PMI-RMP Practice Test

PMI Risk Management Professional (PMI-RMP)®

PMI-RMP overview

  • 200 practice questions
  • 32 flashcards
  • 6 study guide topics
  • 40 key terms

What you'll study

  • Risk Strategy and Planning17%
  • Stakeholder Engagement17%
  • Risk Identification17%
  • Risk Analysis17%
  • Risk Response Implementation16%
  • Risk Monitoring and Reporting16%

The PMI Risk Management Professional (PMI-RMP)® is one of PMI's specialized certifications, positioned alongside credentials such as the PMP®, CAPM®, and PMI-ACP® in PMI's certification catalogue. PMI's own description of the credential is that it lets a practitioner "demonstrate your skills to spot threats early, master risk management, and lead projects to success" - framing it as a specialist credential rather than a general project management one. PMI lists the experience expectation as 3-5 years, so the target audience is a practitioner who has already handled risk work on real projects and wants that expertise formally recognized, often someone whose role is explicitly risk-focused rather than a general project manager. The exam blueprints risk work across six areas: risk strategy and planning, stakeholder engagement, risk identification, risk analysis, risk response implementation, and risk monitoring and reporting. That spread matters for study design - the exam is not a vocabulary test on risk terminology but a test of how you sequence and adapt risk processes across a project's life. Preparation should combine a structured pass through those six areas with heavy practice on scenario-based multiple-choice items, where the work is choosing the best next action rather than recalling a definition. This page is independent study material and is not affiliated with or endorsed by PMI; confirm all exam logistics directly with PMI before booking.

Common mistakes

When a scenario opens a new project or phase, the candidate immediately picks 'identify risks' or 'create the risk register' as the next action, without first checking whether risk appetite, tolerances/thresholds, probability-and-impact definitions, the RBS, and risk roles have been agreed.

The exam's 'what should the project manager do next' stems reward sequence, and identification feels like the obvious first risk activity. Candidates also carry over the habit of treating the risk register as the deliverable of risk management, so they skip the planning decisions that make scoring and prioritisation meaningful.

What to do instead

Before answering any sequencing question, ask yourself: 'Do agreed thresholds and scoring scales exist?' If the scenario shows no tolerance or scale, the correct option is almost always to establish it with the sponsor and key stakeholders. Memorise the order: tailor the approach and define appetite/scales → identify → analyse → plan responses → implement → monitor.

The candidate answers risk-methodology questions with boilerplate - applying a full quantitative Monte Carlo programme to a small, low-complexity project, or using a generic template RBS and register without reference to the delivery approach, contract type, or organisational process assets in the scenario.

Templates are easy to recall and feel 'PMI-correct'. The exam, however, tests tailoring: the environment described (fixed-price contract, agile delivery, regulatory oversight, immature data) is supposed to change the answer.

What to do instead

For every methodology question, extract two things from the stem: the delivery/contract context and the maturity of available data. Large, data-rich, high-stakes → quantitative analysis and detailed reserves. Small, data-poor, fast-moving → qualitative analysis, light documentation, frequent review. If an option ignores the stated context, eliminate it.

Faced with a stakeholder who is uneasy about a risk or has a different tolerance, the candidate selects 'escalate to the sponsor', 'send the risk report to the stakeholder', or 'update the stakeholder register' instead of choosing to meet the stakeholder and understand and address the concern. Similarly, the candidate lets the sponsor be named risk owner for risks the team can own.

Escalation and documentation are visible, defensible actions, so they feel safe under exam pressure. Candidates also confuse 'keeping stakeholders informed' with 'engaging stakeholders', and confuse the risk owner (accountable for managing the risk) with the person performing the response action.

What to do instead

Rank options by directness: talk to the affected stakeholder first, escalate only when authority or tolerance is genuinely exceeded, and report only after the interaction. When assigning ownership, pick the person with the authority and proximity to manage the risk - usually not the sponsor unless the risk is project- or programme-level.

Register entries are written as causes ('the vendor is new'), as effects ('the schedule slips'), or as issues already happening, rather than as a structured cause → uncertain event → effect statement with an assigned owner and a defined trigger.

Natural language descriptions of worries read like risks, and under time pressure candidates accept any negative-sounding statement as a valid risk. Issues versus risks is the single most common conceptual blur in risk work.

What to do instead

Apply a two-second test to every risk in a stem: is it uncertain (may or may not happen) and does it have a cause and a consequence? If it is already happening, it belongs in the issue log and needs an issue response, not a risk response. When a question asks which register entry is best, choose the one with cause, uncertain event, effect, owner, and trigger.

The candidate treats identification as a single early event - relying on brainstorming alone, and not re-running identification after a change request, phase gate, or major assumption failure. Assumptions and constraints are also left unexamined as risk sources.

Most study material presents identification as one process step with one technique, so candidates don't build the reflex that new information generates new risks. Assumption analysis feels like a planning chore rather than a risk technique.

What to do instead

When a stem mentions a change, a gate, or a surprise, look first for options that re-identify risks. Remember the technique toolkit as a checklist you can scan: brainstorming, interviews, Delphi, checklists, assumption and constraint analysis, SWOT, prompt lists, and document review - then pick the one matched to the situation (e.g., Delphi when experts are dispersed and you need anonymity and consensus).

The candidate selects 'perform quantitative risk analysis' for a newly identified, clearly minor risk, or selects 'perform qualitative analysis' when the decision at hand is a major bid/no-bid or reserve-setting call with good data available.

Quantitative analysis sounds more rigorous, so it is picked as the 'more professional' answer. Candidates also forget that the two processes answer different questions: prioritisation versus numerical effect on objectives.

What to do instead

Match the technique to the decision: if the question is 'which risks deserve attention', the answer is qualitative (probability-impact matrix, urgency assessment). If the question is 'how much contingency, or which of two options is worth more', and data exists, the answer is quantitative (decision tree, EMV, sensitivity/tornado, Monte Carlo). If data is insufficient, the fix is to improve the data or proceed qualitatively - not to force a model.

Arithmetic and concept errors in expected monetary value work: summing probabilities instead of weighting impacts, forgetting to net out investment cost in a decision tree, treating EMV as the amount to hold as reserve, and confusing contingency reserve with management reserve.

EMV questions are the only heavily numeric items on the exam, and candidates practise the formula but not the interpretation, so they compute a number and then select the wrong reserve or decision from it.

What to do instead

Write the branches out: EMV of an option = sum of (probability × impact), then subtract the cost of the option before comparing. Contingency reserve covers identified risks and is derived from the analysis (EMV or simulation); management reserve covers unidentified, in-scope-but-unplanned work and sits with the sponsor. If a stem describes an unknown-unknown, the reserve is management reserve.

Response strategy selection is fuzzy: 'transfer' is chosen for risks whose probability cannot be shifted to a third party, 'avoid' is chosen when only the impact is being reduced, and 'accept' is chosen as a default rather than as a deliberate, documented decision for a risk that cannot be economically addressed.

The strategies overlap in everyday speech, so candidates match on the words in the stem rather than on the mechanism. Acceptance also feels like the low-risk option when the candidate is unsure.

What to do instead

Classify by mechanism before reading options: eliminate the cause or the exposure entirely = avoid; reduce probability and/or impact = mitigate; move the financial consequence (not the accountability) to a third party = transfer (insurance, warranty, fixed-price contract); deliberately retain with no action = accept (active acceptance means a contingency plan and reserve); share with a partner who is best able to manage it = exploit/share for opportunities. Then check the option actually changes that mechanism.

Responses are chosen without being made operational: no named response owner, no budget or schedule in the plan, no trigger defined, and no distinction between a contingency plan (planned, for an identified risk), a fallback plan (if the contingency fails), and a workaround (unplanned, for an issue that has occurred). Secondary and residual risks from the chosen response are ignored.

The exam often asks 'what should the project manager do next' right after a response is selected, and candidates jump straight to 'implement the response' or 'update the register' instead of the step that makes it executable. The three plan types are memorised as definitions but not applied.

What to do instead

After choosing a strategy, the next action is to make it actionable: assign the response owner, secure resources and authority, integrate it into the cost and schedule baselines, and define the trigger and contingency/fallback. Then re-analyse for secondary risks created by the response and residual risk left after it - if either is material, that is the answer.

Risk monitoring is reduced to 'update the risk register'. The candidate does not distinguish updating risks from re-evaluating them, from auditing the risk process, and does not think of reserve analysis, variance and trend analysis, or technical performance measurement as monitoring tools when a stem describes drift in cost, schedule, or reserve consumption.

Updating the register is always plausible, so it becomes the default answer for any monitoring question. Candidates also under-learn the tools that produce the evidence for reporting, so they can't recognise the specific situation a stem is describing.

What to do instead

Read the stem for what is changing: a single risk's status → update and reassess; the whole exposure picture → risk review/reassessment; whether the risk process itself is working → risk audit; reserve being consumed faster or slower than planned → reserve analysis; performance drifting without new risks → variance and trend analysis. Choose the tool matched to the evidence described, and remember work performance reports feed the risk report.

Exam requirements can change. Confirm current details with the exam provider.

PMI-RMP practice

200 questions. Each one lists the choices, the correct answer, and an explanation. With JavaScript, this list opens one question at a time. The checker at the top of this page saves progress in this browser when it is available.

  1. Question 1Risk Strategy and Planning

    What is the primary purpose of the risk management plan?

    1. To list every identified risk with its owner and response
    2. To document the technical specifications of all project deliverables
    3. To record the approved cost baseline for the project
    4. To define how risk activities will be performed and funded Correct answer.

    Explanation

    The risk management plan describes the approach, processes, roles, funding, and timing for risk management. It is a planning document, not a repository for individual risks or a substitute for other project baselines.

  2. Question 2Risk Strategy and Planning

    A project sponsor states that the organization will accept no more than a 5 percent chance of exceeding the project budget. This statement best represents:

    1. risk appetite
    2. risk capacity
    3. risk tolerance Correct answer.
    4. risk avoidance

    Explanation

    Risk appetite is the amount of risk an organization is willing to pursue. Risk tolerance is the measurable acceptable variation around an objective, such as a maximum overrun probability.

  3. Question 3Risk Strategy and Planning

    A risk's exposure exceeds the threshold defined for the project manager. According to good risk governance, what should happen next?

    1. The risk should be escalated to the level with authority to manage it Correct answer.
    2. The risk should be accepted by the project manager without escalation
    3. The risk should be deleted from the risk register because it is outside scope
    4. The risk should be reclassified as an issue and closed

    Explanation

    Risk thresholds define the level at which a risk must be escalated to a higher authority. Escalation ensures the risk is managed by someone with the required decision rights and resources.

  4. Question 4Risk Strategy and Planning

    What does a risk breakdown structure primarily provide?

    1. A numeric ranking of risks by expected monetary value
    2. A hierarchical representation of risk sources and categories Correct answer.
    3. A schedule of risk review meetings across the project life cycle
    4. A hierarchical list of project team members and their risk duties

    Explanation

    A risk breakdown structure organizes risk sources and categories in a hierarchy. It helps teams identify risks systematically and compare exposures across categories.

  5. Question 5Risk Strategy and Planning

    Which element is most characteristic of effective risk governance on a project?

    1. A policy that all risks must be transferred to a contractor
    2. Defined risk ownership, authority, and escalation paths Correct answer.
    3. A single risk owner assigned to every risk in the register
    4. Monthly risk workshops attended only by senior management

    Explanation

    Risk governance establishes decision rights, accountability, oversight, and escalation. Clear ownership and authority allow risks to be managed at the appropriate level.

  6. Question 6Risk Strategy and Planning

    A project team sets aside funds to cover known risks that have been identified and analyzed. These funds are best classified as:

    1. contingency reserve Correct answer.
    2. profit margin
    3. cost baseline padding
    4. management reserve

    Explanation

    A contingency reserve is allocated for identified risks and accepted exposures. Management reserve is used for unknown-unknowns outside the approved baseline.

  7. Question 7Risk Strategy and Planning

    An unknown-unknown event occurs that was not in the risk register and requires additional funding. Which reserve should be used, and who typically authorizes it?

    1. Management reserve, authorized by senior management Correct answer.
    2. Management reserve, authorized by the project team
    3. Contingency reserve, authorized by the risk owner
    4. Contingency reserve, authorized by the project manager

    Explanation

    Unknown-unknowns fall outside identified risk exposure and are funded from management reserve. Management reserve is controlled by senior management or the sponsor because it affects the overall budget baseline.

  8. Question 8Risk Strategy and Planning

    During risk planning, a stakeholder consistently overestimates the likelihood of technical failure based on a past project. This behavior is best described as:

    1. risk appetite
    2. risk capacity
    3. risk attitude Correct answer.
    4. risk neutral

    Explanation

    Risk attitude is a stakeholder's perception or bias toward risk, often shaped by experience. It can influence how likelihood and impact are assessed during risk planning.

  9. Question 9Risk Strategy and Planning

    A low-complexity, short-duration project is tailoring its risk process. Which approach is most appropriate?

    1. Adopt the enterprise risk process unchanged for consistency
    2. Use a simplified register and brief, scaled risk reviews Correct answer.
    3. Eliminate risk identification because the project is short
    4. Require full quantitative analysis before every status meeting

    Explanation

    Tailoring scales risk processes to the project's size, complexity, and risk profile. A simpler register and brief reviews maintain rigor without unnecessary overhead.

  10. Question 10Risk Strategy and Planning

    In the risk management plan, what is the risk owner primarily accountable for?

    1. Approving the project budget
    2. Performing all quantitative risk analysis
    3. Maintaining the enterprise risk database
    4. Managing the assigned risk and its response Correct answer.

    Explanation

    The risk owner is accountable for monitoring the assigned risk and ensuring the selected response is implemented and effective. This accountability should be explicit in the risk management plan.

  11. Question 11Risk Strategy and Planning

    What is the main role of an organizational risk management policy?

    1. To set the organization's risk principles and expectations Correct answer.
    2. To replace the project risk register
    3. To list the specific risks for each active project
    4. To calculate the exact contingency reserve for each project

    Explanation

    A risk management policy sets the organization's overall principles, expectations, and mandate for managing risk. Project-level documents then apply that policy to specific objectives and constraints.

  12. Question 12Risk Strategy and Planning

    In risk planning, a risk is best stated as a cause, an uncertain event, and:

    1. an effect on project objectives Correct answer.
    2. a fixed budget amount approved by finance
    3. a named team member's assigned role
    4. a completed change request record

    Explanation

    A well-formed risk statement links a cause to an uncertain event and its potential effect on objectives. This structure supports clear analysis and response planning.

  13. Question 13Risk Strategy and Planning

    Which finding most directly indicates poor risk data quality in the risk register?

    1. Risk owners include both technical and business staff
    2. Many risks lack clear owners or probabilities Correct answer.
    3. Risks are reviewed at every status meeting
    4. The register includes both threats and opportunities

    Explanation

    Risk data quality depends on clear, accurate, and complete information such as descriptions, ownership, and assessed probability and impact. Missing owners or probabilities undermines analysis and response planning.

  14. Question 14Risk Strategy and Planning

    What should determine the frequency and format of risk reporting on a project?

    1. The personal preference of the project scheduler
    2. A fixed monthly cycle applied to every project in the organization
    3. Stakeholder needs and the project's risk profile Correct answer.
    4. The number of risks currently open in the register only

    Explanation

    Risk reporting should be tailored to stakeholder information needs and the project's risk exposure. The risk management plan defines reporting cadence, content, and audience.

  15. Question 15Risk Strategy and Planning

    A key risk indicator is most useful when it:

    1. gives early warning that a risk exposure is rising Correct answer.
    2. replaces the need for risk identification
    3. records only risks that have already occurred
    4. guarantees that the risk will not occur

    Explanation

    A key risk indicator provides an early warning signal about changing risk exposure. It supports proactive monitoring and timely response rather than guaranteeing outcomes.

  16. Question 16Risk Strategy and Planning

    How should an assumption recorded in the assumptions log be treated if it is critical and uncertain?

    1. It should be removed from the project charter
    2. It should be analyzed as a risk source and monitored Correct answer.
    3. It should be converted into a change request immediately
    4. It should be ignored because assumptions are not risks

    Explanation

    A critical, uncertain assumption can become a source of risk if it proves false. It should be analyzed, assigned ownership, and monitored like other risk drivers.

  17. Question 17Risk Strategy and Planning

    How should historical lessons learned be used during risk planning?

    1. To replace stakeholder interviews entirely
    2. To justify avoiding all previously unsuccessful projects
    3. To inform risk identification using similar past work Correct answer.
    4. To set the final cost baseline without further analysis

    Explanation

    Lessons learned provide evidence about past risks, causes, and response effectiveness. They should inform risk identification and response planning for similar work.

  18. Question 18Risk Strategy and Planning

    Which behavior best demonstrates a mature project risk culture?

    1. Risk discussions are limited to the project manager and sponsor
    2. Team members raise risks early without blame, and leaders act Correct answer.
    3. Team members report only risks that already have approved responses
    4. Risks are documented only after they become issues

    Explanation

    A mature risk culture encourages early, transparent reporting and constructive action. Blame-free escalation helps surface risks before they become issues.

  19. Question 19Risk Strategy and Planning

    A risk owned at the program level affects a project's critical path. What is the most appropriate governance action?

    1. The project manager should hide the risk to avoid program interference
    2. The project team should accept the risk without informing the program
    3. Escalate via the defined path and coordinate with the program owner Correct answer.
    4. The risk should be closed at the project level because the program owns it

    Explanation

    Risks should be escalated through the defined governance path to the level with authority. The project manager should also coordinate with the program risk owner because the risk affects project objectives.

  20. Question 20Risk Strategy and Planning

    Who should approve the project risk management plan to ensure it has authority?

    1. Key stakeholders and the sponsor, per governance Correct answer.
    2. Any team member who has risk experience
    3. An external auditor without project authority
    4. The risk register administrator alone

    Explanation

    The risk management plan should be approved by the sponsor and key stakeholders consistent with the project governance structure. Approval confirms commitment to roles, funding, and reporting arrangements.

  21. Question 21Risk Strategy and Planning

    An organization can absorb a maximum financial loss of $2 million before insolvency. This limit represents the organization's:

    1. contingency reserve
    2. risk threshold for a single project
    3. risk capacity Correct answer.
    4. risk appetite

    Explanation

    Risk capacity is the maximum risk an organization can bear before threatening its viability. It is distinct from appetite, which reflects willingness to take risk.

  22. Question 22Risk Strategy and Planning

    When planning risk management for a project within a program, what should the project manager do first?

    1. Create an independent risk process that ignores program reporting
    2. Wait until the program closes before identifying project risks
    3. Align project risk thresholds and reporting with the program Correct answer.
    4. Transfer all project risks to the program manager

    Explanation

    Project risk planning should align with the program's risk framework, including categories, thresholds, and reporting. Alignment supports consistent escalation and aggregated risk visibility.

  23. Question 23Risk Strategy and Planning

    A project has high uncertainty, many interdependent stakeholders, and rapidly changing requirements. How should risk planning address this complexity?

    1. Use adaptive reviews, broad engagement, and flexible reserves Correct answer.
    2. Freeze the risk register after initial approval
    3. Use a single deterministic risk score for all risks
    4. Reduce stakeholder involvement to simplify communication

    Explanation

    Complex, uncertain projects require adaptive risk reviews, broad stakeholder engagement, and flexible reserves. These practices help the team detect change and respond as conditions evolve.

  24. Question 24Risk Strategy and Planning

    Which activity is part of planning for risk identification rather than performing risk identification itself?

    1. Updating a risk response in the register
    2. Selecting the techniques and participants for identification Correct answer.
    3. Assigning a probability to a schedule risk
    4. Documenting a new vendor delivery risk

    Explanation

    Planning risk identification defines how identification will be conducted, including techniques, participants, inputs, and timing. The other activities are execution steps within identification or analysis.

  25. Question 25Risk Strategy and Planning

    Which set of fields is most essential in a newly created risk register?

    1. Description, cause, effect, owner, probability, and response Correct answer.
    2. The project's accounting codes and tax identifiers
    3. Only the risk description and a single due date for each risk
    4. Team member home addresses and phone numbers

    Explanation

    A risk register should capture enough information to understand, analyze, assign, and respond to each risk. Core fields include description, cause, effect, owner, probability, impact, and response.

  26. Question 26Risk Strategy and Planning

    A project manager is about to begin risk management on a large project and needs to define the methodology, roles, funding, and timing for risk activities. Which document should be created?

    1. The stakeholder engagement plan
    2. The risk breakdown structure
    3. The risk management plan Correct answer.
    4. The risk register

    Explanation

    The risk management plan describes how risk management will be structured and performed: methodology, roles and responsibilities, budgeting, timing, and reporting formats. Individual risks and their responses are captured later in the risk register, so the plan must exist first.

  27. Question 27Risk Strategy and Planning

    A project manager wants to reveal where risk exposure concentrates across sources such as technical, commercial, and external factors. Which structure should be used?

    1. The resource breakdown structure
    2. The risk breakdown structure Correct answer.
    3. The work breakdown structure
    4. The organizational breakdown structure

    Explanation

    The risk breakdown structure is a hierarchical representation of risk sources and categories, used during planning to categorize risks and expose where exposure is concentrated. The other breakdown structures decompose scope, resources, or reporting lines rather than risk sources.

  28. Question 28Risk Strategy and Planning

    Which inputs are most relevant when planning how risk management will be performed on a project?

    1. The activity list, duration estimates, and cost baseline
    2. The project charter and stakeholder register Correct answer.
    3. The quality metrics, issue log, and quality control measurements
    4. The resource calendars and team performance assessments

    Explanation

    The charter supplies project objectives, success criteria, high-level risks, and the sponsor's authority, while the stakeholder register identifies who can influence risk decisions and what their risk attitudes are; enterprise environmental factors and organizational process assets also shape the approach. Detailed execution artifacts such as activity lists or quality measurements are not primary inputs to this planning process.

  29. Question 29Risk Strategy and Planning

    A risk is assigned to a functional manager who is accountable for the risk outcome, while a team member is tasked with carrying out the agreed mitigation steps. What is the team member's role?

    1. Risk champion
    2. Risk reviewer
    3. Risk action owner Correct answer.
    4. Risk owner

    Explanation

    The risk owner is accountable for managing the risk and its response overall, whereas the risk action owner performs the specific response actions assigned. The risk management plan should distinguish these roles so accountability is not confused with task execution.

  30. Question 30Risk Strategy and Planning

    The risk response plan documents actions to be taken if a specific risk event occurs, plus a separate set of actions to be used if the primary response proves ineffective. What is the second set of actions called?

    1. A risk response strategy
    2. A fallback plan Correct answer.
    3. A workaround
    4. A contingency plan

    Explanation

    A contingency plan contains predefined actions to be executed if the risk event occurs, while a fallback plan contains actions to be used if the primary or contingency response fails. Workarounds, by contrast, are unplanned responses to issues that were not addressed in advance.

  31. Question 31Risk Strategy and Planning

    Before assessing individual risks, a project manager defines probability and impact scales with explicit descriptive criteria for each level. What is the primary benefit of this step?

    1. It makes risk ratings comparable across assessors Correct answer.
    2. It allows every risk to be assigned to the sponsor
    3. It reduces the number of risks that must be recorded
    4. It removes the need for management reserves

    Explanation

    Explicit scales give all assessors a shared interpretation of each level, so ratings are consistent and can be reliably compared and prioritized. The scales do not change how many risks exist, eliminate reserves, or shift ownership of risks to the sponsor.

  32. Question 32Risk Strategy and Planning

    Six months into execution, a project's scope and vendor base have changed substantially, but the risk management plan has not been revisited. What is the most appropriate action?

    1. Continue using the current plan because it was approved at baseline
    2. Defer any change to the plan until project closure lessons learned
    3. Replace the plan with the risk register at the next gate
    4. Update the plan to reflect the new context and re-approve it Correct answer.

    Explanation

    Planning for risk management is iterative; significant changes in scope, contracts, organization, or environment require the approach, thresholds, roles, and reporting to be revisited and re-approved. Leaving an outdated approach in force means escalations, tolerances, and responsibilities no longer fit the project.

  33. Question 33Risk Strategy and Planning

    An organization accepts high uncertainty in technology choices but has very low tolerance for regulatory non-compliance. A project carries both types of risk. How should risk planning reflect this?

    1. Set category-specific tolerances and prioritize regulatory responses Correct answer.
    2. Record both categories with the same rating scale and no differentiated treatment
    3. Escalate every technology risk to the sponsor because appetite is high
    4. Apply a single uniform threshold to all risks so the project is treated consistently

    Explanation

    Risk appetite can differ by risk category, so the plan should define tolerances per category, often mapped through the risk breakdown structure, and prioritize responses where tolerance is lowest. A uniform threshold ignores the organization's stated position and would misdirect attention and escalation.

  34. Question 34Risk Strategy and Planning

    A risk management plan states that risks must be escalated when they could cause 'significant disruption' or 'major concern'. Reviewers find that different managers escalate different risks. What is the best improvement?

    1. Define thresholds as measurable deviations tied to project objectives Correct answer.
    2. Limit escalation to risks that have already occurred and entered the issue log
    3. Replace thresholds with a statement that the team will use professional judgment
    4. Require all risks to be escalated so that no judgment is needed

    Explanation

    Thresholds must be objective, measurable, and traceable to project objectives, such as a schedule slip beyond two weeks or a cost impact above a stated amount, so escalation decisions are consistent. Vague qualitative wording invites each manager to apply a different interpretation.

  35. Question 35Stakeholder Engagement

    Which item is a core element of the stakeholder register?

    1. The approved cost baseline and its funding requirements
    2. The quality control checklist and inspection results
    3. Each stakeholder's influence and potential impact Correct answer.
    4. The project schedule network and its critical path activities

    Explanation

    The stakeholder register records identification details, an assessment of each stakeholder's influence and potential impact, and a classification of that stakeholder. Baselines, schedules and checklists are documented in other project plans and records.

  36. Question 36Stakeholder Engagement

    In the stakeholder engagement assessment matrix, which level describes a stakeholder who knows about the project but neither supports nor opposes it?

    1. Resistant
    2. Neutral Correct answer.
    3. Leading
    4. Unaware

    Explanation

    The matrix uses five levels: unaware, resistant, neutral, supportive and leading. Neutral means the stakeholder is aware of the project but does not actively support or oppose it.

  37. Question 37Stakeholder Engagement

    On a power/interest grid, how should a stakeholder with high power and low interest be managed?

    1. Kept satisfied Correct answer.
    2. Kept informed
    3. Managed closely with maximum engagement
    4. Monitored with minimal effort

    Explanation

    High power, low interest stakeholders can block outcomes but care little about day-to-day detail, so the aim is to keep them satisfied with concise, sufficient information.

  38. Question 38Stakeholder Engagement

    What is the main purpose of the stakeholder engagement plan?

    1. To define how stakeholders will be engaged Correct answer.
    2. To document the project's quality metrics and tolerances
    3. To list the resources assigned to each scheduled activity
    4. To record the cost and schedule baselines for the project

    Explanation

    The plan describes the strategies and specific actions needed to promote productive involvement of stakeholders in project decisions and execution. It is not a repository for baselines, staffing or quality metrics.

  39. Question 39Stakeholder Engagement

    Which document is the best starting point for deciding who should take part in risk identification?

    1. The cost baseline
    2. The quality management plan
    3. The stakeholder register Correct answer.
    4. The resource calendar

    Explanation

    The stakeholder register lists identified stakeholders along with their influence, interest and classification, which makes it the natural source for selecting participants. Other documents describe availability, budget or quality approach rather than stakeholder characteristics.

  40. Question 40Stakeholder Engagement

    A stakeholder's willingness to accept uncertainty in exchange for a potential benefit is that stakeholder's:

    1. Risk appetite Correct answer.
    2. Risk register entry
    3. Risk threshold
    4. Risk breakdown structure

    Explanation

    Risk appetite is the degree of uncertainty an entity is willing to accept in anticipation of a reward. Thresholds express that appetite as measurable levels of exposure that trigger action.

  41. Question 41Stakeholder Engagement

    A risk owner must be reached immediately and must confirm receipt of the message. Which communication method fits best?

    1. A one-way email sent without a request for acknowledgement
    2. A notice posted on the project intranet site for later reading
    3. A quarterly newsletter sent to the whole organization
    4. Interactive communication such as a call or meeting Correct answer.

    Explanation

    Interactive communication provides immediate two-way exchange and confirmation of understanding, which is essential when timing and acknowledgement matter.

  42. Question 42Stakeholder Engagement

    The salience model classifies stakeholders using power, urgency and which third attribute?

    1. Legitimacy Correct answer.
    2. Cultural fit
    3. Proximity
    4. Risk tolerance

    Explanation

    The salience model uses power, urgency and legitimacy; stakeholders holding all three are considered definitive and receive the highest priority.

  43. Question 43Stakeholder Engagement

    A regulatory body whose approval is required is recorded on the engagement matrix as resistant. What is the most appropriate next step?

    1. Log the resistance as a risk and take no further action
    2. Ask the sponsor to have the approval requirement removed from the plan
    3. Plan engagement to address the regulator's concerns Correct answer.
    4. Submit the request and notify the regulator after implementation

    Explanation

    A gap between the current and desired engagement level calls for targeted action in the engagement plan that addresses the root cause of the resistance.

  44. Question 44Stakeholder Engagement

    In a risk identification workshop, two senior stakeholders dominate the conversation while others stay silent. What should the risk manager do?

    1. End the workshop and collect input by email instead
    2. Record only the senior stakeholders' risks to save time
    3. Let the discussion continue since seniority suggests better insight
    4. Use a facilitated round-robin so every participant contributes Correct answer.

    Explanation

    Facilitation techniques such as round-robin ensure each participant contributes, protecting the group from dominance effects and capturing broader expertise.

  45. Question 45Stakeholder Engagement

    You need expert risk input but want to prevent a dominant personality from shaping the group's view. Which technique is most suitable?

    1. The Delphi technique run in anonymous rounds Correct answer.
    2. A survey of the general public
    3. A single focus group run by the sponsor
    4. An open brainstorming session with all experts together

    Explanation

    Delphi collects expert opinion in anonymous rounds with controlled feedback, which removes the influence of dominant personalities and converges on a considered view.

  46. Question 46Stakeholder Engagement

    A sponsor consistently accepts a schedule risk that other key stakeholders consider unacceptable. What is the most useful interpretation for the risk manager?

    1. The schedule risk should be transferred to a contractor to end the disagreement
    2. The other stakeholders' views can be disregarded because the sponsor funds the project
    3. The risk register should record only the sponsor's view of the risk
    4. Differing tolerances exist and must be reconciled through agreed thresholds Correct answer.

    Explanation

    Stakeholders legitimately hold different tolerances for the same risk, and the risk manager's role is to surface the difference and help the group agree on thresholds rather than let one view silently prevail.

  47. Question 47Stakeholder Engagement

    A project team spans three continents. Which factor most needs consideration when planning risk-related communication?

    1. The length of the project's closure report
    2. Language, time-zone and cultural differences Correct answer.
    3. The preferred font used in risk register templates
    4. The number of meeting rooms available at headquarters

    Explanation

    Cross-border communication must account for language proficiency, time-zone spread and cultural norms, because these directly affect how risk information is interpreted and acted upon.

  48. Question 48Stakeholder Engagement

    A risk owner agrees to a response but has no authority to commit the needed resources. What should the risk manager do first?

    1. Close the risk since a response has been agreed
    2. Reassign the risk to a randomly selected team member
    3. Raise the authority gap with the sponsor or PM Correct answer.
    4. Change the response to accept the risk instead

    Explanation

    A risk owner must have both responsibility and the authority to act; when authority is missing, the gap is resolved at the level that controls the resources, typically the project manager or sponsor.

  49. Question 49Stakeholder Engagement

    A risk exceeds the project manager's authority and will affect deliverables owned by another project. Where should it be escalated?

    1. To the original requester of the affected deliverable
    2. To the next level up, such as the program manager Correct answer.
    3. To the team member who first identified the risk
    4. To the project's procurement specialist

    Explanation

    Risks that exceed the project's authority, or that are shared across projects, are escalated to the level able to authorize and fund a response.

  50. Question 50Stakeholder Engagement

    What is the most direct consequence of failing to identify a relevant stakeholder early?

    1. The risk register will contain too many entries
    2. Their risks surface late, causing rework and resistance Correct answer.
    3. The cost baseline will be revised automatically
    4. The project charter cannot be approved

    Explanation

    Stakeholders overlooked during identification bring requirements, constraints and risks into the project late, which typically produces rework and resistance to decisions already made.

  51. Question 51Stakeholder Engagement

    The engagement matrix shows a stakeholder moving from unaware to supportive, which matches the desired level recorded for that stakeholder. What does this indicate?

    1. The engagement approach is working as intended Correct answer.
    2. The project is over-communicating and should stop
    3. The stakeholder should now be removed from the register
    4. The desired level must be raised again immediately

    Explanation

    Movement toward the desired engagement level is the intended result of planned engagement; once current equals desired, the approach is effective and should be maintained.

  52. Question 52Stakeholder Engagement

    Two stakeholders rate the same risk very differently. Which explanation best fits risk management practice?

    1. Perceptions differ with objectives and experience Correct answer.
    2. The risk register must contain a calculation error
    3. Only the more senior stakeholder's rating is valid
    4. One of them must be misreporting the data

    Explanation

    Risk is perceived through each stakeholder's objectives, prior experience and tolerance, so divergent ratings are expected and are resolved through structured discussion and agreed assessment criteria.

  53. Question 53Stakeholder Engagement

    When should the stakeholder engagement plan be reviewed and updated?

    1. Once, at the end of planning
    2. Only when the sponsor requests it
    3. Only at project closure
    4. Throughout the project as needs change Correct answer.

    Explanation

    Stakeholder sets, influence and engagement needs shift as the project progresses, so the engagement plan is a living document reviewed and updated across the life cycle.

  54. Question 54Stakeholder Engagement

    Which stakeholder is best suited to own a specific technical risk?

    1. The person with knowledge and authority over the response Correct answer.
    2. The stakeholder who first noticed the risk in passing
    3. The project sponsor, because ownership always sits with the sponsor
    4. The stakeholder with the most senior job title in the organization

    Explanation

    A risk owner is the person responsible for selecting and implementing the response, so ownership follows knowledge of the risk area together with the authority to act.

  55. Question 55Stakeholder Engagement

    Three stakeholders satisfy different salience combinations: one has power and legitimacy, one has power and urgency, and one has all three. Which engagement priority is most defensible?

    1. All three should be engaged identically because each holds power
    2. The stakeholder with power and legitimacy should be ignored until a crisis
    3. The stakeholder with all three attributes has the highest priority Correct answer.
    4. The stakeholder with power and urgency should always be deprioritized

    Explanation

    In the salience model, stakeholders holding all three attributes are definitive and demand immediate attention, while those holding two are expectant and those holding one are latent.

  56. Question 56Stakeholder Engagement

    The risk management plan states a low appetite for cost risk, but the sponsor keeps approving cost-risk responses as tolerable. What should the risk manager do?

    1. Apply the sponsor's informal view and ignore the documented plan
    2. Facilitate agreement and update the documented thresholds Correct answer.
    3. Record both versions in the risk register and take no further action
    4. Escalate to the PMO to have the sponsor replaced on the project

    Explanation

    Appetite and thresholds must reflect an agreed, documented position; where practice diverges from the plan, the risk manager facilitates agreement and updates the plan so the team works from one consistent standard.

  57. Question 57Stakeholder Engagement

    Which observation is the strongest evidence that stakeholder engagement in risk management is effective?

    1. Stakeholders raise risks early and fund responses Correct answer.
    2. Attendance at risk workshops is consistently high
    3. Risk meetings are held at the agreed frequency
    4. The stakeholder register contains many entries

    Explanation

    Effective engagement is demonstrated by behaviour that produces value, such as early disclosure of risks and commitment of resources to responses, rather than by activity metrics.

  58. Question 58Stakeholder Engagement

    Why should stakeholders' risk thresholds be understood before risk responses are planned?

    1. Thresholds determine which stakeholders are dropped from the register
    2. Thresholds replace the need for a risk management plan
    3. Thresholds identify who should chair the risk review meetings
    4. Thresholds set the exposure that triggers action Correct answer.

    Explanation

    A threshold is the measurable level of exposure beyond which risk will not be tolerated; responses and escalation paths must therefore be designed to keep exposure within agreed thresholds.

  59. Question 59Stakeholder Engagement

    Which practice most improves the reliability of risk information reaching the risk manager from stakeholders?

    1. A two-way channel with defined feedback and confirmation Correct answer.
    2. Restricting risk discussions to the monthly steering committee
    3. Publishing the risk register on a shared drive without notice
    4. Relying on stakeholders to raise risks only in writing

    Explanation

    Reliable risk information flows through channels that allow dialogue, clarification and confirmation of understanding, so both parties can verify that the message was received and interpreted correctly.

  60. Question 60Stakeholder Engagement

    A stakeholder has high authority over the project budget but little interest in day-to-day risk work. According to a power/interest grid, how should the risk manager engage this stakeholder?

    1. Keep satisfied with periodic summaries of major risks Correct answer.
    2. Monitor with minimal communication until issues arise
    3. Manage closely with frequent detailed risk reviews
    4. Keep informed through weekly detailed risk reports

    Explanation

    On a power/interest grid, stakeholders with high power and low interest are kept satisfied: they receive enough information to remain comfortable without being overwhelmed by detail. Because they can materially affect the project, silence is risky, but intensive day-to-day involvement is unnecessary. The engagement approach should match both dimensions, not just authority.

  61. Question 61Stakeholder Engagement

    Which stakeholder typically supplies the authority and resources needed to implement agreed risk responses?

    1. The procurement manager handling contracts
    2. The project's assigned risk owners
    3. The PMO risk analyst supporting the project
    4. The project sponsor Correct answer.

    Explanation

    The sponsor sits at the level where funding, priority and organizational authority are granted, so responses requiring money, staff or cross-functional commitment are sanctioned there. Risk owners execute responses but generally do not control the resources behind them. Engagement with the sponsor should therefore focus on decisions and support rather than on technical detail.

  62. Question 62Stakeholder Engagement

    Why should stakeholders be involved during risk identification rather than only after risks are assessed?

    1. To shorten the risk identification process
    2. To transfer ownership of all risks to the stakeholders
    3. To surface risks the team alone would overlook Correct answer.
    4. To reduce the number of risks that must be documented

    Explanation

    Different stakeholders see different parts of the project and its environment, so their participation broadens the set of threats and opportunities captured. Involvement at identification also builds earlier ownership of the resulting risks. Waiting until assessment is complete tends to produce blind spots that are expensive to correct later.

  63. Question 63Stakeholder Engagement

    During a risk workshop, the first cost estimate for a risk, offered by a senior manager, shapes every later estimate even though it lacks supporting data. Which cognitive bias is at work?

    1. Optimism bias
    2. Confirmation bias
    3. Availability bias
    4. Anchoring Correct answer.

    Explanation

    Anchoring occurs when an initial figure or position disproportionately influences subsequent judgments, even when it is arbitrary or unsupported. The remedy is to gather independent estimates before group discussion or to have participants estimate privately. Recognizing the bias lets the facilitator reframe the discussion around evidence.

  64. Question 64Stakeholder Engagement

    Two key stakeholders disagree sharply on whether a risk should be accepted or mitigated. What should the risk manager do first?

    1. Escalate the disagreement to the sponsor for a decision
    2. Facilitate a discussion using agreed criteria and data Correct answer.
    3. Record both views in the risk register and take no action
    4. Adopt the position of the stakeholder with most authority

    Explanation

    Disagreement is usually best resolved by returning to the agreed risk appetite, thresholds and objective assessment data, which depersonalizes the debate. Facilitation keeps ownership with the parties who must support the outcome. Escalation or deference should follow only if facilitation fails.

  65. Question 65Stakeholder Engagement

    When reporting risk status to senior executives, which approach best supports their decisions?

    1. Provide the full risk register with the complete history for every entry
    2. Explain the technical detail of every response technique in use
    3. Report only the risks that have already materialized as issues
    4. Summarize top risks with exposure and decisions needed Correct answer.

    Explanation

    Executives need decision-relevant information: which risks matter most, how exposed the project is, what is being done and what choice they must make. Detail belongs in supporting material available on request. Filtering the message to the audience's role is a core engagement principle.

  66. Question 66Stakeholder Engagement

    A subcontractor's work carries a risk that also affects the buyer's schedule. What should the risk manager confirm first?

    1. That the subcontractor has purchased general liability insurance
    2. That the risk is recorded only in the buyer's risk register
    3. That the contract assigns the risk and requires reporting Correct answer.
    4. That the buyer's team has identified a backup supplier

    Explanation

    When a risk crosses organizational boundaries, clarity about who owns it and how its status will be communicated is the foundation for managing it. Contract terms and reporting obligations make that ownership enforceable. Other actions such as insurance or backup suppliers are responses that come after ownership is clear.

  67. Question 67Stakeholder Engagement

    A team proposes transferring a safety-related risk to a small supplier with limited resources. What is the most important consideration for the risk manager?

    1. Whether the supplier can actually bear the consequence Correct answer.
    2. Whether the transfer removes the risk from the risk register
    3. Whether the transfer lowers the project's insurance premiums
    4. Whether the supplier has signed the standard contract terms

    Explanation

    Risk transfer shifts financial or contractual responsibility but never eliminates the underlying threat or the project's accountability to stakeholders. Transfer is only effective if the receiving party has the capacity and competence to absorb the consequence. A supplier that cannot bear the loss simply passes it back, often at the worst moment.

  68. Question 68Stakeholder Engagement

    A risk response requires actions from three different departments before a deadline. What should the risk manager ensure is defined in the response plan?

    1. A contingency reserve held by each department
    2. One department made accountable for coordinating every action
    3. A weekly meeting chaired by the sponsor
    4. Named owners, due dates and accountability per action Correct answer.

    Explanation

    A response spanning several groups only works when each action has a named owner, a date and clear accountability, all traceable to the risk owner. Coordination mechanisms are useful but do not substitute for explicit assignment. Undefined responsibility is the most common reason responses stall.

  69. Question 69Risk Identification

    Which project document provides the most direct information about stakeholder risk sensitivities and communication preferences during risk identification?

    1. Resource calendar
    2. Work breakdown structure
    3. Stakeholder register Correct answer.
    4. Quality management plan

    Explanation

    The stakeholder register records stakeholder interests, influence, expectations, and communication preferences, so it is a primary input for identifying stakeholder-related risks. It does not decompose scope, define quality standards, or schedule resources.

  70. Question 70Risk Identification

    What is the primary purpose of a risk breakdown structure (RBS) during risk identification?

    1. To schedule risk response activities across the project timeline
    2. To organize identified risks into hierarchical categories Correct answer.
    3. To calculate the expected monetary value of each identified risk
    4. To assign each risk to a single accountable owner

    Explanation

    An RBS provides a hierarchical structure of risk sources and categories, helping the team examine each category systematically and reduce gaps. It is not a scheduling, valuation, or ownership-assignment tool.

  71. Question 71Risk Identification

    In a risk identification workshop, what is the main role of a skilled facilitator?

    1. To encourage broad participation and keep focus on risks Correct answer.
    2. To vote on which risks are most important
    3. To approve the final risk register
    4. To replace expert judgment with a standard checklist of common risks

    Explanation

    A facilitator guides the identification process, encourages contributions from all participants, and prevents dominant voices from narrowing the discussion. Voting, approval, and replacing judgment are not facilitation roles.

  72. Question 72Risk Identification

    SWOT analysis is used during risk identification primarily to examine which relationship?

    1. The relationship between the project cost baseline and the schedule baseline
    2. Internal strengths and weaknesses versus external opportunities and threats Correct answer.
    3. The relationship between stakeholder influence and stakeholder interest
    4. The relationship between risk probability and impact

    Explanation

    SWOT examines internal strengths and weaknesses together with external opportunities and threats to surface both negative and positive uncertainties. Cost-schedule, probability-impact, and stakeholder analyses are separate techniques.

  73. Question 73Risk Identification

    Reviewing project documents such as contracts, requirements, and prior lessons learned helps risk identification by:

    1. Revealing assumptions, constraints, and historical issues Correct answer.
    2. Guaranteeing that no significant risks will be missed on the project
    3. Establishing the project budget baseline
    4. Eliminating the need for stakeholder interviews

    Explanation

    Document review looks for assumptions, constraints, contractual terms, requirements gaps, and prior issues that create uncertainty. It supports but never guarantees complete identification and does not replace stakeholder input or set the budget baseline.

  74. Question 74Risk Identification

    Which item is a core component of a risk register entry created during risk identification?

    1. The project's earned value performance metrics and forecasts
    2. The team's vacation schedule
    3. A risk statement with cause, event, and effect Correct answer.
    4. The procurement contract type

    Explanation

    A risk register entry commonly includes a risk statement in cause-event-effect form, plus category, owner, and other attributes. EVM metrics, vacation schedules, and contract type are project data but not core risk-entry components.

  75. Question 75Risk Identification

    Why is risk identification performed repeatedly throughout the project?

    1. Because only the project manager is allowed to identify risks
    2. Because new risks emerge and existing risks change over time Correct answer.
    3. Because all risks must be closed before the next phase begins
    4. Because the risk register must be recreated at each phase gate

    Explanation

    Risk identification is iterative because new information, changes, and evolving conditions create new risks and alter existing ones throughout the project life cycle. The register is updated, not recreated at gates, and identification involves the team, not only the project manager.

  76. Question 76Risk Identification

    How should lessons learned from similar past projects be used during risk identification?

    1. They should replace the risk breakdown structure
    2. They should be ignored because every project is unique in its risks
    3. They should inform checklists and discussions of likely risk sources Correct answer.
    4. They should be used only after risks have occurred

    Explanation

    Lessons learned provide historical evidence of likely risk sources, past failures, and effective responses that can inform checklists and discussion. They supplement, rather than replace, project-specific identification.

  77. Question 77Risk Identification

    A project team wants to reach expert consensus on risks without the dominating effects of seniority or group pressure. Which technique is most appropriate?

    1. Delphi technique Correct answer.
    2. Checklist analysis
    3. Brainstorming
    4. SWOT analysis

    Explanation

    Delphi uses anonymous questionnaires with iterative feedback to build expert consensus while reducing seniority and group-pressure effects. Brainstorming is interactive, and SWOT/checklist analysis are not consensus-building techniques.

  78. Question 78Risk Identification

    During risk identification, a team keeps recording "schedule slippage" as a risk. Which technique best helps them move from symptoms to underlying sources?

    1. Reserve analysis
    2. Monte Carlo simulation
    3. Root cause analysis Correct answer.
    4. Earned value analysis

    Explanation

    Root cause analysis traces symptoms back to underlying causes, helping the team identify the source of potential risk rather than restating a symptom. Simulation, reserve analysis, and earned value analysis do not serve this causal purpose.

  79. Question 79Risk Identification

    Assumption analysis contributes to risk identification by:

    1. Testing assumptions for stability and for risks if they prove false Correct answer.
    2. Validating that all documented assumptions remain correct throughout the project
    3. Converting every assumption into a risk response
    4. Removing assumptions from the project charter

    Explanation

    Assumption analysis tests whether assumptions are valid and stable; if an assumption is false or unstable, the associated uncertainty should be treated as a risk. It does not prove assumptions correct, remove them, or automatically create responses.

  80. Question 80Risk Identification

    What is a key limitation of using a checklist as the sole method for risk identification?

    1. It is limited to risks previously experienced or anticipated Correct answer.
    2. It cannot be combined with expert judgment or other techniques
    3. It is only applicable to procurement risks
    4. It requires quantitative probability estimates

    Explanation

    A checklist is based on prior experience and known categories, so it can miss novel or project-specific risks when used alone. It can be combined with expert judgment and does not require quantitative estimates or apply only to procurement.

  81. Question 81Risk Identification

    A prompt list is best described as:

    1. A numerical ranking of every identified risk by expected monetary value
    2. A list of preassigned risk owners
    3. Categories or questions used to prompt thinking about risks Correct answer.
    4. A schedule of risk review meetings

    Explanation

    A prompt list provides categories, questions, or trigger words that stimulate the team to think of risks that might otherwise be overlooked. It is not an ownership list, meeting schedule, or numerical ranking.

  82. Question 82Risk Identification

    Which action most improves risk identification by leveraging stakeholders?

    1. Waiting until risks occur to ask stakeholders about them
    2. Limiting input to the project manager and sponsor
    3. Using only the risk register from a previous project
    4. Inviting diverse stakeholders to workshops and interviews Correct answer.

    Explanation

    Diverse stakeholders bring different perspectives and knowledge, improving coverage of potential risks. Limiting input, waiting for risks to occur, or relying only on a prior register narrows the identification effort.

  83. Question 83Risk Identification

    Which risk statement is best formed for the risk register?

    1. Schedule slippage is a risk.
    2. The vendor is a risk to the project.
    3. The project schedule may be delayed because the selected vendor might deliver its deliverables late.
    4. Vendor delay compresses integration testing, which can cause schedule slippage. Correct answer.

    Explanation

    A well-formed risk statement links a cause to an uncertain event and its effect on project objectives. Vague statements such as "schedule slippage is a risk" or "the vendor is a risk" do not identify cause and effect clearly.

  84. Question 84Risk Identification

    Grouping identified risks by source such as technical, external, organizational, and project management is an application of:

    1. A responsibility assignment matrix
    2. A resource histogram
    3. A work breakdown structure
    4. A risk breakdown structure Correct answer.

    Explanation

    Grouping risks by source such as technical, external, organizational, and project management applies a risk breakdown structure. A WBS groups deliverables, a resource histogram displays resource usage, and a RAM assigns responsibilities.

  85. Question 85Risk Identification

    In addition to the risk register, what output of risk identification communicates overall project risk exposure and key risk themes?

    1. Risk report Correct answer.
    2. Quality control measurements
    3. Stakeholder engagement plan
    4. Issue log

    Explanation

    The risk report summarizes overall project risk exposure, key individual risks, and risk themes, complementing the detailed risk register. The issue log tracks current issues, while the engagement plan and quality measurements serve other purposes.

  86. Question 86Risk Identification

    Which technique combines silent idea generation, round-robin recording, and group voting to prioritize identified risks?

    1. Delphi technique
    2. Nominal group technique Correct answer.
    3. Root cause analysis
    4. SWOT analysis

    Explanation

    Nominal group technique uses silent idea generation, round-robin sharing, and voting to prioritize ideas while limiting group dominance. Delphi is anonymous and iterative, SWOT examines factors, and RCA traces causes.

  87. Question 87Risk Identification

    After a brainstorming session produces many risk ideas, what does an affinity diagram help the team do?

    1. Eliminate all low-priority risks automatically
    2. Group related ideas into themes Correct answer.
    3. Assign each risk a monetary value
    4. Calculate the probability of each risk

    Explanation

    An affinity diagram organizes a large set of ideas into related themes, making the risk list easier to analyze and structure. It does not estimate probability, assign monetary value, or automatically eliminate risks.

  88. Question 88Risk Identification

    When identifying risks, how should opportunities be treated?

    1. As threats with negative impact
    2. As issues that should be logged only after they actually occur on the project
    3. As assumptions that require no further action
    4. As positive uncertainties recorded and managed alongside threats Correct answer.

    Explanation

    Risk includes both threats and opportunities; positive uncertainties should be recorded and managed so potential benefits can be pursued. Opportunities are not merely issues, assumptions, or threats.

  89. Question 89Risk Identification

    A team recently experienced a severe cyber incident and now identifies cyber risk as the top risk on every project, while ignoring other likely sources. Which cognitive bias is most evident?

    1. Anchoring bias
    2. Confirmation bias
    3. Sunk cost fallacy
    4. Availability bias Correct answer.

    Explanation

    Availability bias overweights recent, vivid, or easily recalled events, such as a recent cyber incident, when assessing risk. Anchoring, confirmation, and sunk cost biases operate differently.

  90. Question 90Risk Identification

    A systems-thinking approach to risk identification would use a context diagram primarily to:

    1. Document the reporting lines and authority of the project team
    2. List the acceptance criteria that each deliverable must satisfy
    3. Show project interactions with external entities and interface uncertainty Correct answer.
    4. Display the project's cost and schedule performance against the baseline over time

    Explanation

    A context diagram maps the project boundary and its interactions with external entities, highlighting interfaces and dependencies that can create uncertainty. Cost performance, reporting lines, and acceptance criteria are documented in other tools.

  91. Question 91Risk Identification

    What is a practical way to improve risk identification when team members are geographically dispersed and culturally diverse?

    1. Use structured virtual workshops with shared visual tools Correct answer.
    2. Restrict participation to one time zone
    3. Avoid documenting risks until the team meets face-to-face
    4. Rely only on asynchronous surveys to avoid scheduling issues

    Explanation

    Structured virtual workshops with clear ground rules and shared visual tools help dispersed and culturally diverse participants contribute and collaborate. Relying only on surveys, restricting time zones, or delaying documentation reduces identification quality.

  92. Question 92Risk Identification

    How does a risk breakdown structure differ from a work breakdown structure?

    1. The RBS organizes deliverables, while the WBS organizes risk sources
    2. The RBS is only used after risks occur, while the WBS is used during planning
    3. The RBS groups risk sources; the WBS groups deliverables and scope Correct answer.
    4. The RBS replaces the WBS for small projects

    Explanation

    The RBS is a hierarchy of risk sources and categories, whereas the WBS is a hierarchy of project deliverables and scope. They serve different purposes and are not substitutes.

  93. Question 93Risk Identification

    A team is unsure whether an item belongs in the assumption log or the risk register. Which distinction is most accurate?

    1. An assumption is accepted as true for planning; a related risk captures uncertainty if it proves false Correct answer.
    2. Assumptions are always certain, so they never belong in risk identification
    3. The risk register contains only opportunities, while the assumption log contains only threats
    4. The assumption log is maintained only by the sponsor, while the risk register is maintained by the team

    Explanation

    An assumption is accepted as true for planning purposes; if its validity is uncertain and could affect objectives, the related uncertainty belongs in the risk register. Assumptions can create risk, and the two logs have distinct purposes.

  94. Question 94Risk Identification

    A project manager must identify risks with a small group of experienced technical specialists who cannot meet at the same time. Which technique is most appropriate?

    1. A Monte Carlo simulation of the project schedule
    2. One-to-one interviews with technical specialists Correct answer.
    3. A risk breakdown structure built by the sponsor
    4. A facilitated workshop with the whole project team

    Explanation

    Interviewing experienced stakeholders is a data-gathering technique that can be conducted individually, so it fits specialists who are unavailable simultaneously. It draws out risks from subject-matter expertise through structured questions. Techniques requiring a common meeting time or a quantitative model do not serve that purpose during identification.

  95. Question 95Risk Identification

    A project manager studies the contract, the WBS, and lessons-learned reports from earlier projects to surface uncertainties. Which risk identification technique is being applied?

    1. Monte Carlo simulation
    2. Document analysis Correct answer.
    3. Root cause analysis
    4. Reserve analysis

    Explanation

    Document analysis is the structured review of project documents such as contracts, plans, and historical records to uncover uncertainties and inconsistencies that may create risk. It works because weaknesses and gaps often show up in the written record before they appear in discussion.

  96. Question 96Risk Identification

    What does a SWOT analysis contribute to the Identify Risks process?

    1. It assigns a single risk owner to every identified event
    2. It replaces the need for expert judgment during the identification process
    3. It broadens risk thinking to internal and external factors Correct answer.
    4. It ranks the identified risks in order of their expected monetary value

    Explanation

    SWOT examines strengths, weaknesses, opportunities, and threats, forcing the team to look inward at the organization and outward at the environment. This wider lens increases the chance of capturing both threats and opportunities that single-viewpoint techniques would miss.

  97. Question 97Risk Identification

    During a risk identification session, a team member starts estimating probability and expected monetary value for each risk the moment it is raised. What guidance should the facilitator give?

    1. Capture risks first and defer quantification to the analysis processes Correct answer.
    2. Record only the risks that can be quantified quickly
    3. Stop identifying risks once the ten largest have been quantified
    4. Continue, because quantification improves the quality of the identified risks

    Explanation

    Identify Risks aims at comprehensiveness; assessing probability and impact belongs to the qualitative and quantitative analysis processes that follow. Mixing the two in one session narrows the discussion and discourages participants from raising uncertainties that are hard to quantify.

  98. Question 98Risk Identification

    A project manager wants risks identified across the entire scope, not only in the areas the team already worries about. Which approach best supports this?

    1. Reviewing only the highest-cost work packages for risk
    2. Logging risks only after they become issues
    3. Using each work package in the WBS as a prompt Correct answer.
    4. Asking the sponsor which areas carry the most risk

    Explanation

    A WBS decomposes the total scope into work packages, so using each package as a prompt ensures every element is examined for uncertainty. This bottom-up coverage counteracts the tendency to focus only on familiar or high-visibility areas.

  99. Question 99Risk Identification

    Before a risk workshop, a project manager wants data on industry benchmarks, regulatory trends, and published research relevant to the project's domain. Which input supplies this?

    1. Organizational process assets, including past project registers
    2. The project charter, including its high-level budget and milestones
    3. The stakeholder engagement plan and its communication matrix
    4. Enterprise environmental factors and industry benchmarks Correct answer.

    Explanation

    Enterprise environmental factors include external conditions such as industry benchmarks, the regulatory environment, market conditions, and published studies. These shape which risks are plausible for the project and are a recognized input to Identify Risks.

  100. Question 100Risk Identification

    A risk register entry notes that if vendor staff turnover exceeds twenty percent, a delivery delay is likely. What is this warning sign called?

    1. A secondary risk created by a chosen risk response
    2. A risk appetite statement approved by the sponsor
    3. A risk trigger, which signals the risk is imminent Correct answer.
    4. A residual risk carried forward from a prior project

    Explanation

    A risk trigger is a symptom or warning sign indicating that a risk has occurred or is about to occur. Documenting triggers lets the team monitor conditions and act before the effect is felt.

  101. Question 101Risk Identification

    A team member reports that the required export permit was never obtained, so the shipment is currently held at customs. How should this be handled?

    1. As an issue in the issue log Correct answer.
    2. As a trigger condition in the risk report
    3. As a high-probability risk in the risk register
    4. As an opportunity to be recorded in the risk register

    Explanation

    A risk is an uncertain future event, whereas a condition that has already occurred and is affecting the project is an issue. Issues are recorded in the issue log and managed through the issue-resolution process; the risk register is reserved for events that may or may not happen.

  102. Question 102Risk Identification

    An organization's historical risk registers record only those risks that actually occurred. How does relying on them as the main identification source affect the new risk list?

    1. Assumptions will be misrecorded as constraints in the register
    2. Expert judgment can no longer be applied during identification
    3. Each listed risk will be given an inflated probability rating
    4. The list will tend to omit mitigated threats and all opportunities Correct answer.

    Explanation

    Historical registers capture realized events, so threats that were successfully avoided or mitigated and opportunities that were exploited leave no trace. Using such records as the primary source therefore biases identification toward past failures and understates the full risk exposure. The records must be supplemented with expert judgment, interviews, and structured techniques.

  103. Question 103Risk Analysis

    In a probability and impact matrix, what does the risk score represent?

    1. The ratio of impact to probability, used to calculate contingency reserve
    2. The product of probability and impact, used to prioritize risks Correct answer.
    3. The average of probability and impact, used to assign risk owners
    4. The sum of probability and impact, used to rank stakeholders

    Explanation

    The risk score is normally the product of probability and impact, which places a risk in a priority band on the matrix. That score helps the team decide which risks need further analysis or a response plan. Sums, ratios, and averages are not the standard basis for matrix scoring.

  104. Question 104Risk Analysis

    What does a risk data quality assessment evaluate?

    1. The total contingency reserve required for the project
    2. The accuracy, reliability, and integrity of the data used to analyze risks Correct answer.
    3. The schedule float available to each risk owner
    4. The number of risks assigned to each category in the risk breakdown structure

    Explanation

    Risk data quality assessment checks whether the information used for risk analysis is accurate, reliable, and of sufficient integrity. Poor-quality data can make probability and impact ratings misleading. It does not determine reserves, float, or category counts.

  105. Question 105Risk Analysis

    In qualitative risk analysis, a risk urgency assessment is used to determine what?

    1. The total monetary value of all identified risks
    2. The probability that a risk will occur
    3. Which risks should be transferred to a vendor
    4. How soon a response may be needed Correct answer.

    Explanation

    Urgency assessment considers how soon a risk response may need to be implemented. It helps prioritize risks that cannot wait for the normal response cycle. Probability and monetary value are separate attributes, and transfer selection is a response strategy decision.

  106. Question 106Risk Analysis

    Categorizing risks by their source in a risk breakdown structure primarily helps to do what?

    1. Assign a numerical probability to every risk
    2. Reveal common root causes and risk concentration Correct answer.
    3. Determine the project budget and schedule baseline
    4. Calculate the expected monetary value of each risk

    Explanation

    Categorization by source groups risks so the team can see patterns, common causes, and areas where risk is concentrated. This supports focused response planning and better communication. It does not itself calculate EMV, set baselines, or assign probabilities.

  107. Question 107Risk Analysis

    Expected monetary value for a risk is calculated as what?

    1. Probability plus impact
    2. Impact divided by probability of occurrence
    3. Probability multiplied by impact Correct answer.
    4. Impact minus probability

    Explanation

    Expected monetary value is the probability of the risk event multiplied by its financial impact. It gives a weighted average value for the risk outcome. Addition, subtraction, and division do not produce the expected value.

  108. Question 108Risk Analysis

    Monte Carlo simulation is best classified as what type of technique?

    1. Risk response planning technique using contractual agreements
    2. Qualitative risk analysis technique
    3. Risk identification technique using structured brainstorming sessions
    4. Quantitative technique using repeated random sampling Correct answer.

    Explanation

    Monte Carlo simulation is a quantitative risk analysis technique that repeatedly samples from input distributions to model possible outcomes. It produces probabilistic results for cost or schedule. It is not a qualitative, identification, or response-planning technique.

  109. Question 109Risk Analysis

    Risk tolerance is best described as what?

    1. The amount of risk a project manager personally prefers to accept
    2. The maximum contingency reserve allowed by organizational policy
    3. The total number of risks that a project can have in its register
    4. The uncertainty an organization will accept to pursue objectives Correct answer.

    Explanation

    Risk tolerance reflects the amount or degree of uncertainty an organization is willing to withstand in pursuit of its objectives. It is broader than a single project manager's preference. It is not a count of risks or a reserve ceiling.

  110. Question 110Risk Analysis

    Which output is produced by Perform Qualitative Risk Analysis?

    1. The approved project management plan
    2. The final project schedule baseline
    3. Risk register updates including risk rankings and priority Correct answer.
    4. The detailed risk response strategy for each individual risk

    Explanation

    Qualitative risk analysis updates the risk register with priority rankings, categories, and other assessments. These updates guide which risks receive further analysis or response planning. The project management plan, schedule baseline, and detailed response strategies are not outputs of this process.

  111. Question 111Risk Analysis

    A tornado diagram is used in quantitative risk analysis to do what?

    1. Display relative influence of uncertain variables on an outcome Correct answer.
    2. Document risk owners and their responsibilities
    3. Show how the probability of each identified risk changes over time
    4. Rank risks by their urgency for response

    Explanation

    A tornado diagram displays sensitivity analysis results, showing which uncertain variables have the greatest influence on a project outcome. Variables are typically ordered from largest to smallest effect. It does not track probability over time, urgency, or ownership.

  112. Question 112Risk Analysis

    Decision tree analysis uses expected monetary value to do what?

    1. Identify all possible risks in a project
    2. Determine the risk appetite of stakeholders
    3. Calculate the schedule variance and performance index of each activity
    4. Compare the expected value of alternative courses of action Correct answer.

    Explanation

    Decision tree analysis calculates the expected monetary value of branches representing alternative decisions and uncertain outcomes. This allows comparison of options under uncertainty. It does not identify risks, calculate schedule variance, or determine stakeholder risk appetite.

  113. Question 113Risk Analysis

    In quantitative risk analysis, the contingency reserve is typically derived from what?

    1. The sum of all identified risk impacts without probability weighting
    2. The total budget allocated for risk response actions
    3. The gap between the deterministic estimate and probabilistic result Correct answer.
    4. The project's planned profit margin

    Explanation

    Contingency reserve is often set as the difference between a deterministic estimate and a probabilistic result at a chosen confidence level. It covers known-unknown risks and overall project uncertainty. It is not based on profit margin, unweighted impacts, or only response-action budgets.

  114. Question 114Risk Analysis

    In a quantitative risk model, positive correlation between two cost variables means what?

    1. When one variable is high, the other also tends to be high Correct answer.
    2. The variables have no effect on the project
    3. One variable always rises while the other falls
    4. The variables are statistically independent

    Explanation

    Positive correlation means the variables tend to move in the same direction. If one cost variable is high, the other is likely to be high as well. Independence and inverse movement describe different correlation relationships.

  115. Question 115Risk Analysis

    Risk appetite differs from risk tolerance in that risk appetite does what?

    1. Describes the risk an organization is willing to seek or retain Correct answer.
    2. Is the maximum deviation allowed from a threshold
    3. Is the same as a risk threshold
    4. Only applies to negative risks

    Explanation

    Risk appetite describes the amount and type of risk an organization is willing to seek or retain in pursuit of value. Tolerance is more about the acceptable variation around thresholds. Appetite applies to both opportunity and threat considerations.

  116. Question 116Risk Analysis

    The Delphi technique is used in risk analysis to do what?

    1. Simulate project cost and schedule outcomes using random sampling
    2. Assign risks to response owners
    3. Calculate the expected monetary value of each identified risk
    4. Reach expert consensus through anonymous iterative questionnaires Correct answer.

    Explanation

    Delphi gathers expert input anonymously over several rounds to reduce bias and converge on consensus. It is useful when expert opinion is needed without dominant personalities influencing the group. It is not a simulation, EMV calculation, or ownership assignment method.

  117. Question 117Risk Analysis

    Assumption analysis in risk analysis is performed to do what?

    1. Calculate the contingency reserve for all known risks
    2. Remove assumptions from the project charter
    3. Confirm that all project assumptions are correct
    4. Identify risks arising from inaccurate or unstable assumptions Correct answer.

    Explanation

    Assumption analysis examines whether project assumptions are valid and stable, and it identifies risks created when they are not. Assumptions are not automatically correct or removed. Reserve calculation is a separate quantitative or planning activity.

  118. Question 118Risk Analysis

    In a probability and impact matrix, a risk in the high-risk zone should generally be what?

    1. Given priority for response planning Correct answer.
    2. Added to the watch list only
    3. Ignored until it occurs
    4. Accepted without further action and monitored periodically

    Explanation

    Risks in the high-risk zone require priority attention, often including a response plan and management focus. Watch-list treatment is more appropriate for lower-rated risks. Ignoring or simply accepting a high risk is usually not appropriate.

  119. Question 119Risk Analysis

    A risk has a 30% probability of a $50,000 loss and a 70% probability of no impact. What is its expected monetary value?

    1. –$15,000 Correct answer.
    2. –$50,000
    3. –$35,000
    4. –$5,000

    Explanation

    Expected monetary value is 0.30 multiplied by –$50,000, which equals –$15,000. The no-impact branch contributes zero. The other values do not result from the correct weighting.

  120. Question 120Risk Analysis

    Which item is an output of Perform Quantitative Risk Analysis?

    1. The communications management plan and stakeholder engagement plan
    2. The stakeholder register
    3. Probabilistic analysis of project cost and schedule outcomes Correct answer.
    4. The approved risk management plan and its subsidiary plans

    Explanation

    Quantitative risk analysis produces probabilistic assessments of project cost and schedule outcomes, often with confidence levels. These results support reserve setting and decision-making. The other documents are developed in different planning processes.

  121. Question 121Risk Analysis

    When prioritizing risks qualitatively, which combination typically receives the highest priority?

    1. High probability and low impact with no urgency
    2. Low probability and high impact
    3. Low probability and low impact
    4. High probability and high impact Correct answer.

    Explanation

    The highest priority generally goes to risks with both high probability and high impact because their expected exposure is greatest. Low-probability or low-impact risks usually receive lower priority unless other factors apply. Urgency can adjust priority but does not replace the probability-impact assessment.

  122. Question 122Risk Analysis

    Which input is most essential for a reliable Monte Carlo schedule simulation?

    1. Probability distributions for activity durations Correct answer.
    2. The approved project charter and business case
    3. The communications management plan and schedule
    4. The stakeholder engagement plan and register

    Explanation

    Monte Carlo schedule simulation requires probability distributions for activity durations or other model inputs. Without realistic distributions, the simulation results are not meaningful. Charter, stakeholder, and communications documents do not provide the variability needed for the model.

  123. Question 123Risk Analysis

    Latin hypercube sampling is used in quantitative risk analysis primarily to do what?

    1. Improve simulation sampling efficiency across the distribution Correct answer.
    2. Calculate deterministic point estimates for each activity
    3. Replace the need for a risk register
    4. Eliminate all uncertainty from the model

    Explanation

    Latin hypercube sampling stratifies the input distribution so samples are spread more evenly, improving simulation efficiency. It does not remove uncertainty or produce deterministic estimates. A risk register is still needed to identify and manage risks.

  124. Question 124Risk Analysis

    Option A has a 60% chance of $100,000 profit and a 40% chance of $40,000 profit. Option B has a 50% chance of $150,000 profit and a 50% chance of $0 profit. Which option has the higher expected monetary value, and what is that value?

    1. Option A with $60,000
    2. Option A with $76,000 Correct answer.
    3. Option B with $150,000
    4. Option B with $75,000

    Explanation

    Option A's EMV is 0.60 × $100,000 plus 0.40 × $40,000, which equals $76,000. Option B's EMV is 0.50 × $150,000 plus 0.50 × $0, which equals $75,000. Therefore Option A is slightly higher.

  125. Question 125Risk Analysis

    Why is risk analysis often repeated throughout the project?

    1. Because the risk register is created only once
    2. Because quantitative analysis is required only at project closure
    3. Because qualitative analysis must precede risk identification
    4. Because new risks emerge and existing risks change over time Correct answer.

    Explanation

    Risk analysis is iterative because the project environment changes, new risks appear, and the probability or impact of known risks can change. Reassessment keeps priorities and responses current. Risk identification precedes qualitative analysis, not the reverse.

  126. Question 126Risk Analysis

    Which technique models the combined effect of individual project risks and other sources of uncertainty on project objectives?

    1. Risk categorization
    2. Monte Carlo simulation Correct answer.
    3. Probability and impact matrix
    4. Risk urgency assessment

    Explanation

    Monte Carlo simulation can combine individual risk events with general uncertainty in cost and schedule variables to model overall project outcomes. It produces a probabilistic distribution rather than a single rating. Categorization, matrices, and urgency assessment do not model combined effects.

  127. Question 127Risk Analysis

    A key limitation of relying only on expert judgment in qualitative risk analysis is what?

    1. It can introduce subjective bias into risk ratings Correct answer.
    2. It eliminates the need for historical data
    3. It always produces quantitative results
    4. It cannot be combined with a probability and impact matrix

    Explanation

    Expert judgment is valuable but can be affected by individual bias, anchoring, or group pressure. Structured techniques and historical data help counter this limitation. Expert judgment is not inherently quantitative and can be used with a probability and impact matrix.

  128. Question 128Risk Analysis

    While performing qualitative risk analysis, a project team notices that many risk register entries have no documented basis, no owner confirmation, and come from a single unverified source. Which technique is intended to address this situation?

    1. Run a sensitivity analysis on the affected risk register entries to see which ones matter most
    2. Move the affected risks to the watch list and defer all further analysis until better data becomes available
    3. Perform a risk data quality assessment to evaluate the reliability, objectivity, and completeness of the risk information Correct answer.
    4. Recalculate the expected monetary value of each affected risk so that the numbers are more precise

    Explanation

    Risk data quality assessment examines whether risk information is accurate, objective, complete, timely, and drawn from credible sources. Because prioritization is only as trustworthy as the data behind it, this technique flags entries needing better data before ranking proceeds. It assesses quality rather than correcting the underlying risk data itself.

  129. Question 129Risk Analysis

    Two risks receive identical probability and impact scores in the matrix, but one is expected to materialize within the next two weeks and the other late in the final phase. Which qualitative analysis step lets the team differentiate them?

    1. Risk urgency assessment, which considers how soon a response must be initiated for the risk Correct answer.
    2. Reserve analysis on the contingency budget, which reveals which risk will occur first
    3. Placement in the probability and impact matrix, which resolves ties between risks scoring the same
    4. Risk categorization through the risk breakdown structure, grouping risks by source so each can be assigned to the right owner

    Explanation

    Risk urgency assessment examines indicators of how soon a risk may occur and how much lead time a response needs, so equal-scoring risks can be ordered by time criticality. A near-term risk may require action now even though its score matches a distant one. This step protects response lead time rather than changing the risk score itself.

  130. Question 130Risk Analysis

    A Monte Carlo cost simulation reports that the project has a 70% probability of being completed for $4.2 million or less. Which statement interprets this output correctly?

    1. The project will cost exactly $4.2 million in 70 out of every 100 simulated iterations
    2. There is a 70% chance that the actual project cost will be at or below $4.2 million Correct answer.
    3. The expected cost is found by multiplying $4.2 million by 0.70, which becomes the budget baseline
    4. The 70th percentile of the cost distribution is located at $4.2 million divided by 0.70

    Explanation

    Simulation results form a cumulative probability distribution, so a confidence level states the chance the outcome falls at or below a given value. A 70% confidence level at $4.2 million means most iterations produced costs at or under that amount. It is neither the most likely cost nor a scaling factor to apply to the estimate.

  131. Question 131Risk Analysis

    In a schedule simulation, several parallel paths converge on a single critical milestone. Individually each path has a good chance of finishing on time, yet the combined chance that all predecessors finish on time is noticeably lower. What is this effect, and how should it be modeled?

    1. Parkinson's law; a fixed percentage should be added to every activity duration on the converging paths
    2. Merge bias, or path convergence; the converging paths should be modeled jointly with their duration distributions rather than assumed to each finish as planned Correct answer.
    3. Correlation; a strong negative correlation should be assigned between the converging paths to offset the loss
    4. Dependency inversion; the milestone should be removed from the model and treated as an external constraint on the receiving paths

    Explanation

    Merge bias occurs because the chance that every converging predecessor meets its date is the combined probability of all of them, which is lower than any single path's chance. The deterministic plan, built on planned dates, hides this effect. Simulation captures it when durations are entered as distributions and the paths are modeled jointly.

  132. Question 132Risk Analysis

    A team scores risks by assigning ordinal ratings from 1 to 5 for probability and 1 to 5 for impact, then multiplying the two ratings together. What is the main analytical weakness of this approach?

    1. Ordinal ratings establish rank order but not equal intervals, so the products are not proportional to real risk exposure Correct answer.
    2. Multiplying probability by impact ignores the organization's stated risk appetite and tolerance thresholds
    3. The multiplication routinely produces scores that exceed the agreed high-risk threshold and so must be normalized
    4. Probability and impact must always be added rather than multiplied, because multiplication distorts the ranking of risks with very different profiles

    Explanation

    On an ordinal scale the numbers express order only; the distance between rank 2 and rank 3 is undefined, so arithmetic on them lacks proportionality. A product of two ranks can rank risks usefully within a matrix, but it cannot be read as a magnitude of exposure. Cardinal estimates are required when quantitative comparisons are needed.

  133. Question 133Risk Analysis

    Before funding an expensive study, a project manager wants to know the ceiling on what any information about uncertain future outcomes could be worth. Which measure provides that ceiling?

    1. The expected monetary value of the decision tree as currently modeled
    2. The contingency reserve calculated from the risk register
    3. The sensitivity analysis of the highest-ranked risk
    4. The expected value of perfect information Correct answer.

    Explanation

    Expected value of perfect information equals the expected payoff with perfect information minus the expected payoff without it. It therefore caps what should be spent on any study, since real studies are costly and imperfect. If the study's cost exceeds that value, the information is not worth buying.

  134. Question 134Risk Analysis

    A team wants to evaluate the project under a few coherent combinations of conditions, such as a pessimistic, a base, and an optimistic future. Which technique fits, and how does it differ from sensitivity analysis?

    1. Monte Carlo simulation, which produces a full probability distribution instead of considering discrete futures
    2. A tornado diagram, which ranks each uncertain variable by its individual contribution to the outcome
    3. Decision tree analysis, which maps sequential decisions and chance nodes rather than alternative futures
    4. Scenario analysis, which varies several factors together to build internally consistent futures, unlike sensitivity analysis, which varies one factor at a time Correct answer.

    Explanation

    Scenario analysis evaluates the project under a small number of coherent, plausible combinations of conditions, so interactions among factors are reflected. Sensitivity analysis instead isolates one variable at a time and holds others constant, which misses combined effects. Both differ from simulation, which samples the full range of inputs.

  135. Question 135Risk Analysis

    A quantitative risk model contains nonlinear relationships, for example cost that rises faster than the size of a scope change. It is run once using only the most likely value of every input, yielding a single-point result. How does that result compare with the distributional simulation?

    1. It is higher, because deterministic single-point models systematically overstate cost while simulations systematically understate it
    2. It is identical, because the most likely value of each input coincides with the peak of its distribution and is therefore the best single estimate
    3. It is unbiased but reported with a narrower confidence interval, since only one iteration was executed instead of a full range
    4. It is biased, because for a nonlinear model the output computed at average inputs differs from the average output across the input distribution Correct answer.

    Explanation

    This is the flaw of averages: substituting expected or most likely inputs into a nonlinear model does not yield the expected output. Simulation propagates whole input distributions and therefore produces the distribution of outcomes. Relying on one point estimate can consistently mislead decision makers even when every input was estimated well.

  136. Question 136Risk Analysis

    In a schedule risk analysis, an activity has a very wide duration range, from 20 to 90 days, but lies on a path with 60 days of total float. The near-critical paths have almost no float. How should the activity's influence on the project completion date be assessed?

    1. It should be excluded from the simulation, because a path with 60 days of float removes the activity's variability from the model
    2. Its variability is largely absorbed by float, so it contributes little to completion-date risk and the near-critical paths should drive the analysis Correct answer.
    3. It is the single largest driver of completion-date risk, because its duration range is the widest of any activity in the model
    4. It should be given the highest probability of occurrence in the risk register so that it is reported alongside the top project risks

    Explanation

    Contribution to completion-date risk depends on both the variability of an activity and the slack available before that variability can reach a milestone. Wide uncertainty on a path with ample float rarely propagates to the end date, while modest uncertainty on a near-critical path flows straight through. The analysis should therefore weight near-critical paths more heavily.

  137. Question 137Risk Response Implementation

    During risk response implementation, who is accountable for executing the agreed response and monitoring its trigger conditions?

    1. The project manager, who holds all accountability
    2. The risk owner assigned to the risk Correct answer.
    3. The project sponsor who funds the response
    4. The PMO risk analyst who maintains the register

    Explanation

    Each identified risk is assigned to a named risk owner who is accountable for monitoring the risk and carrying out the agreed response. The project manager integrates and supports the work but does not absorb accountability for every individual risk.

  138. Question 138Risk Response Implementation

    A team has a primary response in place for a critical supplier delay and has also documented a backup approach to use only if the primary response proves ineffective. What is this backup approach called?

    1. Contingency plan
    2. Fallback plan Correct answer.
    3. Workaround
    4. Corrective action

    Explanation

    A fallback plan is prepared in advance for use if the primary response turns out to be insufficient or ineffective. A contingency plan, by contrast, is executed when the defined trigger condition for the risk occurs.

  139. Question 139Risk Response Implementation

    A previously unidentified risk occurs and the team responds immediately using a solution that was never planned or approved in advance. This unplanned response is best described as a:

    1. Fallback plan
    2. Contingency plan
    3. Secondary response
    4. Workaround Correct answer.

    Explanation

    A workaround is a response developed and applied after a risk that was not identified during planning actually occurs. Because it was unplanned, the risk register and, once the risk materializes, the issue log should be updated.

  140. Question 140Risk Response Implementation

    Which reserve is established to fund approved response plans for identified risks?

    1. Contingency reserve Correct answer.
    2. Cost baseline reallocation
    3. Funding limit reconciliation
    4. Management reserve

    Explanation

    The contingency reserve is set aside to fund approved response plans for identified, known risks. Management reserve, in contrast, covers unforeseen work outside the scope baseline.

  141. Question 141Risk Response Implementation

    After a risk response has been planned and implemented, the exposure that still remains is called:

    1. Accepted risk
    2. Inherent risk
    3. Residual risk Correct answer.
    4. Secondary risk

    Explanation

    Residual risk is what remains after responses have been planned and implemented, and it should be documented and accepted by the appropriate authority. It is a normal outcome of any response strategy.

  142. Question 142Risk Response Implementation

    Implementing a risk response creates a new risk that did not exist before. That new risk is called a:

    1. Secondary risk Correct answer.
    2. Residual risk
    3. Trigger risk
    4. Contingency risk

    Explanation

    A secondary risk arises directly from implementing a response and should be identified, analyzed, and assigned an owner like any other risk. It differs from residual risk, which is what remains of the original exposure.

  143. Question 143Risk Response Implementation

    Which action is an example of the transfer response strategy?

    1. Accepting the risk and monitoring it monthly
    2. Adding schedule float to a critical activity
    3. Building a prototype to test the design early
    4. Purchasing insurance for a construction site Correct answer.

    Explanation

    Transfer shifts the financial consequence of a risk, and ownership of the response, to a third party without eliminating the risk. Insurance is the classic example, since the event can still occur and other impacts may be retained.

  144. Question 144Risk Response Implementation

    An identified risk materializes and now requires active management and resolution. Where should this be recorded?

    1. The issue log Correct answer.
    2. The lessons learned register
    3. The risk register entry only
    4. The change log

    Explanation

    When an identified risk actually occurs it becomes an issue and is tracked in the issue log, where it is assigned, actioned, and closed. The risk register is also updated to reflect the change in status.

  145. Question 145Risk Response Implementation

    A buyer wants to place as much cost-overrun risk as possible on the seller. Which contract type best achieves this?

    1. Cost-plus-fixed-fee contract
    2. Firm-fixed-price contract Correct answer.
    3. Cost-plus-incentive-fee contract
    4. Time-and-materials contract

    Explanation

    Under a firm-fixed-price contract the seller bears the cost of overruns, which places the greatest cost risk on the seller. Cost-reimbursable and time-and-materials arrangements leave more cost risk with the buyer.

  146. Question 146Risk Response Implementation

    A risk owner defines a measurable indicator that will signal that a risk is about to occur so the contingency plan can be activated. This indicator is best described as a:

    1. Risk threshold
    2. Trigger condition Correct answer.
    3. Workaround
    4. Residual risk

    Explanation

    Trigger conditions are early warning indicators defined during planning that signal a risk is imminent or has occurred. They let the owner activate the contingency plan at the right moment rather than reacting late.

  147. Question 147Risk Response Implementation

    A required risk response exceeds the project manager's delegated spending authority. What is the most appropriate action?

    1. Escalate the risk to the level with approval authority Correct answer.
    2. Draw on the management reserve and proceed quietly
    3. Defer the risk until it becomes an issue
    4. Record the risk as accepted and close the entry

    Explanation

    Risks and responses that exceed the project manager's delegated authority must be escalated to the level that can approve the required funds or action. Escalation transfers ownership of the response, not the obligation to keep monitoring the risk.

  148. Question 148Risk Response Implementation

    Management reserve is used to fund:

    1. Unforeseen risks that were never identified Correct answer.
    2. Known risks that already have approved response plans
    3. Workarounds applied to identified risks
    4. Secondary risks created by implemented responses

    Explanation

    Management reserve is held for unforeseen risks that were not identified during risk planning and typically requires sponsor approval to use. Contingency reserve, by contrast, is allocated to identified risks with approved responses.

  149. Question 149Risk Response Implementation

    Once a risk response has been executed, what is the most appropriate update to the risk register?

    1. Move the risk to the assumption log and close it
    2. Delete the risk because the response has been executed
    3. Replace the risk with the action in the schedule
    4. Record status, residual risk, and effectiveness Correct answer.

    Explanation

    The risk register is a living document; after a response is executed it should show implementation status, the residual risk, and the owner's judgment about effectiveness. Deleting the entry would destroy the history needed for audits and lessons learned.

  150. Question 150Risk Response Implementation

    Which action reflects passive acceptance of an identified risk?

    1. Fund any occurrence from the management reserve on request
    2. Transfer it to the customer through a contract change
    3. Document the risk and monitor it with no reserve set aside Correct answer.
    4. Do nothing at all and leave the risk undocumented entirely

    Explanation

    Passive acceptance means documenting the risk and monitoring it without allocating contingency reserve or taking proactive action unless the risk occurs. Active acceptance involves establishing a contingency reserve and a trigger-based plan.

  151. Question 151Risk Response Implementation

    A team identifies an opportunity to finish a critical deliverable early and assigns its two most experienced developers to guarantee that it happens. Which response strategy is being applied?

    1. Accept
    2. Share
    3. Exploit Correct answer.
    4. Enhance

    Explanation

    Exploit is used for opportunities the organization wants to be certain to realize; it removes uncertainty by acting to make the opportunity happen. Enhance raises probability or impact but does not guarantee the outcome.

  152. Question 152Risk Response Implementation

    A company forms a joint venture with a partner to pursue a business opportunity it could not pursue alone. Which opportunity strategy does this illustrate?

    1. Enhance
    2. Share Correct answer.
    3. Mitigate
    4. Exploit

    Explanation

    Sharing allocates ownership of an opportunity, and often its benefits, to a third party better able to capture it, such as through a joint venture or teaming agreement. The project keeps only part of the benefit.

  153. Question 153Risk Response Implementation

    To raise the probability that a favorable regulatory decision will occur, the team hires a specialist to strengthen its submission. Which strategy is this?

    1. Enhance Correct answer.
    2. Exploit
    3. Share
    4. Escalate

    Explanation

    Enhance increases the probability and/or the positive impact of an opportunity without removing the uncertainty. Exploit would instead act to make the opportunity certain.

  154. Question 154Risk Response Implementation

    A stakeholder states that the project can tolerate schedule slippage of up to five days but no more, and the team must act if that level is approached. This statement represents a:

    1. Secondary risk
    2. Contingency plan
    3. Residual risk
    4. Risk threshold Correct answer.

    Explanation

    A risk threshold is the measurable level of exposure above which the organization will not accept the risk and must act. Appetite describes broad willingness to take risk; the threshold makes it operational.

  155. Question 155Risk Response Implementation

    A risk has a 30 percent probability of a $50,000 impact and a 70 percent probability of no impact. What is its expected monetary value?

    1. $15,000 Correct answer.
    2. $3,500
    3. $50,000
    4. $35,000

    Explanation

    EMV is the probability of the event multiplied by its impact: 0.30 x $50,000 = $15,000. This value informs how much contingency reserve should be held for that risk.

  156. Question 156Risk Response Implementation

    The primary purpose of a risk audit during response implementation is to:

    1. Recalculate the project contingency reserve
    2. Obtain sponsor approval of the risk management plan
    3. Assign owners to newly identified risks
    4. Examine whether responses are effective and applied Correct answer.

    Explanation

    A risk audit examines the risk process and the implemented responses to determine whether they are effective and being applied as planned. It produces findings and recommendations rather than merely assigning owners.

  157. Question 157Risk Response Implementation

    Implementing a chosen mitigation response will add two weeks to the schedule and require additional budget. What must occur before the response is executed?

    1. An update to the lessons learned register and nothing more
    2. A verbal agreement from the risk owner recorded in the register
    3. Automatic use of the management reserve by the sponsor
    4. An approved change request through integrated change control Correct answer.

    Explanation

    A response that changes approved baselines must go through integrated change control, and only an approved change request authorizes the revisions. Implementing baseline changes without that approval bypasses project governance.

  158. Question 158Risk Response Implementation

    Halfway through implementation, the risk owner for a high-priority risk leaves the organization. What is the best course of action?

    1. Convert the risk to an issue and stop monitoring it
    2. Reassign ownership and brief the new owner on triggers Correct answer.
    3. Wait until a replacement is appointed before any action
    4. Close the risk and record it in the lessons learned register

    Explanation

    Accountability for a risk must not lapse when an owner leaves; ownership is reassigned and the new owner is briefed on the response, trigger conditions, and reporting. Leaving the exposure unowned undermines the entire response plan.

  159. Question 159Risk Response Implementation

    Reserve analysis shows a contingency reserve of $80,000 while the combined expected monetary value of active risks is $120,000. What does this indicate?

    1. The reserve covers all active risks and the surplus can be released
    2. The reserve is fully sufficient, so no further action is needed
    3. The management reserve must be eliminated to offset the shortfall
    4. The reserve may be insufficient and should be re-evaluated Correct answer.

    Explanation

    When the aggregate EMV of active risks exceeds the contingency reserve, the reserve may not cover the expected exposure. The risk manager should re-evaluate the reserve and escalate for additional funding or changes to the response plans.

  160. Question 160Risk Response Implementation

    A project buys an insurance policy with a $20,000 deductible covering a $500,000 exposure. How is the $20,000 best described?

    1. A transferred risk still borne by the insurer
    2. A secondary risk created by the insurance policy
    3. A management reserve allocation held by the sponsor
    4. A residual risk retained by the project Correct answer.

    Explanation

    A deductible is the portion of a loss the project retains after the insurance response is applied, which is a residual risk. Insurance transfers the covered portion but never the entire exposure.

  161. Question 161Risk Response Implementation

    After three months, a risk owner reports that the implemented mitigation has not reduced the risk's probability as expected. What is the best course of action?

    1. Reassess the response and implement an alternative Correct answer.
    2. Reclassify the risk as an issue and stop monitoring it
    3. Close the risk because a response was already implemented
    4. Increase the contingency reserve without changing the plan

    Explanation

    A response that is not achieving the intended reduction in probability or impact is failing and must be reassessed. If it cannot be corrected, select and implement a different response and update the risk register accordingly.

  162. Question 162Risk Response Implementation

    What is the primary purpose of the Implement Risk Responses process?

    1. To determine which risks should be transferred to a third party
    2. To identify new risks that were not captured during risk planning
    3. To assign a monetary value to each identified project risk
    4. To ensure that agreed-upon risk responses are executed as planned Correct answer.

    Explanation

    Implement Risk Responses exists to close the gap between what was planned and what is actually done, ensuring risk owners execute the agreed responses and that their effect is tracked. It is an execution-phase process rather than an identification or planning one.

  163. Question 163Risk Response Implementation

    During execution, an event occurs that was never entered in the risk register. The team must act immediately to keep the project moving. The action the team improvises is best described as a:

    1. Contingency plan
    2. Fallback plan
    3. Workaround Correct answer.
    4. Secondary response

    Explanation

    A workaround is an unplanned response to a risk that has materialized without having been identified in advance, so no pre-agreed plan exists. By contrast, contingency and fallback plans presuppose a previously identified risk.

  164. Question 164Risk Response Implementation

    A contingency plan has been triggered for an identified risk, but the response is not producing the intended result. The team turns to a pre-prepared alternative course of action kept in reserve. This alternative is called a:

    1. A contingency reserve
    2. A secondary risk
    3. A management reserve
    4. A fallback plan Correct answer.

    Explanation

    A fallback plan is a predetermined alternative that is used if the primary response proves inadequate after the risk occurs. It is developed during response planning so the team is not improvising under pressure.

  165. Question 165Risk Response Implementation

    While implementing an approved mitigation, the risk owner discovers that the response now conflicts with a newly issued regulation. What is the most appropriate course of action?

    1. Remove the risk from the risk register because the response can no longer be applied
    2. Evaluate alternative responses and submit a change request to revise the approved response Correct answer.
    3. Continue the approved response and note the conflict in the risk register
    4. Ask the team to absorb the regulatory impact using the contingency reserve

    Explanation

    An approved response is part of the baselined risk management approach; changing it requires evaluation of alternatives and formal handling through integrated change control. The risk itself remains valid and must still be addressed with a compliant response.

  166. Question 166Risk Response Implementation

    A mitigation has been fully implemented, yet a small amount of exposure remains because eliminating it entirely would cost more than the benefit. This remaining exposure is best described as:

    1. A secondary risk
    2. Residual risk Correct answer.
    3. A contingency plan
    4. A fallback plan

    Explanation

    Residual risk is the exposure that remains after a response has been implemented and accepted by the project team. It should be documented and monitored rather than assumed to have vanished.

  167. Question 167Risk Response Implementation

    A risk is assessed as falling outside the project's scope and authority, and the project team has no ability to influence it. Which response strategy is most appropriate?

    1. Escalate the risk to the appropriate level of the organization Correct answer.
    2. Transfer the risk to a vendor under a fixed-price contract
    3. Accept the risk and monitor it in the risk register
    4. Mitigate the risk by adding schedule buffer to the critical path

    Explanation

    Escalation is used when a risk lies beyond the project's scope or authority, so it is passed to the program, portfolio, or other level that can manage it. The project still records the risk and communicates it, but ownership moves upward.

  168. Question 168Risk Response Implementation

    To avoid a high-severity regulatory risk, the project team removes a feature from the scope baseline. Two months later, a key stakeholder demands that the feature be restored. What is the most appropriate course of action?

    1. Restore the feature, because stakeholders outrank the project manager on scope decisions
    2. Fund the feature's redevelopment from the contingency reserve and re-implement it
    3. Refuse the request and simply log the stakeholder's concern in the issue log
    4. Evaluate the change through integrated change control and reassess the associated risk before deciding Correct answer.

    Explanation

    Avoidance changed the scope baseline, so reversing it is a change that must pass through integrated change control and be accompanied by a fresh risk assessment. Only then can the team judge whether the restored scope reintroduces an unacceptable exposure.

  169. Question 169Risk Monitoring and Reporting

    What is the primary purpose of a risk audit?

    1. To approve revisions to the risk management plan
    2. To assign owners to newly identified project risks
    3. To evaluate how effective the risk process is Correct answer.
    4. To calculate the total contingency reserve required

    Explanation

    A risk audit is a structured examination of how well the risk management process is being applied and whether its outputs are effective. It focuses on process quality and compliance rather than on the status of individual risks. Findings feed corrective actions and process improvement.

  170. Question 170Risk Monitoring and Reporting

    During a weekly review, a team member reports that a previously identified risk's probability has dropped significantly after a design change. What should the risk manager do first?

    1. Escalate the change to the project sponsor for approval
    2. Close the risk and remove it from the risk register
    3. Update the risk register with the revised probability assessment Correct answer.
    4. Release the associated contingency reserve to the project budget

    Explanation

    The risk register is a living document; when new information changes an assessed probability or impact, the entry must be updated promptly. Reserve adjustments and escalation decisions are evaluated afterwards, based on the revised assessment.

  171. Question 171Risk Monitoring and Reporting

    What is a risk trigger?

    1. The person accountable for monitoring a specific risk
    2. The amount of budget set aside for risk responses
    3. A documented response to a risk that has already occurred
    4. An event or condition indicating a risk is about to occur Correct answer.

    Explanation

    A trigger is an observable condition or event that signals a risk is imminent or has occurred, allowing the planned response to be activated. It is distinct from the risk owner, the response itself, and the reserve.

  172. Question 172Risk Monitoring and Reporting

    Which item is typically the primary focus of a periodic risk report to stakeholders?

    1. The complete list of all project team assignments
    2. The project schedule baseline and its approval history
    3. Current risk exposure, trends, and status of key responses Correct answer.
    4. Detailed cost estimates for every project activity

    Explanation

    Periodic risk reporting gives stakeholders a clear picture of current exposure, trends, and the status of key responses so they can make informed decisions. Activity-level cost, staffing, and baseline history belong in other reports.

  173. Question 173Risk Monitoring and Reporting

    What is residual risk?

    1. Risk that has occurred and become an issue
    2. Risk that was never entered in the risk register
    3. Risk remaining after a response has been implemented Correct answer.
    4. Risk created as a direct result of a risk response

    Explanation

    Residual risk is what remains after the planned response has been applied, and it must be acceptable to the organization. Secondary risk, by contrast, is a new risk created by the response itself.

  174. Question 174Risk Monitoring and Reporting

    Whose responsibility is it to monitor a specific risk and its response on an ongoing basis?

    1. The project sponsor
    2. The PMO risk administrator
    3. The assigned risk owner Correct answer.
    4. The project scheduler

    Explanation

    The risk owner is accountable for watching the assigned risk, tracking triggers, executing the response, and reporting status. Others may support the effort, but accountability sits with the named owner.

  175. Question 175Risk Monitoring and Reporting

    A risk burndown chart is used to display what?

    1. The total budget spent on risk responses
    2. Cumulative risk exposure remaining over time Correct answer.
    3. The count of risks assigned to each owner
    4. The number of issues closed each sprint

    Explanation

    A risk burndown chart plots cumulative risk exposure, often severity-weighted, against time to show whether exposure is being reduced as the project progresses. It does not track cost, issue counts, or ownership distribution.

  176. Question 176Risk Monitoring and Reporting

    When can a risk be formally closed in the risk register?

    1. Only at the end of the project during lessons learned
    2. When the risk owner is reassigned to another project
    3. When the risk is no longer relevant or has occurred and been resolved Correct answer.
    4. As soon as its response plan has been documented

    Explanation

    A risk is closed when it can no longer affect the project, either because it has occurred and been resolved or because the related work is complete and conditions have changed. Documenting a response alone does not close a risk.

  177. Question 177Risk Monitoring and Reporting

    Trend analysis of risk data over several reporting periods shows a steady increase in the number of high-severity risks. What does this most likely indicate?

    1. The risk register contains duplicate entries
    2. Overall risk exposure is worsening and needs attention Correct answer.
    3. The project is over budget and behind schedule
    4. The risk identification process is now less effective than before

    Explanation

    Trend analysis examines the direction of risk data across reporting periods. A steadily rising count of high-severity risks points to growing exposure that warrants review of responses and reserves.

  178. Question 178Risk Monitoring and Reporting

    A project has consumed 80 percent of its contingency reserve while only 40 percent of the work is complete. What is the best interpretation?

    1. The project is performing better than planned on risk
    2. Response costs exceed expectations and need review Correct answer.
    3. The reserve was sized too large and should be reduced
    4. Management reserve should be eliminated from the budget

    Explanation

    Reserve consumption should be roughly proportionate to work completed and risk realized. Burning reserve far ahead of progress suggests responses are costing more than planned or more risks have materialized, which calls for analysis and corrective action.

  179. Question 179Risk Monitoring and Reporting

    Which situation should trigger a full reassessment of the project's risks?

    1. A stakeholder requests a copy of the risk report
    2. A team member requests a day off
    3. A major scope change is approved Correct answer.
    4. A routine status meeting is rescheduled

    Explanation

    Significant changes such as approved scope changes, major schedule shifts, or key personnel turnover alter the risk landscape and should trigger reassessment. Routine administrative events do not.

  180. Question 180Risk Monitoring and Reporting

    Technical performance measurement is used in risk monitoring primarily to do what?

    1. Rank all identified risks by their probability and impact
    2. Determine the expected monetary value of each risk response
    3. Calculate the schedule variance for each individual work package
    4. Compare achieved technical parameters with planned values Correct answer.

    Explanation

    Technical performance measurement compares achieved technical parameters with planned values, and deviations act as early warning signs of risk. It complements cost and schedule earned value analysis.

  181. Question 181Risk Monitoring and Reporting

    A risk exceeds the project manager's authority threshold and threatens a program-level objective. What should the project manager do?

    1. Transfer the risk to a contractor through a change order
    2. Close the risk because it is outside project scope
    3. Accept the risk and continue monitoring it locally
    4. Escalate the risk to the appropriate authority Correct answer.

    Explanation

    Escalation moves the risk to the level that has the authority and resources to address it, in line with the escalation criteria in the risk management plan. Accepting or closing it locally would leave the threat unmanaged.

  182. Question 182Risk Monitoring and Reporting

    A risk occurs that was never identified, and the team responds immediately without a pre-approved plan. This response is best described as which of the following?

    1. A workaround Correct answer.
    2. A fallback plan
    3. A contingency plan
    4. A risk transfer

    Explanation

    A workaround is an unplanned response to a risk that was not identified in advance, executed when the risk occurs. Contingency and fallback plans are prepared beforehand.

  183. Question 183Risk Monitoring and Reporting

    During a risk review, several register entries are found to have vague descriptions and no assigned owners. Which action addresses the underlying problem?

    1. Run a risk data quality assessment and fix the entries Correct answer.
    2. Report the entries as issues in the next status meeting
    3. Delete the affected entries to keep the register clean
    4. Increase the contingency reserve to cover the uncertainty

    Explanation

    The underlying problem is poor quality risk data, so it should be addressed through a risk data quality assessment followed by corrective updates. Deleting entries or adding reserve does not fix the root cause.

  184. Question 184Risk Monitoring and Reporting

    Which statement best distinguishes a risk audit from a routine risk review?

    1. A risk audit is always conducted exclusively by the assigned risk owner
    2. An audit evaluates process effectiveness; a review updates risk status Correct answer.
    3. A risk audit is performed only once, at the very end of project closure
    4. A risk review examines process compliance, while an audit examines risk status

    Explanation

    Audits examine whether the risk process is effective and compliant, while reviews focus on the current status of risks and responses. The two serve different purposes and are not interchangeable.

  185. Question 185Risk Monitoring and Reporting

    A key risk indicator crosses its defined threshold. What is the most appropriate next step?

    1. Ignore the indicator until the next quarterly review
    2. Check the indicator against response triggers and act Correct answer.
    3. Immediately close all risks associated with the indicator
    4. Recalculate the project's earned value baseline

    Explanation

    A threshold breach on a key risk indicator means the indicator should be compared with defined triggers and the pre-agreed response enacted. Ignoring it or making unrelated changes does not address the signal.

  186. Question 186Risk Monitoring and Reporting

    After implementing a response to a schedule risk, the team notices a new risk to quality has appeared. How should this be handled?

    1. Treat it as part of the original risk and take no action
    2. Ignore it because it was not part of the original risk statement
    3. Convert it directly into a change request
    4. Record it in the risk register as a secondary risk and assess it Correct answer.

    Explanation

    A secondary risk is a new risk created by implementing a response, and it must be recorded and assessed like any other risk. It is not part of the original risk and does not automatically become a change request.

  187. Question 187Risk Monitoring and Reporting

    A risk heat map on the project dashboard shows several risks moving from the green zone to the red zone. What does this visualization convey?

    1. The risks have been successfully mitigated
    2. The risk register has too many entries to display
    3. The project is ahead of its risk response schedule
    4. Risk severity is increasing and may exceed tolerance Correct answer.

    Explanation

    A heat map plots risks by probability and impact; movement from green to red indicates higher severity and potentially a breach of risk tolerance. It is a communication tool for prioritizing management attention.

  188. Question 188Risk Monitoring and Reporting

    What is the most valuable use of lessons learned captured during risk monitoring?

    1. Providing content for the final project status report
    2. Satisfying the documentation requirements of the audit team
    3. Justifying additional contingency reserve on the current project
    4. Improving risk identification and response on future work Correct answer.

    Explanation

    Lessons learned from monitoring feed the organizational process assets so future projects identify and respond to risks more effectively. The primary value is forward-looking improvement rather than documentation compliance.

  189. Question 189Risk Monitoring and Reporting

    An updated Monte Carlo simulation shows the probability of meeting the cost baseline has fallen from 80 percent to 55 percent. What is the most appropriate interpretation?

    1. Contingency reserve is likely inadequate for the target confidence Correct answer.
    2. The project is now guaranteed to exceed its cost baseline
    3. The simulation model is invalid and should be discarded entirely
    4. The cost baseline should be lowered to restore confidence

    Explanation

    The confidence level from the simulation reflects how adequate reserve is relative to the cost baseline; a drop from 80 to 55 percent signals insufficient reserve for the target confidence. The remedy is to analyze the drivers and adjust reserve or responses, not to abandon the model.

  190. Question 190Risk Monitoring and Reporting

    A project shows favorable cost variance but a rising trend in open high-severity risks and repeated use of management reserve. What conclusion is most defensible?

    1. The risk register can be reduced to high-severity items only
    2. Management reserve should be reclassified as project profit
    3. Risk exposure is declining because costs are under budget
    4. Reported cost performance may mask growing risk exposure Correct answer.

    Explanation

    Cost performance and risk exposure are separate dimensions; favorable cost variance can coexist with rising risk. Reporting should present both so decision makers are not misled by a single indicator.

  191. Question 191Risk Monitoring and Reporting

    Repeated risk audits show that identified risks are rarely reassessed after responses are executed. Which corrective action best addresses this finding?

    1. Reduce the frequency of risk audits to save effort
    2. Require reassessment after each response in the risk process Correct answer.
    3. Reassign all risks to the project manager
    4. Add more risks to the register to increase coverage

    Explanation

    The audit finding points to a process design gap, so the corrective action is to change the process and make reassessment mandatory. Reducing audit frequency or adding risks does not fix the root cause.

  192. Question 192Risk Monitoring and Reporting

    Aggregate project risk exposure exceeds the tolerance stated in the risk management plan, but no single risk is above its individual threshold. What should be reported?

    1. Nothing, because individual risks are within their thresholds
    2. Only the largest individual risk, since it drives the exposure
    3. The aggregate breach and options to restore tolerance Correct answer.
    4. A request to lower the tolerance so the project is compliant

    Explanation

    Risk tolerance applies to aggregate exposure as well as to individual risks, so exceeding it must be reported even when no single risk breaches its own threshold. Reporting should include options for restoring exposure to within tolerance.

  193. Question 193Risk Monitoring and Reporting

    Why does consistency of data definitions and scoring scales matter for risk reporting?

    1. The register should contain only open risks at all times
    2. Consistent scoring and fields enable reliable reporting Correct answer.
    3. Reporting frequency is more important than data consistency
    4. Risk scores can be assigned differently by each team member

    Explanation

    Reliable risk reporting depends on consistent data definitions, scoring scales, and mandatory fields in the register. Without that consistency, aggregation, comparison, and trend analysis become unreliable.

  194. Question 194Risk Monitoring and Reporting

    A risk owner's assessment of a risk's probability is challenged because it is based on personal opinion rather than historical incident data. Which risk data quality dimension is most directly deficient?

    1. Timeliness
    2. Objectivity Correct answer.
    3. Relevance
    4. Accuracy

    Explanation

    Risk data quality is judged on dimensions such as accuracy, objectivity, relevance, and timeliness. Objectivity concerns whether the data is unbiased and supported by evidence rather than personal opinion. The source and basis of the estimate, not only its numerical value, determine this dimension.

  195. Question 195Risk Monitoring and Reporting

    A project manager is preparing the monthly risk report for the steering committee. Which content is most appropriate for this audience?

    1. Each risk owner's daily task assignments and working hours
    2. Every register entry, including closed risks and their full histories
    3. The complete simulation model with every input assumption
    4. Aggregate exposure, top risks, and response status versus tolerance Correct answer.

    Explanation

    Risk reports should be tailored to the decision needs of the audience. Senior governance bodies need a concise view of aggregate exposure, the most significant risks, and whether responses are keeping exposure within tolerance. Detailed register entries and model assumptions are supporting material rather than the headline content.

  196. Question 196Risk Monitoring and Reporting

    The remaining contingency reserve is $40,000, while the expected monetary value of the remaining identified risks is $90,000. What is the most appropriate action?

    1. Take no action because a positive contingency reserve balance still exists
    2. Escalate the shortfall and request additional reserve or replan the responses Correct answer.
    3. Close the highest-rated risks so that the exposure figure decreases
    4. Use the remaining reserve to fund unrelated scope changes

    Explanation

    Contingency reserve should be compared with the exposure of the risks that remain. When the expected monetary value of remaining risks exceeds the remaining reserve, the project is underprotected and the gap must be escalated or the responses replanned. A positive balance alone does not demonstrate adequacy.

  197. Question 197Risk Monitoring and Reporting

    After a response has been implemented, a risk's residual rating remains high and its trigger indicators continue to fire. What should the project manager conclude?

    1. The trigger thresholds should be raised to stop the alerts
    2. The risk can be closed because a response was executed
    3. The response is not effective and should be reassessed or replaced Correct answer.
    4. The residual rating should be lowered to reflect the response effort

    Explanation

    Response effectiveness is judged by whether residual risk falls to an acceptable level and triggers stop firing. If both remain adverse, the implemented response is not controlling the risk. The team should revisit the strategy or select an alternative rather than adjust the reporting.

  198. Question 198Risk Monitoring and Reporting

    A risk metric shows that the average time between identifying a risk and implementing its response has doubled over three reporting periods. What is the most important implication for the risk report?

    1. The probability ratings of all open risks should be decreased to reflect the delay
    2. Risks stay exposed longer, so more may occur before responses are in place Correct answer.
    3. Risk identification is no longer occurring frequently enough across the project
    4. The risk register has grown too large and should be reduced before the next reporting period

    Explanation

    Response lag measures how long risk exposure remains unmitigated. A growing lag means risks stay live longer and are more likely to occur before controls are in place. It is a leading indicator of weakening response implementation, not of register size or identification frequency.

  199. Question 199Risk Monitoring and Reporting

    The risk management plan calls for monthly risk reporting, but a new regulation introduces significant uncertainty midway through the project. What is the most appropriate action?

    1. Stop reporting until the regulatory uncertainty is resolved
    2. Increase reporting frequency and hold an ad hoc risk review with the stakeholders Correct answer.
    3. Continue monthly reporting because the plan defines the reporting cadence
    4. Delegate the reporting to the risk owners and continue as planned

    Explanation

    Reporting cadence should reflect the level of uncertainty and the needs of stakeholders, not merely the original plan. A material change such as new regulation warrants more frequent reporting and an ad hoc risk review. The risk management plan can then be updated to reflect the new cadence.

  200. Question 200Risk Monitoring and Reporting

    Two portfolios contain the same number of high-severity risks, but in one portfolio the risks are all triggered by the same supplier failure. Why should the risk report treat that portfolio's exposure as higher?

    1. Because the number of risks, not their dependency, determines exposure
    2. Because correlated risks can materialize together, producing a larger combined impact Correct answer.
    3. Because supplier risks are automatically classified as high probability
    4. Because high-severity risks are always reported at the portfolio level

    Explanation

    Aggregate exposure depends on both the severity of individual risks and the relationships among them. Correlated risks can be triggered by the same event, so their impacts may compound rather than offset. A simple count of high-severity risks therefore understates the dependent portfolio's exposure.

PMI-RMP flashcards

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Risk Management Plan
The subsidiary plan that defines methodology, roles, funding, timing, risk categories, probability and impact definitions, thresholds, and reporting formats used to manage risk on the project.
Risk Appetite
The amount and type of risk an organization is willing to pursue or retain in pursuit of its objectives. It is set at organizational level and bounds project-level risk taking.
Risk Tolerance
The acceptable variation from a stated objective that an organization or stakeholder is willing to withstand. It is narrower than appetite and is often quantified in cost, time, or quality terms.
Risk Threshold
A measurable level of risk exposure above which action must be taken and below which the risk may be accepted. Thresholds derive from stakeholder tolerance and are recorded in the risk management plan.
Risk Breakdown Structure
A hierarchical, category-based representation of the sources of risk on a project, such as technical, external, organizational, and project management. It structures identification and supports risk categorization.
Contingency Reserve
Time or money included in the approved cost or schedule baseline to cover identified risks that have been accepted. It addresses known-unknowns and is released as those risks materialize.
Risk Owner
The single person accountable for a specific risk, its response, and its monitoring. The role goes to whoever is best positioned with authority and competence, not automatically the project manager.
Stakeholder Register
A project document recording identified stakeholders, their roles, expectations, influence, interest, and risk tolerance. It is a primary input to risk identification and risk communication planning.
Salience Model
A stakeholder classification model using three attributes: power, legitimacy, and urgency. Stakeholders possessing all three are definitive and require the closest engagement and risk communication.
Engagement Assessment Matrix
A tool comparing each stakeholder's current engagement level with the desired level across five categories: unaware, resistant, neutral, supportive, and leading. Gaps drive communication actions.
Power-Interest Grid
A stakeholder mapping tool. High power and high interest stakeholders are managed closely; high power and low interest are kept satisfied; low power and high interest are kept informed; low on both are monitored.
Risk Register
The document recording each identified risk with its identifier, description, cause, effect, category, owner, probability, impact, score, planned response, trigger, and current status.
Cause-Risk-Effect Format
A structured statement separating the root cause, the uncertain event, and the consequence, as in: because of a cause, a risk may occur, leading to an effect on an objective.
Delphi Technique
An anonymous, iterative expert-consensus technique in which a facilitator collects estimates, summarizes them, and re-polls until convergence. It reduces domination by senior or vocal participants.
Assumption Analysis
Examining the project's documented assumptions and constraints for inaccuracy, instability, or inconsistency. Invalid assumptions are a major source of unidentified risk and are logged in the assumption log.
Risk versus Issue
A risk is an uncertain future event that may affect objectives; an issue is a risk that has already occurred. Issues move to the issue log for resolution and tracking.
Expected Monetary Value
A quantitative measure computed as probability multiplied by impact, summed across possible outcomes. It supports comparing risks and selecting decision tree branches on a common monetary basis.
Decision Tree Analysis
A diagram of choices, chance events, and outcomes, each with a probability and value. Expected monetary value is calculated for each branch and the highest-value path is selected.
Tornado Diagram
A sensitivity display ranking risk variables by the size of their effect on an objective. Bars are ordered widest to narrowest, showing which risks most influence the outcome.
Monte Carlo Simulation
A modeling technique that iterates cost or schedule models hundreds to thousands of times using input probability distributions. Outputs a cumulative distribution used to select confidence levels and reserves.
Probability-Impact Matrix
A grid plotting each risk's probability against its impact and mapping the combination to priority bands, such as low, moderate, high, or extreme, according to defined thresholds.
Risk Data Quality Assessment
Evaluating the accuracy, objectivity, reliability, and timeliness of information about a risk. Poor-quality data means the risk should be re-assessed before quantitative analysis or response planning.
Risk Mitigation
A threat response that reduces the probability of occurrence, the impact of occurrence, or both, down to an acceptable residual level. It does not eliminate the risk entirely.
Risk Transfer
A threat response that shifts ownership of the risk and its financial consequence to a third party, such as through insurance, warranties, or fixed-price contracts. The risk itself remains.
Risk Escalation
A response used when a threat or opportunity falls outside the project's scope or the project manager's authority, so it is referred to program, portfolio, or another management level.
Fallback Plan
A pre-developed secondary response implemented when the primary risk response proves insufficient or ineffective. It may be funded from contingency reserve and is documented in the risk register.
Secondary Risk
A new risk created as a direct consequence of implementing a risk response. It must be identified, analyzed, assigned an owner, and managed like any originally identified risk.
Risk Audit
A structured review examining whether the risk management process is being performed effectively and whether risk evaluations are accurate. Findings feed corrective action and process improvement.
Workaround
An unplanned, reactive response to a risk that was not identified or not accepted and has now occurred. Unlike a contingency plan, it is improvised at the time of impact.
Risk Burndown Chart
A graph of cumulative risk exposure plotted against time across the project. It shows whether responses are reducing exposure and whether new identification is outpacing treatment.
Reserve Analysis
Monitoring the remaining contingency reserve against the remaining risk exposure. Reserve trending toward zero while significant risks stay open signals escalation and possible re-planning.
Management Reserve
Budget held outside the performance measurement baseline for unidentified risks and unplanned scope, often called unknown-unknowns. Drawing on it usually requires sponsor or management approval.

PMI-RMP study guide

Risk Strategy and Planning

Setting the frame before naming risks

Risk strategy and planning establishes how the project will manage uncertainty before a single risk is written down. The deliverable is the risk management plan, a subsidiary of the project management plan, covering methodology, roles and responsibilities, budget and schedule for risk work, risk categories (frequently structured as a Risk Breakdown Structure, or RBS), definitions of probability and impact scales, the probability-impact matrix, reporting formats, and tracking. It must trace upward to the organization's risk strategy and to project objectives; a plan that ignores program or portfolio risk policy is a classic wrong answer.

Three terms candidates confuse: risk appetite (how much uncertainty the organization will pursue or retain), risk tolerance (acceptable variation around a threshold), and risk threshold (the concrete limit that triggers escalation). Appetite is a posture; a threshold is a number. Also separate the contingency reserve (for identified risks, sized from expected monetary value or simulation) from the management reserve (for unknown-unknowns, controlled above the project manager).

Traps: treating the plan as written once and frozen (it is revisited at phase gates); naming the project manager as default risk owner; omitting stakeholder appetite and thresholds; confusing the risk management plan with the risk register, which simply holds the risks.

Rule of thumb: if aggregate EMV of identified risks exceeds the reserve you hold, escalate for more contingency or replan; never accept the gap silently.

Worked example: appetite permits a 10% chance of exceeding budget. Simulation shows a 22% probability of overrun. The threshold is breached, so the plan mandates escalation to the sponsor.

Stakeholder Engagement

Risk is a social process

Stakeholders decide whether a risk is tolerable, fund the response, and own the action. Engagement work therefore starts with stakeholder analysis: mapping influence, interest, and each party's risk appetite, then deciding how often and in what form they receive risk information. The risk management plan records the risk appetite and thresholds of key stakeholders, not just the organization's, because a sponsor with low tolerance for schedule slippage will demand escalation far earlier than the matrix alone suggests.

Key mechanics: assign a single accountable risk owner per risk, chosen for authority and proximity to the trigger, and a separate action owner who performs the work. Agree the escalation path and the criteria for using it. Include stakeholders in identification and in choosing responses; responses imposed without owner buy-in fail quietly in execution. Build risk awareness so that bad news travels early.

Traps: assuming the sponsor's tolerance equals the organization's; treating the engagement plan and the communications management plan as the same artifact; communicating risk only upward to the project manager; selecting a response the risk owner has not accepted; confusing a stakeholder's stated optimism with documented tolerance.

Rule of thumb: match engagement depth to influence times exposure. High influence plus high exposure gets a named contact, a regular review cadence, and a standing seat in risk reviews.

Worked example: a regulator has low influence over daily work but high power to stop the project, and zero tolerance for compliance deviation. They are engaged monthly with a compliance-focused risk extract and are consulted before any response that touches regulatory scope.

Risk Identification

Finding risks before they find you

Identification is iterative, not a single workshop. It runs through initiating, planning, executing, and monitoring; new risks appear as design matures and vendors are selected. Techniques to know: brainstorming, the Delphi technique (anonymous, iterative expert consensus, good when personalities dominate), nominal group technique, interviews, root cause analysis such as fishbone diagrams, SWOT analysis, assumption and constraint analysis, prompt lists, document review, and checklists. Checklists alone miss novel risks, so pair them with prompt lists built from the RBS to guarantee category coverage.

Write each risk as cause, then uncertain event, then effect: "Because the vendor may miss the delivery date, we may need to resequence integration testing, resulting in a two-week schedule slip." Vague entries such as "the project may fail" cannot be analyzed, owned, or responded to.

Traps: recording only threats when opportunities belong in the register too; logging an issue as a risk (if it has already happened, it is an issue, not a risk); identifying risks without listing assumptions the register depends on; skipping secondary and residual risks until too late; letting one stakeholder group monopolize the session.

Rule of thumb: every risk gets a cause, an owner, a category from the RBS, and at least one candidate trigger before it enters the register.

Worked example: an assumption analysis reveals the team assumed site access on day one. Because access may be delayed by permitting, that becomes a risk with a named owner and a permit-approval trigger date.

Risk Analysis

From a full register to a ranked, quantified few

Qualitative analysis prioritizes: assess probability and impact using the documented scales, place the risk on the probability-impact matrix, consider data quality, urgency, and manageability, then rank. It is fast, applies to all risks, and drives which risks deserve quantitative treatment. Quantitative analysis applies to the significant few: expected monetary value (EMV), decision tree analysis, sensitivity analysis presented as a tornado diagram, and Monte Carlo simulation.

Know what each output buys you. EMV equals probability times monetary impact and feeds contingency sizing for discrete risks. Decision trees compare alternatives by rolling back EMV through the branches. Sensitivity analysis shows which variable most affects the outcome. Monte Carlo produces a distribution: probability of meeting a date or budget, and a confidence-level contingency figure.

Traps: using qualitative ranking to justify a precise dollar reserve; applying quantitative analysis to every risk regardless of value; ignoring correlation between risks, which understates aggregate exposure; forgetting optimism bias; treating EMV as a prediction rather than a long-run average; forgetting that a risk with low probability but catastrophic impact may outrank a frequent minor one regardless of score.

Rule of thumb: if a risk would not change a decision, do not spend quantitative effort on it.

Worked example: Risk A: 30% chance of a $40,000 rework cost, EMV $12,000. Risk B: 5% chance of a $300,000 penalty, EMV $15,000. Ranked by score, A may look larger; ranked by EMV and consequence, B dominates and gets the response budget.

Risk Response Implementation

Choosing, agreeing, and actually doing it

Response planning selects a strategy per risk, then converts it into funded, scheduled, owned action. Threat strategies: avoid (change the plan to eliminate the threat), transfer (shift financial consequence, e.g., insurance, warranty, fixed-price contract), mitigate (reduce probability or impact), accept (active acceptance funds a contingency; passive acceptance monitors), and escalate (the risk sits outside the project's authority). Opportunity strategies mirror these: exploit, share, enhance, accept, escalate.

Every accepted response needs an owner who agrees to it, an action plan, a trigger, and a place in the schedule or budget. Contingency and fallback plans are written before the trigger fires. Responses often spawn secondary risks (new risks created by the response) and leave residual risks (what remains after the response) - both return to the register for analysis.

Traps: assuming transfer eliminates the risk (reputation and schedule exposure usually remain); confusing active with passive acceptance; escalating a risk that is within the project's authority; costing a response that exceeds the exposure it removes; treating a documented response as implemented when no one has been assigned or funded.

Rule of thumb: a response is real only when it has an owner, a date, and a funding source.

Worked example: integration failure risk, 40% x $80,000 = $32,000 EMV. A prototype costing $8,000 cuts probability to 15%: new EMV $12,000. Net benefit is $32,000 - $12,000 - $8,000 = $12,000, so mitigation is justified.

Risk Monitoring and Reporting

Keeping the register honest

Monitoring answers three questions continuously: are agreed responses being executed, has the exposure changed, and have new risks appeared? Tools include risk reviews in status meetings, risk audits (examining the effectiveness of the risk process and responses), variance and trend analysis, technical performance measurement, reserve analysis (reserve burn-down against remaining exposure), and tracking key risk indicators and triggers against defined thresholds.

Reporting aggregates: top risks with owners and status, exposure trend, reserve status, responses due or overdue, closed risks, and escalations. A risk report that lists only counts of risks is weak; it should communicate aggregate exposure and whether it is moving toward or away from thresholds.

Traps: confusing a risk audit with a quality audit; monitoring the register's contents without reassessing probability and impact; leaving closed risks open or reopening them without evidence; failing to record a workaround used for an unplanned risk so it can be analyzed later; reporting to stakeholders only when a threshold is breached; forgetting lessons learned at closure.

Rule of thumb: reserve analysis is the honest test. If remaining reserve funds are falling faster than remaining risk exposure, the project is consuming contingency it may need later.

Worked example: a supplier-delay indicator is set at two missed milestone updates. At the first miss, the risk is reviewed and contingency is not released. At the second miss, the trigger fires, the fallback supplier is activated, and the sponsor receives an updated exposure report.

PMI-RMP cheat sheet

Quick reference

Risk Strategy and Planning

  • Risk management plan components: methodology, roles and responsibilities, funding, timing, risk categories, probability and impact definitions, probability-impact matrix, thresholds, reporting formats, and tracking.

  • Risk appetite is the willingness to take risk; tolerance is the acceptable variation around an objective; threshold is the measurable level that triggers action.

  • Formula: EMV = probability (0 to 1) x impact (currency or duration); used to compare, rank, and budget individual risks.

  • Contingency reserve covers identified and accepted risks (known-unknowns) and sits inside the cost and schedule baseline; management reserve covers unidentified risks (unknown-unknowns) and sits outside the baseline.

  • The risk breakdown structure organizes risk sources hierarchically by category (technical, external, organizational, project management) and should align with the work breakdown structure.

  • Decision rule: risks below the documented threshold may be accepted with monitoring; risks at or above it require an assigned owner and a funded response.

  • The risk management plan is a subsidiary plan of the project management plan and is approved before risk identification is performed in earnest.

  • Risk governance defines escalation paths: project risks escalate to program or portfolio when they exceed the project manager's authority or the project's scope.

  • Scaling factors that determine how much rigor is applied: project size, complexity, criticality, organizational risk maturity, and contractual or regulatory constraints.

Quick reference

Stakeholder Engagement

  • Risk owner is the single individual accountable for a specific risk and its response, chosen for proximity, authority, and competence rather than automatically being the project manager.

  • Power-interest grid: high power plus high interest means manage closely; high power plus low interest means keep satisfied; low power plus high interest means keep informed; low on both means monitor.

  • Salience model classifies stakeholders by power, legitimacy, and urgency; stakeholders holding all three attributes are definitive and need the closest engagement.

  • Engagement assessment matrix records current versus desired engagement across five levels: unaware, resistant, neutral, supportive, leading; the gap drives communication actions.

  • Anonymous elicitation techniques such as Delphi counter hierarchy effects, domination by senior participants, and groupthink during risk workshops.

  • Stakeholder risk appetite and tolerance are elicited through interviews and documented in the risk management plan; they set the thresholds used in later analysis.

  • Biases to counter explicitly: optimism bias, anchoring on the first estimate, availability heuristic from recent events, and groupthink in workshop settings.

  • Risk communication uses calibrated probability language defined once in the plan (for example, likely equals a stated percentage range) so all stakeholders interpret ratings identically.

Quick reference

Risk Identification

  • Risk definition: an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

  • Cause-risk-effect format: because of a cause, an uncertain event may occur, which would lead to an effect on an objective.

  • Identification techniques: brainstorming, Delphi, nominal group technique, interviews, checklists, prompt lists (PESTLE, TECOP), SWOT, root-cause analysis, assumption and constraint analysis, and document review.

  • Inputs to identification: risk management plan, scope, schedule, cost and resource baselines, assumption log, issue log, lessons learned register, stakeholder register, and procurement documents.

  • An issue is a risk that has already occurred; it moves to the issue log for resolution while unresolved risks stay in the risk register with an owner and response.

  • Identification is iterative and is repeated at phase gates and whenever scope, assumptions, contracts, or the external environment change.

  • Variability risk concerns a range of outcomes around a known parameter; ambiguity risk concerns uncertainty about what is known or how to interpret it.

  • The risk register records identifier, description, cause, effect, category, owner, probability, impact, score, response, trigger, and status.

  • Checklists and prompt lists improve completeness for known categories but miss novel risks, so they are paired with assumption analysis and expert judgment.

Quick reference

Risk Analysis

  • Risk score = probability x impact; the probability-impact matrix maps scores into priority bands defined by organizational thresholds.

  • Qualitative analysis is fast and judgment-based (probability-impact matrix, data quality assessment, urgency assessment, categorization); quantitative analysis is numeric (Monte Carlo, decision trees, sensitivity analysis, EMV).

  • EMV = sum of (probability x outcome value); decision trees select the branch with the highest expected value, and the value of information equals the EMV gain from acquiring it.

  • Monte Carlo simulation iterates the cost or schedule model hundreds to thousands of times over input distributions, producing a cumulative S-curve from which a confidence level such as P80 is read.

  • A tornado diagram orders risk variables by their swing on the objective; the widest bar is the most sensitive driver and the best candidate for quantitative modeling or response attention.

  • Risk data quality assessment rates accuracy, objectivity, reliability, and timeliness; poor-quality data means the risk must be re-evaluated before it is modeled quantitatively.

  • Risk urgency assessment weights risks by time available to respond, so short-fuse risks take priority even when their probability-impact score is only moderate.

  • Correlation among risk variables changes simulated outcomes materially; treating correlated risks as independent understates the range of the modeled result.

  • Quantitative outputs: expected cost and duration, probability of meeting objectives, and the contingency reserve required for a stated confidence level.

Quick reference

Risk Response Implementation

  • Threat strategies: escalate, avoid, transfer, mitigate, accept. Opportunity strategies: escalate, exploit, share, enhance, accept.

  • Avoid eliminates the threat by changing the plan (scope, schedule, or approach); mitigate reduces probability, impact, or both, leaving a residual risk.

  • Transfer shifts ownership of the response and the financial consequence to a third party through insurance, warranty, bond, or fixed-price contract; it does not eliminate the risk.

  • Escalate is used when the risk lies outside the project's scope or the project manager's authority; the project team then does not develop a response of its own.

  • Passive acceptance means acknowledge and monitor with no action; active acceptance means establish a contingency plan, trigger conditions, and a reserve.

  • A contingency plan addresses an identified risk if it occurs; a fallback plan is a secondary response used when the primary response proves inadequate.

  • Secondary risks arise from implementing a response and must be identified, analyzed, and owned like any originally identified risk.

  • Each approved response is assigned an owner, funded from the contingency reserve, and integrated into the cost, schedule, and resource baselines.

  • Response selection criteria: feasibility, cost-effectiveness (response cost should not exceed expected exposure), timeliness, stakeholder agreement, and fit with the assigned owner.

Quick reference

Risk Monitoring and Reporting

  • A risk audit evaluates whether the risk management process is being executed effectively and whether risk evaluations are accurate; it is distinct from a quality audit.

  • Reserve analysis compares remaining contingency reserve with remaining risk exposure; reserve trending toward zero while significant risks stay open is an escalation trigger.

  • A workaround is an unplanned, reactive response to a risk that was not identified or not accepted; a contingency plan is a planned, pre-approved response.

  • Risk register statuses: active or open, occurring, closed (response executed or risk expired), and retired.

  • A risk burndown chart plots cumulative risk exposure over time; a flat or rising line indicates that response implementation is not keeping pace with identification.

  • Variance and trend analysis on cost and schedule, together with technical performance measurement, provides early warning of emerging risk.

  • Risk reporting content: top risks with scores and trends, response implementation status, reserve status, newly identified risks, closed risks, and escalation items.

  • Monitoring uses trigger conditions defined during planning; once a trigger is met, the contingency plan is executed without seeking new approval.

  • Lessons learned from closed risks feed organizational process assets and refine future identification checklists, thresholds, and response templates.

PMI-RMP key terms

Risk management plan

The document that describes how risk management activities will be structured, funded, scheduled, and performed on a project, including roles, methodology, budgeting, timing, and risk categories.

Related: Risk appetite, Risk breakdown structure, Contingency reserve
Risk appetite

The amount and type of risk an organization or project is willing to pursue or retain in order to achieve its objectives, usually expressed in broad, high-level terms.

Related: Risk tolerance, Risk threshold
Risk tolerance

The degree, amount, or variance in risk an organization or stakeholder is willing to accept for a specific objective, often expressed as a measurable range.

Related: Risk appetite, Risk threshold
Risk threshold

A specific measurable level of risk exposure above which the organization will not accept the risk and action must be taken, such as escalation or implementing a response.

Related: Risk tolerance, Risk appetite
Risk attitude

The chosen response of an individual or group to a situation involving uncertainty, shaped by experience, perception, and tolerance, which influences how risks are identified and prioritized.

Related: Risk perception, Risk culture
Risk breakdown structure

A hierarchical representation of potential sources of risk, organized by category, that helps a team identify and structure risks consistently across the project.

Related: Risk register, Risk statement
Contingency reserve

Time or money set aside in the project budget or schedule to address identified risks that have been accepted and for which a response plan exists.

Related: Reserve analysis, Risk response plan
Stakeholder analysis

A process of identifying stakeholders and assessing their interests, influence, expectations, and potential impact on the project, used to plan engagement and risk communication.

Related: Risk communication plan, Risk perception
Risk communication plan

A plan describing how risk information will be shared with stakeholders, including what will be reported, to whom, when, in what format, and by whom.

Related: Stakeholder analysis, Risk report
Risk perception

The subjective interpretation and judgment an individual or group makes about the likelihood and severity of a risk, influenced by experience, values, and biases.

Related: Risk attitude, Risk communication plan
Risk culture

The shared values, beliefs, and behaviors within an organization that shape how people identify, discuss, and act on risk and uncertainty.

Related: Risk attitude, Risk champion
Risk champion

A designated person who promotes risk management practices, supports risk owners, and helps keep attention on risk identification and response across the project or organization.

Related: Risk owner, Risk culture
Risk register

A document that records identified risks, their causes, potential responses, owners, and current status, serving as the central repository for risk information throughout the project.

Related: Risk statement, Risk report, Risk owner
Risk statement

A structured description of a risk in cause-event-effect format, stating the triggering cause, the uncertain event, and the potential consequence for project objectives.

Related: Risk register, Root cause analysis
Brainstorming

A group technique used to generate a broad list of risks by encouraging free-flowing ideas from participants without initial criticism or evaluation.

Related: Delphi technique, Risk breakdown structure
Delphi technique

An anonymous, iterative technique in which experts answer questionnaires, receive summarized feedback, and revise their views until consensus emerges, reducing bias from dominant personalities.

Related: Brainstorming, Risk register
SWOT analysis

An analysis of strengths, weaknesses, opportunities, and threats that helps a team identify internal and external risks that could affect project or organizational objectives.

Related: Brainstorming, Risk breakdown structure
Assumption analysis

A technique that examines documented assumptions and constraints to identify which ones are uncertain or invalid and could create risks if they fail.

Related: Risk statement, Root cause analysis
Root cause analysis

A technique used to find the fundamental reason a risk or problem exists so that responses can address the underlying cause rather than only a surface symptom.

Related: Risk statement, Assumption analysis
Qualitative risk analysis

A process of prioritizing identified risks by assessing their probability of occurrence and impact on objectives, using defined rating scales and subjective judgment.

Related: Probability and impact matrix, Quantitative risk analysis
Quantitative risk analysis

A process of numerically analyzing the combined effect of identified risks and other sources of uncertainty on project objectives, often using simulation and modeling.

Related: Monte Carlo simulation, Expected monetary value
Probability and impact matrix

A grid that combines likelihood and impact ratings for each risk to assign a priority level and guide which risks need further analysis or response.

Related: Qualitative risk analysis, Risk threshold
Expected monetary value

A calculation that multiplies the probability of a risk by its financial impact to express the average expected consequence, used to compare alternatives and size reserves.

Related: Decision tree analysis, Contingency reserve
Monte Carlo simulation

A modeling technique that runs many randomized trials of cost or schedule inputs, including risk ranges, to produce a probability distribution of possible project outcomes.

Related: Quantitative risk analysis, Sensitivity analysis
Sensitivity analysis

A technique that tests how variation in one uncertain input at a time affects project outcomes, often shown in a tornado diagram, to reveal the most influential risks.

Related: Monte Carlo simulation, Decision tree analysis
Decision tree analysis

A diagramming method that maps choices, uncertain events, and their probabilities and payoffs to calculate expected values and compare decision options.

Related: Expected monetary value, Sensitivity analysis
Risk owner

The person assigned accountability for monitoring a specific risk, selecting and implementing the response, and ensuring the risk is managed throughout its life cycle.

Related: Risk response plan, Risk register, Risk champion
Risk response plan

A documented set of actions, owners, resources, and timing for addressing each prioritized risk, including the selected strategy and any contingency measures.

Related: Risk owner, Contingent response strategy, Residual risk
Threat response strategies

Negative risk responses used to deal with threats: avoid by removing the risk, mitigate by reducing probability or impact, transfer by shifting financial consequence, and accept by acknowledging the risk.

Related: Opportunity response strategies, Contingent response strategy
Opportunity response strategies

Positive risk responses used to capture favorable uncertainty: exploit by ensuring the opportunity occurs, enhance by raising its probability or impact, and share by allocating ownership to a capable third party.

Related: Threat response strategies, Risk response plan
Contingent response strategy

A preplanned response executed only if a specific trigger condition occurs, often called a contingency plan, with defined activation criteria and assigned owner.

Related: Fallback plan, Risk response plan
Fallback plan

A backup response implemented when the primary response is insufficient or fails, typically prepared for an accepted risk with a known contingency.

Related: Contingent response strategy, Workaround
Secondary risk

A new risk that arises as a direct result of implementing a risk response, which must be identified and managed alongside the original risk.

Related: Residual risk, Risk response plan
Residual risk

The remaining risk exposure that persists after a response has been implemented, which must be evaluated to decide whether further action is needed.

Related: Secondary risk, Risk response plan
Workaround

An unplanned response to a risk that has occurred and was not covered by a contingency plan, developed quickly to limit the impact.

Related: Fallback plan, Contingent response strategy
Key risk indicator

A leading metric that provides early warning that a risk is becoming more likely or severe, enabling proactive monitoring and timely response.

Related: Risk review, Risk report
Risk audit

A structured review of the effectiveness of risk management processes and responses, often performed by an independent party, to identify improvements and verify compliance.

Related: Risk review, Risk report
Risk review

A periodic activity to reassess identified risks, identify new risks, evaluate response effectiveness, and update the risk register and risk report.

Related: Risk audit, Risk register, Key risk indicator
Reserve analysis

A monitoring technique that compares remaining contingency and management reserves with the risk exposure remaining on the project to determine whether reserves are adequate.

Related: Contingency reserve, Residual risk
Risk report

A document that summarizes overall project risk exposure, key individual risks, response status, and trends for stakeholders, often supported by a risk dashboard.

Related: Risk register, Key risk indicator, Risk communication plan

PMI-RMP study plan

8 weeks · About 8 hours per week

Week 1

Risk Strategy and Planning

  • Draft a one-page risk management strategy outline covering risk appetite, tolerance thresholds, and escalation paths for a project you know

  • Define at least 15 key terms from the risk management vocabulary (appetite, tolerance, threshold, exposure, reserve) in your own words

  • Map how organizational process assets and enterprise environmental factors constrain risk planning in three concrete examples

  • Build a blank risk management plan template with sections for methodology, roles, funding, timing, and reporting cadence

Your checkpoint

A completed risk management plan template plus a 15-term glossary, self-scored against a checklist of 10 required elements

Week 2

Risk Strategy and Planning & Risk Identification

  • Write risk appetite and tolerance statements for cost, schedule, scope, and quality on a sample project

  • Produce a risk breakdown structure with at least four levels and 20 identified risk categories

  • Apply at least five identification techniques (brainstorming, interviews, checklist, assumption analysis, prompt lists) to generate 30 raw risks

  • Convert raw risks into well-formed cause-event-effect statements with an owner placeholder for each

Your checkpoint

A risk register of 30 risks in cause-event-effect format, each tagged to a risk breakdown structure category

Week 3

Risk Identification & Risk Analysis

  • Separate the 30 risks into threats and opportunities and confirm each has a clear trigger

  • Score every risk on probability and impact using a defined 5x5 scale and plot them on a matrix

  • Calculate expected monetary value for at least 10 risks and rank them by exposure

  • Identify three risks that are actually secondary risks or non-risks and justify removing them

Your checkpoint

A probability-impact matrix and ranked expected monetary value table covering all 30 risks, with documented rationale for each score

Week 4

Risk Analysis

  • Perform a qualitative-to-quantitative screen and select the five risks worth modeling

  • Build a decision tree or Monte Carlo simulation for cost and schedule exposure using a spreadsheet

  • Interpret a tornado diagram and explain which three variables drive the most variance

  • Contingency and management reserve calculations justified against the modeled exposure

Your checkpoint

A quantitative analysis workbook with one Monte Carlo or decision tree model, a tornado diagram, and a reserve recommendation with justification

Week 5

Risk Response Implementation

  • Assign a documented response strategy (avoid, transfer, mitigate, escalate, accept; exploit, share, enhance, accept) to every threat and opportunity

  • Write specific response actions with owners, due dates, and success criteria for the ten highest-exposure risks

  • Identify at least five secondary and residual risks created by chosen responses and log them

  • Update the risk register with response costs and confirm each response is proportionate to the exposure

Your checkpoint

A response plan covering all high and extreme risks, each with strategy, action, owner, due date, cost, and residual risk rating

Week 6

Stakeholder Engagement & Risk Monitoring and Reporting

  • Build a stakeholder map classifying every project stakeholder by influence, interest, and risk attitude

  • Script a risk communication approach for each stakeholder group, including what they hear, when, and in what format

  • Define five risk metrics (exposure trend, closed-risk rate, response completion rate, aging of open risks, reserve burn) with formulas

  • Draft a one-page risk report suitable for a steering committee

Your checkpoint

A stakeholder engagement and risk communication plan plus a one-page risk dashboard template with five defined metrics

Week 7

Risk Monitoring and Reporting & Risk Response Implementation

  • Set up a risk review cadence with agenda, inputs, and decision rights for a recurring risk meeting

  • Simulate a risk audit and write three findings with corrective actions

  • Reassess the full risk register as if one month has passed, closing, updating, and adding risks

  • Track reserve consumption against actual drawdowns and flag any variance

Your checkpoint

A risk monitoring pack containing a meeting agenda, three audit findings, an updated register with status changes, and a reserve tracking table

Week 8

Risk Strategy and Planning & Stakeholder Engagement & Risk Identification & Risk Analysis & Risk Response Implementation & Risk Monitoring and Reporting

  • Take two full-length timed practice exams and record scores by domain

  • Rank your four weakest sub-topics and rebuild notes for each in one sitting

  • Rewrite any missed concept as a cause-event-effect style explanation to confirm understanding

  • Assemble a final one-page formula and framework sheet for exam-day recall

Your checkpoint

Two completed timed practice exams with a domain-level score breakdown and a one-page final recall sheet

Milestones

Week 2: You can explain risk appetite versus tolerance versus threshold without notes, and you have 30 risks in cause-event-effect format

Week 4: Your quantitative model produces a defensible reserve number and you can name the top three variance drivers

Week 6: Every high-exposure risk has an owned response, and you have a stakeholder map covering all influencer groups

Week 7: You can run a risk review from agenda to updated register in under 60 minutes

Week 8: Practice exam scores trend upward across all six domains, with no domain below 70 percent

PMI-RMP exam day

Your checklist

Government-issued photo ID with your signature

Bring the original (not a photocopy) and make sure the name matches your PMI and test-provider registration exactly, including middle names and suffixes. If your ID name differs from your registration, resolve it in advance - confirm the accepted ID types with your test provider.

Appointment confirmation and PMI eligibility/PMI ID number

Have the confirmation email or appointment number accessible (printed or on paper, since phones usually stay in a locker). Note your PMI ID in case the proctor needs to reconcile your record.

A second form of identification

Some test centers request a secondary ID such as a credit card or employee badge. This is not universally required - confirm with your test provider whether one is needed at your location.

Travel and arrival plan (or a completed online-proctoring system test)

For a test center: know the address, parking, and transit time, and plan to arrive well ahead of your appointment slot. For online proctoring: run the equipment/system check and confirm your testing environment meets the provider's requirements at least a day in advance.

Transportation backup and a realistic arrival buffer

Plan to be at the center (or logged in) earlier than your appointment - PMI guidance has historically suggested roughly 30 minutes early for check-in, but confirm the exact check-in window on your appointment confirmation.

Approved testing accommodations confirmed in advance

If you need extra time, a separate room, or other accommodations, these must be requested and approved before test day through the provider's process. Bring the approval documentation if the provider instructs you to.

A plan for personal items

Leave study notes, smartwatches, phones, and bags at home or plan to store them in the provided locker. Nothing except approved items goes to the workstation; confirm the specific permitted-items list with your test provider.

Knowledge that no personal calculator or scratch paper is allowed

The delivery system provides on-screen tools for any calculation you may need. Do not bring your own calculator, paper, or pen - confirm the exact list of provided tools with your test provider.

Rest, food, water, and medication logistics

Sleep 7–8 hours the night before, eat a normal meal beforehand, and bring only what the provider permits (some centers allow a water bottle in the locker for break use). Plan any medication timing around the appointment.

A one-page personal summary you review and then put away

Your own condensed notes: the risk process flow, qualitative vs. quantitative technique selection, risk response strategies (avoid, mitigate, transfer, accept, escalate / exploit, enhance, share, accept), and key formulas you actually use. Review it before you enter - not inside the testing room.

A read-through of the candidate agreement and testing rules

You will be asked to accept confidentiality and conduct terms. Read them beforehand so you are not reading them for the first time under time pressure.

Plan the day

72 hours before

Confirm all logistics in writing: appointment time and location (or proctoring link), ID name match, accommodations approval, and permitted items. Fix any mismatch now, because it cannot be fixed on test day.

72 to 48 hours before

Do targeted review only on your two weakest performance domains. Take one timed mini-set (roughly 40–60 questions) to rehearse pacing, then review only the explanations for questions you missed - no new source material.

48 to 24 hours before

Stop learning new content. Re-read your own one-page summary and the risk-management process sequence. Pack your ID and confirmation. For online proctoring, repeat the system test and clear your desk and room.

24 hours before

Protect your sleep. No late-night cramming, no alcohol, no all-nighter. Lay out clothes, ID, confirmation, and travel plan. Set two alarms. Do a final 15-minute skim of your summary and then stop.

Morning of

Eat a normal meal, hydrate moderately, and avoid caffeine spikes if you are sensitive. Do not open new study material - a last-minute fact you half-learn can create doubt that costs you more than it earns. Leave with buffer time.

At check-in

Present your ID, complete the check-in and any security screening calmly, store personal items as directed, and use the restroom before you sit down. Ask the proctor to clarify anything about breaks, tools, or the interface before the clock starts.

First 3–5 minutes of the test

If the interface allows it, write down your pacing targets and any formula you plan to use. Budget roughly 70–75 seconds per question on average (about 210 minutes across 170 questions - verify the current timing and item count with PMI before test day).

During the test

Answer in three passes: first pass answers everything you know quickly; flag anything requiring calculation or long reading; second pass returns to flagged items. Never leave a question blank - there is no penalty for a wrong answer, so guess and move on.

At any scheduled or unscheduled break

Stand up, drink water, breathe, and reset. Check the clock before you leave the room - if the break is unscheduled, the timer typically keeps running, so keep it short.

Final 15 minutes

Stop opening new items. Use remaining time only to resolve flagged questions, confirm you have no unanswered items, and submit deliberately.

Rules to check

  • Identity: the name on your ID, your PMI record, and your registration must match. Bring valid, unexpired, government-issued photo ID with signature. If you have any doubt about accepted documents, confirm with your test provider before the appointment.

  • Permitted items: phones, smartwatches, notes, and bags stay in the locker or outside the testing room. Unauthorized materials at the workstation can result in your exam being voided - get the definitive list from your provider.

  • Breaks: verify the current break policy (scheduled vs. unscheduled, and whether the clock continues) with your test provider at check-in, and plan your pacing around what you are actually given.

  • Scoring: the PMI-RMP exam has historically been 170 multiple-choice questions delivered in about 210 minutes, with a subset of items not scored, and a criterion-referenced (not a fixed percentage) passing standard that PMI does not publish. Confirm the current item count, duration, and score-report format on PMI's website before test day.

  • Confidentiality: you will agree not to record, reproduce, or discuss exam content. Sharing remembered questions - including in study groups or online - breaches the agreement and can invalidate your result.

  • Technical or environmental problems: raise your hand (test center) or notify the proctor immediately (online) rather than troubleshooting silently. Ask for a case or incident number before you leave.

  • Tools: use only the on-screen calculator, notepad, and other tools the delivery system provides. Do not bring your own.

  • Time management is a rule, not a preference: if a question exceeds roughly two minutes, flag it, make your best selection, and move on. Unanswered questions score the same as wrong ones.

PMI-RMP FAQ

How many PMI-RMP practice questions are available?

The practice set has 200 PMI-RMP questions. Each one includes the choices, the correct answer, and an explanation, and the set is free to read with no signup.

How many PMI-RMP flashcards are available?

The flashcard set has 32 PMI-RMP cards. Each card shows the term and its definition.

Which topics does the PMI-RMP study material cover?

The PMI-RMP study material has 6 sections, including Risk Strategy and Planning, Stakeholder Engagement, and Risk Identification.

What format facts does the catalog list for the PMI-RMP exam?

The catalog lists these item types: multiple choice for the PMI-RMP exam.