of a loaded boom be greater than the radius measured before the lift?

    1. The counterweight moves outward as the boom swings
    2. The outriggers settle into the ground under the load
    3. The hoist line stretches and pays out extra rope
    4. The boom deflects under load, increasing the radius Correct answer.

    Explanation

    Boom deflection under load lowers the boom tip and moves it outward, which increases the true radius. Because capacity falls as radius grows, the chart must be checked at the loaded radius. This is why operators allow for deflection when working near a chart limit.

  133. Question 133Load Chart Use and Capacity Determination

    A lift uses a 2,000 lb spreader beam and a 10,500 lb load. The hook block weighs 500 lb and the chart capacity at the working radius is 13,500 lb. What total load is applied against the chart?

    1. 10,500 lb
    2. 13,000 lb Correct answer.
    3. 13,500 lb
    4. 12,500 lb

    Explanation

    The chart sees the load plus everything suspended with it: 10,500 plus 2,000 plus 500 equals 13,000 lb. That is below the 13,500 lb rating, so the lift is within capacity. Omitting the spreader beam or hook block would understate the load on the chart.

  134. Question 134Load Chart Use and Capacity Determination

    The range diagram in a crane's load chart documentation is used to determine:

    1. Boom length and angle for a given radius and height Correct answer.
    2. Counterweight required to balance the load
    3. Outrigger float size needed for the ground condition
    4. Wire rope breaking strength for each part of line

    Explanation

    The range diagram plots boom tip height against radius for each boom length, letting the operator find the boom length and angle that reach a desired point. Once the geometry is known, the corresponding load chart rating can be selected. It does not address rope strength, float sizing, or counterweight.

  135. Question 135Load Chart Use and Capacity Determination

    When a crane will travel with a suspended load, the capacity used must come from:

    1. A separate pick-and-carry chart covering travel and tire limits Correct answer.
    2. The same values as the on-outriggers chart
    3. Boom structural strength alone, with no stability check
    4. The on-rubber chart with a 15 percent increase allowed

    Explanation

    Pick-and-carry ratings are published separately from stationary ratings because travel adds dynamic loads, tire limits, and ground-condition effects. These charts are typically much lower than stationary on-rubber ratings. Using any other chart for a traveling lift understates the demands on the machine.

  136. Question 136Load Chart Use and Capacity Determination

    A load with a large sail area is being lifted in a steady wind. How should the lift be handled?

    1. Ignore any wind below 20 mph, since it cannot affect the load
    2. Use the chart's over-the-rear rating instead of the side rating
    3. Add the wind speed in miles per hour directly to the load weight in pounds
    4. Reduce the load or stop the lift per the manufacturer's wind limits Correct answer.

    Explanation

    Wind acting on a large surface area adds force to the load and side load to the boom, and the chart ratings assume still-air conditions. The manufacturer's wind limits and any load-area restrictions must be followed. When those limits are approached, the load must be reduced or the lift postponed.

  137. Question 137Load Chart Use and Capacity Determination

    At a fixed boom length, the boom is lowered so the angle decreases. What happens to capacity?

    1. It increases, because less rope is on the drum
    2. It stays the same, since the boom length did not change
    3. It decreases, because the radius increases Correct answer.
    4. It increases, because the boom is closer to horizontal

    Explanation

    Lowering the boom at a fixed length increases the working radius, and capacity drops as radius grows. The chart ties capacity to radius, not to boom angle directly. This is why the load chart must be rechecked whenever the boom is repositioned.

  138. Question 138Load Chart Use and Capacity Determination

    A crane is set up with the jib erected and offset. Which chart governs the lift?

    1. The main boom chart, because the boom carries the jib
    2. Whichever chart gives the higher capacity at that radius
    3. The jib chart for that boom, jib length, and offset Correct answer.
    4. The on-rubber chart for the crane's travel configuration

    Explanation

    When the jib is erected, the manufacturer publishes a separate rating that depends on boom length, jib length, and jib offset angle. That rating must be used, along with deductions for the jib and any stowed equipment. Selecting a more favorable chart is never permitted.

  139. Question 139Load Chart Use and Capacity Determination

    The capacity plate on the crane shows a value that disagrees with the load chart kept in the cab. What should the operator do?

    1. Use the plate, because it is permanently attached to the crane
    2. Use whichever value is higher for the planned lift
    3. Stop and resolve the difference with the manufacturer Correct answer.
    4. Use the chart, because it is more detailed

    Explanation

    Conflicting capacity information means the ratings cannot be verified, and no lift should proceed until the correct data is confirmed. The manufacturer or a qualified person must reconcile the plate and the chart. Choosing the more convenient number risks overloading the crane.

  140. Question 140Load Chart Use and Capacity Determination

    A chart note states that capacities above the bold line are limited by structural strength and those below the line by stability. What does this mean?

    1. Above the line, stability governs; below it, strength governs
    2. The line marks the radius beyond which the crane cannot slew
    3. The line separates on-rubber ratings from outrigger ratings
    4. Above the line, strength governs; below it, stability governs Correct answer.

    Explanation

    Long radii are typically stability-limited, where tipping is the controlling hazard, while short radii are structural, where boom or cylinder strength governs. The line on the chart marks where the controlling limit changes. Both regions still require the load to stay within the published value.

  141. Question 141Load Chart Use and Capacity Determination

    A crane is set with outriggers fully extended on one side and partially extended on the other. Which rating applies?

    1. The full-extension rating reduced by 25 percent
    2. The chart rating for fully extended outriggers on both sides
    3. The average of the full and partial extension ratings
    4. The chart rating for the least-extended outrigger configuration Correct answer.

    Explanation

    The crane's support geometry is only as good as its least favorable side, so the chart for the partial extension governs. Published partial-extension ratings already account for the reduced stance. Averaging or applying an arbitrary percentage is not permitted.

  142. Question 142Load Chart Use and Capacity Determination

    The rated capacity limiter alarms as the load approaches the limit, yet the operator's hand calculation shows only 98 percent of chart capacity. What is the best action?

    1. Stop and verify radius, boom length, and configuration Correct answer.
    2. Add counterweight so the crane has more capacity
    3. Continue slowly, because the alarm is only a warning
    4. Override the limiter, since the calculated load is under 100 percent

    Explanation

    A discrepancy between the limiter and the hand calculation usually means the actual radius, boom length, or configuration differs from what was assumed. The lift should stop until the true geometry is measured and the correct chart page is used. Overriding the device or guessing defeats the safety system.

  143. Question 143Load Chart Use and Capacity Determination

    Two cranes lift a load whose center of gravity is closer to crane A. How is the load shared between the hooks?

    1. Crane A carries the larger share, based on the moment balance Correct answer.
    2. Equally, because both hooks are attached to the same load
    3. Crane A carries all of it, since it is nearest the center of gravity
    4. In proportion to each crane's maximum rated capacity

    Explanation

    A suspended load distributes to the pick points inversely with their horizontal distance from the load's center of gravity. The crane nearer the center of gravity therefore carries the larger share. Each crane must be rated for its share plus its own rigging, and the lift plan should state those shares.

  144. Question 144Load Chart Use and Capacity Determination

    Besides stability, which limit commonly governs a crane's rated capacity when operating on rubber?

    1. The hoist line pull limit
    2. Only the boom's structural strength
    3. Tire and axle capacity Correct answer.
    4. The counterweight's mounting bolts

    Explanation

    On-rubber ratings account for the load carried by the tires and axles as well as for tipping. Tire load limits can control the rating before stability does, especially with a heavy counterweight or a long boom. This is one reason on-rubber charts are substantially lower than outrigger charts.

  145. Question 145Load Chart Use and Capacity Determination

    The capacity printed in a load chart at a given boom length and radius represents:

    1. gross capacity before lifting attachments are deducted Correct answer.
    2. the load the hook block alone is rated to support
    3. payload weight only, with attachments already deducted
    4. the tipping load of the crane with no margin applied

    Explanation

    Load chart values are gross figures: they state the total load, including the hook block and all rigging, that may be handled at that boom length and radius. To find the payload you may actually pick, you deduct the weight of the hook block, slings, shackles, and any other attachments below the boom tip from the chart value.

  146. Question 146Load Chart Use and Capacity Determination

    Working radius for a lift is measured horizontally from the crane's center of rotation to:

    1. the centerline of the crane's front bumper
    2. the center of gravity of the load Correct answer.
    3. the nearest edge of the load
    4. the outer edge of the outrigger float on the load side

    Explanation

    Radius is the horizontal distance from the center of rotation of the crane to the center of gravity of the load, because that is the distance that produces the tipping moment. Measuring to the near edge of a load understates the radius and overstates the available capacity.

  147. Question 147Load Chart Use and Capacity Determination

    To determine the greatest payload that may be lifted at a given radius and boom length, the operator must subtract the weight of the hook block and:

    1. the boom, jib, and boom foot pin
    2. the crane's counterweight and carbody
    3. the slings, shackles, and other rigging below the boom tip Correct answer.
    4. the outrigger floats, pads, and blocking

    Explanation

    Everything hanging below the boom tip is part of the gross load and must be deducted from the chart capacity to find the allowable payload. Counterweight, boom, and outriggers are part of the crane itself and are already accounted for in the published rating.

  148. Question 148Load Chart Use and Capacity Determination

    The boom length needed for a lift falls between two lengths shown on the chart, and the manufacturer does not permit interpolation for boom length. The operator must use the capacity for:

    1. the average of the two listed boom lengths
    2. the next shorter boom length listed
    3. either length, whichever gives the larger capacity
    4. the next longer boom length listed Correct answer.

    Explanation

    When the required boom length is not charted and interpolation is not permitted, the conservative practice is to use the next longer boom length, because a longer boom at the same radius carries a lower rating. Using the shorter length would overstate capacity.

  149. Question 149Load Chart Use and Capacity Determination

    Capacity values in the outrigger section of a load chart assume that the crane is level and that:

    1. all outriggers are fully extended on firm footing Correct answer.
    2. the floats bear directly on undisturbed soil without pads
    3. the outriggers are extended only as far as site obstructions allow
    4. at least two outriggers carry the full load before the lift begins

    Explanation

    Outrigger ratings are based on the crane being level with the outrigger beams fully extended and the floats bearing on a supporting surface strong enough to carry the load. If any of these conditions is not met, the published rating does not apply.

  150. Question 150Load Chart Use and Capacity Determination

    Which of the following is counted as part of the gross load that must be compared with the chart capacity?

    1. The weight of the crane's counterweight
    2. The weight of the boom and jib
    3. The weight of the outrigger beams
    4. The weight of the hook block, slings, and shackles Correct answer.

    Explanation

    Gross load is everything suspended from the boom tip: the payload plus the hook block, slings, shackles, spreader beams, and other rigging. Machine components such as counterweight, boom, and outriggers are already reflected in the rating.

  151. Question 151Load Chart Use and Capacity Determination

    At a fixed boom length, if the lift can be made at a shorter radius than originally planned, the crane's available capacity:

    1. decreases, because the load line is shorter
    2. stays the same, because the boom length is unchanged
    3. decreases, because the boom is closer to vertical
    4. increases as the chart rating rises Correct answer.

    Explanation

    Capacity ratings rise as radius decreases because the tipping moment produced by the load is smaller closer in. At a fixed boom length, moving the load closer to the crane therefore increases the capacity read from the chart.

  152. Question 152Load Chart Use and Capacity Determination

    A crane is rigged with an overhaul (headache) ball instead of a hook block. The weight of the ball:

    1. must be deducted from the chart capacity Correct answer.
    2. may be disregarded because the ball is not a load-handling device
    3. is already built into the published chart capacity
    4. is deducted only when the boom is shorter than 60 ft

    Explanation

    Any weight suspended below the boom tip is part of the gross load, and that includes an overhaul ball, a hook block, or a load cell. Its weight must be subtracted from the chart capacity before deciding how much payload may be lifted.

  153. Question 153Load Chart Use and Capacity Determination

    A chart note states that the listed capacities are for a freely suspended load. This note means that:

    1. the boom must be fully retracted before making the lift
    2. pulling or dragging the load sideways is outside the rating Correct answer.
    3. the hook must be fitted with a swivel to prevent rotation
    4. the load must be lifted at a reduced line speed

    Explanation

    A freely suspended load hangs vertically, so the only significant force on the boom is the vertical load at the charted radius. Pulling, dragging, or side-loading the load introduces forces the chart does not cover and can reduce the crane's effective capacity.

  154. Question 154Load Chart Use and Capacity Determination

    The measured working radius falls between two radii listed on the chart, and the manufacturer does not permit interpolation. The operator must use the capacity at:

    1. the average of the two listed capacities
    2. the next shorter radius listed
    3. the maximum radius covered by the chart
    4. the next longer radius listed Correct answer.

    Explanation

    Where interpolation is not authorized, the operator must use the next longer radius, because capacity falls as radius increases and that value is conservative. Using the shorter radius would overstate the crane's capability at the actual measured radius.

  155. Question 155Load Chart Use and Capacity Determination

    Chart capacity at the working radius is 18,500 lb. The hook block weighs 900 lb, the slings and shackles weigh 400 lb, and a stowed jib requires a 1,200 lb deduction. The greatest payload is:

    1. 18,500 lb
    2. 15,600 lb
    3. 17,200 lb
    4. 16,000 lb Correct answer.

    Explanation

    All deductions are subtracted from the chart capacity before the payload is determined: 18,500 minus 900, minus 400, minus 1,200 equals 16,000 lb. Omitting any of these items would allow an overload.

  156. Question 156Load Chart Use and Capacity Determination

    A lift requires 9,000 lb of gross load, and the chart capacity at the working radius is 12,000 lb. The crane is loaded to what percentage of its rated capacity?

    1. 80 percent
    2. 60 percent
    3. 133 percent
    4. 75 percent Correct answer.

    Explanation

    Utilization is the gross load divided by the chart capacity at the working radius: 9,000 divided by 12,000 equals 0.75, or 75 percent. The gross load must include the hook block and all rigging, not just the payload.

  157. Question 157Load Chart Use and Capacity Determination

    If a mobile crane is set up out of level, the load chart:

    1. no longer applies and the crane must first be leveled Correct answer.
    2. still applies as long as the swing is limited to 90 degrees
    3. still applies, because the chart includes an allowance for slope
    4. still applies if the outriggers on the low side sit on pads

    Explanation

    Chart ratings assume the crane is level within the manufacturer's tolerance. An out-of-level crane changes the geometry of the supporting base, shifts load onto individual outriggers, and introduces side loading, so the published capacities cannot be relied upon until the crane is leveled.

  158. Question 158Load Chart Use and Capacity Determination

    At the same working radius, a crane fitted with a longer boom will generally have:

    1. a higher capacity, because the boom tip is higher
    2. a higher capacity whenever the boom is kept below 45 degrees
    3. a lower capacity for that radius Correct answer.
    4. the same capacity, because the radius is unchanged

    Explanation

    A longer boom weighs more and is more flexible, so at any given radius the chart must show a lower rating than for a shorter boom. Radius alone does not determine capacity; boom length is a separate variable read from the chart.

  159. Question 159Load Chart Use and Capacity Determination

    If the area of an outrigger float or its pad is doubled while the load carried by that outrigger stays the same, the pressure on the ground:

    1. increases by the square of the area
    2. doubles
    3. stays the same
    4. is halved Correct answer.

    Explanation

    Ground bearing pressure equals force divided by contact area. If the force stays constant and the contact area doubles, the pressure on the ground drops by half, which is why larger floats and mats improve bearing capacity.

  160. Question 160Load Chart Use and Capacity Determination

    A crane is set up with a counterweight different from the one the chart was published for. The chart capacities:

    1. may still be used if the boom is kept over the rear
    2. may still be used if the outriggers are fully extended
    3. do not apply; use the rating for the actual configuration Correct answer.
    4. may still be used if the load is reduced by 10 percent

    Explanation

    Load charts are configuration-specific, and counterweight is one of the configuration variables that determines the rating. A different counterweight requires the chart or supplement published for that exact configuration; an arbitrary percentage reduction is not a substitute.

  161. Question 161Load Chart Use and Capacity Determination

    The load line is being run over the auxiliary (rooster) sheave instead of the main boom head. The capacity to use is:

    1. the auxiliary head rating for that boom and radius Correct answer.
    2. the main boom head rating reduced by 5 percent
    3. the main boom head rating, because the boom is unchanged
    4. the jib rating for the same radius

    Explanation

    Charts publish separate ratings for the main boom head and the auxiliary head because the load path and structural limits differ. When the line runs over the auxiliary head, the capacity must be read from the auxiliary head rating at that boom length and radius.

  162. Question 162Load Chart Use and Capacity Determination

    Which of the following requires the operator to obtain a different rating from the load chart?

    1. Repositioning the hook over the same pick point
    2. Using a longer choker on each sling leg
    3. Attaching a second tag line to the load
    4. Installing a jib on the boom Correct answer.

    Explanation

    Adding a jib changes the crane's configuration and therefore its rating, so the chart section that covers the jib must be used. Changes to slings, tag lines, or hook position within the same radius affect deductions or rigging, not the chart selection.

  163. Question 163Load Chart Use and Capacity Determination

    A boom deflects under load, so the actual radius becomes larger than the radius measured before the lift. The operator should:

    1. add 5 percent to the chart capacity to correct for deflection
    2. check the capacity at the larger loaded radius Correct answer.
    3. disregard the change, because the chart assumes a straight boom
    4. assume the radius returns to its original value once the load is landed

    Explanation

    Capacity must be verified at the radius that exists while the load is suspended, because that is the radius producing the overturning moment. If deflection increases the radius, the operator must re-read the chart at the larger radius and confirm the gross load is still within the rating.

  164. Question 164Load Chart Use and Capacity Determination

    A chart lists these capacities for a given boom length: 12 ft, 34,000 lb; 15 ft, 27,000 lb; 18 ft, 22,000 lb; 21 ft, 18,000 lb. The gross load, including hook block and rigging, is 20,000 lb. The greatest radius at which the lift may be made is:

    1. 18 ft Correct answer.
    2. 15 ft
    3. 12 ft
    4. 21 ft

    Explanation

    The gross load of 20,000 lb is within the 22,000 lb rating at 18 ft but exceeds the 18,000 lb rating at 21 ft. The greatest acceptable radius is therefore 18 ft, since the next charted radius out is below the required load.

  165. Question 165Load Chart Use and Capacity Determination

    A long load is rigged so that its center of gravity hangs 5 ft beyond the point directly below the boom tip. The horizontal distance from the crane's center of rotation to the point below the boom tip is 20 ft. The radius to use for the chart is:

    1. 20 ft
    2. 15 ft
    3. 25 ft Correct answer.
    4. 5 ft

    Explanation

    Radius is measured to the center of gravity of the load, not to the point below the boom tip. When the center of gravity hangs 5 ft beyond that point, the effective radius becomes 20 plus 5, or 25 ft, and the chart must be read at that larger radius.

  166. Question 166Load Chart Use and Capacity Determination

    Which of these lifts develops the greatest overturning moment about the crane?

    1. 11,000 lb at a radius of 36 ft Correct answer.
    2. 30,000 lb at a radius of 12 ft
    3. 15,000 lb at a radius of 24 ft
    4. 24,000 lb at a radius of 15 ft

    Explanation

    Load moment is the load multiplied by its radius. The 11,000 lb load at 36 ft produces 396,000 lb-ft, while the other three combinations each produce 360,000 lb-ft, so that lift creates the largest moment even though it is not the heaviest load.

  167. Question 167Load Chart Use and Capacity Determination

    One outrigger of a set crane carries 62,000 lb. Its float is 24 in by 24 in. Ignoring any mat, the average ground pressure under the float is approximately:

    1. 7,750 psf
    2. 62,000 psf
    3. 15,500 psf Correct answer.
    4. 2,580 psf

    Explanation

    Ground bearing pressure is force divided by contact area. A 24 in by 24 in float covers 2 ft by 2 ft, or 4 square feet, so 62,000 lb divided by 4 sq ft gives about 15,500 psf, which is why mats are often needed to spread the load.

  168. Question 168Load Chart Use and Capacity Determination

    A manufacturer permits interpolation between charted radii. The chart shows 24,000 lb at 15 ft and 19,000 lb at 20 ft for the boom in use. Using linear interpolation, a gross load of 21,500 lb may be lifted at a maximum radius of approximately:

    1. 17.5 ft Correct answer.
    2. 15 ft
    3. 19 ft
    4. 20 ft

    Explanation

    Capacity falls by 5,000 lb over 5 ft, or 1,000 lb per foot. Moving from 24,000 lb down to 21,500 lb is a drop of 2,500 lb, which corresponds to 2.5 ft, so interpolation gives a maximum radius of 17.5 ft.

  169. Question 169Load Chart Use and Capacity Determination

    During a pick-and-swing, the load passes through a radius where the chart capacity is lower than at the pick point and lower than at the set point. The lift:

    1. must be based on the lowest capacity along the swing path Correct answer.
    2. may proceed if the load moment limiter does not alarm
    3. may be planned using the capacity at the set point
    4. may be planned using the capacity at the pick point

    Explanation

    The crane must remain within its rating at every point in the operation, so the controlling value is the lowest capacity encountered anywhere along the swing. Using only the pick or set point capacity ignores the more restrictive condition the load passes through.

  170. Question 170Communication and Hand Signals

    Which hand signal directs the operator to stop the crane's motion?

    1. Arm extended, palm down, sweep arm back and forth Correct answer.
    2. Forearm vertical, forefinger up, move hand in small circles
    3. Both arms raised overhead, hands opened and closed repeatedly
    4. Arm extended, palm up, move arm up and down vertically

    Explanation

    The standard stop signal is the arm extended horizontally with the palm down, moved back and forth horizontally. It tells the operator to stop whatever motion is in progress and hold. It is the one signal every crew member is permitted to give.

  171. Question 171Communication and Hand Signals

    How does a signal person give the emergency stop signal?

    1. Both hands clasped together in front of the chest
    2. Both arms extended, palms down, moved back and forth Correct answer.
    3. Arm extended forward with hand open, pushing motion
    4. One arm extended, palm down, moved back and forth

    Explanation

    The emergency stop signal uses both arms extended horizontally with palms down, moved rapidly back and forth. Using both arms distinguishes it from the ordinary stop signal and communicates that immediate, urgent action is required. The operator must respond at once without waiting for confirmation.

  172. Question 172Communication and Hand Signals

    During a lift, who is responsible for directing the crane operator's movements?

    1. Any competent person who is within sight of the load
    2. The signal person designated for that lift Correct answer.
    3. Any rigger on the crew who notices a problem
    4. The equipment owner's representative at the site

    Explanation

    Only one person at a time gives signals, and that person is the signal person designated for the lift. Limiting direction to one source prevents conflicting commands to the operator. Other crew members may still give a stop signal if they see an emergency.

  173. Question 173Communication and Hand Signals

    A signal person holds a forearm vertical with the forefinger pointing up and moves the hand in a small horizontal circle. What does this signal mean?

    1. Hoist the load Correct answer.
    2. Lower the load
    3. Raise the boom
    4. Stop the swing

    Explanation

    The vertical forearm with the forefinger up, circling the hand in a small horizontal motion, is the hoist signal. It directs the operator to raise the load with the hoist. Its counterpart, lowering the load, uses the arm extended downward with the forefinger pointing down and the same small circling motion.

  174. Question 174Communication and Hand Signals

    The signal person extends an arm with the fingers closed and the thumb pointing downward. What does this signal direct the operator to do?

    1. Lower the boom Correct answer.
    2. Lower the load
    3. Dog all functions
    4. Retract the boom

    Explanation

    An extended arm with the fingers closed and the thumb pointing down is the lower the boom signal. Thumb direction indicates boom travel, so raising the boom is the same signal with the thumb pointing up. Lowering the load is a separate signal using a downward-pointing forefinger and a circling hand.

  175. Question 175Communication and Hand Signals

    A signal person clasps both hands in front of the body. What does this signal mean?

    1. Hold the load at its present height
    2. Dog everything and hold all motions Correct answer.
    3. Travel the crane forward at creep speed
    4. Swing the boom slowly in the signaled direction

    Explanation

    Clasping the hands in front of the body is the dog everything signal. It tells the operator to bring all motions to a hold and engage the clutches and brakes so the machine stays locked. The operator keeps the controls in that condition until a new signal is given.

  176. Question 176Communication and Hand Signals

    When radio voice signals are used to direct a crane, which requirement applies?

    1. The radio must be on a frequency monitored by the utility
    2. Signals must be prearranged and understood Correct answer.
    3. Any crew member may transmit as long as the radio is on
    4. Hand signals are prohibited whenever a radio is in use

    Explanation

    Voice signals sent by radio must be prearranged and clearly understood by both the operator and the signal person before the lift begins. The operator must know exactly which words mean hoist, lower, stop, and so on. Hand signals remain a valid backup and are not displaced by radio use.

  177. Question 177Communication and Hand Signals

    Mid-lift, the operator loses radio contact with the signal person. What should the operator do?

    1. Complete the current movement, then shut down the crane
    2. Continue the lift using hand signals from the rigger
    3. Signal back with the horn and keep operating
    4. Stop and hold until communication is restored Correct answer.

    Explanation

    When communication with the designated signal person is lost, the operator stops and holds until it is restored. Without a reliable signal link the operator cannot know what is happening at the load. Resuming requires re-establishing communication with the signal person, not with another crew member.

  178. Question 178Communication and Hand Signals

    A crew member who is not the designated signal person gives a stop signal during a lift. What should the operator do?

    1. Stop the operation immediately Correct answer.
    2. Ask the signal person to confirm the signal
    3. Continue, because only the signal person may signal
    4. Sound the horn and finish the movement

    Explanation

    The operator must obey a stop signal from anyone on the job, regardless of who gave it. The rule exists so that a person who sees a hazard can halt the crane at once. Continuing while a stop signal is being given is never acceptable.

  179. Question 179Communication and Hand Signals

    The signal person holds both fists in front of the chest with the thumbs pointing toward each other. What does this signal mean?

    1. Swing the boom right
    2. Extend the boom
    3. Retract the boom Correct answer.
    4. Dog everything

    Explanation

    With both fists in front of the body, the direction the thumbs point shows how the boom should telescope. Thumbs pointing toward each other mean retract, while thumbs pointing away from each other mean extend. The two signals are mirror images, so thumb direction is the deciding detail.

  180. Question 180Safety, Standards, and Operator Responsibilities

    Under OSHA's crane standard, what is the minimum required clearance between any part of a crane and overhead power lines energized up to 50 kV?

    1. 25 feet
    2. 10 feet Correct answer.
    3. 50 feet
    4. 5 feet

    Explanation

    OSHA's clearance table sets 10 feet as the minimum distance for lines energized up to 50 kV, with greater distances required as voltage rises. The required distance increases stepwise (15, 20, 25, 35, and 45 feet) for higher-voltage lines. Unless the line is de-energized and grounded or the voltage is confirmed and other precautions taken, the table distance governs.

  181. Question 181Safety, Standards, and Operator Responsibilities

    A signal person extends an arm horizontally with the palm down and moves the arm back and forth horizontally. Which signal is being given?

    1. Swing right
    2. Raise the boom
    3. Stop Correct answer.
    4. Lower the load

    Explanation

    The horizontal arm with palm down moved side to side is the standard stop signal in the crane hand signal set. Signal persons and operators must use one agreed set of signals so commands are unambiguous. When in doubt about a signal, the operator stops the operation.

  182. Question 182Safety, Standards, and Operator Responsibilities

    What is the primary purpose of placing crane mats or floats under the outriggers?

    1. To spread load over a larger area Correct answer.
    2. To increase available boom length
    3. To speed up crane setup
    4. To reduce the crane's footprint

    Explanation

    Outrigger floats and mats increase the contact area so the outrigger force is distributed over more ground, lowering bearing pressure and reducing the risk of the ground failing beneath the float. The crane's rated capacity depends on a stable supporting surface. Mats do not change the crane's structural or stability ratings.

  183. Question 183Safety, Standards, and Operator Responsibilities

    Who has the authority to stop a crane operation when an unsafe condition is recognized?

    1. Anyone who recognizes the hazard Correct answer.
    2. The crane inspector only
    3. The site superintendent only
    4. The lift director only

    Explanation

    Stop-work authority belongs to every person on the site, not just those in formal supervisory roles. A hazard such as a failing footing or a worker under a suspended load must be acted on immediately by whoever sees it. The operator in particular must stop whenever a condition creates a safety concern.

  184. Question 184Safety, Standards, and Operator Responsibilities

    What is the main purpose of holding a pre-lift meeting before a complex or critical lift?

    1. To review the lift plan Correct answer.
    2. To record the operator's certificate
    3. To measure the load's center of gravity
    4. To log the daily inspection

    Explanation

    A pre-lift meeting brings the crew together to walk through the lift plan, confirm assignments, and discuss hazards and contingencies before work starts. It is a communication step, not a substitute for inspections or load calculations. Everyone involved should understand their role and the sequence of operations.

  185. Question 185Safety, Standards, and Operator Responsibilities

    A crane equipped with a load moment indicator is approaching its rated capacity and the LMI alarm sounds. What should the operator do?

    1. Stop and reduce load or radius Correct answer.
    2. Increase engine speed to finish faster
    3. Continue slowly and rely on boom strength
    4. Disable the LMI to finish the lift

    Explanation

    The load moment indicator warns that the crane is at or near its rated capacity for the current configuration, so continuing risks structural overload or tipping. The operator must stop and change the lift geometry or the load before proceeding. Defeating a safety device is never an acceptable response to an alarm.

  186. Question 186Safety, Standards, and Operator Responsibilities

    During setup, one outrigger float sinks noticeably into soft soil before the lift begins. What is the correct action?

    1. Extend that outrigger further into the soil
    2. Have a worker stand on the float to add weight
    3. Continue the lift but reduce the load by 10 percent
    4. Stop and re-set the crane on a prepared surface Correct answer.

    Explanation

    The load chart assumes a firm, level supporting surface; a sinking float means that assumption is not met and the crane could tip. The operation must stop until the footing is corrected by relocating the crane or improving the surface. An arbitrary load reduction does not restore stability.

  187. Question 187Safety, Standards, and Operator Responsibilities

    A pre-use inspection reveals several broken wires in one lay of a hoist rope plus a kink. What should be done with the rope?

    1. Remove the rope from service for evaluation Correct answer.
    2. Cut out the damaged section and keep using the rope
    3. Continue because broken wires are normal wear
    4. Use the rope if the load is reduced by half

    Explanation

    Broken wires concentrated in one lay and a kink are removal criteria that indicate the rope has lost strength and may not spool properly. The rope must be taken out of service and evaluated by a qualified person before any further use. Load reduction does not make a damaged rope acceptable.

  188. Question 188Safety, Standards, and Operator Responsibilities

    The anti-two-block alarm sounds as the hook block nears the boom tip. What must the operator do?

    1. Stop hoisting immediately Correct answer.
    2. Lower the boom to the ground
    3. Extend the boom for clearance
    4. Continue hoisting at slow speed

    Explanation

    Two-blocking occurs when the hook block contacts the boom tip, which can part the hoist rope and drop the load. The alarm means the limit is being approached, so the hoisting motion must stop at once and the load lowered. Continuing to hoist defeats the purpose of the device.

  189. Question 189Safety, Standards, and Operator Responsibilities

    Where must barricades be placed around a crane whose superstructure rotates during operation?

    1. Around the full swing radius Correct answer.
    2. Only at the cab door
    3. Only in front of the crane
    4. Only where the load is landed

    Explanation

    The rear and sides of the rotating superstructure and counterweight sweep through an arc that can crush anyone standing inside it. Barricades must enclose the entire swing radius so no one can enter the path of travel. Marking only part of the arc leaves an unprotected hazard.

  190. Question 190Safety, Standards, and Operator Responsibilities

    The load chart shows 9,000 lb capacity at the planned radius, and the load itself weighs 7,000 lb. What must the operator still account for?

    1. Number of signal persons on site
    2. Color coding of the load slings
    3. Wind speed at the ground level
    4. Rigging and below-the-hook device weight Correct answer.

    Explanation

    Rated capacities apply to the gross load, which includes the load, all rigging, and any below-the-hook lifting device such as a spreader beam. With 2,000 lb of margin at that radius, the added rigging weight can easily consume the remaining capacity. The operator must total everything that hangs from the hook.

  191. Question 191Safety, Standards, and Operator Responsibilities

    Two workers are giving the operator conflicting hand signals at the same time. What should the operator do?

    1. Follow the signal from the more experienced worker
    2. Follow the signal from the nearer worker
    3. Follow whichever signal seems safest
    4. Stop until one designated signal person is used Correct answer.

    Explanation

    Only one designated signal person should direct the crane, so conflicting signals mean the communication system has broken down. The operator stops the motion until a single signal source is established. Guessing which signal to obey risks moving the load in the wrong direction.

  192. Question 192Safety, Standards, and Operator Responsibilities

    A crane's boom contacts an energized overhead power line. What should the operator do first?

    1. Climb down the ladder quickly
    2. Jump clear and run from the crane
    3. Remain in the cab and warn others away Correct answer.
    4. Touch the hook to ground the crane

    Explanation

    The operator is safest staying inside the cab, which acts as a faraday cage, and should warn others to stay clear while attempting to move the crane away from the line if it can be done safely. Leaving the machine exposes the operator to step and touch potential. Personnel on the ground must keep everyone away until the line is de-energized.

  193. Question 193Safety, Standards, and Operator Responsibilities

    The operator must step away from the controls during a lift. What is the required practice?

    1. Lower the load and shut down before leaving Correct answer.
    2. Leave the load suspended if the pause is short
    3. Set the load on the truck bed and leave the engine running
    4. Have a rigger watch the load while away

    Explanation

    A suspended load must never be left unattended because hydraulic drift, wind, or equipment failure can move it onto people below. The operator lands the load and shuts the crane down before leaving the controls. No worker on the ground can substitute for an operator at the controls.

  194. Question 194Safety, Standards, and Operator Responsibilities

    Which inspection must be completed before the crane is used at the start of each shift?

    1. Pre-shift inspection by the operator Correct answer.
    2. Annual inspection by a qualified person
    3. Inspection only after a repair
    4. Monthly periodic inspection

    Explanation

    The operator performs a pre-shift inspection of the crane each shift before use, checking items such as fluid levels, guards, control response, and safety devices. Periodic and annual inspections occur on longer cycles and supplement rather than replace the daily check. Repair-related inspections are event-driven, not shift-driven.

  195. Question 195Safety, Standards, and Operator Responsibilities

    Wind at the boom tip is approaching the manufacturer's maximum allowable wind speed for the lift. What should the operator do?

    1. Wait for wind to drop below 25 mph
    2. Continue because the load is light
    3. Stop the lift and follow the wind procedure Correct answer.
    4. Reduce boom length and keep lifting

    Explanation

    Manufacturers publish maximum wind speeds for crane operation because wind acts on both the load and the boom's exposed area. When the limit is approached or exceeded, the lift stops and the manufacturer's procedure for securing the crane is followed. No single generic wind speed applies to every crane and load configuration.

  196. Question 196Safety, Standards, and Operator Responsibilities

    Voltage on an overhead line has been confirmed with the utility as 230 kV. Using OSHA's minimum clearance table, what distance must be maintained between the crane and the line?

    1. 15 feet
    2. 10 feet
    3. 20 feet Correct answer.
    4. 25 feet

    Explanation

    OSHA's table of minimum clearance distances steps up with voltage: 10 feet up to 50 kV, 15 feet over 50 to 200 kV, and 20 feet over 200 to 350 kV. A confirmed 230 kV line therefore requires 20 feet. Higher bands (500 to 750 kV, for example) require 25 feet.

  197. Question 197Safety, Standards, and Operator Responsibilities

    When a crane is used to hoist personnel in a suspended platform, the total load must not exceed what portion of the crane's rated capacity for that configuration?

    1. 25 percent
    2. 100 percent
    3. 75 percent
    4. 50 percent Correct answer.

    Explanation

    Crane-supported personnel platforms are limited to 50 percent of the crane's rated capacity for the configuration in use, which provides reserve margin because the platform is occupied. The platform, personnel, tools, and rigging all count toward that total. Operating at full chart capacity is never permitted for personnel handling.

  198. Question 198Safety, Standards, and Operator Responsibilities

    Under OSHA's crane standard, a comprehensive inspection of the crane by a qualified person must be performed at least how often?

    1. Every 6 months
    2. Every 3 years
    3. Every 12 months Correct answer.
    4. Every 5 years

    Explanation

    Cranes in regular service require a comprehensive inspection at least annually, conducted by a qualified person, in addition to periodic inspections on a shorter cycle and the operator's pre-shift checks. When the equipment is idle for an extended period or undergoes certain repairs, additional inspections are triggered. A five-year interval applies to operator certification, not equipment inspection.

  199. Question 199Safety, Standards, and Operator Responsibilities

    A crane is set up with outriggers fully extended on firm ground, and the chart shows 12,000 lb for that setup. The planned pick requires booming over the rear, where the chart shows 9,500 lb at the same radius. Which rating governs the lift?

    1. The higher of the two ratings at that radius
    2. The 12,000 lb rating shown for the outrigger setup
    3. The 9,500 lb rating for that quadrant Correct answer.
    4. The average of the two quadrant ratings

    Explanation

    Load charts publish different capacities for different areas of operation because stability and structural strength vary around the crane. The rating for the quadrant where the boom is actually working controls the lift. Choosing a more favorable figure from another quadrant would authorize an unsafe pick.

NCCCO Mobile Crane flashcards

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Daily pre-shift inspection
Before each shift, check wire rope, hooks, rigging, brakes, clutches, limit switches, LMI/RCL, outriggers, tires, leaks, and alarms; correct defects before lifting.
Wire rope removal criteria
Remove running rope with six randomly distributed broken wires in one lay, three broken wires in one strand in one lay, wear over one-third wire diameter, or kinking and crushing.
Hook throat opening limit
Remove a hook from service when throat opening has increased more than 15 percent or when wear exceeds 10 percent of the original dimension, unless manufacturer specifies otherwise.
LMI and anti-two-block check
Confirm the load moment indicator/rated capacity limiter and anti-two-block device are powered, calibrated, and working; never bypass or disable these safety devices.
Outrigger pad purpose
Outrigger pads spread crane force over a larger soil area, reducing bearing pressure and settlement; size them for the actual crane, load, and soil capacity.
Crane leveling requirement
Set the crane level within the manufacturer's tolerance before lifting; many mobile crane load charts require level within 1 percent of grade.
Fully extended outriggers
Use the outrigger spread shown on the load chart; partial extension or on-rubber operation is permitted only if a specific chart covers that configuration.
Ground bearing pressure formula
Ground bearing pressure equals total weight carried by one outrigger divided by the effective pad area; include crane, counterweight, load, and rigging.
Counterweight and boom configuration
Capacity depends on actual counterweight, boom length, jib, and reeving; a chart for one configuration is not valid for another.
Swing radius barricade
Barricade the area within the rotating superstructure and counterweight swing radius, and keep personnel out during operation.
Setup near excavations
Keep outriggers and crawlers back from excavations, trenches, and buried utilities; soil near an edge may not support the crane's bearing pressure.
Shock loading
Shock loading is a sudden force from jerking, snatching, or rapidly stopping a load; it can exceed rated capacity and damage boom or wire rope.
Suspended load rule
Never leave the operator station with a load suspended; if the operator must leave, lower the load and secure the crane first.
Side loading
Side loading pulls the boom sideways or drags a load, creating forces the boom is not designed for; lift vertically unless the manufacturer approves otherwise.
Pick-and-carry travel
Travel with a load only when the manufacturer's pick-and-carry chart permits it, with boom low, load near ground, slow speed, and correct tire pressure.
Anti-two-block device
The anti-two-block device prevents the hook block from contacting the boom tip, which can part wire rope and drop the load; test it before lifting.
Load radius measurement
Radius is the horizontal distance from the crane's center of rotation to the center of the load or hook, not to the boom tip.
Gross capacity deductions
Subtract hook block, slings, spreader beams, jib, auxiliary boom head, and all rigging below the boom tip from the chart's gross capacity.
Between chart radii
If the actual radius falls between two chart radii, use the capacity for the next longer radius; never interpolate upward.
Area of operation
Load charts may give different capacities over the front, side, and rear; use the chart for the actual boom position and outrigger spread.
Boom deflection effect
Under load, boom deflection increases the actual load radius and can reduce capacity; recheck radius after the load is applied.
Emergency stop signal
Any person may give the emergency stop signal; the operator must stop immediately, set brakes, and not resume until the signalperson or supervisor clears it.
Designated signalperson
Only one designated, qualified signalperson should direct the operator at a time; the operator must obey that person except for an emergency stop from anyone.
Radio communication test
Before the lift, test radios, agree on channel and voice signals, and identify a backup signalperson in case communication fails.
Unclear signal response
If a hand signal or radio instruction is unclear, the operator must stop and wait until clear communication is restored.
Hoist hand signal
Hoist: forearm vertical, forefinger pointing up, and hand moving in a small horizontal circle.
Dog everything signal
Dog everything: clasp hands in front of the body; it tells the operator to stop and hold all crane functions.
Power line approach distance
OSHA minimum approach: 10 ft for 50 kV or less, 15 ft for 50–200 kV, 20 ft for 200–350 kV, and greater distances for higher voltages.
Operator refusal authority
The operator has the authority and duty to stop and refuse any lift that is unsafe, exceeds capacity, or violates standards or the manufacturer's instructions.
Governing standards
Mobile crane operations follow OSHA 29 CFR 1926 Subpart CC, ASME B30.5, and the manufacturer's manual; the most restrictive applicable requirement governs.
Inspection types
Mobile cranes require shift, monthly, and annual/comprehensive inspections; deficiencies must be corrected and recorded before the crane is returned to service.
Qualified rigger and signalperson
Only qualified riggers and signalpersons may perform rigging and signaling duties; the operator must verify qualifications before starting the lift.

NCCCO Mobile Crane study guide

Site and Equipment Inspection

What the exam tests

A site and equipment inspection is really two inspections: the ground/site and the crane. Walk the travel path and setup area for soft spots, voids, uncompacted fill, slopes, excavations, buried utilities, overhead lines, and swing or clearance hazards. Verify access, barricades, and that the crane can be set up level within manufacturer limits. Then perform the pre-shift inspection: fluid levels, leaks, tires, outrigger pads and floats, structural cracks, pins and keepers, wire rope, sheaves, hooks, safety latches, limit switches, the load moment indicator (LMI), anti-two-block device, horn, lights, fire extinguisher, and the load chart in the cab. Document deficiencies; tag out and remove the crane from service if a safety-related item is defective.

Traps

Questions confuse a pre-shift walkaround with periodic or annual inspections. Safety devices must be functional; never bypass an LMI or anti-two-block device. Wire rope rejection criteria include broken wires, kinks, bird-caging, crushing, corrosion, and heat damage. Hook traps include a missing latch, throat opening beyond the limit, excessive wear, and cracks. Power-line questions test minimum approach distances, which increase with voltage.

Rule of thumb

If a safety device is inoperable or the ground cannot be verified, the crane is not ready. For energized lines up to 50 kV, keep at least 10 ft; higher voltages require greater clearance.

Crane Setup and Configuration

Setup is a capacity decision

The load chart is valid only for the configuration actually on the crane. Setup and configuration include outrigger spread (full, partial, or retracted), blocking and mats, level condition, boom length and telescoping mode, jib stowed or erected, counterweight, auxiliary head, number of parts of line, and tire pressure for on-rubber work. Ground bearing pressure depends on crane weight plus load, outrigger reactions, and pad area; use mats or cribbing to spread pressure and verify that underground voids are not present. Assemble per the manufacturer, with pins, keepers, and locks secured. Never assume "full outriggers" if floats are not extended or beams are not pinned.

Traps

Partial-outrigger charts have lower capacity and may require further reductions. On-rubber charts are separate and usually much lower. Radius is measured from the crane's center of rotation, or boom pivot according to the chart, to the hook-not from the outrigger. Counterweight and jib configurations change charts; a stowed jib may still add weight. "Level" means within the manufacturer's tolerance, not merely looking level. Asymmetric outrigger setups are generally not permitted unless the manufacturer provides a chart.

Worked example

A chart shows 14,000 lb at a 20 ft radius with full outriggers and the jib stowed. If the jib is erected or an outrigger beam is not fully extended, that 14,000 lb value no longer applies. Re-enter the chart using the actual configuration.

Crane Operation

Control the load, not just the lever

Operation starts with a pre-lift meeting: confirm load weight, rigging, radius, chart, signal person, travel path, and environmental limits. Keep the hoist line vertical; side loading, dragging, and shock loading can collapse a boom or tip a crane. Watch boom deflection, which increases radius and reduces capacity. Use taglines where practical. Never two-block; the anti-two-block device is a backup, not an operating tool. Telescoping or booming with a load changes radius and capacity, so follow the manufacturer's chart and procedure. Wind, icy conditions, and poor visibility are stop-and-reassess triggers.

Traps

Pick-and-carry and travel with a load are charted operations with low capacities and specific boom positions. Free swing can let the load run away; know when to use the swing brake or lock. Multiple-crane lifts require a plan and a lift director. Personnel lifting requires an approved platform and chart. The biggest trap is assuming capacity stays constant while booming down or telescoping out.

Rule of thumb

If the hoist line is not plumb, stop and correct the radius rather than "helping" the load with the boom. A side-loaded boom is a structural hazard, not a rigging shortcut.

Load Chart Use and Capacity Determination

Gross capacity is not allowable load

Load charts give gross capacity for a specific radius, boom length, angle, quadrant, outrigger condition, counterweight, and parts of line. To find the allowable load, subtract from gross capacity everything that hangs from the boom: hook block or ball, slings, shackles, spreader bars, buckets, and personnel platform. Then compare the result to the actual load weight. Confirm the chart's radius definition and area of operation. Structural and stability limits both matter; the lower one governs. Interpolation may be allowed only where the manufacturer permits it.

Traps

Using boom length where radius is required; measuring radius to the load instead of to the hook; using a full-outrigger chart with partial outriggers; forgetting hook block and rigging deductions; reading the wrong column for quadrant or boom mode; and assuming a chart for one crane applies to another. Remember: adding parts of line does not increase chart capacity-the chart already assumes a configuration.

Worked example

Gross chart capacity at the actual radius is 12,000 lb. The hook block weighs 600 lb, and slings plus shackles weigh 300 lb. Allowable load = 12,000 − 900 = 11,100 lb. A 10,500 lb load is acceptable; an 11,300 lb load is not.

Communication and Hand Signals

One voice, one signal

Effective communication prevents most crane accidents. The signal person must be qualified and positioned to see the load, the operator, and the path. Use a dedicated radio channel or standardized hand signals, and agree on signals in the pre-lift meeting. Hand signals include hoist (forearm vertical, forefinger up, small circle), lower (arm down, forefinger down, small circle), boom up or down (thumb up or down), swing (point in the direction of swing), stop (palm down, arm swept horizontally), and emergency stop (both arms extended, palms down, swept). "Dog everything" means hold all functions. Anyone may give an emergency stop signal.

Traps

Questions test who may signal: only the designated signal person, except that anyone may give an emergency stop. Multiple signal persons create confusion unless the plan assigns one. Radio failure means stop. Hand signals must not be "interpreted"; if unclear, stop. Taglines control rotation but are not communication devices. For blind lifts, use a signal person with continuous visibility or a relay.

Rule of thumb

If you cannot see the load, the signal person, or the landing zone, stop until communication is restored.

Safety, Standards, and Operator Responsibilities

The operator's duty is personal

The operator is responsible for safe operation and has stop-work authority. Know and follow OSHA 1926 Subpart CC, ASME B30.5, the manufacturer's manual, and the load chart. Certification and qualification are required; the operator must be trained on the specific crane type and familiar with its controls, safety devices, and charts. Pre-shift inspections, refueling precautions, fire extinguisher readiness, fall protection, lockout/tagout during maintenance, and power-line safety are operator concerns. Do not operate a crane with an inoperable safety device, an unreadable load chart, or unsafe ground conditions. Report incidents and deficiencies promptly.

Traps

Questions suggest the operator can rely on someone else's judgment for capacity or setup. The operator still must verify. Certification does not replace training on a particular crane. Safety devices may not be bypassed. Annual inspections do not replace daily pre-shift inspections. "Competent person" and "qualified person" are not interchangeable. A lift director or supervisor can plan the lift, but the operator retains the duty to refuse an unsafe operation.

Rule of thumb

When in doubt, stop, lower the load to a safe position, and verify with the manual, chart, supervisor, or engineer before continuing.

NCCCO Mobile Crane cheat sheet

Quick reference

Site and Equipment Inspection

  • Pre-shift inspection covers wire rope, hooks, rigging, brakes, clutches, limit switches, LMI/RCL, outriggers, tires, fluid leaks, and alarms; correct defects before lifting.

  • Wire rope removal: 6 randomly distributed broken wires in one lay, 3 broken wires in one strand in one lay, wear exceeding 1/3 of wire diameter, or kinking/crushing.

  • Hook removal: cracks, deformation, throat opening increase greater than 15%, wear greater than 10% of original dimension, or missing/damaged safety latch.

  • Verify LMI/RCL and anti-two-block devices are powered, calibrated, and functioning; never bypass or disable safety devices.

  • Outrigger pads must distribute force over enough area to prevent settlement; check soil bearing, voids, utilities, and slopes under each float.

  • Level the crane within manufacturer tolerance before lifting; many charts require level within 1% of grade.

  • Inspect slings and rigging for cuts, broken wires, burns, knots, distorted hardware, and missing tags; remove damaged gear from service.

  • Check site for power lines, excavations, underground utilities, traffic, pedestrians, wind, and weather before setup and throughout the shift.

Quick reference

Crane Setup and Configuration

  • Extend outriggers fully and set floats on stable cribbing unless the load chart specifically covers a partial or on-rubber configuration.

  • Ground bearing pressure = total weight on each outrigger ÷ effective pad area; include crane, counterweight, load, and rigging.

  • Match load chart to actual boom length, jib, counterweight, outrigger spread, and reeving; a different configuration requires a different chart.

  • Barricade the swing radius and keep personnel clear of the counterweight and rotating superstructure.

  • Keep setup away from excavations, trenches, utility trenches, and buried utilities; maintain required slope setback and clearance.

  • Assemble boom and jib with correct pins, retainers, and reeving; confirm boom angle and length sensors read correctly.

  • Check that outrigger beams, jacks, and floats are free of damage and that beams are pinned or locked in the charted position.

Quick reference

Crane Operation

  • Avoid shock loading: start and stop smoothly, take up slack gradually, and never jerk a load.

  • Never leave the operator station with a load suspended; if leaving controls, lower load and secure crane.

  • Avoid side loading and dragging loads; boom and rope are designed for vertical lifting unless manufacturer approves otherwise.

  • Travel with a load only when the manufacturer's pick-and-carry chart permits it; keep boom low, load near ground, and travel slow.

  • Use anti-two-block device and warning; two-blocking can part wire rope and drop the load.

  • Plan multiple-crane lifts with equal load sharing, a qualified lift plan, and one designated leader/signalperson.

  • Stop operations when wind, lightning, visibility, or ground conditions exceed manufacturer or site limits.

  • Account for load swing, centrifugal force, and wind drift when swinging; use taglines to control rotation.

Quick reference

Load Chart Use and Capacity Determination

  • Radius is horizontal distance from crane center of rotation to center of the load/hook, not to boom tip.

  • Read capacity at the actual radius, boom length, quadrant/area, and configuration; if between chart radii, use the next longer radius.

  • Deduct from gross chart capacity: hook block, slings, spreader beams, jib, auxiliary boom head, and all below-boom-tip rigging.

  • Boom deflection increases actual radius and reduces capacity; verify radius after load is applied.

  • Capacity can differ by area of operation (over front, side, rear) and by outrigger spread; use chart for actual position.

  • Jib capacities are separate and lower; deduct jib weight and all rigging per chart notes.

  • Never exceed rated capacity; the load chart and manufacturer's operating manual govern.

  • On-rubber capacities apply only to specific pick-and-carry configurations and tire pressures; never use them for static lifts.

Quick reference

Communication and Hand Signals

  • Use standard ASME B30.5 hand signals; only one designated signalperson directs the operator at a time.

  • Any person may give an emergency stop signal, and the operator must stop immediately when it is given.

  • Test radio communication before the lift; agree on channel, voice signals, and a backup signalperson if communication fails.

  • If a signal is unclear or communication is lost, stop the operation until clear communication is restored.

  • Hoist signal: forearm vertical, forefinger pointing up, move hand in small horizontal circle.

  • Lower signal: arm extended downward, forefinger pointing down, move hand in small horizontal circle.

  • Stop signal: arm extended, palm down, move arm back and forth horizontally.

  • Dog everything signal: clasp hands in front of body.

Quick reference

Safety, Standards, and Operator Responsibilities

  • OSHA 29 CFR 1926 Subpart CC and ASME B30.5 set mobile crane requirements; manufacturer's manual and load chart take precedence when more restrictive.

  • Minimum approach distance to power lines: 10 ft for ≤50 kV; 15 ft for 50–200 kV; 20 ft for 200–350 kV; 25 ft for 350–500 kV; 35 ft for 500–750 kV; 45 ft for 750–1000 kV.

  • Operator has authority and duty to stop and refuse any lift that is unsafe or not in compliance.

  • Never operate a crane under the influence of alcohol, drugs, or medication that impairs judgment or reaction.

  • Inspections include shift, monthly, and annual/comprehensive; keep records and correct deficiencies before operation.

  • Only qualified riggers and signalpersons may perform those duties; verify qualifications before the lift.

  • Do not bypass, disable, or remove LMI/RCL, anti-two-block, or other safety devices.

  • Report accidents, near misses, damage, and malfunctions; remove crane from service until repaired and inspected.

NCCCO Mobile Crane key terms

Pre-shift inspection

A visual and functional check the operator performs before each shift, covering wire rope, hydraulic leaks, safety devices, controls, and the carrier, with deficiencies corrected before work begins.

Related: Wire rope inspection, Anti-two-block device
Wire rope inspection

Examination of hoist and boom ropes for broken wires, kinks, corrosion, birdcaging, and diameter loss, compared against the manufacturer's removal criteria before the rope is returned to service.

Related: Pre-shift inspection, Hook latch
Anti-two-block device

A sensing system that warns the operator, or stops hoist, boom-lower, and telescope-out motion, before the load block or ball contacts the boom tip.

Related: Two-blocking, Load moment indicator
Load moment indicator

An onboard computer that senses boom angle, boom length, and pressure to show rated capacity, actual load, and radius, warning the operator as capacity is approached.

Related: Rated capacity limiter, Anti-two-block device
Rated capacity limiter

A control device that automatically stops crane functions when the load or moment exceeds the rated capacity for the current boom and outrigger configuration.

Related: Load moment indicator, Load chart
Swing radius barricade

A physical barrier or marked boundary that keeps workers clear of the area swept by the rotating superstructure and counterweight.

Related: Pinch point, Swing brake
Pinch point

Any place where a person's body could be caught between moving crane parts, such as the counterweight and a wall or the boom and the cab.

Related: Swing radius barricade, Swing brake
Hook latch

A spring-loaded gate on the hook that closes the throat so slings, chains, and lines cannot slip off during a lift.

Related: Wire rope inspection, Pre-shift inspection
Outrigger pad

A rigid plate or cribbing placed under an outrigger float to spread the crane's load over a larger area and lower the pressure on the ground.

Related: Ground bearing pressure, Outrigger beam
Ground bearing pressure

The force per unit area that a crane's outrigger float or track imposes on the soil, mat, or slab beneath it, which must stay below the ground's capacity.

Related: Outrigger pad, Crane level
Crane level

The condition of the crane being set up within the manufacturer's tolerance for level, since an out-of-level crane loses capacity and may tip.

Related: Ground bearing pressure, Load chart
Boom length

The distance from the boom pivot to the boom tip with telescoping sections extended, used with boom angle to find capacity on the load chart.

Related: Boom angle, Load chart
Boom angle

The angle of the boom measured above horizontal, read from the boom angle indicator and used to determine working radius and rated capacity.

Related: Boom length, Load chart
Jib

An auxiliary boom section mounted at the main boom tip to add height and reach; it adds weight and reduces the crane's rated capacity.

Related: Deduction, Boom length
Counterweight

Removable weights mounted at the rear of the upper works that balance the load and improve stability; the amount must match the load chart being used.

Related: Load chart, Stability
Outrigger beam

The sliding structural member that extends the outrigger float outward from the carrier, widening the crane's support base for lifting.

Related: Outrigger pad, Ground bearing pressure
Two-blocking

Contact between the load block or ball and the boom tip, which can break wire rope, damage the boom, or drop the load.

Related: Anti-two-block device, Load moment indicator
Side loading

Pulling or dragging a load sideways so the boom is forced out of its designed lifting plane, which can bend the boom or tip the crane.

Related: Shock loading, Stability
Shock loading

A sudden application or release of force, such as snatching a load off the ground, that produces stresses much greater than the load's static weight.

Related: Side loading, Structural capacity
Tag line

A rope tied to the load and held by a worker on the ground to control swinging and rotation while the crane moves the load.

Related: Hand signals, Wind and sail area
Swing brake

A friction brake that holds or slows rotation of the upper works; it is not intended as a service brake for stopping a swinging load.

Related: Swing radius barricade, Pinch point
Wind and sail area

The force wind exerts on the boom and load, increased by large, light loads that act like sails, raising radius and side load.

Related: Side loading, Load chart
Parts of line

The number of rope falls running between the boom tip and the load block; more parts increase capacity and reduce hoist speed.

Related: Gross capacity, Net capacity
Gross capacity

The rated capacity read directly from the load chart for a given boom, radius, and configuration, before any deductions are made.

Related: Net capacity, Deduction
Net capacity

The usable lifting capacity left after the weight of the hook block, slings, and other below-the-tip attachments is subtracted from the gross capacity.

Related: Gross capacity, Deduction
Deduction

A weight subtracted from the load chart value for items such as the hook block, jib, auxiliary sheave, and rigging, as required by chart notes.

Related: Gross capacity, Net capacity, Jib
Load chart

The manufacturer's table or graph giving rated capacities for specific boom lengths, angles, radii, quadrants, and outrigger configurations.

Related: Working radius, Gross capacity, Area of operation
Working radius

The horizontal distance from the crane's center of rotation to the center of the load, including boom deflection, used to enter the load chart.

Related: Boom angle, Load chart
Area of operation

The zone around the crane, such as over the front, side, rear, or full 360 degrees, that determines which capacity column applies.

Related: Load chart, Structural capacity
Structural capacity

The lifting limit set by the strength of crane components such as the boom, pins, cylinders, and wire rope, as opposed to tipping.

Related: Stability, Load chart
Stability

The crane's resistance to overturning about its tipping axis; it usually controls capacity at long radius or over the side.

Related: Structural capacity, Counterweight
Hand signals

Standardized arm and hand movements from ASME B30.5 that a signalperson uses to direct the operator when voice communication is not used.

Related: Qualified signalperson, Emergency stop signal
Qualified signalperson

A person trained and evaluated to give crane signals, who knows the crane's motions, the applicable standard, and the hazards of the lift.

Related: Hand signals, Emergency stop signal
Emergency stop signal

A signal that anyone on the site may give at any time, requiring the operator to stop all crane motion immediately and hold position.

Related: Hand signals, Qualified signalperson
Power line minimum approach distance

The closest a crane, boom, or load may come to an energized line, set by OSHA according to line voltage unless the line is de-energized and grounded.

Related: OSHA 29 CFR 1926 Subpart CC, Critical lift
Critical lift

A lift that meets defined risk criteria, such as exceeding a set percentage of capacity, using multiple cranes, or lifting personnel, and needs a written plan.

Related: Operator's manual, Refusal of unsafe lift
Operator's manual

The manufacturer's document containing setup, inspection, operation, maintenance, and capacity information that the operator is required to follow.

Related: Load chart, ASME B30.5
ASME B30.5

The consensus standard for mobile and locomotive cranes that covers construction, marking, inspection, testing, and safe operation in the United States.

Related: OSHA 29 CFR 1926 Subpart CC, Operator's manual
OSHA 29 CFR 1926 Subpart CC

The federal construction rule for cranes and derricks, covering operator certification, inspections, signalpersons, power line safety, and ground conditions.

Related: ASME B30.5, Power line minimum approach distance
Refusal of unsafe lift

The operator's right and duty to stop or refuse a lift they believe is unsafe, even when pressured by a supervisor or customer.

Related: Critical lift, Operator's manual

NCCCO Mobile Crane study plan

8 weeks · About 7 hours per week

Week 1

Load Chart Use and Capacity Determination

  • Define gross capacity, net capacity, and maximum allowable load, and compute net capacity by deducting all lifting-gear weight from the chart value.

  • Locate the correct boom length and radius intersection on a manufacturer load chart for at least five different configurations.

  • Distinguish structural limits from stability limits and state which governs at short radius versus long radius.

  • Calculate working radius from measured boom angle and boom length using the cosine relationship, and verify against a tape measurement.

Your checkpoint

A worked problem set of 20 capacity problems with all arithmetic shown, scored at 85% or better.

Week 2

Load Chart Use and Capacity Determination & Crane Operation

  • Apply correct deductions (headache ball, load block, slings, jib, auxiliary sheave) to determine net capacity across 10 chart scenarios.

  • Determine when parts of line and rated line pull govern capacity instead of the boom table, and compute the effective limit.

  • Identify the chart notes and warnings that invalidate a capacity value, such as unlevel crane, outriggers not fully extended, side loading, and travel.

  • Sequence the pre-lift checks an operator completes before the first pick of a shift.

Your checkpoint

An 80% or higher score on a 30-question timed quiz covering load charts and pre-lift checks.

Week 3

Crane Operation

  • Set up and level a crane on outriggers, verifying float extension, pad contact, and that all tires are clear of the ground where required.

  • Calculate ground bearing pressure for a given outrigger load and select a mat size that keeps pressure under the soil capacity.

  • Manage radius by measuring at the load hook and accounting for boom deflection and load swing during the lift.

  • Sequence a lift plan covering hazard identification, rigging verification, signalperson briefing, and trial lift.

Your checkpoint

A written lift plan for a 5-ton pick at 40 ft radius, including hazard list, rigging selection, and signal plan.

Week 4

Crane Operation

  • Identify the conditions that require a critical lift plan and list the contents such a plan must contain.

  • Apply minimum approach distances to power lines for each voltage class and state the required actions following contact.

  • Describe safe practice for pick-and-carry, travel with a suspended load, and multi-crane lifts, including when each is prohibited.

  • Explain how wind, side loading, rapid swing, and boom flex affect stability and capacity.

Your checkpoint

A 40-question practice exam on Domain 3 completed at 80% or higher.

Week 5

Crane Setup and Configuration

  • Verify ground conditions, blocking, and levelness before any configuration change or assembly task begins.

  • Describe the assembly and disassembly sequence for boom sections, and state the duties of the assembly director and the pin and clip verification checks.

  • Confirm counterweight and jib installation checks and determine when a stowed or swing-away jib changes the load chart in use.

  • Position a crane on a sample site diagram, calculating clearances and confirming the planned area of operation.

Your checkpoint

A setup checklist of at least 25 items applied to a sample site description, with position and clearance calculations shown.

Week 6

Site and Equipment Inspection & Crane Setup and Configuration

  • Perform a documented pre-shift inspection covering fluids, tires, wire rope, hook and latch, limit switches, alarms, and outriggers.

  • Inspect wire rope samples and identify removal criteria including broken wires, kinks, crush damage, corrosion, and diameter reduction.

  • Separate daily, periodic, and annual inspection requirements and state the record-keeping obligation for each.

  • Confirm the load chart, operator manual, and capacity decals are present and match the crane's current configuration.

Your checkpoint

A completed mock inspection form on a scenario with 10 planted defects, with at least 9 of 10 correctly identified.

Week 7

Safety, Standards, and Operator Responsibilities & Communication and Hand Signals

  • List operator, signalperson, and rigger responsibilities under the applicable consensus standard and OSHA crane rules.

  • Demonstrate the 20 standard hand signals and the corresponding voice or radio commands, without reference.

  • Explain signalperson qualification requirements, when a signalperson is mandatory, and the operator's stop-work authority.

  • State the correct response when a signal is unclear, duplicated, or the load approaches a prohibited zone.

Your checkpoint

A recorded or instructor-witnessed demonstration of 20 hand signals plus a 20-question signals quiz scored at 90%.

Week 8

Load Chart Use and Capacity Determination & Crane Operation

  • Complete two full-length timed practice exams and break down the score by domain to rank remaining weak areas.

  • Re-drill every missed load chart item until accuracy on that item type reaches 95%.

  • Reproduce from memory a one-page reference sheet of capacity formulas, deduction rules, and approach distances.

  • Verify readiness on the two lowest-scoring domains with a focused 30-question set on each.

Your checkpoint

Two full-length practice exams at 85% or higher with no individual domain below 80%.

Milestones

Week 2: Net capacity calculated correctly on 8 of 10 chart scenarios, including all deductions and parts-of-line limits.

Week 4: Domain 3 practice exam passed at 80% or higher, and a complete written lift plan produced.

Week 6: Inspection defects identified at 90% or better, and boom assembly sequence described in correct order from memory.

Week 8: Two full-length exams at 85% or higher with every domain at 80% or above before scheduling the test.

NCCCO Mobile Crane exam day

Your checklist

Government-issued photo ID

Bring an unexpired photo ID whose name matches your registration exactly. Acceptable ID forms and any secondary ID requirement vary - confirm with the provider before test day.

Appointment confirmation and site directions

Have your confirmation (printed or on your phone) plus the site address, gate/entrance instructions, parking notes, and the examiner's contact number. Test sites are often industrial yards with limited signage.

Required personal protective equipment

Typical site PPE is a hard hat, safety glasses, work gloves, and safety-toe boots; many sites also require high-visibility clothing. Exact PPE requirements are site-specific - confirm with the provider and bring your own; loaner gear may not be available.

Work clothing appropriate for the site

Long pants and a shirt with sleeves are standard for crane operation; avoid loose clothing, dangling jewelry, and open-toe or slip-on footwear. Confirm any additional dress code with the provider.

Written confirmation of which endorsement you are testing

Know whether you are scheduled for the fixed cab, swing cab, or lattice boom practical (or more than one). Verify the schedule matches what you prepared for; a mismatch is best resolved before test day.

Pre-operational inspection knowledge

Be ready to perform and verbally describe a pre-operational inspection of the crane you will operate. Study the manufacturer's operator manual and inspection checklist for that crane type - the examiner will not prompt you through items.

Hand signal proficiency

Review standard crane hand signals; you may be required to respond to signals or demonstrate signaling during the practical. Confirm with the provider whether signaling is scored in your exam version.

Water, snacks, and weather protection

You may spend time outdoors or waiting between tasks. Bring water, sun or rain protection, and layers; avoid alcohol and any impairing medication in the days before.

Physical readiness and self-certification

Get a full night's sleep and arrive rested. Do not test if you are ill, injured, or impaired - discuss rescheduling options with the provider rather than testing.

Payment and paperwork status

Confirm your exam fee is paid and any registration paperwork is complete before you travel. Bring any forms the provider told you to bring; ask whether a retest can be scheduled at the same site if needed.

Plan the day

72 hours before

Reconfirm arrival time, site address, examiner contact, and exactly which crane type and endorsement your practical covers with the provider.

72 hours before

Walk through a full pre-operational inspection out loud, in order, using the relevant manufacturer's checklist - access, fluids, tires/tracks, wire rope, hooks and latches, rigging, load chart, controls, horns and alarms, housekeeping.

72 hours before

Review standard hand signals and your load chart fundamentals; plan a calm, smooth operating sequence rather than fast movements.

72 hours before

Lay out and pack PPE, work clothing, ID, and confirmation. Check the weather forecast for the test site and plan for heat, cold, or rain.

24 hours before

Confirm transportation and departure time with extra margin; confirm the gate or check-in procedure if the site is secured.

24 hours before

Do a final light review only - pre-op inspection order, hand signals, basic load chart use. Stop studying early and sleep.

24 hours before

No alcohol, no unfamiliar equipment, no late-night practice. Eat normally and hydrate.

Morning of

Eat a real meal, arrive early enough to park, check in, and use the restroom before your turn - aim well ahead of your scheduled time.

Morning of

Bring only what you need on the course; stow bags, silence your phone, and put on PPE before entering the test area.

During the test

Listen to the examiner's full briefing and ask clarifying questions about a task before you begin it, not in the middle of it.

During the test

Verbalize your pre-operational inspection findings, call out what you are doing, and use smooth, deliberate control inputs - smoothness scores better than speed.

During the test

If you lose track of the course, stop the crane safely and ask the examiner to repeat the instruction rather than guessing.

Rules to check

  • Present your photo ID at check-in. Your name must match your registration; if it does not, contact the provider before test day rather than at the site.

  • Only the candidate and the practical examiner belong in the cab or on the course. Spectators, supervisors, and coworkers may not coach, prompt, or signal you.

  • Silence and stow phones and other devices. Photography, video, or audio recording of the exam is generally prohibited - confirm the provider's policy in advance.

  • Follow every site safety rule and examiner instruction. Any unsafe act, horseplay, or refusal to follow direction can stop the test and may result in failure.

  • Ask the examiner how breaks, restroom access, and time between tasks are handled before you start, and get permission before leaving the test area.

  • Each task is scored against a defined list of errors with a maximum allowable and, typically, disqualifying errors that fail the task outright. The exact criteria and allowed error counts are provider-specific - confirm them with the provider.

  • If the test is interrupted by weather, equipment problems, or a site emergency, the examiner decides whether and how testing resumes. Do not attempt to continue on your own.

  • Practical results and any retest eligibility, waiting period, or fee are governed by the certifying body's policy - confirm the retest process with the provider before you leave the site.

NCCCO Mobile Crane FAQ

How many NCCCO Mobile Crane practice questions are available?

The practice set has 199 NCCCO Mobile Crane questions. Each one includes the choices, the correct answer, and an explanation, and the set is free to read with no signup.

How many NCCCO Mobile Crane flashcards are available?

The flashcard set has 32 NCCCO Mobile Crane cards. Each card shows the term and its definition.

Which topics does the NCCCO Mobile Crane study material cover?

The NCCCO Mobile Crane study material has 6 sections, including Site and Equipment Inspection, Crane Setup and Configuration, and Crane Operation.

What format facts does the catalog list for the NCCCO Mobile Crane exam?

The catalog lists these item types: multiple choice, computer-based written examination, separate hands-on practical examination, and separate written examinations by crane type/configuration (e.g., fixed cab, swing cab, lattice boom) for the NCCCO Mobile Crane exam.