PRINCE2 7 Foundation Practice Test

PRINCE2 Project Management Foundation (Version 7)

PRINCE2 7 Foundation overview

  • 200 practice questions
  • 32 flashcards
  • 6 study guide topics
  • 39 key terms

What you'll study

  • Projects and the PRINCE2 project context17%
  • PRINCE2 principles17%
  • People17%
  • PRINCE2 practices17%
  • PRINCE2 processes16%
  • Tailoring PRINCE2 to the project environment16%

The PRINCE2 Project Management Foundation (Version 7) is an entry-level project management certification offered by PeopleCert. It is built on a best-practice method that PeopleCert describes as trusted by over 2 million professionals worldwide, and it is intended to give candidates a strong foundation for a career in project management.

It suits people moving into project work - coordinators, team members, aspiring project managers - as well as experienced practitioners who want a shared, structured vocabulary for running projects. No prior certification is required to begin.

The syllabus follows the architecture of PRINCE2 7: the project context and why projects differ from business as usual; the principles that should not be tailored away; the people element, covering leadership, teams and communication; the practices, including business case, organising, plans, risk, quality, issues and progress; the processes, from starting up a project through to closing it; and tailoring, which is treated as mandatory rather than optional.

Preparation is usually self-directed: read the official guidance once for principles and people, again for the practices, then test yourself on roles, management products and process activities rather than memorising prose. Practice questions build the habit of choosing the best answer among several plausible ones. Independent question banks like ours supplement, and never replace, the official material. Confirm fee, question count, time limit and pass mark with PeopleCert before booking.

This page is an independent study resource. It is not affiliated with, endorsed by, or sponsored by PeopleCert.

Common mistakes

Answers questions about what a project delivers by swapping 'output', 'outcome' and 'benefit' interchangeably - for example calling a new booking system a benefit and the resulting increase in sales an output.

Everyday project language uses the three words loosely, but PRINCE2 draws a hard line between them because the business case, the benefits management approach and the Senior User's accountability all depend on that line.

What to do instead

Memorise the chain as a sentence you can write from memory: the project creates an output (the product), which enables an outcome (the new operational state), which delivers a benefit (the measurable value). Practise on a project you know: name one output, one outcome and one benefit, then check which of the three the project team actually builds.

Recites the seven principles from memory but treats them as optional good practice, choosing answer options in which a principle is quietly dropped to suit a small or agile project.

The practices and processes are explicitly tailorable, so candidates over-extend the idea of flexibility to the principles as well - the one part of PRINCE2 that cannot be tailored out.

What to do instead

Fix the rule in mind: principles are universal and self-validating, and only the way they are applied is tailored. For each principle, write one sentence describing what evidence would show it is being applied, and use that sentence to eliminate options that contradict it.

Selects answers in which the Project Board reviews day-to-day work, or in which the Project Manager escalates every issue upwards, instead of applying the principle of manage by exception.

Candidates read 'the board is accountable for the project' as 'the board is involved in the project', blurring accountability with operational decision-making.

What to do instead

Hold the tolerance loop in mind: the board sets tolerances, the Project Manager works within them, and escalation happens only when a tolerance is forecast to be exceeded, via an Exception Report. For any 'who decides X' question, ask first whether X falls inside the Project Manager's delegated tolerance.

Skims the People material and answers stakeholder questions using process logic - for example stating that stakeholders are engaged once during Starting up a Project, or that engaging them is the Project Board's job.

People reads like general management common sense, so it gets the least revision time, yet the exam phrases these questions in PRINCE2-specific terms about who engages stakeholders, when, and which management product records how it will be done.

What to do instead

Treat People as examinable content: learn that stakeholder identification and engagement continues throughout the project, that the Project Manager is responsible for it, and that it is planned and recorded in a management product rather than left informal. Answer in PRINCE2's wording, not intuitive HR wording.

Confuses management products with near-identical names - using an End Stage Report where an End Project Report is required, a Lessons Log where a Lessons Report is required, or a Project Brief where the project initiation documentation is required.

The products come in families with almost the same names, and candidates learn them as a list of titles rather than by purpose, timing and audience.

What to do instead

Build a three-column table for each product: purpose, the process in which it is created or updated, and who approves or receives it. Study the classic pairs side by side (End Stage vs End Project Report, Lessons Log vs Lessons Report, Project Brief vs project initiation documentation) so the difference is explicit rather than assumed.

Treats quality assurance, quality control and project assurance as the same thing, so questions about quality planning are answered by naming the wrong role or the wrong activity.

All three terms sit in the same vocabulary, and PRINCE2 separates reviewing whether the project's quality methods are sound from checking whether a specific product meets its quality criteria.

What to do instead

Anchor each term to the question it answers: quality control asks 'does this product meet its quality criteria, and who takes part in the review?'; quality assurance asks 'are the project's quality methods sound and being followed?'; project assurance asks 'is the project being run properly from this stakeholder's point of view?'. Learn which role performs each and where each appears in the quality management approach.

Answers plan questions from activity lists rather than from products - for example scheduling tasks first and adding product descriptions later, or muddling which plan level the Project Board actually approves.

Most candidates come from activity-based planning tools, whereas PRINCE2 planning is product-based, and the plan hierarchy with its different approvers is easy to skim because the terms feel familiar.

What to do instead

Practise building a small plan in PRINCE2 order every time: product breakdown structure, then product descriptions, then product flow diagram, then activities, dependencies, resources and estimates, then the schedule. Separately learn the plan levels (project, stage, team) and which management level approves each one.

Places familiar activities in the wrong process - for example putting the appointment of the Project Board or the creation of the daily log into Initiating a Project, or treating Managing a Stage Boundary and Closing a Project as interchangeable.

The processes overlap in content (both boundary processes produce reports and update the business case), and candidates learn the process names as a sequence without learning each process's trigger and purpose.

What to do instead

For every process, learn the trigger, the purpose and the outputs unique to it before memorising its activities. Concentrate on the boundaries: Starting up a Project runs from the mandate to the request to initiate; Managing a Stage Boundary is used only at a stage end or when an exception plan is needed; Closing a Project confirms product acceptance and the arrangements for benefits.

Mixes up the decision points, choosing 'authorise the project' when the question concerns approving the Project Brief, or 'authorise a stage' when the question concerns closing the project.

All five decision points sound like generic board approval, and their names differ by only a word or two, so candidates answer from the gist of the option rather than from the specific authorisation.

What to do instead

Learn the decision points as a numbered set, each paired with what it authorises: DP1 authorise initiation, DP2 authorise the project, DP3 authorise a stage or exception plan, DP4 give ad hoc direction, DP5 authorise project closure. Recite the pairs until the mapping is automatic.

Reads tailoring as 'cut what you don't need', so answers strip out principles, roles or management products to fit a small project, or choose an option where tailoring is left implicit and unrecorded.

Tailoring is often the last area revised and is easily reduced to a slogan about scaling, which invites the intuition that PRINCE2 is simplified by removing elements.

What to do instead

Learn tailoring as adapting how the practices, processes and products are applied to the project's environment while every principle remains satisfied; nothing is dropped without justification. Where two options look workable, prefer the one in which the tailoring decision is explicitly recorded, for example in the project initiation documentation.

Exam requirements can change. Confirm current details with the exam provider.

PRINCE2 7 Foundation practice

200 questions. Each one lists the choices, the correct answer, and an explanation. With JavaScript, this list opens one question at a time. The checker at the top of this page saves progress in this browser when it is available.

  1. Question 1Projects and the PRINCE2 project context

    According to PRINCE2, which statement best defines a project?

    1. A recurring set of activities carried out to achieve routine operational targets
    2. An ongoing management structure that coordinates the organization's strategic investments
    3. A temporary organization created to deliver business products against an agreed business case Correct answer.
    4. A permanent team of people that maintains the organization's existing services and operational products

    Explanation

    PRINCE2 defines a project as a temporary organization created for the purpose of delivering one or more business products according to an agreed business case. The definition combines the temporary nature of the organization with the need for justification.

  2. Question 2Projects and the PRINCE2 project context

    Which of the following is one of the characteristics that PRINCE2 uses to describe a project?

    1. It is governed by a permanent portfolio office
    2. It is repeated on a regular operational cycle
    3. It is funded from a single departmental budget
    4. It is unique and introduces change Correct answer.

    Explanation

    PRINCE2 characterizes projects as temporary, cross-functional, unique, involving uncertainty and introducing change. Uniqueness and the introduction of change are therefore defining features of every project.

  3. Question 3Projects and the PRINCE2 project context

    Which statement describes business as usual rather than a project?

    1. Work is temporary and the team is disbanded once the objectives are achieved
    2. Work is ongoing and repetitive, maintaining existing products and services Correct answer.
    3. Work is cross-functional and brings together a temporary team of specialists
    4. Work introduces a defined change with a clear start and an end date

    Explanation

    Business as usual is the ongoing, repetitive activity that maintains existing products and services. Projects are the temporary, cross-functional means by which change is introduced.

  4. Question 4Projects and the PRINCE2 project context

    Which statement best describes a programme?

    1. The total investment an organization makes in all of its change initiatives
    2. The routine operational activity that keeps the organization running day to day
    3. A temporary organization coordinating related projects to deliver outcomes Correct answer.
    4. A single large project that has an extended duration and a much larger budget than most

    Explanation

    A programme is a temporary, flexible organization created to coordinate, direct and oversee related projects and activities so that outcomes and benefits are delivered. The individual projects within it deliver the outputs.

  5. Question 5Projects and the PRINCE2 project context

    What does the term 'portfolio' mean in PRINCE2?

    1. A single project that has been assessed as high risk and needs board oversight
    2. The collection of documents produced during the initiation of a single project
    3. The complete set of an organization's investments in change, including programmes Correct answer.
    4. A group of related projects that are managed together to deliver strategic benefits

    Explanation

    A portfolio is the totality of an organization's investment in the changes needed to meet its strategic objectives, and it includes programmes, projects and other change activity. It provides the top-level context in which change initiatives are selected and prioritised.

  6. Question 6Projects and the PRINCE2 project context

    PRINCE2 defines project management as the planning, delegating, monitoring and control of all aspects of the project, and the motivation of those involved, in order to...

    1. achieve the project objectives within expected performance targets Correct answer.
    2. remove all uncertainty from the project's delivery approach
    3. satisfy the personal objectives of the project board members
    4. deliver every one of the project's products ahead of the agreed schedule

    Explanation

    The PRINCE2 definition focuses on achieving the project objectives within expected performance targets for time, cost, quality, scope, benefits and risk. Uncertainty can be managed but never eliminated.

  7. Question 7Projects and the PRINCE2 project context

    Why does PRINCE2 need to be tailored to each project's context?

    1. Because each project must be run with a different set of principles
    2. Because the method is only suitable for small and low-risk projects
    3. Because tailoring removes the need for a project business case
    4. Because projects vary in size, complexity, risk and environment Correct answer.

    Explanation

    PRINCE2 is designed to be tailored so that the method and its documentation are proportionate to the project's size, complexity, risk, importance and organizational environment. The principles themselves are never tailored away.

  8. Question 8Projects and the PRINCE2 project context

    Which term describes the result of change that normally affects real-world behaviour and circumstances?

    1. An outcome Correct answer.
    2. A product description
    3. An output
    4. A benefit

    Explanation

    PRINCE2 distinguishes outputs (the products created), outcomes (the result of using the outputs, which affects behaviour and circumstances) and benefits (measurable improvements from an outcome perceived as advantageous).

  9. Question 9Projects and the PRINCE2 project context

    A project is described as 'cross-functional'. What does this mean in practice?

    1. It is managed by a single department using its own standard processes
    2. It draws together people with different skills from across the organization Correct answer.
    3. It requires every department in the organization to contribute funding
    4. It must be delivered by an external supplier rather than internal staff

    Explanation

    Projects are cross-functional because they bring together people from different parts of the organization, and often from outside it, to supply the skills needed to deliver the products. This is one reason projects need clearly defined roles and coordination.

  10. Question 10Projects and the PRINCE2 project context

    Why do projects typically involve more uncertainty than business as usual?

    1. Because project teams are not allowed to use established standards
    2. Because projects do not require an agreed business case
    3. Because each project is unique, so past experience is only a partial guide Correct answer.
    4. Because projects never have a defined end date or a fixed and stable scope of work

    Explanation

    Uniqueness means each project faces a combination of factors that has not been encountered in exactly the same form before, so previous experience reduces uncertainty but does not remove it. This is why risk management is central to projects.

  11. Question 11Projects and the PRINCE2 project context

    How do projects relate to an organization's strategy?

    1. Projects are limited to delivering cost savings within the finance function
    2. Projects replace the need for strategic planning in an organization
    3. Projects are used only when operational performance is already satisfactory
    4. Projects are the means by which change needed to deliver strategy is introduced Correct answer.

    Explanation

    Projects are the mechanism an organization uses to introduce the change required to achieve its strategic objectives. They turn strategy into delivered products and, ultimately, into business change.

  12. Question 12Projects and the PRINCE2 project context

    A project forms part of a programme. What is the main implication for that project?

    1. It can ignore corporate standards because the programme sets its own
    2. It no longer needs its own business case or project board
    3. It must deliver all of the programme's benefits on its own
    4. It must align with the programme's objectives and report into its governance Correct answer.

    Explanation

    A project within a programme must be consistent with the programme's objectives and operate within the programme's governance arrangements, while still retaining its own management structures such as a project board.

  13. Question 13Projects and the PRINCE2 project context

    An organization runs a project that is not part of any programme. What is the correct PRINCE2 view?

    1. The project automatically becomes a portfolio-level initiative
    2. The project still sits within a corporate context of standards and strategy Correct answer.
    3. The project must first establish a programme before it can start
    4. The project does not need a project board because there is no programme above it

    Explanation

    A standalone project is still commissioned and governed within a corporate context that sets strategy, standards and constraints. The absence of a programme changes the reporting line, not the need for governance.

  14. Question 14Projects and the PRINCE2 project context

    Why must a project have an agreed business case?

    1. To justify the investment and provide the basis for continued justification Correct answer.
    2. To describe the technical method used to build the outputs
    3. To list the individuals who will be working on the project team
    4. To record the detailed design of each of the project's products

    Explanation

    The project definition requires delivery of products according to an agreed business case. The business case justifies the investment and is reviewed throughout the project so that work continues only while it remains viable.

  15. Question 15Projects and the PRINCE2 project context

    In PRINCE2, what is meant by a project's 'delivery approach'?

    1. The specialist methods and techniques used to create the project's products Correct answer.
    2. The PRINCE2 processes used to manage the project
    3. The governance arrangements set by the project board
    4. The schedule of management stage boundaries

    Explanation

    PRINCE2 distinguishes project management, which directs and controls the project, from the delivery approach, which is the specialist way the products are created, such as an engineering or agile delivery method.

  16. Question 16Projects and the PRINCE2 project context

    What typically happens to a project's outputs once the project has closed?

    1. They are transferred to the programme board for ongoing maintenance
    2. They remain under the project manager's control indefinitely
    3. They are handed over and used within business as usual Correct answer.
    4. They are archived and never used again by the organization

    Explanation

    A project delivers products that will be used to create change, so outputs are handed over to the appropriate operational area and used in business as usual after closure. Benefits are then realized in that operational environment.

  17. Question 17Projects and the PRINCE2 project context

    An organization creates a temporary structure to oversee five related projects that together will transform how it serves its customers. What is this structure?

    1. A portfolio
    2. A project board
    3. A project assurance team
    4. A programme Correct answer.

    Explanation

    A temporary structure that coordinates a group of related projects to deliver outcomes of strategic importance is a programme. The individual projects deliver the outputs that together enable those outcomes.

  18. Question 18Projects and the PRINCE2 project context

    Which statement best explains why projects are described as 'temporary'?

    1. They end whenever the project manager decides to leave the organization
    2. They have a defined start and end, after which the team is disbanded Correct answer.
    3. They are funded only while an external supplier contract remains in place
    4. They last for a fixed period of exactly one year

    Explanation

    Temporary means the project has a defined start and a defined end, reached when its objectives are met or the project is terminated early. The temporary organization is then disbanded.

  19. Question 19Projects and the PRINCE2 project context

    In PRINCE2, which level of management sits above the project board in a project's context?

    1. Project support
    2. The team manager
    3. Corporate or programme management Correct answer.
    4. Project assurance

    Explanation

    Corporate or programme management commissions the project, issues the project mandate and sets the constraints within which the project board directs the project. The other roles operate at or below board level.

  20. Question 20Projects and the PRINCE2 project context

    In PRINCE2, what is a 'benefit'?

    1. Any product or service that the project delivers to the customer organization
    2. The total cost of all the resources used by the project throughout its life
    3. A risk or opportunity that has a positive impact on the project's objectives
    4. A measurable improvement from an outcome that is perceived as advantageous Correct answer.

    Explanation

    Benefits are the measurable improvements that result from an outcome and that a stakeholder perceives as advantageous. They are distinct from both outputs and outcomes.

  21. Question 21Projects and the PRINCE2 project context

    Which statement correctly distinguishes a portfolio from a programme?

    1. A portfolio covers all change investment, while a programme coordinates related projects Correct answer.
    2. A portfolio is a group of related projects, while a programme is the complete investment in change
    3. A portfolio is temporary, while a programme is permanent
    4. A portfolio delivers benefits directly, while a programme only produces outputs

    Explanation

    A portfolio is the whole of an organization's investment in change and provides the context for selecting and prioritising initiatives; a programme is a temporary organization coordinating a set of related projects and activities to deliver outcomes.

  22. Question 22Projects and the PRINCE2 project context

    Which statement correctly describes the relationship between project management and the delivery approach?

    1. They describe the same set of activities in different parts of the method
    2. Project management controls the work; the delivery approach provides specialist methods to create products Correct answer.
    3. The delivery approach is used only where no project board exists
    4. Project management creates the products; the delivery approach controls the project's stages

    Explanation

    PRINCE2 covers project management, which directs, controls and assures the work. The delivery approach is separate and consists of the specialist practices used to create the products, which PRINCE2 does not prescribe.

  23. Question 23Projects and the PRINCE2 project context

    Why is change usually managed through a project rather than within ongoing operations?

    1. Projects allow change to happen without affecting business as usual
    2. Projects provide a temporary, focused structure with clear accountability for the change Correct answer.
    3. Projects guarantee that the intended benefits will be realized
    4. Projects remove the need to involve senior management in any decisions

    Explanation

    A project creates a temporary organization with defined roles, a business case and stage boundaries, giving focus and accountability for delivering change that everyday operations cannot provide. Operations are still affected, and benefits must still be realized afterwards.

  24. Question 24Projects and the PRINCE2 project context

    Which statement about the realization of benefits is correct?

    1. Benefits can only be measured by the project manager
    2. Benefits are realized only during the project's final management stage
    3. Benefits are exactly the same thing as the project's outputs
    4. Benefits are usually realized after the project closes, within business as usual Correct answer.

    Explanation

    Because benefits arise from using the outputs, they typically emerge after handover, once the products are in operational use. The business case identifies the expected benefits and how they will be measured.

  25. Question 25Projects and the PRINCE2 project context

    A government department must apply national procurement rules to all of its projects. How does this affect its use of PRINCE2?

    1. The rules form part of the project context, and PRINCE2 is tailored to accommodate them Correct answer.
    2. The rules are irrelevant because PRINCE2 has its own procurement process
    3. The rules apply only to programmes and never to individual projects
    4. The rules override PRINCE2, so the method cannot be used on these projects

    Explanation

    Organizational, legal and regulatory constraints are part of the context in which a project operates. Tailoring PRINCE2 to work within those constraints keeps the method appropriate while ensuring compliance.

  26. Question 26Projects and the PRINCE2 project context

    In PRINCE2, which term describes any individual, group or organization that can affect, be affected by, or perceive itself to be affected by the project?

    1. User
    2. Supplier
    3. Stakeholder Correct answer.
    4. Executive

    Explanation

    PRINCE2 uses 'stakeholder' broadly to cover anyone with an interest in, or influence over, the project, whether internal or external. The term is deliberately wider than supplier, user or executive, each of which describes a specific role or interest.

  27. Question 27Projects and the PRINCE2 project context

    What is meant by 'business as usual' in the context of projects?

    1. The ongoing operational activities that maintain the organization's current services Correct answer.
    2. The set of all projects and programmes within a portfolio
    3. The final stage in which project outputs are handed over
    4. The work carried out by the project board to direct the project

    Explanation

    Business as usual refers to the permanent, ongoing operations that keep an organization running, as distinct from the temporary effort of a project. Projects are used to introduce change into business as usual.

  28. Question 28Projects and the PRINCE2 project context

    PRINCE2 identifies three stakeholder interests that must be represented in the project organization. Which set of interests is correct?

    1. Executive, project manager and team manager
    2. Customer, sponsor and delivery team
    3. Business, user and supplier Correct answer.
    4. Internal, external and regulatory

    Explanation

    PRINCE2 names the business, user and supplier interests, which respectively reflect the case for the project, the needs of those who will use its outputs, and the practical ability to deliver. Project board roles are designed so that these three interests are represented.

  29. Question 29Projects and the PRINCE2 project context

    In PRINCE2, what distinguishes the customer from the supplier in a project?

    1. The customer specifies the desired result and the supplier provides resources to deliver it. Correct answer.
    2. The customer provides the specialist resources and the supplier accepts the deliverables.
    3. The customer is always external to the organization and the supplier is always internal.
    4. The customer directs the project board and the supplier manages the project day to day.

    Explanation

    PRINCE2 treats the customer as the party that specifies what is wanted and may provide funding, while the supplier provides the resources and expertise needed to deliver it. In a commercial context these may be separate organizations.

  30. Question 30Projects and the PRINCE2 project context

    PRINCE2 describes projects as 'unique'. What does this mean?

    1. Every project must use a different delivery approach from previous projects.
    2. Every project must deliver a product that has never been created anywhere before.
    3. Each project has a distinct combination of inputs, constraints and outcomes. Correct answer.
    4. Each project must be managed by a different project manager.

    Explanation

    Uniqueness means that no two projects are identical: each has its own set of objectives, constraints, stakeholders and outcomes. This is why PRINCE2 must be tailored rather than applied identically to every project.

  31. Question 31Projects and the PRINCE2 project context

    In PRINCE2, what is a 'dis-benefit'?

    1. A negative consequence of the project for one or more stakeholders Correct answer.
    2. A benefit that is realized later than originally planned
    3. A risk that has materialized and reduced an expected benefit
    4. A cost that was not included in the approved project budget

    Explanation

    A dis-benefit is an outcome that stakeholders perceive as negative, such as disruption or loss of a service during transition. It is recorded alongside benefits so that the overall balance of advantage can be assessed in the business case.

  32. Question 32Projects and the PRINCE2 project context

    An organization wants to prioritize and balance investment across all of its projects, programmes and other change activity. Which level of management is responsible?

    1. Portfolio management, because it balances all change initiatives against strategic objectives Correct answer.
    2. Programme management, because it coordinates related projects and business change
    3. Business as usual management, because it maintains existing services
    4. Project management, because it coordinates the delivery of each individual project

    Explanation

    Portfolio management takes a whole-organization view, selecting and balancing projects, programmes and other work so that limited resources support strategic objectives. Programme management coordinates related projects, but only portfolio management covers the full set of change initiatives.

  33. Question 33Projects and the PRINCE2 project context

    Which statement correctly distinguishes the host organization from the project organization?

    1. The host organization is always the supplier; the project organization is always the customer.
    2. The host organization provides the permanent setting; the project organization is temporary. Correct answer.
    3. The host organization owns the project's products; the project organization owns the organization's strategy.
    4. The host organization is temporary; the project organization is permanent.

    Explanation

    The host organization is the permanent organization within which the project operates and which will own and use the results. The project organization is created for the life of the project and is disbanded at closure.

  34. Question 34Projects and the PRINCE2 project context

    Why should a project's business case be reviewed at each stage boundary?

    1. To confirm the project remains viable as costs, risks, benefits and context change Correct answer.
    2. To recalculate the project's budget and schedule at every stage boundary
    3. To replace the business case with a new one written by the project manager
    4. To confirm that all planned outputs have already been delivered

    Explanation

    The business case is a living document because the assumptions behind it can change as the project progresses. Reviewing it at stage boundaries allows the project board to confirm continued viability and, if necessary, to stop or redirect the project.

  35. Question 35PRINCE2 principles

    PRINCE2 7 describes a set of principles. How many principles does it define?

    1. Seven Correct answer.
    2. Four
    3. Six
    4. Five

    Explanation

    PRINCE2 7 defines seven principles: continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products and tailor to suit the project environment.

  36. Question 36PRINCE2 principles

    Which PRINCE2 principle allows work to be delegated within agreed limits so that decisions are escalated only when those limits are threatened?

    1. Focus on products
    2. Manage by exception Correct answer.
    3. Manage by stages
    4. Learn from experience

    Explanation

    Manage by exception gives people authority to act within defined tolerances and requires escalation as soon as a forecast breach becomes apparent, so senior management is involved at the right level without micromanaging.

  37. Question 37PRINCE2 principles

    What does the continued business justification principle require of a project?

    1. A justifiable reason to start that is documented and re-confirmed Correct answer.
    2. A business case written once during initiation and then filed for audit
    3. A sponsor who personally funds the project from their own private budget
    4. A guaranteed financial return approved before the project is authorized

    Explanation

    The principle requires a justifiable reason for the project to exist, and that reason must be documented, maintained and reviewed so that the project is stopped or changed if the justification is lost.

  38. Question 38PRINCE2 principles

    What does the learn from experience principle require a project to do with lessons?

    1. Limit lesson reviews to the project board to avoid distracting the team
    2. Store lessons in the issue register until the project closes
    3. Seek, record and act on lessons, and share them with others Correct answer.
    4. Gather lessons only from its own stages, not from other projects

    Explanation

    Lessons must be actively sought from previous work and from the project itself, recorded, acted upon and passed on so that others benefit from them.

  39. Question 39PRINCE2 principles

    Which principle requires that the interests of the business, the user and the supplier are each represented and that accountabilities are clear?

    1. Focus on products
    2. Defined roles and responsibilities Correct answer.
    3. Manage by exception
    4. Tailor to suit the project environment

    Explanation

    Defined roles and responsibilities establishes a project organization in which the business, user and supplier interests are represented and each person's accountability is understood.

  40. Question 40PRINCE2 principles

    What does the focus on products principle require to happen before activities are planned?

    1. That the project board has met at least once
    2. That the products required are defined and agreed Correct answer.
    3. That the budget is fully committed
    4. That all team members are recruited

    Explanation

    Focus on products means the project defines and agrees what it will deliver, including quality expectations, before deciding which activities are needed to produce it.

  41. Question 41PRINCE2 principles

    Which principle states that PRINCE2 should be adapted to the size, complexity, importance, capability and risk of the project?

    1. Learn from experience
    2. Tailor to suit the project environment Correct answer.
    3. Manage by stages
    4. Defined roles, responsibilities and organization

    Explanation

    Tailoring makes the method proportionate: the principles always apply, but the processes, themes and management products are adapted to the project's context.

  42. Question 42PRINCE2 principles

    How should the PRINCE2 principles be applied on a project?

    1. Only the principles relevant to the project's sector need be applied
    2. They apply only to the directing a project and managing product delivery processes
    3. All seven must be applied, although how they are implemented can be tailored Correct answer.
    4. At least four of the seven must be applied, chosen during initiation

    Explanation

    All seven principles must be applied for a project to be managed in accordance with PRINCE2; tailoring affects how they are applied, not whether they are applied.

  43. Question 43PRINCE2 principles

    A project board wants to authorize work in controlled increments and review the project at defined points rather than approving everything at the outset. Which principle supports this?

    1. Manage by exception
    2. Focus on products
    3. Manage by stages Correct answer.
    4. Continued business justification

    Explanation

    Manage by stages divides the project into management stages so the board authorizes one stage at a time, reviewing progress at each boundary before committing further resources.

  44. Question 44PRINCE2 principles

    At the end of stage two, forecasts show the expected benefits have fallen sharply, although the project is within its cost and time tolerances. What should happen under the PRINCE2 principles?

    1. The project should continue as planned because it remains within its agreed cost and time tolerances
    2. The business case should be reassessed and the project stopped or changed if it is invalid Correct answer.
    3. The decision should be delegated to the team manager who is currently delivering the stage
    4. The business case should be updated only when the project reaches its closure

    Explanation

    Continued business justification requires the business case to be reviewed as the project progresses; if the justification is lost, the project must be stopped or changed even when cost and time are on track.

  45. Question 45PRINCE2 principles

    At the start of a project, the project manager reviews lessons from similar projects. At each stage boundary the team checks whether those lessons have been applied. Which principle does this illustrate?

    1. Defined roles and responsibilities
    2. Manage by stages
    3. Learn from experience Correct answer.
    4. Focus on products

    Explanation

    Learn from experience requires lessons to be sought at the start, applied during the work and reviewed as the project progresses, rather than gathered only at the end.

  46. Question 46PRINCE2 principles

    A team manager is delivering a work package with agreed tolerances. Midway through, a forecast shows the work will exceed its cost tolerance. What should the team manager do?

    1. Escalate the forecast exception to the project manager promptly Correct answer.
    2. Continue and report the overspend in the end stage report
    3. Amend the business case to absorb the additional cost
    4. Wait until the next highlight report is due before taking any action

    Explanation

    Manage by exception requires escalation as soon as a forecast breach of tolerance is apparent, so that the level above can decide how to respond while there is still time to act.

  47. Question 47PRINCE2 principles

    A project is being organized so that those who fund the project, those who will use its products and those who will supply them are all represented on the project board. Which principle is being applied?

    1. Focus on products
    2. Defined roles and responsibilities Correct answer.
    3. Continued business justification of the project
    4. Manage by stages

    Explanation

    Defined roles and responsibilities requires a structure in which the business, user and supplier interests are each represented and accountabilities are agreed.

  48. Question 48PRINCE2 principles

    A small, low-risk project is being run using PRINCE2. The project manager proposes a simplified business case, combined roles and a single management stage. Which principle does this demonstrate?

    1. Manage by exception
    2. Continued business justification of the project
    3. Tailor to suit the project environment Correct answer.
    4. Manage by stages

    Explanation

    Tailoring adapts the method's processes, themes and products to the project's size, risk and complexity while keeping all seven principles in place.

  49. Question 49PRINCE2 principles

    How does the manage by stages principle affect the level of detail in project plans?

    1. Detailed planning is left entirely to the team managers for all stages
    2. Only the final stage is planned in detail, once all of the products have been completed and accepted
    3. Every stage is planned in the same level of detail before the project is authorized to proceed
    4. The next stage is planned in detail, later ones only at a high level until their turn Correct answer.

    Explanation

    Manage by stages allows detailed planning to be limited to the next stage, with later stages planned at a higher level until more information is available, which supports progressive refinement.

  50. Question 50PRINCE2 principles

    A team keeps arguing about whether a deliverable is finished. Applying the focus on products principle, what should be agreed and documented?

    1. The budget and timescale allocated to the deliverable
    2. The name of the person who will sign off the end stage report
    3. The purpose and quality criteria of the product Correct answer.
    4. The number of activities needed to produce the deliverable

    Explanation

    Focus on products requires each product to be defined in terms of its purpose, composition and quality criteria, so that acceptance is judged objectively rather than debated.

  51. Question 51PRINCE2 principles

    When should the learn from experience principle be applied?

    1. Continuously, throughout all processes and stage boundaries Correct answer.
    2. During starting up a project, before any other work begins
    3. Whenever the project board asks for a formal lessons review
    4. At the end of each stage and at project closure

    Explanation

    Learning is not a one-off activity: lessons are sought, recorded and acted upon continuously as the project progresses, as well as being reviewed at stage boundaries and at closure.

  52. Question 52PRINCE2 principles

    Under the continued business justification principle, who is accountable for the business case throughout the project?

    1. The team manager
    2. The executive Correct answer.
    3. The senior user
    4. The project manager

    Explanation

    The executive is accountable for the business case, ensuring it is developed, maintained and reviewed so that the project remains justified throughout.

  53. Question 53PRINCE2 principles

    Which action best illustrates the tailor to suit the project environment principle?

    1. Removing the project board because the project manager is very experienced
    2. Applying every PRINCE2 product and process exactly as described, whatever the project's size
    3. Dropping the business case because a single department is sponsoring the project
    4. Combining PRINCE2 with the organization's existing governance processes where they add value Correct answer.

    Explanation

    Tailoring adapts PRINCE2 to the organization's environment and to the project's characteristics, and may include integrating existing governance provided the principles remain applied.

  54. Question 54PRINCE2 principles

    Which factor most influences how many management stages a project should have?

    1. The size, complexity, risk and duration of the project Correct answer.
    2. The number of changes raised during the previous stage
    3. The number of products listed in the product breakdown structure
    4. The number of team members available to the project

    Explanation

    The number and length of management stages are set during initiation to reflect the project's scale, risk and complexity, so that each stage is a manageable unit of control.

  55. Question 55PRINCE2 principles

    Why does manage by exception require tolerances to be set at each level of the project organization?

    1. So the project manager can approve changes that exceed the project board's tolerance
    2. So each level knows what it may decide without escalating Correct answer.
    3. So tolerances can be renegotiated whenever a stage is running late
    4. So team managers can report directly to corporate management

    Explanation

    Tolerances define the delegated authority at each level, making it clear when a decision can be taken locally and when a forecast breach must be escalated as an exception.

  56. Question 56PRINCE2 principles

    Why is it important, under defined roles and responsibilities, that the business, user and supplier interests are all represented in the project organization?

    1. It balances the views of those who fund, use and build the products Correct answer.
    2. It guarantees that the supplier carries the financial risk of the whole project
    3. It removes the need for a project manager on smaller projects
    4. It ensures that every decision is taken by majority vote

    Explanation

    Representing all three interests ensures the project is not driven by a single perspective and that accountabilities for funding, using and supplying are clear.

  57. Question 57PRINCE2 principles

    A project manager says that focusing on products matters only at the end of a stage, when deliverables are handed over. What is wrong with this view?

    1. Product descriptions are required only for physical goods, not for services
    2. Handover is not part of the method, so products are never formally accepted
    3. Products need only be defined by the supplier, not agreed with the users
    4. Product definitions drive planning, estimating and control throughout Correct answer.

    Explanation

    Products are defined early so that they can be planned, estimated, resourced and controlled; acceptance at handover is only the final use of a product definition that has guided the work throughout.

  58. Question 58PRINCE2 principles

    Which statement best describes the relationship between the PRINCE2 principles?

    1. They reinforce one another, for example stages provide points to re-confirm justification Correct answer.
    2. They conflict in some situations, so the project board decides which principle takes precedence in each case
    3. They are independent of one another and may be applied in isolation
    4. They are ranked in order of importance, with continued business justification first

    Explanation

    The principles are complementary rather than a checklist of separate items; for example, management stages create the boundaries at which business justification is reviewed and lessons are shared.

  59. Question 59PRINCE2 principles

    A portfolio office requires every project to produce an identical set of management products and hold identical board meetings regardless of size. Why does this conflict with tailoring?

    1. Because a uniform approach ignores differences in size, complexity and risk Correct answer.
    2. Because tailoring applies only to products, not to the governance arrangements of the wider organization
    3. Because management products may be defined only by the project manager
    4. Because organizations are not permitted to set portfolio-level standards

    Explanation

    Tailoring requires the method to be proportionate to the project's characteristics; identical products and meetings for every project can create unnecessary overhead on small work or leave gaps on complex work.

  60. Question 60PRINCE2 principles

    Which of these is one of the seven PRINCE2 principles?

    1. Manage by exception Correct answer.
    2. Manage by delegation
    3. Manage by objectives
    4. Manage by consensus

    Explanation

    The seven principles are continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products and tailor to suit the project environment. A project must apply all seven to be a PRINCE2 project, so none of them is optional.

  61. Question 61PRINCE2 principles

    What must a project have in order to satisfy the continued business justification principle?

    1. A fixed-price contract with the delivery supplier, agreed before work starts
    2. A programme board that oversees the work of the project board
    3. A minimum of three management stages so progress is reviewed often
    4. A business case that is reviewed and updated as the project proceeds Correct answer.

    Explanation

    The principle requires a justifiable reason for the investment, recorded in a business case. The business case is not approved once and filed; it is maintained and re-checked at defined points so that the project continues only while the justification holds.

  62. Question 62PRINCE2 principles

    Under the learn from experience principle, what should happen to lessons identified while a project is running?

    1. They are recorded, acted on and shared so others can use them Correct answer.
    2. They are stored until the project closes so the next project can review them
    3. They are kept by the project manager as personal reference notes
    4. They are reported only to the project board at end stage assessments

    Explanation

    Learning is continuous, not an end-of-project activity. Lessons are captured when they arise, used to adjust the current work, and made available to other teams and future projects.

  63. Question 63PRINCE2 principles

    A project manager prepares a table showing, for each management product, who is accountable for it and who contributes to it, and then confirms that everyone named understands and accepts this. Which principle is being applied?

    1. Manage by stages
    2. Focus on products
    3. Defined roles and responsibilities Correct answer.
    4. Tailor to suit the project environment

    Explanation

    The principle requires an explicit project organization in which roles, responsibilities and accountability are agreed and understood. Clarifying who is accountable for each product, and checking that people accept it, is a direct application of that rule.

  64. Question 64PRINCE2 principles

    A project manager is adapting PRINCE2 for a small, low-risk project. Which element must still be applied in full?

    1. The seven processes
    2. The management products
    3. The seven themes
    4. The seven principles Correct answer.

    Explanation

    Tailoring covers themes, processes, roles and management products, which can be combined, simplified or scaled down. The principles are the constant element and must be present in every PRINCE2 project, whatever its size or risk.

  65. Question 65PRINCE2 principles

    What is a tolerance in PRINCE2?

    1. The permitted deviation from plan before escalation to the next level Correct answer.
    2. The time allowed for a team to complete a work package
    3. The contingency budget that the project manager may spend without approval
    4. The quality standard that a product must meet before it is accepted

    Explanation

    Tolerances are the boundaries within which a management level may act without referring upwards. If a forecast shows a plan will be exceeded beyond them, the deviation is escalated as an exception to the level above.

  66. Question 66PRINCE2 principles

    Which statement describes a management stage?

    1. The period between two progress reports submitted to the project board
    2. A group of related activities carried out by one team under a single work package
    3. A phase of specialist delivery work defined by the supplier's own method
    4. A period of the project managed on a day-to-day basis by the project manager Correct answer.

    Explanation

    A management stage is the unit of delegation and control: the project board authorizes one stage at a time and reviews the project at each boundary. Specialist or technical stages belong to the supplier's way of working and may run within or across management stages.

  67. Question 67PRINCE2 principles

    A project manager reports progress as the percentage of planned activities completed. Why does this weaken control under the focus on products principle?

    1. Activities can be finished while the products are not fit for purpose Correct answer.
    2. It gives the project board more detail than it needs to make decisions
    3. It prevents the team from starting work until every product is defined
    4. It makes it harder for the project manager to forecast resource costs

    Explanation

    Focus on products defines the project through the products to be delivered and their quality criteria. Progress and acceptance are judged by products completed and approved, so measuring effort spent can report success while the required outputs are still missing or unusable.

  68. Question 68PRINCE2 principles

    Why does the learn from experience principle require lessons to be sought from outside the project team as well as from within it?

    1. The team's own experience is limited, so outside lessons reveal pitfalls it would miss Correct answer.
    2. External lessons are more reliable because they have been formally reviewed and approved
    3. External sources are the only place lessons can be recorded for future use
    4. Outside lessons are needed only where the team has no experience of the work

    Explanation

    The principle asks the team to draw on the experience of earlier projects, other teams and wider sources, because a single team's view is narrow and it may otherwise repeat mistakes others have already made. Lessons gathered are then applied and passed on.

  69. Question 69People

    A newly formed project team is unsure of its objectives and looks to the project manager for direction on how to proceed. In Tuckman's model of team development, which stage does this describe?

    1. Norming
    2. Performing
    3. Storming
    4. Forming Correct answer.

    Explanation

    In the forming stage, team members are polite, dependent on the leader and unclear about their roles and the task. Conflict tends to appear later, in storming, before agreed ways of working emerge in norming.

  70. Question 70People

    A project manager makes sure that new team members are introduced to colleagues and included in team briefings. Which level of Maslow's hierarchy of needs is primarily being addressed?

    1. Esteem needs
    2. Social needs Correct answer.
    3. Physiological needs
    4. Safety needs

    Explanation

    Social needs concern belonging, acceptance and relationships with others, which inclusion and introductions directly support. Physiological needs relate to basics such as rest and pay, safety to security, and esteem to recognition and status.

  71. Question 71People

    Which statement best distinguishes leadership from management in a project context?

    1. Leadership is about assigning tasks and monitoring progress against the plan
    2. Leadership is about documenting roles and responsibilities in the project organization
    3. Leadership is about inspiring and enabling people to commit to a shared direction Correct answer.
    4. Leadership is about controlling scope changes through formal decision gates

    Explanation

    Leadership concerns direction, alignment and commitment, whereas management concerns planning, organizing and controlling work to produce consistent results. PRINCE2 recognizes that a project manager needs both, but they are not the same activity.

  72. Question 72People

    According to Kotter's approach to leading change, which activity comes first?

    1. Creating a sense of urgency Correct answer.
    2. Building a guiding coalition
    3. Generating short-term wins
    4. Communicating the vision

    Explanation

    Kotter's sequence starts by establishing a sense of urgency so that people see the need to act. Only then is a guiding coalition formed, a vision developed and communicated, and later wins consolidated.

  73. Question 73People

    What does the change curve primarily describe?

    1. The rate at which a project's benefits are realized after transition
    2. The typical emotional stages an individual goes through when facing change Correct answer.
    3. The project lifecycle stages used to deliver a change
    4. The sequence of formal stages a change must pass through governance

    Explanation

    The change curve describes the emotional reaction of individuals as they absorb and come to terms with change, often beginning with shock or denial. It is about personal response, not about governance, delivery stages or benefit realization.

  74. Question 74People

    What is the main purpose of stakeholder analysis?

    1. To estimate the cost of engaging external suppliers
    2. To define the quality criteria that deliverables must meet
    3. To record the decisions made at each project board meeting
    4. To identify stakeholders and assess their interest in and influence over the project Correct answer.

    Explanation

    Stakeholder analysis identifies who is affected by or can affect the project and assesses their interest and influence, so that engagement can be planned appropriately. Decisions, quality criteria and supplier costs are handled by other project information.

  75. Question 75People

    Which emotional intelligence capability is about recognizing your own emotions and how they affect your behavior and decisions?

    1. Self-awareness Correct answer.
    2. Relationship management
    3. Empathy
    4. Motivation

    Explanation

    Self-awareness is the ability to notice your own feelings, moods and drives and understand their effect on others. Empathy concerns reading other people's feelings, while relationship management concerns handling interactions.

  76. Question 76People

    What should a communication plan for a project define?

    1. Who needs what information, when, and in what form Correct answer.
    2. The tolerance levels delegated to the project manager
    3. The procedure for escalating issues to the project board
    4. The technical standards that deliverables must meet

    Explanation

    A communication plan sets out the information needs of stakeholders and how those needs will be met, including audience, content, timing, format and responsibility. Technical standards, tolerances and escalation routes are covered elsewhere.

  77. Question 77People

    A team member complains about their pay and working conditions. According to Herzberg's two-factor theory, improving these will:

    1. Increase the team member's sense of achievement
    2. Have no effect on the team member's satisfaction
    3. Remove dissatisfaction but not create positive motivation Correct answer.
    4. Motivate the team member to higher levels of performance

    Explanation

    Pay and working conditions are hygiene factors: when inadequate they cause dissatisfaction, but improving them only prevents dissatisfaction rather than creating motivation. Motivation comes from motivators such as achievement, responsibility and growth.

  78. Question 78People

    A project manager believes that team members avoid responsibility and therefore monitors every task closely. Which view of people does this reflect?

    1. Theory X Correct answer.
    2. Maslow's esteem needs
    3. Herzberg's motivators
    4. Theory Y

    Explanation

    Theory X assumes that people dislike work and avoid responsibility, which justifies close supervision and control. Theory Y assumes the opposite, that people seek responsibility and can be trusted with discretion.

  79. Question 79People

    A highly capable team member has lost confidence after a setback. Which leadership approach is most appropriate?

    1. Controlling: increase reporting requirements and sign-offs
    2. Directing: give detailed instructions and check each step
    3. Supporting: encourage, listen and involve them in decisions Correct answer.
    4. Delegating: hand over full responsibility with no further contact

    Explanation

    The person has the competence but lacks confidence, so a supportive style that rebuilds confidence and involves them in decisions fits best. Directive or controlling approaches suit low competence, while delegating suits people who are both able and confident.

  80. Question 80People

    Two team members disagree strongly about how the work should be divided and are challenging each other's competence. What is the most appropriate response from the project manager?

    1. Ignore the disagreement so that the team can resolve it independently
    2. Escalate the matter to the project board for a decision
    3. Reassign one of the team members to another team
    4. Acknowledge the conflict and facilitate agreement on ways of working Correct answer.

    Explanation

    This behavior is typical of the storming stage, which is resolved when the project manager surfaces the conflict and helps the team agree how it will work together. Ignoring, escalating or removing people avoids the underlying issue.

  81. Question 81People

    In Kotter's eight steps for leading change, which step immediately follows 'communicating the change vision'?

    1. Generating short-term wins
    2. Empowering broad-based action Correct answer.
    3. Creating a sense of urgency
    4. Building a guiding coalition

    Explanation

    The sequence runs from urgency, to a guiding coalition, to a vision, to communicating it, and then to empowering broad-based action by removing barriers. Short-term wins come after that empowerment, not immediately after communication.

  82. Question 82People

    In Bridges' model of transition, in which phase are people most likely to feel disoriented, with old routines gone but new ones not yet established?

    1. New beginnings
    2. Consolidation
    3. Neutral zone Correct answer.
    4. Endings

    Explanation

    Bridges describes endings, a neutral zone and new beginnings. The neutral zone is the unsettling in-between period when the old way has gone but the new way is not yet routine.

  83. Question 83People

    Which approach is most likely to reduce resistance to a planned change?

    1. Withhold details until every uncertainty has been resolved
    2. Involve the people affected early in shaping the change Correct answer.
    3. Announce the change only once it is fully implemented
    4. Use formal authority to enforce compliance quickly

    Explanation

    Involvement gives people a sense of ownership and reduces the feeling that change is being imposed on them. Late announcement, enforcement and secrecy tend to increase anxiety, rumour and opposition.

  84. Question 84People

    In a RACI chart, how many people should be accountable for a given activity?

    1. The whole team collectively
    2. As many people as need to approve the work
    3. One representative from each team involved
    4. Exactly one person Correct answer.

    Explanation

    Accountability means owning the outcome and having the authority to approve it, so it should rest with exactly one person per activity. Several people may be responsible for doing the work, but shared accountability diffuses ownership.

  85. Question 85People

    A stakeholder has a high level of interest in the project and high power to influence its outcome. How should they be engaged?

    1. Keep satisfied without involving them extensively
    2. Monitor with minimal effort
    3. Manage closely: engage regularly and involve them in key decisions Correct answer.
    4. Keep informed with regular but general updates

    Explanation

    Stakeholders who are both influential and interested need close management, with regular two-way engagement and involvement in significant decisions. Other strategies suit stakeholders with different combinations of power and interest.

  86. Question 86People

    A project manager agrees a personal development objective with a team member and provides coaching to help them reach their potential. Which level of Maslow's hierarchy is primarily being supported?

    1. Social needs
    2. Self-actualisation Correct answer.
    3. Physiological needs
    4. Safety needs

    Explanation

    Self-actualisation concerns growth, development and achieving one's potential, which development objectives and coaching directly support. Safety, social and physiological needs are met by security, belonging and basic working conditions.

  87. Question 87People

    Which practice is most likely to strengthen collaboration in a team spread across several locations?

    1. Reducing contact so that people can focus on their own tasks
    2. Agreeing clear communication rhythms and shared ways of working Correct answer.
    3. Relying mainly on email for all decisions and updates
    4. Holding fewer meetings to avoid time-zone difficulties

    Explanation

    Distributed teams collaborate better when expectations are explicit, with agreed communication rhythms, channels and shared working practices. Relying on a single lean channel or cutting contact erodes trust and shared understanding.

  88. Question 88People

    A team member is struggling with a personal issue and their work is slipping. Which response best demonstrates empathy?

    1. Waiting to see whether their performance recovers on its own
    2. Listening to their situation and agreeing temporary adjustments Correct answer.
    3. Reassigning their work without discussion to protect the schedule
    4. Reminding them of the performance targets in their objectives

    Explanation

    Empathy involves seeking to understand another person's feelings and perspective, then responding appropriately. Listening and agreeing temporary adjustments acknowledges the person while keeping the work on track.

  89. Question 89People

    Which option shows three Kotter steps in the correct order?

    1. Communicate the vision, then create urgency, then build a guiding coalition
    2. Build a guiding coalition, then create urgency, then communicate the vision
    3. Create urgency, then build a guiding coalition, then communicate the vision Correct answer.
    4. Create urgency, then generate short-term wins, then build a guiding coalition

    Explanation

    Kotter's sequence begins with urgency, then forms a guiding coalition, then develops and communicates a vision. Short-term wins come much later, after barriers are removed and action is underway.

  90. Question 90People

    Which statement best distinguishes Bridges' transition model from the change curve?

    1. Bridges focuses on the stages people pass through as they let go of the old and embrace the new, rather than on emotional reactions alone Correct answer.
    2. Bridges sets out the sequence of project processes needed to deliver change
    3. Bridges explains how benefits are realized after a project closes
    4. Bridges describes the formal approval stages a change must pass through

    Explanation

    Bridges' model is about transition: endings, a neutral zone and new beginnings, describing how people disengage from the old way and adopt the new. The change curve is more concerned with the emotional reactions individuals display during change.

  91. Question 91People

    A team member is dissatisfied with a rigid approval process but is motivated by the challenge of the work itself. According to Herzberg, which action is most likely to improve motivation?

    1. Simplify the approval process
    2. Give them more challenging and responsible work Correct answer.
    3. Increase their salary
    4. Improve the physical working environment

    Explanation

    Challenge and responsibility are motivators, which raise satisfaction and drive. Removing irritants such as a rigid process or improving pay addresses hygiene factors and only prevents dissatisfaction.

  92. Question 92People

    Two team members respond to the same change very differently: one is enthusiastic from the outset, the other is angry. What does this illustrate about the change curve?

    1. The stages occur only after the project has closed
    2. A person who reacts with anger will never reach acceptance
    3. The change curve applies only to the project manager
    4. People move through the stages at different speeds and not necessarily in a fixed sequence Correct answer.

    Explanation

    The change curve is a guide to common reactions, not a fixed timetable; individuals start at different points and progress at different rates. Some may even skip stages or revisit them as the change unfolds.

  93. Question 93People

    A project manager notices they are becoming impatient during a meeting and deliberately pauses before responding. Which emotional intelligence capability is being applied?

    1. Self-regulation, managing one's own emotions Correct answer.
    2. Social skill, building and maintaining networks
    3. Empathy, understanding other people's feelings
    4. Self-awareness, recognising one's own emotions

    Explanation

    Noticing the impatience draws on self-awareness, but deliberately pausing to control the response is self-regulation. Self-regulation is about managing disruptive impulses so that they do not distort behavior.

  94. Question 94People

    A newly formed project team is polite and cautious in meetings, is unsure who should do what, and looks to the project manager for direction on every decision. Which stage of Tuckman's team development model does this describe?

    1. Forming Correct answer.
    2. Storming
    3. Performing
    4. Norming

    Explanation

    Tuckman describes a sequence in which a group moves from polite dependence on the leader, through conflict about roles and ways of working, into agreed norms, and finally into self-managing high performance. Politeness, uncertainty about roles and reliance on the project manager are the hallmarks of the forming stage.

  95. Question 95People

    Which activity is most characteristic of leadership rather than of management in a project?

    1. Controlling change through formal stage boundaries
    2. Setting direction and inspiring commitment to a vision Correct answer.
    3. Allocating resources to work packages as agreed
    4. Producing plans and monitoring progress against them

    Explanation

    Leadership is concerned with establishing direction, aligning and motivating people, and generating commitment to a shared vision. Management is concerned with planning, organising, resourcing and controlling work so that agreed outputs are delivered.

  96. Question 96People

    During a restructuring, a team member becomes anxious about whether their contract will be renewed. Using Maslow's hierarchy of needs, which level is currently dominating their motivation?

    1. Safety needs Correct answer.
    2. Social needs
    3. Esteem needs
    4. Self-actualisation needs

    Explanation

    Maslow's hierarchy places security, stability and freedom from threat at the safety level, which sits directly above basic physiological needs. Anxiety about continued employment is a threat to security, so safety needs are the ones being frustrated.

  97. Question 97People

    A project manager notices that a normally vocal team member has gone quiet and senses rising tension between two others, even though nothing has been said openly. Which emotional intelligence capability are they using?

    1. Self-regulation
    2. Social awareness Correct answer.
    3. Relationship management
    4. Self-awareness

    Explanation

    Social awareness is the capability of perceiving and understanding the emotions of others and the emotional climate of a group. Noticing changes in someone's behaviour and sensing tension before it is voiced is an act of perception, not of intervening.

  98. Question 98People

    A project manager must tell a team member that their work will not be extended, a message that is sensitive and likely to prompt questions. Which approach is most appropriate?

    1. Sending a detailed email so the message is fully documented
    2. Asking a colleague to mention it informally in passing
    3. Discussing it face to face in a private two-way conversation Correct answer.
    4. Posting the message on the team's shared workspace

    Explanation

    The choice of communication channel should reflect the complexity and sensitivity of the message. Difficult, personal messages are best delivered through a rich, two-way channel that allows immediate questions, clarification and reading of the person's reaction.

  99. Question 99People

    Which action best demonstrates effective delegation by a project manager?

    1. Giving detailed step-by-step instructions and checking each step of the work
    2. Handing over the task and reviewing it only when the stage ends
    3. Agreeing the outcome and reporting points, then letting them decide how Correct answer.
    4. Transferring the task but retaining every decision for themselves throughout

    Explanation

    Effective delegation transfers authority to act as well as the task, within agreed boundaries, while the project manager retains accountability and sets checkpoints. Agreeing the outcome, limits and reporting points gives the person room to decide the method without losing control.

  100. Question 100People

    A project manager leads a team drawn from several countries and disciplines. Which action is most likely to make the team inclusive?

    1. Keeping cultural and personal differences out of team discussions
    2. Actively inviting and using contributions from all members in decisions Correct answer.
    3. Selecting team members with similar backgrounds so that friction is reduced
    4. Asking everyone to adopt the project manager's preferred working style

    Explanation

    Inclusion means that people with different backgrounds and perspectives feel able to contribute and are heard when decisions are made. Deliberately seeking out and using those contributions converts diversity into better decisions and stronger commitment.

  101. Question 101People

    Two team members disagree about which technical design should be adopted. Both present evidence, and the discussion is focused on the work rather than on personalities. How should the project manager respond?

    1. Escalate the disagreement to the project board for a decision
    2. Let them resolve it alone without involving the project manager
    3. Facilitate the discussion so the disagreement is used to test assumptions Correct answer.
    4. Tell both members to stop debating and follow the original approach

    Explanation

    Disagreement about the content of the work is task conflict, which can be constructive because it exposes assumptions and improves solutions. The project manager's role is to manage that debate so it stays focused on the work and reaches a sound decision.

  102. Question 102People

    Why should a project manager adapt their leadership style as a project progresses?

    1. Because the most effective style is fixed by the project manager's personality
    2. Because stages and team maturity differ, so the balance of direction and support should be adapted Correct answer.
    3. Because leadership style should be decided by the project board and applied uniformly to all team members
    4. Because a participative style is always the most motivating option

    Explanation

    Situational approaches to leadership hold that the right balance of direction and support depends on the demands of the situation and the competence and confidence of the people involved. As a team matures and the work changes, a style that once worked well may become inappropriate.

  103. Question 103PRINCE2 practices

    What is the purpose of the PRINCE2 business case practice?

    1. To judge whether the project is desirable, viable and achievable Correct answer.
    2. To record the quality criteria for each project product
    3. To define who is accountable for the project's deliverables
    4. To set the tolerances within which the project will be managed

    Explanation

    The business case practice establishes and maintains the mechanism used to judge whether the project is desirable, viable and achievable. It is developed at the start of the project, refined during initiation and reviewed at every stage boundary and at project closure.

  104. Question 104PRINCE2 practices

    The organization practice requires that three primary stakeholder interests are represented on the project board. Which are they?

    1. Business, user and supplier Correct answer.
    2. Executive, senior user and project assurance
    3. Customer, sponsor and delivery team
    4. Business, project manager and team manager

    Explanation

    PRINCE2 identifies business, user and supplier as the three primary interests that must be represented on the project board. They are represented by the executive, the senior user(s) and the senior supplier(s) respectively.

  105. Question 105PRINCE2 practices

    Which PRINCE2 product records the quality activities planned for the project and the results of the quality control performed?

    1. Quality register Correct answer.
    2. Benefits management approach
    3. Product description
    4. Quality management approach

    Explanation

    The quality register is the log in which planned quality activities and their results are recorded and tracked. It provides the audit trail that shows the required quality activities were carried out and accepted.

  106. Question 106PRINCE2 practices

    In product-based planning, which step is carried out first?

    1. Create the product flow diagram
    2. Create the product breakdown structure
    3. Write the project product description Correct answer.
    4. Write the product descriptions

    Explanation

    Product-based planning starts with the project product description, which captures the purpose, composition and acceptance criteria of the final product. Only once the final product is understood can the product breakdown structure, product descriptions and product flow diagram be derived.

  107. Question 107PRINCE2 practices

    What is the purpose of the risk management approach?

    1. To describe how risk will be managed on the project Correct answer.
    2. To justify why the project is worth investing in
    3. To list every risk that has been identified so far
    4. To delegate specific risk tolerances to the project manager

    Explanation

    The risk management approach is the document that sets out the risk management procedure, roles and responsibilities, risk appetite, and the techniques and reporting to be used. It is the 'how' of risk management rather than a record of individual risks.

  108. Question 108PRINCE2 practices

    Which PRINCE2 product is used to record and track issues raised during a project?

    1. Quality register
    2. Lessons log
    3. Risk register
    4. Issue register Correct answer.

    Explanation

    The issue register captures and tracks all issues, including requests for change, off-specifications and concerns, together with their assessment, decisions and status. It is the single source of information about the progress of each issue.

  109. Question 109PRINCE2 practices

    What is the purpose of the progress practice?

    1. To define the reporting lines between the project board and team managers
    2. To monitor progress against plans and provide forecasts and control information Correct answer.
    3. To measure whether the project's benefits have been realised
    4. To decide which change requests should be approved

    Explanation

    The progress practice establishes and maintains mechanisms to monitor progress against the plans and to provide the project board and project manager with forecasts and control information. Control is exercised by comparing actuals with the plan and acting on the difference.

  110. Question 110PRINCE2 practices

    When is the business case first developed in a PRINCE2 project?

    1. At each stage boundary, when the project plan is updated
    2. During the initiation stage, as part of the project initiation documentation
    3. At the end of the project, when benefits are reviewed
    4. During starting up a project, as an outline business case Correct answer.

    Explanation

    An outline business case is created during starting up a project so that the project board can authorise initiation. It is then refined into a full business case during initiating a project and maintained throughout the project.

  111. Question 111PRINCE2 practices

    A project board member is appointed to represent the people who will use the project's products and to specify the associated benefits. Which role is this?

    1. Executive
    2. Project assurance
    3. Senior user Correct answer.
    4. Senior supplier

    Explanation

    The senior user represents the user interest on the project board; the role is accountable for specifying the needs of those who will use the products and for monitoring that the benefits are realised. The executive represents the business interest and owns the business case.

  112. Question 112PRINCE2 practices

    Where are the acceptance criteria for the project's final product defined?

    1. In the stage plan
    2. In the project product description Correct answer.
    3. In the quality register
    4. In the benefits management approach

    Explanation

    The project product description contains the customer's quality expectations expressed as acceptance criteria, together with the purpose and composition of the final product. Acceptance criteria provide the basis for the project board's acceptance of the finished project.

  113. Question 113PRINCE2 practices

    A project manager needs to show the order in which products will be produced and the dependencies between them. Which output of product-based planning is used for this?

    1. Project product description
    2. Product description
    3. Product flow diagram Correct answer.
    4. Product breakdown structure

    Explanation

    The product flow diagram takes the products from the breakdown structure and arranges them to show the sequence of development and the dependencies between them. It becomes the basis for identifying activities, dependencies and resource requirements in the plan.

  114. Question 114PRINCE2 practices

    A project purchases insurance to cover the financial impact of a risk should it occur. Which risk response is being used?

    1. Accept
    2. Transfer Correct answer.
    3. Avoid
    4. Reduce

    Explanation

    Transferring a risk places the financial ownership of the impact on a third party, for example through insurance or a fixed-price contract. The risk event may still occur, but the project no longer bears the financial consequence.

  115. Question 115PRINCE2 practices

    What is the purpose of the change control approach?

    1. To record the status of each change request raised on the project
    2. To summarise the project's progress against the stage plan
    3. To define how changes will be identified, assessed, approved and implemented Correct answer.
    4. To describe how the project's products will be tested and accepted

    Explanation

    The change control approach specifies how changes and other issues will be handled, including who may raise them, how they are assessed, who holds the change authority and how the change budget is used. It is a definition of the process, not a record of individual changes.

  116. Question 116PRINCE2 practices

    Which report does the project manager produce at the end of a stage so that the project board can decide whether to continue?

    1. Highlight report
    2. End stage report Correct answer.
    3. Exception report
    4. Checkpoint report

    Explanation

    The end stage report summarises the stage's performance against its plan and is the key input to the end stage assessment, at which the board authorises the next stage. It is produced for every stage boundary, including the final one.

  117. Question 117PRINCE2 practices

    Which of the following is an example of a dis-benefit?

    1. An increase in customer complaints during the transition to a new process Correct answer.
    2. The cost of software licences purchased for the project
    3. The additional revenue expected from a new product line
    4. A reduction in staff overtime after the new system is introduced

    Explanation

    A dis-benefit is an outcome of the project that is perceived as negative by one or more stakeholders. It differs from a cost because it is a consequence of the project's outcome rather than a resource consumed in delivering it, and it is recorded in the business case alongside the benefits.

  118. Question 118PRINCE2 practices

    A product description includes quality criteria and a quality tolerance. What is the purpose of the quality tolerance?

    1. To define the method that will be used to check the product
    2. To state the permissible variation from the quality criteria Correct answer.
    3. To identify who is responsible for approving the product
    4. To describe the product's purpose and composition

    Explanation

    Quality tolerance states the acceptable deviation from the quality criteria, so that a product can still be accepted when it is not an exact match. It allows proportionate control rather than demanding perfection on every criterion.

  119. Question 119PRINCE2 practices

    Which statement describes a stage plan?

    1. It is produced by the team manager for a single work package
    2. It is created only when a stage's tolerances are forecast to be exceeded
    3. It covers the whole project from start to completion
    4. It provides the detailed basis for day-to-day control by the project manager Correct answer.

    Explanation

    A stage plan is produced by the project manager before the stage begins and is detailed enough to be the basis for day-to-day control. It sits below the project plan (which covers the whole project) and above team plans (which cover work packages).

  120. Question 120PRINCE2 practices

    Which PRINCE2 product contains the assessment of each identified risk, including its probability, impact and proximity?

    1. Risk register Correct answer.
    2. Lessons log
    3. Quality register
    4. Risk management approach

    Explanation

    The risk register holds each risk's cause, event and effect, together with its assessment of probability, impact and proximity, its response and its owner. It is updated throughout the project as risks change and as responses are implemented.

  121. Question 121PRINCE2 practices

    What is the purpose of project assurance?

    1. To provide administrative support to the project manager
    2. To check that the project complies with the organization's quality standards
    3. To monitor all aspects of the project's performance on behalf of the project board Correct answer.
    4. To carry out the technical work needed to produce the project's products

    Explanation

    Project assurance is the project board's responsibility to monitor the project independently of the project manager, covering business, user and supplier interests. It is distinct from quality assurance, which is provided from outside the project to confirm that the project's quality approach is sound.

  122. Question 122PRINCE2 practices

    A project manager forecasts that a stage will exceed its agreed time tolerance. What should the project manager do?

    1. Extend the stage end date and inform the team managers
    2. Wait until the end of the stage and report it in the end stage report
    3. Ask the change authority to approve a change request
    4. Raise an exception report to the project board Correct answer.

    Explanation

    Where a forecast shows a delegated tolerance will be breached, management by exception requires the project manager to escalate the matter to the project board. This is done through an exception report, after which the board may direct that an exception plan be prepared.

  123. Question 123PRINCE2 practices

    Which statement correctly distinguishes a request for change from an off-specification?

    1. A request for change proposes an alteration to a baselined product; an off-specification reports non-conformance to agreed criteria Correct answer.
    2. A request for change can be raised only by the project board; an off-specification can be raised only by a team manager
    3. A request for change is recorded in the risk register; an off-specification is recorded in the quality register
    4. A request for change reports a product that fails to meet its criteria; an off-specification proposes an alteration to a baselined product

    Explanation

    A request for change asks for approval to modify a product that is already baselined, whereas an off-specification records that a product has been, or is forecast to be, produced outside its agreed criteria. Both are types of issue and are recorded in the issue register and assessed through the change control approach.

  124. Question 124PRINCE2 practices

    Which activity belongs to quality planning rather than quality control?

    1. Defining the quality criteria for a product in its product description Correct answer.
    2. Carrying out a quality inspection of a completed product
    3. Obtaining approval of a product from the nominated approver
    4. Recording the results of a quality review in the quality register

    Explanation

    Quality planning defines what quality is required and how it will be achieved, through the quality management approach, product descriptions with quality criteria and the quality register of planned activities. Quality control is the execution of those planned activities and the recording of their outcome.

  125. Question 125PRINCE2 practices

    Under what circumstances is an exception plan produced?

    1. To replace a plan that can no longer be achieved within its agreed tolerances Correct answer.
    2. To give the project board a summary of stage progress
    3. To replace a team plan once all its work packages are complete
    4. To document the lessons learned during a stage

    Explanation

    An exception plan is prepared after an exception has been escalated and the project board has asked for it; it replaces the plan that can no longer be delivered within its tolerances. It covers the period from the point of the exception to the end of the plan it replaces and is itself subject to approval.

  126. Question 126PRINCE2 practices

    How does risk appetite differ from risk tolerance?

    1. Risk appetite is the amount of risk the organization will accept, while risk tolerance sets thresholds that trigger escalation Correct answer.
    2. Risk appetite applies only to opportunities, while risk tolerance applies only to threats
    3. Risk appetite is recorded in the risk register, while risk tolerance is recorded in the business case
    4. Risk appetite is the threshold that triggers escalation, while risk tolerance is the amount of risk that may be taken

    Explanation

    Risk appetite expresses the amount and type of risk an organization is willing to accept in pursuit of its objectives. Risk tolerance translates that appetite into measurable thresholds for a project, stage or work package, so that a forecast breach can be escalated.

  127. Question 127PRINCE2 practices

    Which statement distinguishes an end stage report from an end project report?

    1. An end stage report confirms benefits realised; an end project report forecasts future benefits
    2. An end stage report is produced by the project board; an end project report is produced by the project manager
    3. An end stage report covers the whole project; an end project report covers a single stage
    4. An end stage report supports the decision to continue; an end project report evaluates overall project performance Correct answer.

    Explanation

    The end stage report reviews performance of one stage and gives the project board the information it needs to authorise the next stage. The end project report reviews performance against the project's baselines as a whole and is used to confirm closure and handover of the products.

  128. Question 128PRINCE2 practices

    A project is midway through delivery and the project board wants clarity on who is answerable for keeping the business case valid. Which role holds that accountability?

    1. Project assurance
    2. The Senior User
    3. The Executive Correct answer.
    4. The project manager

    Explanation

    Accountability for the business case rests with the Executive, who must be able to justify continued investment at each stage boundary and confirm the project stays aligned with corporate objectives. Other roles supply information to the business case, but they cannot take on the accountability itself.

  129. Question 129PRINCE2 practices

    What is the purpose of the quality register?

    1. To record the quality criteria that have been defined for each product.
    2. To describe the quality approach, roles and responsibilities for the project.
    3. To capture the lessons that arise from quality reviews so they can be reused.
    4. To record the quality management activities planned for the project and the results of those activities. Correct answer.

    Explanation

    The quality register is the control log for the quality practice: it lists the quality management activities that have been planned, who is responsible and when they are due, and it is updated with the outcome once each activity has been carried out. It therefore provides the basis for tracking and controlling quality across the project.

  130. Question 130PRINCE2 practices

    A team manager is running a work package that spans several weeks. What is the purpose of the checkpoint report the team manager produces?

    1. To ask the project board for authority to begin the next stage.
    2. To report progress on the work package to the project manager at an agreed frequency. Correct answer.
    3. To define the products, tolerances and reporting needs of the work package.
    4. To inform the project board of the progress of the stage as it nears its end.

    Explanation

    A checkpoint report is the team manager's regular progress report to the project manager, produced at a frequency agreed when the work package was accepted. Its purpose is to give the project manager enough information to control the work package within its tolerances between stage boundaries.

  131. Question 131PRINCE2 practices

    A project manager is starting product-based planning for a stage and wants to know which element is created first.

    1. The product breakdown structure Correct answer.
    2. The activity schedule
    3. The cost estimate for the stage
    4. The product flow diagram

    Explanation

    Product-based planning starts by decomposing the scope of the plan into the products that must be delivered, recorded in a product breakdown structure. Product descriptions, dependencies, estimates and the schedule are all derived from that first breakdown.

  132. Question 132PRINCE2 practices

    A newly identified risk has been entered in the risk register and a risk owner has been assigned to it. What is that risk owner accountable for?

    1. Carrying out the response actions once they have been agreed.
    2. Providing independent assurance on the effectiveness of the project's risk management.
    3. Managing, monitoring and controlling all aspects of the risk, including initiating a response. Correct answer.
    4. Approving the risk management approach on behalf of the project board.

    Explanation

    The risk owner is the single point of accountability for a particular risk and is responsible for keeping it under control throughout its life, including deciding what response is appropriate and monitoring whether it remains effective. The work of implementing the agreed actions sits with a different role.

  133. Question 133PRINCE2 practices

    What is the purpose of a configuration item record?

    1. To hold the status, version and relationships of a product that is under configuration control. Correct answer.
    2. To list all the issues and change requests that have been raised during the project.
    3. To describe the approach for identifying, controlling and tracking the project's products.
    4. To authorize changes to products that have already been baselined.

    Explanation

    Configuration item records are the mechanism by which configuration management keeps track of each product: what version exists, what state it is in, who owns it and how it relates to other products. They allow the project to know exactly what is baselined and what has changed.

  134. Question 134PRINCE2 practices

    A project manager has agreed a work package with a team manager. For which aspect of that work is the team manager accountable?

    1. Producing and maintaining the benefits management approach.
    2. Producing the products of the work package within the agreed tolerances. Correct answer.
    3. Authorizing the project to move into the next stage.
    4. Confirming at each stage boundary that the business case remains viable.

    Explanation

    By accepting a work package, the team manager takes on responsibility for delivering its products to the agreed quality, time and cost tolerances, and for escalating any forecast breach to the project manager. Authority for the stage and for the business case stays at project board level.

  135. Question 135PRINCE2 practices

    A project will deliver a new online booking system. Which statement correctly distinguishes the output, the outcome and the benefit?

    1. The system is the outcome, and the increase in revenue is the output.
    2. The system is the benefit, and the change in customer booking behaviour is the output.
    3. Outputs, outcomes and benefits are interchangeable terms for what a project delivers.
    4. The system is an output, changed booking behaviour is an outcome, and the revenue gain is a benefit. Correct answer.

    Explanation

    Outputs are the products the project actually delivers, outcomes are the resulting change in the way the organization or its customers operate, and benefits are the measurable improvements that arise from those outcomes. The business case must express benefits in measurable terms so that they can later be confirmed.

  136. Question 136PRINCE2 practices

    A risk is recorded as: 'Because only one supplier can provide the specialist component, the project may be delayed by four weeks if that supplier fails to deliver.' Which part of this statement is the risk cause?

    1. The project requires a specialist component.
    2. The project is delayed by four weeks.
    3. Only one supplier can provide the specialist component. Correct answer.
    4. The supplier fails to deliver.

    Explanation

    A well-formed risk statement separates the cause (the situation that gives rise to the risk), the event (what may happen) and the effect (the impact if it does happen). Identifying the cause explicitly helps the project choose a response that addresses the root situation rather than only its consequences.

  137. Question 137PRINCE2 processes

    Which PRINCE2 process is triggered by the project mandate?

    1. Managing a Stage Boundary
    2. Directing a Project
    3. Initiating a Project
    4. Starting up a Project Correct answer.

    Explanation

    The project mandate is the trigger for Starting up a Project, which decides whether the project is viable enough to justify the effort of initiating it. Initiating a Project is only entered once the project board has authorised initiation.

  138. Question 138PRINCE2 processes

    Which process creates the project initiation documentation (PID)?

    1. Starting up a Project
    2. Controlling a Stage
    3. Directing a Project
    4. Initiating a Project Correct answer.

    Explanation

    Initiating a Project assembles the PID from all of the initiation outputs and presents it to the board so the project can be authorised. Starting up a Project only produces the project brief and outline business case.

  139. Question 139PRINCE2 processes

    Which process is owned by the project board rather than by the project manager?

    1. Managing Product Delivery
    2. Directing a Project Correct answer.
    3. Closing a Project
    4. Controlling a Stage

    Explanation

    Directing a Project is the board's own process and contains its decision points, such as authorising initiation, the project, stage or exception plans, and closure. The project manager owns the other processes and supports the board in its decisions.

  140. Question 140PRINCE2 processes

    Which process covers the project manager's day-to-day management of a management stage?

    1. Managing a Stage Boundary
    2. Initiating a Project
    3. Managing Product Delivery
    4. Controlling a Stage Correct answer.

    Explanation

    Controlling a Stage is where the project manager authorises work packages, monitors progress, deals with issues and risks, and reports to the board. Managing Product Delivery covers the team manager's work on the products.

  141. Question 141PRINCE2 processes

    Which process includes the activity 'Accept a work package'?

    1. Controlling a Stage
    2. Managing Product Delivery Correct answer.
    3. Managing a Stage Boundary
    4. Directing a Project

    Explanation

    In Managing Product Delivery the team manager accepts the work package from the project manager, executes it and delivers the completed products. Authorising the work package is a separate activity performed by the project manager in Controlling a Stage.

  142. Question 142PRINCE2 processes

    Which process must the board complete before Initiating a Project can begin?

    1. Managing a Stage Boundary
    2. Directing a Project Correct answer.
    3. Controlling a Stage
    4. Starting up a Project

    Explanation

    Initiating a Project begins only when the board, in Directing a Project, authorises initiation on the basis of the project brief. Directing a Project is therefore the trigger for initiation even though the brief itself was produced earlier.

  143. Question 143PRINCE2 processes

    Which process includes the activity 'Recommend project closure'?

    1. Controlling a Stage
    2. Closing a Project Correct answer.
    3. Directing a Project
    4. Managing a Stage Boundary

    Explanation

    Closing a Project prepares closure, hands over products, evaluates the project and then recommends closure to the board. The board itself authorises project closure in Directing a Project.

  144. Question 144PRINCE2 processes

    After reviewing the PID, which Directing a Project activity commits the organisation to the project?

    1. Authorise the project Correct answer.
    2. Give ad hoc direction
    3. Authorise initiation
    4. Authorise a stage plan

    Explanation

    'Authorise the project' is the board's decision that approves the PID and commits resources to the whole project. 'Authorise initiation' only approves the work needed to prepare the PID.

  145. Question 145PRINCE2 processes

    Which Starting up a Project activity draws on experience from similar past projects and records it for later use?

    1. Design the project management team
    2. Prepare the outline business case
    3. Plan the initiation stage
    4. Capture previous lessons Correct answer.

    Explanation

    'Capture previous lessons' reviews lessons from comparable projects and records them in the lessons log so they can shape the project during initiation and delivery. The other activities deal with the business justification, the initiation plan or the team structure.

  146. Question 146PRINCE2 processes

    Which of these is a Directing a Project activity?

    1. Give ad hoc direction Correct answer.
    2. Authorise a work package
    3. Receive completed work packages
    4. Plan the next stage

    Explanation

    Directing a Project contains the board's decisions plus the ability to give ad hoc direction whenever the board wishes to steer the project. Authorising work packages and receiving completed ones belong to Controlling a Stage, and planning the next stage belongs to Managing a Stage Boundary.

  147. Question 147PRINCE2 processes

    In Controlling a Stage, what does the project manager do when a team manager reports that a work package is complete?

    1. Produce an exception plan
    2. Receive the completed work package Correct answer.
    3. Authorise the work package
    4. Escalate the issue to the project board

    Explanation

    The project manager receives completed work packages and confirms that the products meet their quality criteria before accepting them. Authorising a work package happens before the work starts, not when it finishes.

  148. Question 148PRINCE2 processes

    Which Managing a Stage Boundary activity assesses whether the business case remains viable before approval of the next stage is requested?

    1. Update the business case Correct answer.
    2. Produce an exception plan
    3. Plan the next stage
    4. Report stage end

    Explanation

    Managing a Stage Boundary updates the business case to confirm the project is still justified and consistent with the next stage plan. The stage end report then presents the position to the board, which decides in Directing a Project.

  149. Question 149PRINCE2 processes

    Which process produces an exception report when stage tolerances are forecast to be breached?

    1. Managing Product Delivery
    2. Directing a Project
    3. Managing a Stage Boundary
    4. Controlling a Stage Correct answer.

    Explanation

    Controlling a Stage includes capturing and examining issues and risks and escalating those that threaten tolerances to the board through an exception report. Managing a Stage Boundary produces the exception plan once the board has authorised it.

  150. Question 150PRINCE2 processes

    Which product does the project manager produce in Controlling a Stage to keep the project board informed of progress?

    1. Lessons report
    2. Highlight report Correct answer.
    3. End stage report
    4. Checkpoint report

    Explanation

    Highlight reports are produced at the frequency agreed in the communication management approach and are sent from the project manager to the board. Checkpoint reports flow from the team manager to the project manager.

  151. Question 151PRINCE2 processes

    Which Closing a Project activity assesses whether the project's products are delivering the expected benefits?

    1. Evaluate the project Correct answer.
    2. Prepare planned closure
    3. Recommend project closure
    4. Hand over products

    Explanation

    'Evaluate the project' compares what was delivered against the project plan and business case, including benefits realized so far. Benefits that accrue after closure are addressed through the benefits management approach.

  152. Question 152PRINCE2 processes

    In which process does the project manager authorise a work package to a team manager?

    1. Managing Product Delivery
    2. Controlling a Stage Correct answer.
    3. Managing a Stage Boundary
    4. Directing a Project

    Explanation

    Authorising a work package is a Controlling a Stage activity carried out by the project manager, who agrees the products, tolerances and reporting with the team manager. The team manager then accepts the work package in Managing Product Delivery.

  153. Question 153PRINCE2 processes

    Which Initiating a Project activity establishes tolerances and the reporting arrangements the board will use?

    1. Refine the business case
    2. Set up the project controls Correct answer.
    3. Assemble the project initiation documentation
    4. Create the project plan

    Explanation

    'Set up the project controls' defines tolerances, reporting mechanisms and the control arrangements the board will rely on. The PID is assembled afterwards from all of the initiation outputs.

  154. Question 154PRINCE2 processes

    Which report does the project manager produce at the end of a stage for the project board?

    1. Highlight report
    2. End stage report Correct answer.
    3. Checkpoint report
    4. Exception report

    Explanation

    The end stage report is produced in Managing a Stage Boundary and summarises performance against the stage plan to support the board's decision on the next stage. Highlight reports cover progress during a stage.

  155. Question 155PRINCE2 processes

    Before starting work on the products in a work package, what must a team manager do in Managing Product Delivery?

    1. Produce a highlight report
    2. Accept the work package Correct answer.
    3. Update the business case
    4. Authorise the next stage

    Explanation

    The team manager accepts the work package, confirming the products, quality criteria, tolerances and reporting requirements, before executing the work. Only then does delivery of the products begin.

  156. Question 156PRINCE2 processes

    Which process is used at the end of the project to hand over products and obtain closure?

    1. Closing a Project Correct answer.
    2. Initiating a Project
    3. Starting up a Project
    4. Managing a Stage Boundary

    Explanation

    Closing a Project prepares planned or premature closure, hands over the products, evaluates the project and recommends closure to the board. Managing a Stage Boundary is used at the end of earlier stages only.

  157. Question 157PRINCE2 processes

    A stage is forecast to exceed its cost tolerance. Which sequence of activities is correct?

    1. CS produces an exception plan and sends it to the team manager for approval
    2. MP escalates directly to the board and rewrites the business case
    3. DP produces an exception plan and issues it as a new work package
    4. CS escalates via an exception report, DP authorises, SB produces the plan Correct answer.

    Explanation

    Controlling a Stage captures the forecast breach and escalates it to the board with an exception report. The board decides in Directing a Project whether to request an exception plan, which is then produced in Managing a Stage Boundary.

  158. Question 158PRINCE2 processes

    Which pairing of process and product is correct?

    1. Initiating a Project - project brief
    2. Managing a Stage Boundary - end stage report Correct answer.
    3. Closing a Project - highlight report
    4. Starting up a Project - project initiation documentation

    Explanation

    Managing a Stage Boundary reports stage end and produces the end stage report for the board. The project brief belongs to Starting up a Project, the PID to Initiating a Project, and highlight reports to Controlling a Stage.

  159. Question 159PRINCE2 processes

    The board decides to stop the project before its planned end. Which process and activity address this?

    1. Closing a Project - prepare premature closure Correct answer.
    2. Closing a Project - prepare planned closure
    3. Directing a Project - authorise a stage plan
    4. Managing a Stage Boundary - produce an exception plan

    Explanation

    Closing a Project distinguishes planned closure from premature closure; the latter is used when the project is stopped early and still covers handover of completed products, lessons and evaluation. The board then authorises closure in Directing a Project.

  160. Question 160PRINCE2 processes

    In Managing a Stage Boundary, against which baseline must the next stage plan be aligned?

    1. The communication management approach
    2. The stage plan for the current stage
    3. The benefits management approach
    4. The project plan Correct answer.

    Explanation

    The next stage plan is derived from the project plan, which is updated in Managing a Stage Boundary so that the two remain consistent. The business case is also updated to confirm the project is still justified.

  161. Question 161PRINCE2 processes

    Which statement correctly describes the relationship between Controlling a Stage and Managing Product Delivery?

    1. MP produces highlight reports for the board
    2. CS authorises work packages that MP accepts Correct answer.
    3. MP authorises work packages that CS accepts
    4. Both processes are performed by the project board

    Explanation

    The project manager in Controlling a Stage authorises a work package, and the team manager in Managing Product Delivery accepts it and becomes accountable for delivering the agreed products. Control of the stage remains with the project manager.

  162. Question 162PRINCE2 processes

    Which Directing a Project activity allows the project board to respond to a situation that arises between scheduled board meetings?

    1. Authorise project closure
    2. Give ad hoc direction Correct answer.
    3. Authorise initiation
    4. Authorise a stage or exception plan

    Explanation

    Directing a Project is the board's process and includes an activity for giving direction at any time, not only at planned decision points. Ad hoc direction is used when the project manager needs a board decision or guidance between meetings. The other activities are scheduled decision points tied to specific products.

  163. Question 163PRINCE2 processes

    What is the minimum number of management stages that a PRINCE2 project can have?

    1. Two, initiation plus delivery
    2. Four, one for each process
    3. Three, initiation, delivery and closure
    4. One Correct answer.

    Explanation

    PRINCE2 does not prescribe a fixed number of management stages; the number is set by the project board based on the level of control required. A project may be run as a single management stage. Processes such as Initiating a Project and Closing a Project are not themselves stages.

  164. Question 164PRINCE2 processes

    A team manager reports a supplier delay that may affect the stage. In which Controlling a Stage activity would the project manager first record and assess this?

    1. Capture and examine issues and risks Correct answer.
    2. Review work package status
    3. Take corrective action
    4. Escalate the issue to the project board

    Explanation

    Controlling a Stage includes an activity for capturing and examining issues and risks, which covers logging the concern, assessing its impact and deciding how to handle it. Only after that assessment can the project manager decide whether corrective action or escalation is needed. Escalation is a possible outcome rather than the first step.

  165. Question 165PRINCE2 processes

    How does a team manager normally keep the project manager informed of progress at the frequency agreed within a work package?

    1. By issuing an exception report
    2. By issuing a checkpoint report Correct answer.
    3. By issuing a highlight report
    4. By issuing an end stage report

    Explanation

    Managing Product Delivery requires the team manager to report progress to the project manager at the frequency and in the format set out in the work package, using checkpoint reports. Highlight reports and end stage reports are produced by the project manager, not the team manager. This keeps the reporting line between the two roles clear.

  166. Question 166PRINCE2 processes

    At a stage boundary, the project manager must reassess whether the project remains worthwhile before the next stage plan is submitted. Which product is updated for this purpose?

    1. Communication management approach
    2. Project brief
    3. Business case Correct answer.
    4. Benefits management approach

    Explanation

    Managing a Stage Boundary includes updating the business case so the project board can judge whether the project is still justified before committing to the next stage. The business case holds the justification, costs, risks and expected benefits. Other approaches may be reviewed, but the business case is the product that carries the justification decision.

  167. Question 167PRINCE2 processes

    During Initiating a Project, the project manager needs to set out the project's risk appetite, risk procedures and risk responsibilities. Which product records this?

    1. Project plan
    2. Business case
    3. Quality management approach
    4. Risk management approach Correct answer.

    Explanation

    The risk management approach defines how risk will be identified, assessed and controlled on the project, including appetite, procedures and roles. It forms part of the project initiation documentation. The business case and project plan draw on the approach but do not define it.

  168. Question 168PRINCE2 processes

    A stage is forecast to finish within all of its tolerances. Which sequence correctly describes how work moves into the next stage?

    1. Managing a Stage Boundary, then Directing a Project, then Controlling a Stage Correct answer.
    2. Directing a Project, then Managing a Stage Boundary, then Controlling a Stage
    3. Managing a Stage Boundary, then Controlling a Stage, then Directing a Project
    4. Controlling a Stage, then Directing a Project, then Managing a Stage Boundary

    Explanation

    When a stage is within tolerance, the project manager prepares the end stage report and the next stage plan in Managing a Stage Boundary. The project board then decides whether to authorise the next stage in Directing a Project. Only after authorisation does the project manager begin controlling the new stage and authorising work packages.

  169. Question 169Tailoring PRINCE2 to the project environment

    Which PRINCE2 principle requires the method to be adapted to the project's size, complexity, importance, capability and risk?

    1. Tailor to suit the project Correct answer.
    2. Learn from experience and share lessons
    3. Focus on products and their quality criteria
    4. Manage by exception using tolerances

    Explanation

    The principle 'tailor to suit the project' requires PRINCE2 to be adapted deliberately to the project's context, including its size, complexity, importance, capability and risk. Tailoring is therefore a principle, not an optional extra.

  170. Question 170Tailoring PRINCE2 to the project environment

    Where should a PRINCE2 project record its approach to tailoring the method?

    1. In the business case
    2. In the project log
    3. In the communication management approach
    4. In the project initiation documentation Correct answer.

    Explanation

    The tailoring approach is part of the project initiation documentation (PID), which records how the method will be applied for that project. This gives the project board a basis for approving the tailored approach.

  171. Question 171Tailoring PRINCE2 to the project environment

    How does PRINCE2 treat its seven principles when a project is tailored?

    1. They are tailored by the board at each stage
    2. They may be omitted for simple projects
    3. They may be replaced by organizational standards
    4. They must always be applied and are not tailored Correct answer.

    Explanation

    The principles are universal and must always be applied; tailoring adapts how the method is applied, not whether the principles apply. A project that drops a principle is not applying PRINCE2.

  172. Question 172Tailoring PRINCE2 to the project environment

    What is the main purpose of tailoring PRINCE2?

    1. To avoid producing any management products during the project
    2. To reduce the number of principles that are applied to the project
    3. To fit the method to the project's context Correct answer.
    4. To replace the project board with a single accountable sponsor

    Explanation

    Tailoring makes PRINCE2 proportionate to the project's environment, scale, complexity and risk while retaining its principles. It is not a way to remove governance or rigour.

  173. Question 173Tailoring PRINCE2 to the project environment

    Who should approve the tailoring approach for a PRINCE2 project?

    1. The project support officer
    2. The team manager
    3. The project board Correct answer.
    4. The project manager alone

    Explanation

    The project manager prepares the tailoring approach, which is included in the PID, and the project board approves the PID. This ensures the tailored approach is consistent with the project's governance needs.

  174. Question 174Tailoring PRINCE2 to the project environment

    How should the level of tailoring be determined for a project?

    1. It should be the same for every project in the organization
    2. It should be delegated entirely to the supplier
    3. It should reflect size, complexity, risk and importance Correct answer.
    4. It should be as light as possible to save time and cost

    Explanation

    Tailoring should be proportionate to the project's characteristics, including its size, complexity, risk and importance. A lighter approach may suit a small project, while a complex project may need more formality.

  175. Question 175Tailoring PRINCE2 to the project environment

    A programme mandates four stages, but the project is small and low risk. What is an acceptable tailoring action?

    1. Remove the manage by stages principle for this project
    2. Ask the team manager to approve fewer stages
    3. Retain four stages because stage count can never change
    4. Combine stages with project board approval Correct answer.

    Explanation

    The number of management stages can be tailored, so stages may be combined where justified by the project's scale and risk. The decision should be agreed through the project's governance, normally the project board.

  176. Question 176Tailoring PRINCE2 to the project environment

    What constraint applies when tailoring PRINCE2 management products?

    1. They must all be produced exactly as described in the manual
    2. Only the business case may be tailored in this way
    3. They may be combined if their purpose is still met Correct answer.
    4. They may be omitted without any approval

    Explanation

    Management products can be combined, simplified or produced in a different format, provided the information needed for their purpose is still available. Tailoring does not remove the need for the purpose to be fulfilled.

  177. Question 177Tailoring PRINCE2 to the project environment

    In a small project, the project manager also performs project support. How is this treated in PRINCE2 tailoring?

    1. It requires a change to one of the principles
    2. It means project assurance is no longer needed
    3. It is prohibited because roles must remain separate
    4. Roles can be combined if accountability is clear Correct answer.

    Explanation

    PRINCE2 roles can be combined on smaller projects, provided responsibilities and accountability remain clear and independent assurance is not compromised. Tailoring roles does not remove the need for defined roles and responsibilities.

  178. Question 178Tailoring PRINCE2 to the project environment

    An organization uses the term 'work package owner' instead of 'team manager'. What does PRINCE2 tailoring allow?

    1. Local terms can be used while keeping responsibilities Correct answer.
    2. Terminology must remain exactly as in the manual
    3. Changing terminology requires a programme mandate
    4. Terminology can change only if a principle is dropped

    Explanation

    PRINCE2 terminology can be adapted to local language or organizational conventions, provided the underlying role and its responsibilities remain clear. Tailoring terminology does not change the principles.

  179. Question 179Tailoring PRINCE2 to the project environment

    How can PRINCE2 be tailored for an agile delivery approach?

    1. By dropping the business case for agile projects
    2. By replacing manage by stages with continuous delivery
    3. By aligning stages and products with agile iterations Correct answer.
    4. By removing defined roles and responsibilities

    Explanation

    PRINCE2 can be tailored to work with agile delivery by aligning management stages, product descriptions and controls with iterations. The principles, including manage by stages and continued business justification, still apply.

  180. Question 180Tailoring PRINCE2 to the project environment

    When should the tailoring approach be reviewed during a project?

    1. Only at project closure
    2. Never after the project initiation documentation is approved
    3. Only when the project manager changes
    4. At stage boundaries and after significant change Correct answer.

    Explanation

    Tailoring is not a one-off activity; it should be revisited at stage boundaries and when significant changes affect the project's context, risk or approach. This keeps the method proportionate as the project evolves.

  181. Question 181Tailoring PRINCE2 to the project environment

    What distinguishes embedding PRINCE2 in an organization from tailoring it for a project?

    1. Tailoring is one-off; embedding is continuous
    2. There is no practical difference between the two terms
    3. Embedding is done by the project board, tailoring by the programme
    4. Embedding is organization-wide; tailoring fits a project Correct answer.

    Explanation

    Embedding concerns the organization's wider adoption of PRINCE2, such as standards, guidance and capability. Tailoring applies the method to the specific context of an individual project.

  182. Question 182Tailoring PRINCE2 to the project environment

    A low-risk, low-value project has a simple business case. What is appropriate tailoring?

    1. It must be as detailed as for any high-risk project
    2. It is replaced by the project log
    3. It can be omitted because the risk is low
    4. It can be simplified but still justify the project Correct answer.

    Explanation

    The business case can be tailored to be lighter for a low-risk project, but it must still provide sufficient justification for continued investment. The continued business justification principle is not removed by tailoring.

  183. Question 183Tailoring PRINCE2 to the project environment

    Which statement about tailoring and the PRINCE2 principles is correct?

    1. Tailoring may relax a principle if the board agrees
    2. Tailoring applies only to processes and not principles
    3. Principles are tailored first and processes afterwards
    4. Tailoring adapts how principles are applied, not whether Correct answer.

    Explanation

    Tailoring changes how the principles are applied in practice, for example the form of products or the frequency of controls. It cannot remove or weaken a principle.

  184. Question 184Tailoring PRINCE2 to the project environment

    How can PRINCE2 processes be tailored?

    1. Processes must always be applied in full
    2. Only the closing a project process can be tailored
    3. Processes can be combined if their purpose is met Correct answer.
    4. Processes can be removed entirely for small projects

    Explanation

    Process activities can be scaled, combined or performed differently as long as the purpose of each process is still achieved. Tailoring processes does not mean abandoning the process purposes.

  185. Question 185Tailoring PRINCE2 to the project environment

    A project has stable, low-risk delivery. How might progress controls be tailored?

    1. Increase reporting to weekly regardless of need
    2. Delegate all progress control to the supplier
    3. Reduce reporting and rely on exception reporting Correct answer.
    4. Remove all stage boundary reports

    Explanation

    Where delivery is stable and low risk, reporting frequency can be reduced and exception-based reporting used, provided the project board still receives the information it needs. Controls should remain proportionate to risk.

  186. Question 186Tailoring PRINCE2 to the project environment

    What is the purpose of tailoring a product description?

    1. To replace the product with a milestone
    2. To remove quality criteria so that work proceeds faster
    3. To avoid using product-based planning
    4. To set purpose, composition and quality criteria Correct answer.

    Explanation

    A product description can be tailored in format and detail, but it should still define the product's purpose, composition and quality criteria. These elements support product-based planning and quality control.

  187. Question 187Tailoring PRINCE2 to the project environment

    What level of documentation should a tailored PRINCE2 project produce?

    1. No documentation if the project is small
    2. The maximum level required by the manual
    3. Exactly the same as a programme would produce
    4. Sufficient to support decisions and control Correct answer.

    Explanation

    Documentation should be sufficient to support decision-making, control and governance for that project, no more and no less. Tailoring allows the form and amount to vary with the project's context.

  188. Question 188Tailoring PRINCE2 to the project environment

    Which tailoring action is appropriate for a small, simple project?

    1. Remove the project board to speed up decisions
    2. Use one stage and combine products sensibly Correct answer.
    3. Drop the lessons log to reduce paperwork
    4. Apply all processes in full to avoid risk

    Explanation

    A small, simple project can use fewer management stages and combine or simplify management products where their purpose is still met. Governance roles and principles are retained.

  189. Question 189Tailoring PRINCE2 to the project environment

    For a large, complex, high-risk project, tailoring should typically do what?

    1. Add controls and assurance proportionate to risk Correct answer.
    2. Use the same approach as a small, simple project
    3. Avoid documenting any of the tailoring decisions
    4. Reduce governance to speed up delivery

    Explanation

    A large, complex or high-risk project usually needs more formality, stronger controls and additional assurance to manage risk. Tailoring remains proportionate, but the proportion is higher.

  190. Question 190Tailoring PRINCE2 to the project environment

    How can project assurance be tailored?

    1. It must always be performed by the project board
    2. It can be replaced by team manager checks
    3. It can be omitted if the project manager is experienced
    4. Its level and frequency can be adjusted to risk Correct answer.

    Explanation

    Project assurance can be tailored in level, frequency and method according to the project's risk and complexity. Its purpose, providing independent assurance to the project board, must still be met.

  191. Question 191Tailoring PRINCE2 to the project environment

    A project must comply with external regulatory standards. How does tailoring handle this?

    1. Regulatory requirements need only be recorded at project closure
    2. Tailoring should build regulations in without dropping principles Correct answer.
    3. External regulatory standards override the PRINCE2 principles
    4. PRINCE2 cannot be used in a regulated environment at all

    Explanation

    Tailoring can incorporate regulatory requirements into the method's products, controls and stages while still applying the PRINCE2 principles. External standards are part of the project environment that tailoring must address.

  192. Question 192Tailoring PRINCE2 to the project environment

    Why should the rationale for tailoring decisions be recorded?

    1. To satisfy the supplier's contractual requirements only
    2. To provide an audit trail and support later review Correct answer.
    3. To replace the business case in the PID
    4. To avoid any project board involvement

    Explanation

    Recording why tailoring decisions were made provides an audit trail and supports review when the project context changes. It also helps demonstrate that the method remains proportionate and principles are still applied.

  193. Question 193Tailoring PRINCE2 to the project environment

    A project is delivered under a fixed-price contract with a supplier. What tailoring consideration applies?

    1. All management products must be produced by the supplier
    2. PRINCE2 principles can be waived in fixed-price contracts
    3. Commercial terms may require stronger supplier controls Correct answer.
    4. The supplier should approve the business case

    Explanation

    Commercial arrangements are part of the project environment and may justify more formal supplier controls, acceptance criteria and reporting. Tailoring must still respect the PRINCE2 principles.

  194. Question 194Tailoring PRINCE2 to the project environment

    When tailoring PRINCE2 roles on a small project, which role must remain independent from the project manager?

    1. Project administrator
    2. Project assurance Correct answer.
    3. Team manager
    4. Project support

    Explanation

    Project assurance provides independent oversight of the project manager's work, so combining the two roles removes the independence that assurance depends on. Other roles, such as project support and team manager, may be combined with the project manager on a small project where the responsibilities can still be fulfilled.

  195. Question 195Tailoring PRINCE2 to the project environment

    A small project is delivered by a single team and has one delivery stage. How can the plans theme be tailored?

    1. Replace plans with a daily task list maintained by the team.
    2. Retain project, stage and team plans at all levels to preserve full control.
    3. Use a project plan and a stage plan, omitting separate team plans. Correct answer.
    4. Use only a team plan and rely on the project manager to monitor progress informally.

    Explanation

    Plans should be proportionate to the size and complexity of the project. Where one team works directly to the stage plan, separate team plans may add little value, but project and stage plans still provide the direction and control the project board needs.

  196. Question 196Tailoring PRINCE2 to the project environment

    A supplier has an established risk process that the project will use. What is the correct tailoring action for the risk theme?

    1. Discard the supplier's process and create a new PRINCE2 risk register.
    2. Rely on the supplier's process without documenting it, since the supplier is responsible for risk.
    3. Confirm the supplier's process meets PRINCE2 risk requirements and document the agreed approach in the risk management approach. Correct answer.
    4. Keep two separate risk processes so that customer and supplier risks are never combined.

    Explanation

    Tailoring can adopt an existing process when it satisfies the PRINCE2 requirements for the theme. The agreed approach should be documented so that everyone understands how risks will be identified, assessed and controlled, and a shared view of risk should be maintained where appropriate.

  197. Question 197Tailoring PRINCE2 to the project environment

    A project expects very few low-impact changes. How should the change theme be tailored while keeping control?

    1. Record changes informally in team meetings only.
    2. Remove change control and let the team absorb changes within normal work.
    3. Require the project board to approve every change, regardless of size.
    4. Use a simple change control procedure with agreed tolerances and a single issue register. Correct answer.

    Explanation

    Change control can be simplified to suit a project with few low-impact changes, but it should not be removed. Agreed tolerances allow appropriate delegated decisions, and a single register keeps changes visible and auditable.

  198. Question 198Tailoring PRINCE2 to the project environment

    A project will follow the organization's established quality management system. How should the quality theme be tailored?

    1. Create a separate project quality system to avoid conflict with corporate standards.
    2. Omit quality control activities because the corporate system already covers them.
    3. Ask the project board to perform all quality reviews personally.
    4. Reference the corporate quality standards in the quality management approach and align product descriptions with them. Correct answer.

    Explanation

    Tailoring should make use of existing organizational standards where they are suitable, while documenting how they apply to the project. Product descriptions should reflect the required quality criteria and methods so that quality control remains specific to the products being delivered.

  199. Question 199Tailoring PRINCE2 to the project environment

    A customer and a supplier from different organizations will jointly deliver a project. What is the most important tailoring consideration for the organization theme?

    1. Project assurance should be shared informally between staff from both organizations.
    2. Both organizations should use identical internal accounting codes.
    3. The roles, responsibilities and interfaces between the organizations should be agreed and documented, including who fulfils project board roles. Correct answer.
    4. The supplier should take all project board roles to ensure accountability.

    Explanation

    In a multi-organizational project, tailoring must clarify how PRINCE2 roles and responsibilities are divided between the parties. Documenting the interfaces and accountabilities helps prevent gaps, overlaps and conflicts between customer and supplier responsibilities.

  200. Question 200Tailoring PRINCE2 to the project environment

    A project team is spread across several time zones. How should the communication management approach be tailored?

    1. Increase the number of project board meetings to compensate for distance.
    2. Rely on informal messages between team members without a documented approach.
    3. Hold all communications in a single weekly meeting at the project manager's local time.
    4. Specify communication methods, frequency, timing and responsibilities that take account of the time zones. Correct answer.

    Explanation

    The communication management approach should define how, when and by whom information will be exchanged, tailored to the needs of the project. For a distributed team, timing, methods and responsibilities need to reflect the practical constraints of different time zones.

PRINCE2 7 Foundation flashcards

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Project definition
A project is a temporary organization created to deliver one or more business products according to an agreed business case, and it introduces change.
Project versus business as usual
Projects are temporary and deliver change, while business as usual is ongoing operational work that maintains existing products and services.
PRINCE2 method structure
PRINCE2 integrates principles, people, practices and processes; it is a flexible method tailored to the project context rather than a rigid sequence of prescribed tasks.
Project context factors
Project context includes organizational strategy, governance, stakeholders, constraints, delivery approach, risk, scale and the external environment in which the project operates.
Continued business justification
A PRINCE2 principle requiring a project to have a justifiable reason to start and to remain justified throughout, with the business case reviewed and updated.
Learn from experience principle
A PRINCE2 principle requiring lessons to be sought, recorded and acted upon throughout the project, not only at closure, to improve performance.
Defined roles principle
A PRINCE2 principle requiring roles, responsibilities and relationships to be defined and agreed so that accountability and decision-making are clear.
Manage by exception
A PRINCE2 principle where tolerances are set for objectives and management action is taken only when a forecast exceeds those delegated limits.
Focus on products
A PRINCE2 principle requiring the project to define and agree products, their quality criteria and acceptance criteria before work is authorized.
PRINCE2 People element
The People element addresses behaviours, relationships and communication needed to lead change, lead teams and collaborate with stakeholders throughout a project.
Stakeholder collaboration
Collaborating with stakeholders involves identifying them, understanding their interests and influence, planning engagement and maintaining communication appropriate to their needs.
Team leadership
Project leadership creates a clear purpose, builds trust, supports collaboration and enables people to take responsibility for delivering agreed products and outcomes.
Communication planning
Communication planning defines what information each audience needs, when and how it will be provided, and how feedback will be obtained and handled.
Emotional intelligence
Emotional intelligence is the ability to recognize and manage one's own emotions and understand others' feelings, supporting constructive relationships and effective stakeholder engagement.
Business case practice
The business case practice establishes mechanisms to judge whether the project is desirable, viable and achievable, and to keep the business case updated.
Organizing practice
The organizing practice defines the project's roles, responsibilities, accountability and relationships, including the project board, project manager and team roles.
Plans practice
The plans practice provides a common framework for planning at project, stage and team levels, including product-based planning and exception plans when tolerances are forecast to be exceeded.
Quality practice
The quality practice defines quality planning, quality control and quality assurance, using product descriptions, quality criteria, reviews and a quality register.
Risk practice
The risk practice manages uncertainty through a risk management approach, risk register, risk appetite and tolerance, and planned responses to threats and opportunities.
Issues practice
The issues practice captures and manages requests for change, off-specifications and problems, using an issue register, issue reports and change control.
Starting up a project
The SU process ensures prerequisites are met, appoints the project board and manager, captures lessons and prepares the project brief and initiation stage plan.
Directing a project
The DP process enables the project board to authorize initiation, the project, stage or exception plans and closure, and to give ad hoc direction.
Initiating a project
The IP process establishes baselines and management approaches, prepares the project initiation documentation and enables the project board to authorize the project.
Controlling a stage
The CS process authorizes work packages, monitors progress, manages issues and risks, reports progress and escalates exceptions to the project board.
Managing product delivery
The MP process covers accepting, executing and delivering a work package, with the team manager ensuring products meet agreed quality criteria.
Managing a stage boundary
The SB process reviews the stage, updates the project plan and business case, prepares the next stage plan and requests project board authorization.
Closing a project
The CP process confirms product acceptance, reviews benefits and lessons, prepares closure and hands over products and responsibilities.
Tailoring PRINCE2
Tailoring applies PRINCE2 appropriately to the project's scale, complexity, risk, organization and delivery approach while retaining all seven principles.
Tailoring management products
PRINCE2 management products can be combined, simplified or adapted; the project should record which products are required and how they will be used.
Tailoring roles
PRINCE2 roles can be combined or shared in smaller projects, but accountability must remain clear and project board responsibilities must not be bypassed.
Tailoring and principles
Tailoring may change practices, processes, roles and documentation, but it must not remove or weaken the seven PRINCE2 principles.
Tailoring documentation
Tailoring decisions should be documented, agreed by the project board and reflected in the project initiation documentation and management approaches.

PRINCE2 7 Foundation study guide

Projects and the PRINCE2 project context

What makes work a project

PRINCE2 defines a project as a temporary organisation created to deliver one or more business products according to an agreed business case. That definition carries the characteristics examiners test: projects are temporary (defined start and end), unique (a defined set of products), cross-functional, uncertain, and they exist to bring about change. Work that repeats indefinitely is business as usual, not a project.

Where projects sit

A project is usually part of a wider context: a programme (coordinated projects delivering business change and outcomes), a portfolio (the organisation's total investment), or a standalone project commissioned by a customer. Separate the customer (specifies the products and the benefits sought) from the supplier (provides resources and delivery expertise).

The PRINCE2 framework

PRINCE2 is a framework made up of seven principles, seven practices and seven processes, supported by guidance on people and on the project context, including linear/sequential, iterative/agile and hybrid ways of delivering. It is not a prescribed method to be applied literally.

Traps: descriptions of routine operational activity presented as projects; questions implying PRINCE2 is 'one size fits all'; confusing programme management (outcomes, business change) with project management (outputs and products).

Rule of thumb: if you cannot write a business case for the work, and it has no defined end, it is business as usual - not a project.

PRINCE2 principles

The seven principles

The principles are the universal, enduring obligations of a PRINCE2 project: continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, and tailor to the environment. They are the reason PRINCE2 works, and they are what makes an approach 'PRINCE2'.

They are universal (they apply to every project, whatever its size, type or delivery approach), self-validating (proven in practice over decades) and empowering (they give people confidence to shape the method).

Applying them in practice

Each principle has a visible consequence. Continued business justification means a viable business case that is reviewed and updated at stage boundaries and whenever a significant issue arises. Learn from experience means lessons are sought at the start, recorded in the lessons log, and acted on - not just collected at the end. Manage by exception means tolerances are set so that only exceptions escalate. Focus on products means the plan is product-based and quality is defined against product descriptions.

Traps: questions suggesting principles may be selected ('apply at least five'), reduced or tailored away. Principles are not tailored - only the practices and processes are adapted to the environment. Another trap is claiming lessons are captured only at closure, or that the business case is written once and never revisited.

Worked example: a project with no approved business case, or one whose business case is never re-checked, fails continued business justification - so it is not being run according to PRINCE2, however many documents it produces.

People

Why people get their own guidance

Projects are delivered by people, and most project failures are traced to behaviour, communication and change resistance rather than technique. The People guidance in PRINCE2 therefore sits alongside the principles and practices and is applied through all of them; it is not a practice and not a process, so questions that call it one are wrong.

The areas to know

Organisational change management - understand that change affects individuals differently; people move through stages of reaction to change and need information, involvement and support to adopt it. Leadership and team management - adapt style to the team's competence and commitment (situational leadership); a project manager coordinates, while a leader builds commitment. Communication - communication is two-way and needs a sender, a receiver, a message and a feedback loop; barriers include jargon, culture, distance, filtering and assumed understanding. Stakeholder engagement - identify stakeholders, analyse interest and influence, and plan engagement; this is documented in the communication management approach.

Traps: treating People as a seventh practice; assuming communication has happened because a report was issued; assuming conflict is always destructive; confusing the project manager's people responsibilities with the project board's direction role.

Rule of thumb: match communication to the stakeholder - high influence and high interest gets active, regular, two-way engagement; low interest gets minimal, efficient updates.

PRINCE2 practices

The seven practices

Business case (why), organising (who), plans (what, how much, when), quality (what does good look like), risk (what if), issues (what is happening now), and progress (where are we now, where going next). Each has a purpose, an approach tailored to the project, roles and responsibilities, and a set of management products.

Points examiners press

  • Issues covers all concerns: a change request is a type of issue, but not every issue is a change. The issue register and lessons log sit here.
  • Risk distinguishes cause, event and effect; the risk owner is accountable for managing the risk, the risk actionee carries out the response. Risks are not only threats.
  • Quality distinguishes quality planning (product descriptions, quality criteria, quality methods), quality control (reviews, testing) and quality assurance (independent checking of the quality process).
  • Progress owns the checkpoint report, highlight report, end stage report, end project report and daily log, plus tolerances and exception escalation.
  • Plans distinguishes project, stage and team plans, and uses product-based planning (product breakdown, product descriptions, product flow diagram).

Traps: putting lessons in the risk register; calling the project manager the risk owner; treating the daily log as an issues practice product; confusing project assurance with quality assurance.

Worked example: a supplier requests an extra two weeks. It is an issue (a request for change), recorded in the issue register and assessed for impact on the business case, plan, risks and quality before being escalated against tolerances - it is not simply a scheduling note.

PRINCE2 processes

The seven processes

Starting up a project (pre-project: appoint the executive and project manager, capture lessons, outline business case, choose the project approach, assemble the project brief, plan initiation) → Directing a project (authorise initiation, the project, each stage or exception plan, give ad hoc direction, authorise closure) → Initiating a project (refine the business case, set up controls, create the project plan, prepare the approaches, assemble the PID) → Controlling a stage → Managing product delivery → Managing a stage boundary → Closing a project.

Key ownership: the project board directs, the project manager controls the stage, the team manager manages product delivery. Controlling a stage includes authorising work packages, monitoring, reviewing stage status, reporting highlights, capturing and examining issues and risks, escalating, and taking corrective action. Managing a stage boundary plans the next stage, updates the project and business case, reports stage end, and produces exception plans; it is not used at the end of the final stage, where closing a project applies.

Traps: mixing up which process creates which product - project brief (starting up), PID (initiating), work package (controlling a stage/managing product delivery), highlight and exception reports (controlling a stage), end project report and lessons report (closing). Also, directing a project runs throughout; it is not a one-off.

Worked example: the project manager forecasts a breach of stage tolerances. She escalates an exception report to the project board, which may authorise an exception plan produced during managing a stage boundary.

Tailoring PRINCE2 to the project environment

Tailoring is a principle, not an option

'Tailor to the environment' is one of the seven principles, so every PRINCE2 project must be tailored - but only the practices and processes are adapted; the principles always apply in full. Tailoring happens at two levels: the organisation may define a standard approach, and the project then tailors that further to its size, scale, complexity, risk, delivery approach and governance constraints.

What gets tailored

Products (combine, simplify or omit management products where justified), processes (activities may be combined or done concurrently; some may be delegated), roles (one person may hold more than one role on a small project), terminology, and the delivery approach (linear, iterative/agile or hybrid). Tailoring decisions are recorded - typically in the project initiation documentation - and revisited as the project evolves; tailoring is continuous, not a one-off at start-up.

Traps: questions that treat tailoring as 'removing what you dislike' or as permission to skip principles; questions implying tailoring is decided only by the project manager without project board involvement (the board approves the approach via the PID); confusion between organisational-level tailoring and project-level tailoring.

Rule of thumb: combine roles where practical, but never let one person hold both project manager and project assurance - assurance must be independent of the work it checks. Likewise keep the project board's accountability distinct from the project manager's.

Worked example: a three-month, low-risk, single-team project may run one delivery stage, combine the project manager and team manager roles, and use a two-page business case - while still maintaining a business case, tolerances, defined roles and product-focus.

PRINCE2 7 Foundation cheat sheet

Quick reference

Projects and the PRINCE2 project context

  • A project is a temporary organization created to deliver one or more business products according to an agreed business case.

  • Projects are characterized by change, temporary duration, uniqueness, cross-functional involvement and uncertainty.

  • Business as usual is ongoing operational work that maintains existing products and services; projects deliver change and then hand over.

  • PRINCE2 integrates principles, people, practices and processes, and it is tailored to the project context.

  • Project context includes organizational strategy, governance, stakeholder expectations, constraints, delivery approach, risk and scale.

  • PRINCE2 recognizes business, user and supplier stakeholder interests; the business case should balance them.

  • Project management is planning, delegating, monitoring and controlling all aspects of the project and motivating those involved to achieve objectives.

  • A project's objectives cover time, cost, quality, scope, benefits and risk; tolerances are set for these.

Quick reference

PRINCE2 principles

  • PRINCE2 has seven principles: continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, and tailor to suit the project environment.

  • Principles are universal, self-validating and empowering; they must be applied for a project to be managed according to PRINCE2.

  • Continued business justification requires a justifiable reason to start and evidence that the project remains justified.

  • Learn from experience requires lessons to be sought, recorded and acted upon throughout the project.

  • Defined roles and responsibilities require roles, responsibilities and relationships to be agreed and understood.

  • Manage by stages requires at least two management stages: an initiation stage and at least one further stage.

  • Manage by exception sets tolerances for objectives and escalates only when forecast performance exceeds delegated limits.

  • Focus on products requires products, quality criteria and acceptance criteria to be defined before work is authorized.

  • Tailor to suit the project environment adapts the method to scale, complexity, risk and organizational context.

Quick reference

People

  • People is a PRINCE2 element that addresses behaviours, relationships and communication in projects.

  • Effective stakeholder collaboration includes identifying stakeholders, analysing interests and influence, planning engagement and maintaining communication.

  • Communication planning defines audiences, information needs, timing, channels, responsibilities and feedback mechanisms.

  • Project leadership creates purpose, builds trust, supports collaboration and enables accountability.

  • Emotional intelligence supports self-awareness, empathy and relationship management in project teams.

  • Change affects people; successful change requires clear purpose, engagement and support for those affected.

  • Team effectiveness depends on clear roles, shared objectives, appropriate skills and constructive working relationships.

  • Culture, values and behaviour influence how teams communicate, make decisions and respond to change.

Quick reference

PRINCE2 practices

  • The seven practices are business case, organizing, plans, quality, risk, issues and progress.

  • Business case practice judges whether the project is desirable, viable and achievable and keeps the business case updated.

  • Organizing practice defines roles, responsibilities, accountability and relationships, including project board and team roles.

  • Plans practice provides project, stage and team plans; product-based planning defines products before activities.

  • Quality practice covers quality planning, quality control and quality assurance, using product descriptions and a quality register.

  • Risk practice uses a risk management approach, risk register, risk appetite, tolerances and responses to threats and opportunities.

  • Issues practice manages requests for change, off-specifications and problems through an issue register and change control.

  • Progress practice uses tolerances, checkpoints, highlight reports, end stage assessments and exception reports.

  • Practices are tailored to the project; management products can be combined or simplified if the principles are maintained.

Quick reference

PRINCE2 processes

  • PRINCE2 has seven processes: starting up a project, directing a project, initiating a project, controlling a stage, managing product delivery, managing a stage boundary and closing a project.

  • Starting up a project ensures prerequisites, appoints the project board and project manager, captures lessons and prepares the project brief.

  • Directing a project enables the project board to authorize initiation, the project, stage or exception plans and closure.

  • Initiating a project establishes baselines and management approaches and prepares the project initiation documentation.

  • Controlling a stage authorizes work packages, monitors progress, manages issues and risks, and escalates exceptions.

  • Managing product delivery covers accepting, executing and delivering work packages to agreed quality criteria.

  • Managing a stage boundary reviews the stage, updates the project plan and business case, and prepares the next stage plan.

  • Closing a project confirms product acceptance, reviews benefits and lessons, and prepares handover and closure.

  • Process activities transform inputs into outputs; they can be tailored, but the principles must still be applied.

Quick reference

Tailoring PRINCE2 to the project environment

  • Tailoring is the PRINCE2 principle that adapts the method to the project environment.

  • Tailoring considers scale, complexity, risk, duration, organizational standards, stakeholders and delivery approach.

  • Tailoring may change practices, processes, roles, terminology and management products.

  • Tailoring must not remove or weaken any of the seven PRINCE2 principles.

  • Management products can be combined, simplified or adapted; the project records which products are required.

  • Roles can be combined or shared in smaller projects, but accountability and project board responsibilities remain.

  • Tailoring decisions are documented, agreed by the project board and reflected in the project initiation documentation.

  • Agile delivery can be tailored with timeboxes, prioritized requirements and iterative development while retaining PRINCE2 governance.

PRINCE2 7 Foundation key terms

Project

A temporary organization, with a defined start and end, that is created to deliver one or more business products in line with an agreed business case.

Related: Programme, Business case, Project board
Programme

A group of related projects and other work managed together in a coordinated way to achieve outcomes and benefits that could not be realized if each project were managed separately.

Related: Portfolio, Project
Portfolio

The collection of an organization's projects, programmes and other work, managed together so the organization can prioritize investment, balance risk and allocate finite resources across that work.

Related: Programme, Project environment
Project environment

The internal and external surroundings in which a project operates, including strategy, culture, governance, stakeholders, technology, regulation and market conditions, all of which influence how the project is run.

Related: Tailoring, Portfolio
Continued business justification

The principle that a project must have a documented, valid reason to continue, and that this justification is reviewed and re-confirmed at every decision point rather than assumed to remain true.

Related: Business case, Manage by exception
Learn from experience

The principle that teams seek out and apply knowledge from earlier work and from their own project, taking time to reflect and feed lessons into decisions throughout.

Related: Lessons log, Managing a stage boundary
Defined roles and responsibilities

The principle that every project must have a clear, agreed structure of roles, with responsibilities and decision rights understood and used, matched to the project's size and complexity.

Related: Project board, Project manager
Manage by exception

The principle of delegating authority within pre-agreed tolerances so that only deviations beyond those limits are escalated to the next management level for a decision.

Related: Tolerance, Exception
Focus on products

The principle that the project defines and agrees what it must deliver, including its products, quality criteria and scope, before planning the activities needed to create them.

Related: Product description, Work package
Tailor to the environment

The principle that PRINCE2 is adapted in depth and rigour to suit the project's size, complexity, risk, importance and its organizational and commercial setting.

Related: Tailoring, Delivery approach
Stakeholder

Any individual, group or organization with an interest in, influence over, or exposure to the project's activities and outcomes, whether that interest is positive, negative or neutral.

Related: Stakeholder engagement, Communication management approach
Stakeholder engagement

The planned work of identifying stakeholders, analysing their interests and influence, and communicating with and involving them so they support the project and its outcomes.

Related: Stakeholder, Communication management approach
Leadership

The behaviour of influencing, motivating and enabling people to commit to and deliver project objectives, providing direction and support rather than only administering tasks and paperwork.

Related: Stakeholder engagement, Project manager
Communication management approach

A management product that sets out who needs project information, what they need, when and in what form it will be provided, and who is responsible for sending it.

Related: Stakeholder engagement, Stakeholder
Business case

A practice and its key management product: the practice establishes whether the project is desirable, viable and achievable, and the product records the reasons for the project and the justification for continued investment.

Related: Continued business justification, Executive, Benefits management approach
Benefits management approach

A management product that defines how and when the project's benefits will be measured, who is responsible for each, and how outcomes will be reviewed after the project closes.

Related: Business case, Senior user
Project board

The accountable management group for the project, made up of the executive, senior users and senior suppliers, which directs the project, takes key decisions and authorizes each stage.

Related: Executive, Senior user, Senior supplier
Executive

The single owner of the business case on the project board, accountable for the project's justification and overall direction and for ensuring it delivers the intended outcomes.

Related: Business case, Project board
Senior user

A project board role representing those who will use the project's products, specifying their needs and expected benefits and monitoring that the delivered solution meets them.

Related: Business case, Benefits management approach
Senior supplier

A project board role representing the parties who build the products, accountable for the technical and commercial feasibility of what is delivered and for committing supplier resources.

Related: Work package, Project board
Project manager

The role responsible for the day-to-day management of the project within the tolerances set by the project board, planning the work, allocating it and reporting progress.

Related: Work package, Highlight report, Tolerance
Tolerance

The agreed amount of deviation permitted from planned targets for time, cost, scope, quality, benefits and risk before the deviation must be reported as an exception.

Related: Exception, Manage by exception
Exception

A situation where it becomes clear that planned targets or the project's business justification will be, or may be, breached beyond agreed tolerances, requiring escalation for a decision.

Related: Exception plan, Tolerance
Management stage

A section of the project for which the project board authorizes work and funds in advance, and at the end of which progress and continued justification are reviewed.

Related: Controlling a stage, Managing a stage boundary
Exception plan

A plan produced to replace the remainder of a stage or project plan after an exception, showing how the work will recover to agreed tolerances and submitted for board approval.

Related: Exception, Managing a stage boundary
Product description

A statement of the purpose, composition, quality criteria, quality methods and source of a single product, used to plan and control the work needed to create it.

Related: Acceptance criteria, Work package
Acceptance criteria

The measurable conditions that the project's final products must satisfy for the users and the business to accept them as fit for purpose.

Related: Product description, Project brief
Lessons log

A running record of lessons identified during the project, together with the actions taken in response, used to inform current decisions and summarized for others later.

Related: Learn from experience
Risk register

The record of identified risks, each with its cause, potential effect, assessment, owner and planned response, kept up to date throughout the project.

Related: Issue register
Issue register

The record of issues raised on the project, showing for each its description, severity, owner, current status and the corrective action or change decided.

Related: Exception, Risk register
Project brief

The short document produced while starting up a project that sets out the project's purpose, outline business case, project product description and delivery approach, and is used to authorize initiation.

Related: Project initiation documentation, Business case
Project initiation documentation

The document produced during initiating a project that brings together the project's justification, scope, products, plans, approaches and governance arrangements, forming the basis for board authorization.

Related: Project brief, Business case
Work package

An instruction from the project manager to a team describing the products to be produced, the constraints, tolerances, quality checks and reporting required for a defined piece of work.

Related: Product description, Checkpoint report
Highlight report

A report from the project manager to the project board at agreed intervals, summarizing progress during a stage against the stage plan, together with forecasts, risks and issues.

Related: Controlling a stage, Project board
Checkpoint report

A regular progress report from a team manager to the project manager describing work completed, products and quality checks done, and any issues or deviations from the work package.

Related: Work package, Highlight report
Controlling a stage

The process in which the project manager directs and monitors the work within a stage, authorizing work packages, dealing with issues and reporting progress to the board.

Related: Management stage, Highlight report
Managing a stage boundary

The process in which the project manager prepares the next stage, reviews the current stage's performance and continued justification, and seeks board approval to proceed.

Related: Management stage, Exception plan
Tailoring

The deliberate adaptation of PRINCE2's practices, processes and management products, including their use, depth and formality, to fit a project's situation while keeping the principles intact.

Related: Tailor to the environment, Delivery approach
Delivery approach

The approach chosen for creating the project's products, such as a predictive, agile or hybrid way of working, selected according to the nature of the solution and the environment.

Related: Tailoring, Project brief

PRINCE2 7 Foundation study plan

8 weeks · About 7 hours per week

Week 1

PRINCE2 practices

  • Define the purpose, minimum requirements and key management products for each of the seven PRINCE2 practices.

  • Match every practice to the project roles that are accountable or responsible for its products.

  • Explain how the business case practice enables continued business justification throughout a project.

  • Draft a personal reference card for each practice using only your own wording.

Your checkpoint

Seven self-written practice reference cards, each covering purpose, minimum requirements, key products and accountable roles, produced without consulting notes on the final pass.

Week 2

PRINCE2 practices & Projects and the PRINCE2 project context

  • Apply the organizing and plans practices to an invented project scenario and identify at least three role conflicts to resolve.

  • Distinguish project work from business as usual using three examples drawn from your own organization.

  • Describe each aspect of project performance and name the PRINCE2 products that report on it.

  • Label the integrated elements of the PRINCE2 framework with the products, roles and documents that sit within each.

  • Answer 15 practice questions on practices and project context and log the reasoning behind each wrong answer.

Your checkpoint

A one-page framework map linking the integrated elements to the seven practices, accompanied by a scored 15-question practice set with written corrections.

Week 3

Projects and the PRINCE2 project context & PRINCE2 principles

  • State all seven principles from memory and give one worked example of each being applied and one of each being breached.

  • Explain how the principles constrain tailoring without dictating specific techniques or documentation.

  • Describe how project scale, complexity, commercial arrangements and organizational setting change the way PRINCE2 is applied.

  • Compare the project management team structure for a small low-risk project with that of a large multi-team project, justifying each difference.

Your checkpoint

A principles table with applied and breached examples for all seven principles, plus a two-column comparison of team structures for a small and a large project.

Week 4

PRINCE2 principles & People

  • Describe how each project management team role contributes to leading, delegating and communicating within a project.

  • Identify stakeholder engagement activities and assign them to the roles that own them across the project lifecycle.

  • Resolve five workplace-style scenarios in which team behaviour, communication or role ambiguity threatens project progress.

  • Complete a timed 60-question mock on domains 1 to 4 and analyse every incorrect answer down to the underlying fact missed.

Your checkpoint

A timed 60-question mock (domains 1 to 4) scored and fully reviewed, with a ranked list of your five weakest topics and a written correction for each.

Week 5

People & PRINCE2 processes

  • Sequence the seven processes and the activities within each from memory.

  • Describe the purpose, key inputs, key outputs and decision points of starting up a project, directing a project and initiating a project.

  • Map which project board decisions trigger movement between the early processes and who is responsible for each product.

  • Explain how the people element influences the way stages are authorised and work is delegated.

Your checkpoint

A hand-drawn process diagram showing all seven processes, their activities and the management products that trigger each transition, annotated with the roles involved.

Week 6

PRINCE2 processes & Tailoring PRINCE2 to the project environment

  • Describe the activities and products of controlling a stage, managing product delivery, managing a stage boundary and closing a project.

  • Explain the tailoring guidance supplied for each of the seven processes.

  • Separate what may legitimately be tailored from what must never be changed.

  • Justify tailoring decisions for a small low-risk project and for a large high-risk project across all seven processes.

Your checkpoint

A tailoring justification document covering all seven processes for two contrasting scenarios, with a one-line rationale for every adaptation made.

Week 7

PRINCE2 practices & Tailoring PRINCE2 to the project environment

  • Tailor each of the seven practices for a scenario by choosing between embedded, scaled and simplified options and justifying the choice.

  • Explain how PRINCE2 is adapted when the project sits inside a programme or a multi-project environment.

  • Re-test the two weakest topics identified in week 4 and confirm they are closed out.

  • Answer 40 tailoring and practice questions under time pressure and rewrite notes for any concept missed.

Your checkpoint

A 40-question tailoring and practices set scored at 80% or above, plus rewritten summary notes for every missed concept.

Week 8

PRINCE2 processes & Tailoring PRINCE2 to the project environment

  • Complete two full timed mock exams covering all six domains and score each against your week 4 baseline.

  • Redraw the seven-process model and the seven-practice card set from memory without prompts.

  • Convert every remaining recurring error into a single-line memory rule and rehearse those rules aloud.

  • Confirm exam-day logistics: question pacing, flag-and-return strategy and time allocation per question.

Your checkpoint

Two completed timed mocks at 75% or above, plus a one-page 'final rules' sheet containing every recurring error turned into a memory cue.

Milestones

Week 2: You can state the purpose and minimum requirements of all seven practices without notes, and score at least 75% on a 15-question practices and context set.

Week 4: You score at least 70% on a timed 60-question mock covering domains 1 to 4 and can explain the reason behind every incorrect answer you gave.

Week 6: You can draw the complete process model from memory and justify at least one tailoring decision for each of the seven processes in both a small and a large scenario.

Week 8: You score 75% or above on two consecutive full timed mocks and have no open review items left on your weak-topic list.

PRINCE2 7 Foundation exam day

Your checklist

Valid government-issued photo ID

Bring the original ID you booked with; the name must match your registration exactly. Accepted document types vary by location and delivery method - confirm the list with the provider before exam day (needs_review).

Booking confirmation and login details

Have your candidate/registration number and the username and password for your exam-institute account to hand; you may need them at check-in. Write them on paper only if the provider permits it, otherwise memorise them.

Reliable internet connection with a backup plan

For an online-proctored sitting, run the provider's system/equipment test in advance. Have a phone hotspot or a second network available as a fallback, and know the provider's support number in case of a technical failure.

Webcam, microphone and speakers/headset that work

Test all three before the exam. Headset and earphone rules differ between providers and sittings - confirm whether they are permitted at your sitting (needs_review).

Private, quiet, well-lit room with a clear desk

The proctor must be able to see you, your hands and the desk surface. Remove papers, books, sticky notes, second screens and any wall charts - this is a closed-book exam.

Computer that meets the provider's system requirements

Close all other applications, disable notifications and pop-ups, and stop any syncing or backup software before you launch the exam. Check whether a second monitor must be disconnected.

Mains power or a fully charged device

Plug in the laptop or ensure the battery comfortably exceeds the exam duration so a power loss cannot end your sitting.

Knowledge of the exam format

60 multiple-choice questions in 60 minutes, closed book, one mark per question, pass mark 55% (33 of 60). Knowing this lets you pace at roughly one minute per question.

Completed at least one timed mock under exam conditions

Do this in the final days so that timing, question style and the 'best answer' phrasing feel familiar rather than new on the day.

Read the provider's candidate handbook / exam instructions

It contains the current rules on ID, room conditions, permitted items, technical failure procedure and results. Rules change, so read the version issued with your booking rather than relying on second-hand advice.

Arrive/log in early

Plan to be ready well before the start time to allow for identity checks and room scans. Confirm the exact check-in window with the provider (needs_review).

Water in a clear container (only if permitted)

Some providers allow a clear glass or bottle, others do not. Confirm the rule for your sitting; if in doubt, do without (needs_review).

Plan the day

72 hours before

Confirm the date, start time and time zone of your sitting, and check that your ID is valid and unexpired. Run the provider's system test on the exact machine and network you will use. Read the candidate handbook once more. Sit one full timed mock, then spend remaining time on weak areas - typically the purpose of each principle, the theme-to-process mapping, and the management products and role responsibilities.

72 hours before (revision focus)

Prioritise understanding 'which role does this' and 'which process does this happen in' style questions, plus the business case, product-based planning and the tailoring concept. Do not start new topics in the last 24 hours.

24 hours before

Do light revision only: one summary sheet of definitions and the seven principles. Prepare the room and desk, charge and test equipment, lay out your ID, and note the support phone number. Check traffic or travel plans if attending a test centre. Eat properly, set two alarms, and get a full night's sleep - recall matters more than one extra hour of cramming.

Morning of the exam

Eat and hydrate. Clear the desk again, switch off and put away your phone and any smartwatch, close all applications, and shut the door to the room. Log in early with your ID ready, complete the identity check and room scan calmly, and keep a single sheet of notes nearby only if you will use it before check-in - nothing may be used once the exam has begun.

During the exam - first pass

Work at about one minute per question. Read the whole stem before the options, identify what is being asked (BEST, FIRST, TRUE, which role, which process), and eliminate clearly wrong options. Answer every question as you go; there is no negative marking for a wrong answer, but a blank scores zero.

During the exam - handling difficulty

If a question takes much longer than a minute, flag it and move on. Use the review screen at the end to return to flagged items with fresh eyes. Keep an eye on the clock at the halfway point - you should be around question 30.

Final minutes

Use the last five to ten minutes to confirm no question is unanswered and to revisit flagged items. Change an answer only when you have a clear reason; first instincts on well-revised material are often right. Submit and note any provisional result shown on screen.

Rules to check

  • This is a closed-book exam: no notes, textbooks, printed aids, phone apps or reference material of any kind may be used during the sitting.

  • Present valid photo ID whose name matches your booking. Accepted ID types vary - confirm the list with the provider in advance and bring the original, not a photocopy.

  • No one else may be in the room and you must not communicate with anyone during the exam. In an online-proctored sitting, stay within camera view and do not leave the desk without the proctor's permission.

  • Mobile phones, smartwatches and other devices must be switched off and out of reach for the duration, even if you are not using them.

  • There is normally no scheduled break in a 60-minute exam, and the clock does not stop. Confirm the break policy with your provider if you have any concern.

  • Every question carries one mark and there is no negative marking, so answer all 60 questions - a blank and a wrong answer score the same only if you leave it blank, so always guess if necessary.

  • The pass mark is 55% (33 of 60 correct). Results are usually displayed or issued provisionally after submission, with the formal record available through the provider's candidate account.

  • If you need extra time or another reasonable adjustment (for example, because the exam is not in your first language), request it from the provider well before the exam date; eligibility and permitted allowances are set by the provider - confirm the current policy with them.

PRINCE2 7 Foundation FAQ

How many PRINCE2 7 Foundation practice questions are available?

The practice set has 200 PRINCE2 7 Foundation questions. Each one includes the choices, the correct answer, and an explanation, and the set is free to read with no signup.

How many PRINCE2 7 Foundation flashcards are available?

The flashcard set has 32 PRINCE2 7 Foundation cards. Each card shows the term and its definition.

Which topics does the PRINCE2 7 Foundation study material cover?

The PRINCE2 7 Foundation study material has 6 sections, including Projects and the PRINCE2 project context, PRINCE2 principles, and People.

What format facts does the catalog list for the PRINCE2 7 Foundation exam?

The catalog lists these item types: multiple choice for the PRINCE2 7 Foundation exam.