FS Surveying Practice Test

Fundamentals of Surveying (FS) Exam

FS Surveying overview

  • 200 practice questions
  • 32 flashcards
  • 9 study guide topics
  • 40 key terms

What you'll study

  • Pre-Examination Activities11.11%
  • Surveying Instruments and Procedures11.11%
  • Boundary and Cadastral Surveys11.11%
  • Photogrammetry and Remote Sensing11.11%
  • Geodesy and Geodetic Surveying11.11%
  • Surveying Calculations and Adjustments11.11%
  • Mapping and Platting11.11%
  • Construction Surveys11.11%
  • Business and Professional Practice11.12%

The Fundamentals of Surveying (FS) exam is the NCEES examination that NCEES describes as generally the first step toward becoming a licensed professional surveyor (P.S.). It is designed for recent graduates and students who are close to finishing an undergraduate surveying degree from an ABET-accredited program. The FS is computer-based and is administered year-round in testing windows at NCEES-approved Pearson test centers. It contains 110 questions, and the appointment is six hours long: a 2-minute nondisclosure agreement, an 8-minute tutorial, 5 hours and 20 minutes of exam time, and a 25-minute scheduled break. The exam fee is $225, payable directly to NCEES. Registration and scheduling are handled through MyNCEES, but many licensing boards require a separate application or approval before you can register, so confirm your board’s process early. Results are typically available within 7–10 business days and are reported as pass or fail; failing candidates receive a diagnostic report by major topic. Prepare with NCEES exam prep materials, review the calculator policy and Examinee Guide, and practice pacing for the 5-hour-20-minute exam block.

Common mistakes

Computes a horizontal distance or coordinate inverse directly from State Plane coordinates and reports it as the ground distance, never applying elevation or scale factors.

Grid coordinates look like ordinary plane coordinates, and the problem may hand you the zone scale factor and average elevation in a separate sentence that is easy to treat as background information.

What to do instead

Before any inverse, write 'grid' or 'ground' next to the number. Convert with combined factor CF = EF x SF, where EF = R/(R + h); carry the combined factor to at least six decimals and state the result's basis in the answer.

Runs a traverse adjustment by distributing the linear misclosure to latitudes and departures first, using bearings computed from unadjusted angles, and only afterwards spreads the angular misclosure.

Adjustment is learned as a checklist, and the angular step feels like a formality that can be tacked on at the end of the computation sheet.

What to do instead

Fix the order: (1) angular misclosure, (2) distribute it and recompute each azimuth, (3) compute latitudes and departures from adjusted azimuths, (4) linear misclosure, (5) apply the compass rule to lat/dep, (6) recompute coordinates and verify closure is zero.

Finds a monument that does not match the record distance and resolves the conflict by holding the deed distance and calling the monument 'off' or 'not the original'.

Record numbers feel authoritative and precise, while an old pipe or stone looks crude, so the candidate defers to the number.

What to do instead

Apply the hierarchy of evidence: natural monuments, then artificial monuments, then courses and distances, then area. Monuments control; distances yield. Use the record distance only as corroboration of the monument's identity, and state the reasoning explicitly.

Substitutes percent grades directly into vertical curve equations as if they were decimals (uses g = 3 instead of 0.03), producing elevations that are wrong by a factor of 100.

Exam statements give grades in percent while formula sheets and textbooks show g as a slope, and the unit is never written down during the calculation.

What to do instead

Convert every grade to a decimal at the moment you extract it from the problem and write the conversion on the page. Sanity-check by computing the elevation change over the full curve (g2 - g1)xL/2) and confirming it matches the PVI elevations within a few hundredths.

Inverts the photogrammetric scale relationship, dividing flying height above terrain by focal length when asked for the scale denominator, or multiplying when it should divide.

The relation S = f/H is simple, but the '1:S' convention and the need to use height above mean terrain rather than above datum invite a flip.

What to do instead

Write S = f/H with both terms in the same units to get a dimensionless ratio, then invert for 1:S. Check the direction: increasing flying height must make the scale smaller (larger denominator); a result that violates that check is wrong.

Reduces total station distances without confirming the prism constant and EDM offset in the instrument, or applies a -30 mm constant to a prism that is actually 0 mm.

Instruments ship with a default constant and the setting persists between jobs, and in the field the discrepancy is small enough to be absorbed by other errors.

What to do instead

Treat prism constant as a recorded observation: check and log the instrument setting against the prism label before the session, and verify with a known baseline or a check shot between two coordinated points. In exam items, state the constant you assumed.

Computes slope-stake catch-point offsets in a single pass using the cut or fill depth measured at the centerline, without accounting for the different depth at the actual catch point.

The centerline depth is the only elevation shown on the cross-section, and the one-step formula looks complete.

What to do instead

Recognize that cut/fill varies with offset: solve iteratively or algebraically for the offset d where the ground elevation equals the design elevation at that same offset, adding the half-width of the traveled way and shoulders first, then converging once or twice and rounding to the nearest 0.1 ft.

Computes a parcel area by the coordinate method from a list of corner coordinates without verifying that the traverse closes, then reports the raw algebraic sum of cross products as the area.

The shoelace routine is quick to apply mechanically, and the sign convention and the division by two are easy to drop under time pressure.

What to do instead

Close the coordinate list by repeating the first point, sum the cross products, take the absolute value, and divide by two; verify with an independent rough rectangle estimate and check that units are square feet before converting to acres by dividing by 43,560.

Answers professional-practice items by assuming a limitation-of-liability clause or a client's waiver removes the surveyor's duty to exercise reasonable care toward the public and third parties.

Candidates reason from the commercial relationship (the client pays) rather than from the statutory public-protection standard, and contract language sounds absolute.

What to do instead

Separate the two issues: a contract clause may allocate or cap risk between contracting parties, but it does not lower the standard of care or extinguish duties owed to the public, adjoining owners, and third parties who reasonably rely on the work.

Starts computing a boundary from the deed calls immediately, skipping the chain-of-title and adjoiner research and the field reconnaissance of found monument evidence.

Computation feels like progress and the research step produces no numbers, so it gets compressed or deferred until the computations disagree.

What to do instead

Do the research and reconnaissance first and document it: pull the subject and adjoiner deeds and plats, list every record and found monument with its position and condition, and only then begin the boundary resolution, using research to explain discrepancies rather than to patch them afterwards.

Exam requirements can change. Confirm current details with the exam provider.

FS Surveying practice

200 questions. Each one lists the choices, the correct answer, and an explanation. With JavaScript, this list opens one question at a time. The checker at the top of this page saves progress in this browser when it is available.

  1. Question 1Pre-Examination Activities

    When beginning a boundary survey of an urban lot, which activity belongs to the pre-examination (pre-field) stage?

    1. Searching public records for deeds, plats, and prior surveys Correct answer.
    2. Measuring the distances between found monuments with a total station
    3. Drafting the final boundary plat for the client's signature
    4. Setting new monuments at the calculated corner positions

    Explanation

    Pre-examination activities gather and evaluate record information before any field measurements or monumentation occur. Setting monuments and measuring distances are field operations performed after the research is complete, and the plat is a post-field deliverable.

  2. Question 2Pre-Examination Activities

    A survey crew needs to cross private land that is neither owned by the client nor controlled by the client. Before entering, the crew should:

    1. Wait for the client to escort the crew at all times
    2. Obtain the landowner's permission or other lawful authority Correct answer.
    3. Enter only after notifying the local police department of the visit
    4. Enter without notice if the parcel is unfenced

    Explanation

    A surveyor generally needs the landowner's consent, a statutory right of entry with proper notification, or a court order before entering land held by a third party. Permission should be documented and occupants notified before mobilization.

  3. Question 3Pre-Examination Activities

    Why is a utility locate request typically submitted before any ground disturbance during a survey?

    1. To satisfy the boundary evidence requirement contained in the deed of record
    2. To obtain the coordinates of the nearest benchmarks
    3. To have buried utilities marked before probing or excavating Correct answer.
    4. To establish the legal description of the parcel

    Explanation

    One-call locate services mark public buried facilities before excavation so that crews do not strike them while probing for monuments or setting stakes. The locate ticket also documents compliance with state damage-prevention law.

  4. Question 4Pre-Examination Activities

    Which project document normally establishes the scope of services, deliverables, schedule, and fee for a survey?

    1. The deed for the subject parcel
    2. The signed contract or written agreement with the client Correct answer.
    3. The recorded subdivision plat
    4. The state minimum standards of practice for boundary surveys

    Explanation

    The executed agreement defines what the surveyor will deliver, when, and for how much, and it controls if later disputes arise. Deeds and plats are evidence about the land, and state standards set a regulatory floor rather than a project scope.

  5. Question 5Pre-Examination Activities

    What is the main purpose of obtaining a title commitment before a land title survey?

    1. To set the fee the surveyor may charge for the survey
    2. To prove that the boundary monuments are still in their original positions
    3. To replace the need for deed research in the county records
    4. To identify the record easements and encumbrances the survey must address Correct answer.

    Explanation

    The title commitment identifies the record parties in interest and lists the easements and encumbrances that the survey must locate or note. It is a starting point for research, not a substitute for examining the underlying recorded instruments.

  6. Question 6Pre-Examination Activities

    Which set of documents is most commonly assembled during pre-field research for a boundary survey?

    1. Soil test reports and septic design plans
    2. Deeds, plats, recorded surveys, and easement records Correct answer.
    3. Equipment calibration certificates and repair invoices
    4. Employee time cards and payroll records

    Explanation

    Boundary research centers on the written record of land: deeds in the chain of title, subdivision plats, previously recorded surveys, and documents creating roads and easements. These records establish what rights exist and where the record calls place them.

  7. Question 7Pre-Examination Activities

    Before beginning observations, a surveyor checks the total station's plate bubble, optical plummet, and tribrach. The purpose of these checks is to:

    1. Verify the radio link to the data collector
    2. Ensure the instrument is centered and leveled over the point Correct answer.
    3. Confirm the battery voltage is sufficient for a full day
    4. Verify that the reflectorless range meets the project specification

    Explanation

    The bubble, plummet, and tribrach control how well the instrument is centered and leveled over the station mark. Errors here are systematic and propagate into every measurement taken from the setup.

  8. Question 8Pre-Examination Activities

    The subject deed refers to a 60-foot road but does not state whether 60 feet is the right-of-way width or the traveled way. The best pre-field step is to:

    1. Ask the client which interpretation they prefer
    2. Measure the road in the field and adopt the measured width
    3. Check the plat, dedication documents, and adjoiner deeds for the dedicated width Correct answer.
    4. Assume that 60 feet is the traveled way width and offset the line 30 feet from centerline

    Explanation

    When a deed call is ambiguous, the surrounding record resolves it: the plat, the dedication instrument, and the adjoiner deeds normally state the dedicated right-of-way width. Field measurement cannot establish a record width because the traveled way is often narrower than the dedication.

  9. Question 9Pre-Examination Activities

    A title commitment lists a 20-foot utility easement without stating where it lies. Before field work the surveyor should:

    1. Omit the easement because its location is not of record
    2. Obtain the recorded instrument that created the easement Correct answer.
    3. Show the easement centered on the property's rear lot line, since utility easements are usually placed there
    4. Locate the easement by finding the nearest overhead power line

    Explanation

    An easement's location is determined by the instrument that created it and any referenced plat or exhibit. The surveyor must read that document rather than infer a location from typical practice or surface features.

  10. Question 10Pre-Examination Activities

    Many jurisdictions require a surveyor who sets or rehabilitates a boundary monument to file a corner record or record of survey. The main purpose is to:

    1. Transfer ownership of the monument to the county
    2. Guarantee that the monument will never be disturbed
    3. Establish the assessed value of the parcel
    4. Give public notice of the monument and its basis Correct answer.

    Explanation

    Filing perpetuates survey evidence by placing the monument's position, ties, and the reasoning behind it in the public record. Later surveyors and landowners can then rely on and check the monument without repeating the original work.

  11. Question 11Pre-Examination Activities

    When planning to use existing geodetic control for a project, the surveyor should consult the NGS datasheet primarily to:

    1. Determine the legal owner of the monument and any access rights to it
    2. Compute the fee the client will be charged for each recovered monument
    3. Obtain a permit from the agency that owns the land to occupy the monument site
    4. Check the monument's coordinates, condition, and last recovery date Correct answer.

    Explanation

    A datasheet publishes the station's adjusted coordinates, the mark description, and the history of reported conditions. Reviewing it tells the surveyor whether the mark is likely usable and when it was last confirmed to exist.

  12. Question 12Pre-Examination Activities

    To determine whether a parcel lies within a special flood hazard area during project planning, a surveyor should consult:

    1. The state's survey minimum standards
    2. The client's homeowner insurance policy
    3. The FEMA Flood Insurance Rate Map panel covering the site Correct answer.
    4. The county's zoning ordinance text and the official zoning map for the site

    Explanation

    Flood Insurance Rate Maps delineate special flood hazard areas and base flood elevations by panel. Zoning regulates permitted uses and density but does not define flood zones.

  13. Question 13Pre-Examination Activities

    Why should the horizontal and vertical datum and the required accuracy be confirmed with the client before field work begins?

    1. They fix the units, datum, and accuracy the deliverable must meet Correct answer.
    2. They determine how many monuments must be set at each corner
    3. They are needed to obtain the utility locate ticket
    4. They set the legal location of every boundary line under the state's boundary law

    Explanation

    Datum and accuracy specifications define how coordinates and elevations are expressed and the tolerance against which the work will be tested. Agreeing on them before mobilization prevents rework when the deliverable is rejected for using the wrong reference frame or an inadequate standard.

  14. Question 14Pre-Examination Activities

    A total station is being prepared for a precise traverse, and the surveyor notices the prism constant entered in the instrument does not match the prism being used. The correct action is to:

    1. Change the prism constant to match the prism and verify with a known baseline Correct answer.
    2. Leave the entry as it is and apply an averaged correction to all distances in the office
    3. Use reflectorless mode for all shots instead
    4. Double the number of rounds and average the results

    Explanation

    A prism constant mismatch is a systematic error that biases every distance by the same amount. It must be corrected at the source and confirmed on a known baseline before observations begin.

  15. Question 15Pre-Examination Activities

    Field work is planned on the shoulder of a two-lane highway. Which pre-field item belongs in the plan?

    1. A list of neighboring property owners' telephone numbers in case of complaints
    2. A traffic control plan and permits consistent with state work-zone standards Correct answer.
    3. A copy of the client's marketing brochure showing the project location
    4. A revised fee estimate for the client's lender reflecting the added field time

    Explanation

    Work along a traveled roadway requires a traffic control plan that conforms to the state's adopted work-zone manual, along with any permits the highway authority requires. This is arranged during planning so that crews and equipment are protected once on site.

  16. Question 16Pre-Examination Activities

    A one-call locate service has marked the public utilities at the site. Before probing for monuments on a commercial lot, the crew should recognize that:

    1. Every buried facility on the site has now been marked and is safe to probe
    2. The marks are guaranteed by law to be accurate to within six inches of the buried utility
    3. Probing is prohibited once a locate ticket has been issued
    4. Privately owned facilities are usually not marked by the one-call service Correct answer.

    Explanation

    One-call systems generally cover only the member utilities that subscribe to them, so privately owned lines such as site lighting, irrigation, and service laterals must be located separately. The excavator remains responsible for confirming that the area is clear before disturbing the ground.

  17. Question 17Pre-Examination Activities

    In preparing a fee estimate for a survey, which factor most directly drives field labor cost?

    1. The number of paper copies of the final plat requested by the client
    2. The font used on the final plat
    3. Site size, access, and the effort needed to recover monuments Correct answer.
    4. The county recorder's fee schedule for filing the record of survey

    Explanation

    Field labor is driven by how long the crew must be on site, which depends on the area to be covered, terrain and access, and how difficult the monument search proves to be. Drafting style, copies, and recording fees are small or fixed costs by comparison.

  18. Question 18Pre-Examination Activities

    A client supplies a 25-year-old survey of the property. In pre-field research, the surveyor should:

    1. Treat it as a record document whose evidence must be evaluated against deeds and found monuments Correct answer.
    2. Discard it because surveys expire after ten years
    3. Adopt its boundary lines as the correct location of the corners, since a licensed surveyor prepared it
    4. File it with the county as the current record of survey

    Explanation

    An older survey is useful record evidence of what was found and set at the time, but it does not control over the deeds or over the monuments themselves. The current surveyor must evaluate it critically and field-verify its monument calls.

  19. Question 19Pre-Examination Activities

    For an ALTA/NSPS Land Title Survey, which pre-field step is required to define the scope properly?

    1. Selecting every Table A item so that the survey will be as complete and as useful as possible
    2. Relying on the title company to choose Table A items without client input
    3. Applying Table A only when the property is larger than one acre
    4. Negotiating the applicable Table A items with the client and title company in writing Correct answer.

    Explanation

    Table A items are optional and become part of the survey only when they are specifically negotiated and confirmed in writing among the surveyor, client, and title company. Ordering all items indiscriminately increases cost without matching the transaction's needs.

  20. Question 20Pre-Examination Activities

    A surveyor is retracing boundaries originally created under the U.S. Public Land Survey System. The strongest pre-field evidence source is:

    1. The current tax assessor's parcel map
    2. The original GLO plats and field notes, together with later dependent resurvey records Correct answer.
    3. A modern GIS parcel layer published by the county assessor and updated from deed descriptions
    4. Aerial imagery from a free web mapping service

    Explanation

    Original General Land Office plats and field notes record the positions and descriptions of the corners as established, and later dependent resurveys build on that evidence. Derivative products such as GIS layers and assessment maps are compiled for other purposes and carry no boundary authority.

  21. Question 21Pre-Examination Activities

    A surveyor suspects the subject parcel may have been created without the subdivision approval required at the time. To evaluate this, the surveyor should:

    1. Confirm that the parcel has its own separate tax identification number and appears on the current tax roll
    2. Trace the chain of title to the effective date of the subdivision regulations and check for approvals Correct answer.
    3. Measure the parcel's area and compare it with the minimum lot size required by the current zoning ordinance
    4. Ask the client whether the parcel was legally created when it was originally conveyed

    Explanation

    Whether a division of land was lawful depends on the regulations in force when the parcel was created, so the chain of title must be traced to that date and checked for recorded approvals or documented exemptions. Current zoning and the client's recollection do not establish historical compliance.

  22. Question 22Pre-Examination Activities

    A deliverable must be expressed in State Plane coordinates. Which combination of pre-field decisions is required?

    1. The zone, the horizontal datum and epoch, and the projection and units Correct answer.
    2. The zone and the county's recording format for plats
    3. The zone and the vertical datum only
    4. Only the zone name, because the datum and epoch do not affect State Plane coordinates in practice

    Explanation

    State Plane coordinates are meaningless without the zone, the datum and realization or epoch, and the projection and units used to compute them. Different realizations of the same datum can differ by a meter or more, so the epoch must be stated for modern GNSS-derived coordinates.

  23. Question 23Pre-Examination Activities

    In a formal quality control program for a large boundary survey, what should happen to the research file and computations before mobilization?

    1. They are archived in the project file until the field crew requests them
    2. They are checked by a second qualified reviewer Correct answer.
    3. They are sent directly to the client for approval of boundary locations
    4. They are reviewed only if the client asks for a review

    Explanation

    Independent review before mobilization catches research omissions and computational errors while corrections are still inexpensive. A second qualified person who did not prepare the work provides the objectivity the check is meant to achieve.

  24. Question 24Surveying Instruments and Procedures

    Which surveying instrument is designed primarily to measure both horizontal and vertical angles?

    1. A planimeter
    2. A stereoscope
    3. A clinometer
    4. A theodolite Correct answer.

    Explanation

    A theodolite carries a graduated horizontal circle and a vertical circle, so both horizontal and vertical angles can be read from the same setup. Instruments such as planimeters measure area, while a clinometer reads only slope angles.

  25. Question 25Surveying Instruments and Procedures

    What is the main function of a tribrach in a surveying instrument setup?

    1. To illuminate the cross hairs for night observation
    2. To measure the slope distance to a target
    3. To attach the instrument to the tripod head and allow it to be levelled Correct answer.
    4. To record the horizontal circle readings

    Explanation

    The tribrach is the fitting that screws onto the tripod head and carries the instrument, with three foot screws for levelling. It may also house an optical plummet for centring, but its primary structural role is mounting and levelling.

  26. Question 26Surveying Instruments and Procedures

    A total station is best described as a combination of which two instruments?

    1. A compass and a clinometer
    2. A level and a levelling staff
    3. A GNSS receiver and a data logger
    4. An electronic theodolite and an electronic distance meter Correct answer.

    Explanation

    A total station measures angles electronically like a theodolite and distances by electro-optical means, then combines them to compute coordinates. The onboard processor and data storage support the field computations.

  27. Question 27Surveying Instruments and Procedures

    The optical plummet fitted to a theodolite or total station is used to:

    1. Measure the height of the instrument above the station mark
    2. Centre the instrument precisely over the ground mark Correct answer.
    3. Check that the levelling staff is held vertically
    4. Focus the telescope on distant objects

    Explanation

    The optical plummet provides a line of sight down the vertical axis so the observer can see the ground mark and adjust the instrument until it sits directly above it. Centring here means bringing the vertical axis through the station point.

  28. Question 28Surveying Instruments and Procedures

    In levelling, a backsight is a staff reading taken on:

    1. The instrument station itself
    2. A point chosen because of its steep slope
    3. The final point of the levelling run
    4. A point whose elevation is known or assumed Correct answer.

    Explanation

    A backsight is taken on a point of known or assumed elevation to establish the height of the instrument for that setup. It is normally the first reading after the instrument has been set up.

  29. Question 29Surveying Instruments and Procedures

    The sensitivity of a spirit-level bubble tube increases when:

    1. A more viscous liquid is used in the tube
    2. The radius of curvature of the tube is decreased
    3. The tube is shortened while its radius stays the same
    4. The radius of curvature of the tube is increased Correct answer.

    Explanation

    Sensitivity is governed by the angle through which the tube must tilt to move the bubble by one division, and a larger radius of curvature produces a smaller angle, hence a more sensitive bubble. A longer tube and larger bore also improve sensitivity.

  30. Question 30Surveying Instruments and Procedures

    A prismatic compass is used in surveying to measure:

    1. The horizontal distance between two points
    2. The difference in elevation between two points
    3. The magnetic bearing of a line Correct answer.
    4. The area enclosed by a closed traverse

    Explanation

    A prismatic compass gives the magnetic bearing of a line directly, since the line of sight and the graduated ring are read together through the prism. Bearings are referenced to magnetic north and must be corrected for local magnetic declination if true bearings are needed.

  31. Question 31Surveying Instruments and Procedures

    The two-peg test is carried out on a level in order to:

    1. Determine the height of the instrument at each setup
    2. Verify that the tripod is standing on firm ground
    3. Detect and quantify collimation error in the line of sight Correct answer.
    4. Check whether the staff graduations are accurate

    Explanation

    The test compares height differences obtained with equal and with unequal sight lengths; any discrepancy between them reveals that the line of sight is not parallel to the bubble tube axis. The size of the discrepancy gives the amount of collimation error over the long sight.

  32. Question 32Surveying Instruments and Procedures

    Collimation error exists in a level when the line of sight:

    1. Is not horizontal when the instrument stands on sloping ground
    2. Is not perpendicular to the vertical axis
    3. Is not parallel to the axis of the bubble tube Correct answer.
    4. Does not pass through the optical centre of the objective lens

    Explanation

    The line of collimation is defined by the intersection of the cross hairs with the optical axis of the telescope, and it must be parallel to the bubble tube axis when the bubble is centred. If it is not, the reading varies with sight length even though the instrument has been levelled.

  33. Question 33Surveying Instruments and Procedures

    In spirit levelling, the correction for atmospheric refraction is approximately:

    1. Zero, since refraction is ignored in all levelling work
    2. Equal to the curvature correction and acting in the same direction
    3. One-seventh of the curvature correction and acting in the opposite direction Correct answer.
    4. Seven times the curvature correction and acting in the opposite direction

    Explanation

    Refraction bends the line of sight downwards towards the earth, so a staff appears higher than it really is, which opposes the curvature effect that makes it appear lower. Empirically the refraction effect is about one-seventh of the curvature effect, giving a combined correction of about 0.0673D squared metres with D in kilometres.

  34. Question 34Surveying Instruments and Procedures

    If a levelling staff is held leaning instead of truly vertical, the effect on the result is that:

    1. The reading is greater than the true value, so the point's level is computed too low Correct answer.
    2. The reading is unaffected because it is taken at the central cross hair
    3. The reading is smaller than the true value, so the point's level is computed too high
    4. The reading is greater than the true value, so the point's level is computed too high

    Explanation

    A leaning staff places the graduation actually sighted farther up the staff than the vertical height to the line of sight, so the reading is always too large. Since the reduced level is obtained by subtracting the reading from the height of instrument, the computed level comes out too low.

  35. Question 35Surveying Instruments and Procedures

    A total station is set to a prism constant of zero, but a prism with a constant of minus 30 mm is actually used. The effect on the measured distances is that:

    1. Every distance is in error by the same fixed amount Correct answer.
    2. The error grows in proportion to the measured distance
    3. No error arises unless the sight is longer than one kilometre
    4. Vertical angles are affected but distances are not

    Explanation

    The prism constant is a fixed offset applied to every measurement to compensate for the extra light path inside the prism and its housing. A mismatch between the set value and the real prism therefore shifts all distances by the same amount, here 30 mm, independent of range.

  36. Question 36Surveying Instruments and Procedures

    Air temperature and pressure must be entered into a total station before measuring distances because:

    1. The speed of light in air varies with these, so the measured distance needs correcting Correct answer.
    2. The instrument cannot complete its levelling routine until they are entered
    3. They shift the zero of the vertical circle
    4. They are needed in order to compute the prism constant

    Explanation

    Electro-optical distance measurement converts travel time into distance using the speed of light in air, which depends on temperature and barometric pressure. Entering the actual values lets the instrument apply the atmospheric correction to the raw measurement.

  37. Question 37Surveying Instruments and Procedures

    Averaging horizontal circle readings taken in the face-left and face-right positions eliminates errors due to:

    1. Incorrect centring over the station mark
    2. Graduation errors in the horizontal circle
    3. Collimation and horizontal-axis errors Correct answer.
    4. The vertical axis not being truly vertical

    Explanation

    Transiting the telescope reverses the effect of the line-of-sight and trunnion-axis misalignments on the circle reading, so the mean of the two faces removes them. Errors in levelling and centring produce effects that do not reverse with face and must be controlled by careful setup.

  38. Question 38Surveying Instruments and Procedures

    The circular (box) bubble mounted on an instrument or tribrach is provided mainly to:

    1. Bring the instrument approximately level before fine levelling Correct answer.
    2. Indicate the direction of magnetic north
    3. Measure small angles of tilt to arc-second accuracy
    4. Check the verticality of ranging rods

    Explanation

    A circular bubble is comparatively insensitive and is used to get the instrument roughly level, after which the more sensitive plate or tube bubble is centred with the foot screws. This two-stage approach speeds up setting up without sacrificing precision.

  39. Question 39Surveying Instruments and Procedures

    Real-time kinematic (RTK) GNSS positioning of a rover requires:

    1. A prism mounted on the rover and a total station at the base
    2. The rover antenna to be levelled to within one arc-second
    3. A correction stream from a base station or a network service Correct answer.
    4. The rover to be set on a known point for every observation

    Explanation

    RTK resolves the carrier-phase ambiguities at the rover in real time using corrections transmitted from a base receiver or a network service. Positions are computed in three dimensions, so the antenna needs only to be held steady and roughly plumbed.

  40. Question 40Surveying Instruments and Procedures

    When a levelling staff has to be held upside down against a ceiling or bridge soffit, the reading is recorded as negative because:

    1. The point cannot be levelled and must be observed from another side
    2. The staff zero is above the line of sight, so the point lies above the instrument Correct answer.
    3. The reading must be doubled to allow for the reversed graduations
    4. The reading is positive but the instrument height must be reduced

    Explanation

    With the staff inverted, its zero end sits at the high point and the graduations increase downwards, so the sighted graduation corresponds to a point above the line of sight. Treating the reading as negative in the height-of-instrument computation gives the correct, higher reduced level.

  41. Question 41Surveying Instruments and Procedures

    In stadia tacheometry with a horizontal line of sight, the horizontal distance is obtained by multiplying the staff intercept by:

    1. 100 Correct answer.
    2. 200
    3. 50
    4. 20

    Explanation

    For a horizontal sight the distance equals the multiplying constant times the intercept between the upper and lower stadia hairs plus the additive constant, which is normally zero for an internal-focusing telescope. The conventional multiplying constant is 100.

  42. Question 42Surveying Instruments and Procedures

    Two pegs A and B are 60 m apart. With the level set exactly midway, the staff readings are 1.500 m on A and 1.200 m on B. The level is then moved to a point 10 m from A on the line AB, where the readings are 1.400 m on A and 1.110 m on B. What is the collimation error over the 50 m sight to B?

    1. 0.290 m
    2. 0.300 m
    3. 0.005 m
    4. 0.010 m Correct answer.

    Explanation

    From the midpoint the sights are equal, so collimation error and curvature-refraction cancel and the true height difference is 1.500 minus 1.200, or 0.300 m with B higher. From the second setup the apparent difference is 1.400 minus 1.110, or 0.290 m, the shortfall of 0.010 m being the collimation error accumulated over the 50 m sight to B.

  43. Question 43Surveying Instruments and Procedures

    A level takes a sight of 500 m. Using the combined curvature and refraction correction of 0.0673D squared, with D in kilometres and the result in metres, the magnitude of the correction is:

    1. 0.067 m
    2. 0.034 m
    3. 0.017 m Correct answer.
    4. 0.008 m

    Explanation

    With D equal to 0.5 km, the correction is 0.0673 times 0.25, which is about 0.0168 m, or 0.017 m. It is subtracted from the staff reading because the combined effect makes the staff appear too high.

  44. Question 44Surveying Instruments and Procedures

    A total station set on an unknown point observes three known control points to fix its own coordinates. The computed position becomes unreliable when:

    1. The instrument height is measured with a steel tape
    2. The occupied point lies on the circle passing through the three known points Correct answer.
    3. The observations are taken on both faces
    4. The three known points are more than 500 m from the instrument

    Explanation

    The angles subtended by three fixed points are the same for every position on the circle through those points, so the resection has no unique solution on that circle. Surveyors avoid this danger circle by choosing control points that do not put the station on it.

  45. Question 45Surveying Instruments and Procedures

    In reciprocal levelling between two points that are far apart, the mean of the two height differences obtained with the instrument placed near each point eliminates:

    1. Errors in the graduations of the staff
    2. Curvature, refraction and collimation error Correct answer.
    3. The effect of the instrument height
    4. Only the effect of the staff not being held vertical

    Explanation

    In the two setups the long and short sights are interchanged, so any error that depends on sight length - curvature, refraction and collimation - affects each height difference by equal and opposite amounts. Averaging the pair therefore cancels them, which is why reciprocal levelling is used across rivers and ravines.

  46. Question 46Boundary and Cadastral Surveys

    How many sections are contained in a standard township of the Public Land Survey System?

    1. 36 Correct answer.
    2. 64
    3. 16
    4. 24

    Explanation

    A standard township is a square six miles on a side, laid out as a grid of six sections by six sections, which yields 36 sections of one square mile (640 acres) each.

  47. Question 47Boundary and Cadastral Surveys

    Within a PLSS township, section 1 is located at which corner?

    1. Northwest corner
    2. Northeast corner Correct answer.
    3. Southwest corner
    4. Southeast corner

    Explanation

    Section numbering starts with section 1 in the northeast corner and runs westward across the top tier, then zigzags east-west through successive tiers, finishing with section 36 in the southeast corner.

  48. Question 48Boundary and Cadastral Surveys

    A metes and bounds description defines a parcel chiefly by:

    1. Reference to a lot and block number on a recorded subdivision plat
    2. Coordinates referenced to a state plane grid
    3. Aliquot parts of a section in the public land survey
    4. Calls for courses and distances from a point of beginning Correct answer.

    Explanation

    Metes and bounds descriptions trace the perimeter of a parcel with calls for course (bearing) and distance from a described point of beginning, closing back on that point.

  49. Question 49Boundary and Cadastral Surveys

    In the Public Land Survey System, the east-west line from which tiers of townships are counted is the:

    1. Guide meridian
    2. Base line Correct answer.
    3. Standard parallel
    4. Principal meridian

    Explanation

    The base line runs east-west and, with the north-south principal meridian, forms the origin of the survey; township tiers are counted north and south from the base line.

  50. Question 50Boundary and Cadastral Surveys

    In a well-drafted metes and bounds description, the point of beginning should be:

    1. A readily identifiable monument or record reference Correct answer.
    2. The point of highest elevation on the property
    3. The nearest section corner in the government survey
    4. The approximate center of the parcel

    Explanation

    The point of beginning anchors the whole description, so it must be something a surveyor can locate with confidence, such as an original monument, a record intersection, or a well-defined physical feature.

  51. Question 51Boundary and Cadastral Surveys

    On a government plat, the meander line along a river most nearly represents:

    1. The limit of riparian rights
    2. The ordinary high water mark of the river
    3. A line run to compute water area Correct answer.
    4. The thread of the stream

    Explanation

    Meander lines are run only to calculate the area of the water body so it can be excluded from the fractional lots; they are not boundaries unless the water has since receded from the meander line.

  52. Question 52Boundary and Cadastral Surveys

    The water-related rights of an owner whose land borders a lake or sea are described as:

    1. Riparian rights
    2. Littoral rights Correct answer.
    3. Appurtenant rights
    4. Prescriptive rights

    Explanation

    Littoral is the term applied to land bordering a sea, lake, or pond, while riparian refers to land bordering a flowing stream or river.

  53. Question 53Boundary and Cadastral Surveys

    A right to cross a neighbor's land acquired through long, open, continuous use without permission is called a:

    1. Prescriptive easement Correct answer.
    2. Profit a prendre
    3. License
    4. Covenant

    Explanation

    Use that is open, continuous, and adverse for the statutory period creates a prescriptive easement, the easement counterpart of adverse possession.

  54. Question 54Boundary and Cadastral Surveys

    A parcel described as the SW 1/4 of the NE 1/4 of Section 12 contains approximately how many acres?

    1. 40 acres Correct answer.
    2. 160 acres
    3. 20 acres
    4. 80 acres

    Explanation

    A section contains 640 acres, so the NE 1/4 is 160 acres and the southwest quarter of that quarter is one-quarter of 160, or 40 acres.

  55. Question 55Boundary and Cadastral Surveys

    Government lots that depart from regular aliquot parts are created chiefly because:

    1. The plat was recorded after the township was subdivided
    2. A meander line or boundary truncates the regular subdivision Correct answer.
    3. The section was subdivided into regular aliquot parts
    4. Two deeds to the same section overlap

    Explanation

    Where a section boundary is cut by a navigable water body, a reservation, or a closing line, the remainder cannot be described as regular aliquot parts, so the plat numbers fractional lots.

  56. Question 56Boundary and Cadastral Surveys

    An original section corner has been completely destroyed and no reliable evidence of its position survives. In retracement it is treated as a:

    1. Lost corner Correct answer.
    2. Obliterated corner
    3. Closing corner
    4. Witness corner

    Explanation

    A corner is lost when both the monument and any acceptable evidence of its original location are gone, so its position must be restored by proportionate measurement from surviving corners.

  57. Question 57Boundary and Cadastral Surveys

    A lost quarter-section corner lies on the straight line between two found section corners. The correct method to reestablish it is:

    1. Record bearing and distance from the nearest corner
    2. Double proportionate measurement
    3. Random traverse from the nearest found monument
    4. Single proportionate measurement along the line Correct answer.

    Explanation

    A corner lying on a single line between two known corners is restored by single proportionate measurement, distributing the record distance in proportion to the measured distance between the found corners.

  58. Question 58Boundary and Cadastral Surveys

    Two deeds describe overlapping parcels, and the grantor owned both tracts when the earlier deed was delivered. The overlap is generally resolved in favor of:

    1. The senior right of the earlier conveyance Correct answer.
    2. The later deed, if its description is more detailed
    3. The junior deed, if it was recorded first
    4. Equal division of the overlap between the owners

    Explanation

    Because the grantor no longer owned the land covered by the first deed, the later deed cannot convey it; the earlier, senior conveyance prevails.

  59. Question 59Boundary and Cadastral Surveys

    A river abandons its channel during a flood and cuts a new course. The boundary between the riparian owners:

    1. Follows the nearest meander line
    2. Remains at the old channel Correct answer.
    3. Follows the new channel
    4. Shifts to the middle of the abandoned bed only by agreement

    Explanation

    A sudden change of channel is avulsion, and boundaries are not moved by avulsion, so the owners keep the old channel line as their boundary.

  60. Question 60Boundary and Cadastral Surveys

    Under a notice recording statute, a later purchaser who takes without knowledge of an earlier unrecorded conveyance prevails because the later purchaser:

    1. Received a quitclaim deed
    2. Took without notice of the earlier interest Correct answer.
    3. Recorded first in point of time
    4. Paid the highest price for the land

    Explanation

    A notice statute protects a subsequent purchaser who pays value and takes without notice of the prior unrecorded interest, whether or not that purchaser records first.

  61. Question 61Boundary and Cadastral Surveys

    Two adjoining owners, uncertain of the true line, agree on a boundary and occupy to it for many years. The doctrine that governs is:

    1. Easement by necessity
    2. Adverse possession
    3. Boundary by agreement Correct answer.
    4. Prescription

    Explanation

    Where the true line is uncertain and the owners agree on a line and occupy to it, courts enforce the agreed boundary, sometimes called boundary by agreement.

  62. Question 62Boundary and Cadastral Surveys

    The essential element of boundary by acquiescence is:

    1. A written deed describing the line
    2. Mutual recognition of a line as the boundary over time Correct answer.
    3. Payment of property taxes on the disputed strip by one owner for many years
    4. A recorded survey showing the line

    Explanation

    Acquiescence rests on the conduct of adjoining owners who treat a particular line as the boundary and let the statutory period pass without objection.

  63. Question 63Boundary and Cadastral Surveys

    A closing corner is established where:

    1. A section line crosses a navigable stream
    2. A survey line closes on a standard parallel Correct answer.
    3. A section corner falls inside a meandered lake
    4. A meander line meets a section line

    Explanation

    Closing corners are set where a surveyed line, such as a township or range line, closes on a standard parallel or other correction line instead of meeting an existing corner.

  64. Question 64Boundary and Cadastral Surveys

    A deed describes a tract as 'containing 10 acres, more or less.' The stated quantity generally:

    1. Yields to monuments and to courses and distances Correct answer.
    2. Overrides the courses and distances in the deed
    3. Voids the conveyance for indefiniteness
    4. Controls over any monument called for in the deed

    Explanation

    Quantity is the weakest of the deed calls; it gives way to monuments and then to courses and distances, and 'more or less' signals that the area is only approximate.

  65. Question 65Boundary and Cadastral Surveys

    A retracing surveyor finds that the original government surveyor set a corner 20 feet from where the record distances would place it. The retracing surveyor should:

    1. Set a new corner at the computed record position and note the old one as erroneous
    2. Reject the monument and reestablish the line strictly by the record distance
    3. Follow the original surveyor's footsteps and hold the monument as set Correct answer.
    4. Correct the discrepancy only if it exceeds the deed's stated tolerance

    Explanation

    Retracement follows the original survey as executed; an original monument controls even if it was set in error, because the government survey fixed the boundary when the patent issued.

  66. Question 66Boundary and Cadastral Surveys

    Rank the following deed calls from strongest to weakest controlling weight:

    1. Quantity, course and distance, artificial monument, natural monument
    2. Natural monument, artificial monument, course and distance, quantity Correct answer.
    3. Artificial monument, natural monument, quantity, course and distance
    4. Course and distance, natural monument, quantity, artificial monument

    Explanation

    The classic hierarchy of evidence places natural monuments first, then artificial monuments, then courses and distances, and finally quantity or area.

  67. Question 67Boundary and Cadastral Surveys

    Land is added gradually and imperceptibly to the bank of a navigable river by the action of the water. The new land belongs to:

    1. The adjoining owner only if the addition is platted and recorded
    2. The state, because it owns the bed of a navigable river
    3. The federal government under the equal footing doctrine
    4. The adjoining riparian owner Correct answer.

    Explanation

    Accretion, meaning a gradual and imperceptible addition, belongs to the riparian owner even where the state owns the bed of the navigable water.

  68. Question 68Photogrammetry and Remote Sensing

    A vertical aerial photograph is taken with a camera of 152 mm focal length from a flying height of 3050 m above the ground. What is the approximate scale of the photograph?

    1. 1:50,000
    2. 1:20,000 Correct answer.
    3. 1:2,000
    4. 1:200,000

    Explanation

    For a vertical photograph the scale at ground level is the focal length divided by the flying height above ground, f/H. Here 0.152 m divided by 3050 m gives about 1/20,070, which rounds to 1:20,000.

  69. Question 69Photogrammetry and Remote Sensing

    What is the function of the fiducial marks on a metric aerial photograph?

    1. They define the photo coordinate axes and locate the principal point Correct answer.
    2. They record the flying height of the exposure station above sea level
    3. They record the solar azimuth and elevation at the instant of exposure
    4. They mark the overlap shared by adjacent flight strips in a block

    Explanation

    Fiducial marks are exposed in the camera focal plane by small indices at calibrated positions around each frame. Joining opposite marks establishes the photo coordinate axes and their intersection locates the principal point, which is the basis of interior orientation.

  70. Question 70Photogrammetry and Remote Sensing

    Normal practice for a stereoscopic vertical aerial photographic mission is to provide about:

    1. 60 per cent endlap and 30 per cent sidelap Correct answer.
    2. 10 per cent endlap and 5 per cent sidelap
    3. 20 per cent endlap and 60 per cent sidelap
    4. 90 per cent endlap and 50 per cent sidelap

    Explanation

    Standard vertical photography is flown with about 60 per cent endlap along each strip and 30 per cent sidelap between adjacent strips. This gives comfortable stereo overlap plus enough redundant rays for block adjustment.

  71. Question 71Photogrammetry and Remote Sensing

    An orthophoto is best described as:

    1. An image resampled to uniform scale with relief displacement removed Correct answer.
    2. A frame exposed with the camera axis deliberately tilted
    3. A mosaic of uncorrected photographic prints joined at visible seam lines
    4. An image recorded only in the thermal infrared region

    Explanation

    Orthorectification uses a terrain model to displace every pixel so that the result behaves like a vertical view of a horizontal map surface. Positions can then be measured directly on the image at one constant scale.

  72. Question 72Photogrammetry and Remote Sensing

    How many distinct brightness levels can be stored in an 8-bit image?

    1. 1,024
    2. 65,536
    3. 256 Correct answer.
    4. 8

    Explanation

    Radiometric resolution of n bits provides 2^n quantisation levels. Eight bits therefore give 2^8 = 256 levels, normally numbered 0 to 255.

  73. Question 73Photogrammetry and Remote Sensing

    What is the defining property of a sun-synchronous satellite orbit?

    1. The satellite stays above the same equatorial point at all times
    2. It crosses a given latitude at nearly the same local solar time Correct answer.
    3. Its orbital plane is fixed in inertial space and passes over both poles
    4. It matches the altitude and period of the orbit used by crewed stations

    Explanation

    In a sun-synchronous orbit the precession of the orbital plane roughly matches the Earth's motion around the Sun, at about one degree per day. The satellite therefore crosses each latitude at nearly the same local solar time, keeping sun elevation and shadow direction consistent between dates.

  74. Question 74Photogrammetry and Remote Sensing

    In remote sensing, temporal resolution refers to:

    1. The number of spectral bands recorded by the sensor
    2. The interval between repeat views of the same area Correct answer.
    3. The range of radiance values the sensor can record
    4. The solid angle instantaneously viewed by the sensor

    Explanation

    Temporal resolution is the revisit interval, that is, how often the same ground area can be imaged again. It depends on the orbit, the swath width and whether the sensor can point off-nadir.

  75. Question 75Photogrammetry and Remote Sensing

    On a vertical photograph taken from 1800 m above datum, a point 60 m above datum lies 80 mm from the principal point. What is its relief displacement?

    1. 0.33 mm
    2. 4.00 mm
    3. 2.67 mm Correct answer.
    4. 1.33 mm

    Explanation

    Relief displacement is d = r·h/H, where r is the radial distance from the principal point, h the height above datum and H the flying height above datum. Here d = 80 mm × 60 m / 1800 m ≈ 2.67 mm.

  76. Question 76Photogrammetry and Remote Sensing

    On a tilted aerial photograph, the point lying midway between the principal point and the photo nadir is called the:

    1. Plumb point
    2. Secondary principal point
    3. Isocenter Correct answer.
    4. Ground nadir

    Explanation

    Tilt separates the principal point, where the optical axis meets the photo, from the nadir, where the plumb line meets it. The bisector of the angle between those two lines meets the photo at the isocenter, halfway between them.

  77. Question 77Photogrammetry and Remote Sensing

    A sensor that records several hundred narrow, contiguous spectral bands is described as:

    1. Hyperspectral Correct answer.
    2. Orthochromatic
    3. Panchromatic
    4. Multispectral

    Explanation

    Hyperspectral instruments record hundreds of narrow, contiguous bands so that a nearly continuous spectrum can be reconstructed for each pixel. Multispectral sensors record only a few comparatively broad bands.

  78. Question 78Photogrammetry and Remote Sensing

    An aerial camera has a 100 mm focal length and a pixel size of 10 µm. At a flying height of 1000 m above ground, what is the ground sample distance?

    1. 10 m
    2. 1.0 m
    3. 0.01 m
    4. 0.10 m Correct answer.

    Explanation

    Ground sample distance is the pixel size multiplied by flying height and divided by focal length. Here 10 µm × 1000 m / 100 mm = 0.00001 m × 10,000 = 0.10 m per pixel.

  79. Question 79Photogrammetry and Remote Sensing

    The blue-grey haze that degrades high-altitude aerial imagery is caused mainly by:

    1. Absorption of microwave energy by water vapour near the ground
    2. Stray light emitted by the optical components of the sensor
    3. Scattering of short wavelengths by atmospheric molecules Correct answer.
    4. Specular reflection from wet ground surfaces beneath the aircraft

    Explanation

    Rayleigh scattering varies roughly as the inverse fourth power of wavelength, so blue light is scattered far more strongly than red. The scattered light forms a path radiance that reduces image contrast, which is why haze looks blue and why longer-wavelength bands are less affected.

  80. Question 80Photogrammetry and Remote Sensing

    The Normalised Difference Vegetation Index is computed as:

    1. (NIR − Red) / (NIR + Red) Correct answer.
    2. (NIR + Red) / (NIR − Red)
    3. (Red − NIR) / (Red + NIR)
    4. NIR / Red

    Explanation

    NDVI contrasts the strong near-infrared reflectance of healthy vegetation with chlorophyll absorption in the red band, and the normalised difference confines the result to the range −1 to +1. Values near +1 indicate dense green vegetation, while soil and water give values near zero or below.

  81. Question 81Photogrammetry and Remote Sensing

    To orthorectify a satellite image of mountainous terrain, the additional input required beyond interior and exterior orientation is:

    1. A higher radiometric bit depth for the image
    2. A digital elevation model of the terrain Correct answer.
    3. A larger number of ground control points alone
    4. A radiometric calibration file for the sensor

    Explanation

    Orthorectification must shift every pixel by the relief displacement that corresponds to its ground elevation, so the height of each point has to be supplied. Without terrain heights a rugged scene cannot be correctly rectified, however many control points are used.

  82. Question 82Photogrammetry and Remote Sensing

    Which statement correctly distinguishes a digital surface model from a digital terrain model?

    1. A DTM includes buildings and trees, whereas a DSM shows bare earth
    2. A DSM is a vector product, whereas a DTM is always a raster product
    3. A DSM shows the tops of vegetation and buildings, a DTM shows bare earth Correct answer.
    4. A DSM is produced only from radar data, a DTM only from optical data

    Explanation

    Both are elevation models, but the DSM records the first surface encountered, such as tree crowns and rooftops, while the DTM is a bare-earth surface with those features removed. Matching over overlapping photographs naturally produces a DSM.

  83. Question 83Photogrammetry and Remote Sensing

    Deriving the ground coordinates of an object point from its measured image coordinates in two overlapping photographs is known as:

    1. Space resection
    2. Bundle adjustment
    3. Relative orientation
    4. Space intersection Correct answer.

    Explanation

    Each photograph defines a ray from its perspective centre through the measured image point, and two such rays intersect at the point's position in space. The camera stations and attitudes must already be known, so intersection normally follows resection or a block adjustment.

  84. Question 84Photogrammetry and Remote Sensing

    Which resampling method gives each output pixel the value of the nearest input pixel and therefore creates no new radiometric values?

    1. Bicubic spline
    2. Nearest neighbour Correct answer.
    3. Bilinear interpolation
    4. Cubic convolution

    Explanation

    Nearest neighbour copies the value of the input pixel closest to the output pixel centre, so no new values are invented. It is preferred when class labels or spectral fidelity must be preserved, although edges can appear blocky.

  85. Question 85Photogrammetry and Remote Sensing

    What causes speckle in a radar image?

    1. A geometric distortion produced by steep terrain slopes and strong relief
    2. Granular noise caused by coherent interference of the scattered returns Correct answer.
    3. A loss of signal caused by dense cloud cover over the target
    4. A systematic drift in the transmitted radar wavelength

    Explanation

    Coherent returns from many small scatterers inside a resolution cell add with random relative phase. The resulting constructive and destructive interference produces the salt-and-pepper speckle pattern, which is reduced by multi-looking or adaptive filtering.

  86. Question 86Photogrammetry and Remote Sensing

    A stereopair has a parallax of 87.6 mm at datum and 90.0 mm for a point of interest, and the flying height is 3000 m above datum. What is the height of the point above datum?

    1. 80 m Correct answer.
    2. 160 m
    3. 40 m
    4. 120 m

    Explanation

    Height from a parallax difference is h = H·Δp/(P + Δp), where P is the parallax at datum and Δp the parallax difference. With H = 3000 m, P = 87.6 mm and Δp = 2.4 mm, h = 3000 × 2.4 / 90.0 = 80 m.

  87. Question 87Photogrammetry and Remote Sensing

    An image classification has an overall accuracy of 0.85 and a chance agreement of 0.60. What is the kappa coefficient?

    1. 0.40
    2. 0.25
    3. 0.625 Correct answer.
    4. 0.85

    Explanation

    Kappa is the observed agreement minus chance agreement, divided by one minus chance agreement. Here (0.85 − 0.60) / (1 − 0.60) = 0.25 / 0.40 = 0.625.

  88. Question 88Photogrammetry and Remote Sensing

    In interferometric SAR, the phase difference between two acquisitions of the same area is used mainly to:

    1. Remove speckle noise from the amplitude image by averaging many looks
    2. Convert the image from slant-range to ground-range geometry
    3. Measure slant-range differences, giving topography or surface motion Correct answer.
    4. Separate the transmitted pulse from the received echo in the antenna

    Explanation

    The phase difference between two complex radar images is proportional to the two-way path-length difference between them. Interpreting that as relative slant range yields elevation models, and for repeat passes with a stable geometry it resolves surface displacement of a fraction of the wavelength.

  89. Question 89Photogrammetry and Remote Sensing

    Radar layover occurs where:

    1. A near-range slope is steeper than the look angle, so its top returns first Correct answer.
    2. A slope faces away from the radar so that no energy is returned to it
    3. The satellite returns over the same area on a later repeat orbit
    4. The radar wavelength is shorter than the scale of surface roughness

    Explanation

    In side-looking radar the slant range to the top of a steep slope facing the sensor can be shorter than to its base, so the top is recorded first and the slope appears to lean over toward the sensor. The opposite case, on slopes facing away, produces radar shadow.

  90. Question 90Geodesy and Geodetic Surveying

    The flattening f of a reference ellipsoid is defined as:

    1. the difference of the semi-axes divided by the semi-minor axis
    2. the difference of the semi-axes divided by the semi-major axis Correct answer.
    3. the semi-major axis divided by the semi-minor axis of the ellipsoid
    4. the semi-minor axis divided by the semi-major axis of the ellipsoid

    Explanation

    Flattening measures how much an ellipsoid departs from a sphere and is computed from the semi-axes as f = (a - b) / a. For the WGS84 ellipsoid this gives about 1/298.257. It is a dimensionless ratio, so it has no units.

  91. Question 91Geodesy and Geodetic Surveying

    In geodesy, the geoid is best described as:

    1. the Earth's topography smoothed to its mean elevation above sea level
    2. the sphere whose radius equals the mean radius of the Earth
    3. the equipotential surface of gravity that approximates mean sea level Correct answer.
    4. the reference ellipsoid adopted for a particular geodetic datum

    Explanation

    The geoid is the level surface of the gravity field that coincides most closely with mean sea level, extended conceptually under the continents. It is a physical surface, not a mathematical one, so it is irregular. Orthometric heights are reckoned from it.

  92. Question 92Geodesy and Geodetic Surveying

    A geodetic datum is:

    1. the parameters fixing an ellipsoid's placement and orientation Correct answer.
    2. the mean value of gravity observed over a network of stations
    3. the grid origin used to define a map projection zone
    4. the ellipsoid formed by rotating an ellipse about its minor axis

    Explanation

    A datum supplies the position, orientation and scale of a reference ellipsoid relative to the Earth, together with the coordinates of at least one defining station. Without a datum, ellipsoidal coordinates have no unique meaning in space. Modern datums are usually realised through a network of satellite-derived station coordinates.

  93. Question 93Geodesy and Geodetic Surveying

    The angle at a point between the equatorial plane and the normal to the reference ellipsoid is the:

    1. geocentric latitude
    2. geodetic latitude Correct answer.
    3. reduced latitude
    4. astronomical latitude

    Explanation

    Geodetic latitude is defined by the ellipsoid normal, which is the direction used in ellipsoidal coordinate computations. Astronomic latitude uses the direction of gravity instead, and geocentric latitude uses the radius vector from the Earth's centre. Reduced latitude is an auxiliary parameter used in some ellipsoid formulae.

  94. Question 94Geodesy and Geodetic Surveying

    In the Earth-Centred Earth-Fixed (ECEF) Cartesian coordinate system, the Z axis is aligned with:

    1. the Earth's mean rotation axis Correct answer.
    2. the direction of the Greenwich meridian at the equator
    3. the local vertical at the origin of the datum
    4. the normal to the ellipsoid at 45 degrees latitude

    Explanation

    ECEF coordinates rotate with the Earth, with the Z axis pointing along the conventional terrestrial pole and the X axis toward the Greenwich meridian in the equatorial plane. The Y axis completes a right-handed system. Positions of satellites and receivers are commonly computed in this frame.

  95. Question 95Geodesy and Geodetic Surveying

    The Universal Transverse Mercator grid divides the Earth into 60 zones, each spanning:

    1. 3 degrees of longitude
    2. 4 degrees of longitude
    3. 6 degrees of longitude Correct answer.
    4. 12 degrees of longitude

    Explanation

    UTM zones are each 6 degrees wide in longitude, numbered from zone 1 at 180 degrees west. Limiting the zone width keeps scale distortion within acceptable bounds away from the central meridian. Each zone has its own central meridian and false easting.

  96. Question 96Geodesy and Geodetic Surveying

    In the UTM projection, the scale factor on the central meridian of a zone is:

    1. 0.9996 Correct answer.
    2. 1.0000
    3. 1.0006
    4. 0.9990

    Explanation

    UTM applies a central-meridian scale factor of 0.9996 so that the projection surface cuts the ellipsoid along two lines roughly 180 km either side of the meridian. Scale is exactly unity on those two lines and reaches about 1.0004 at the zone edges. This balances distortion across the zone.

  97. Question 97Geodesy and Geodetic Surveying

    The combined factor used to convert a horizontal ground distance to a grid distance is obtained as the:

    1. grid scale factor added to elevation factor
    2. grid scale factor minus elevation factor
    3. grid scale factor multiplied by elevation factor Correct answer.
    4. grid scale factor divided by elevation factor

    Explanation

    The elevation factor brings the measured distance down to the ellipsoid, and the grid scale factor then carries it onto the projection plane. Because both act as multipliers on the length, the combined factor is their product. Applying it to a ground distance yields the corresponding grid distance.

  98. Question 98Geodesy and Geodetic Surveying

    The meridian component of the deflection of the vertical at a station is given by:

    1. the longitude difference times the cosine of the latitude
    2. the astronomic latitude minus the geodetic latitude Correct answer.
    3. the longitude difference times the sine of the latitude
    4. the geodetic latitude minus the astronomic latitude

    Explanation

    The deflection of the vertical has two components: the meridian component, equal to the astronomic latitude minus the geodetic latitude, and the prime-vertical component, equal to the astronomic minus geodetic longitude multiplied by the cosine of the latitude. Both follow from comparing gravity-based and ellipsoid-based directions. The components are usually only a few seconds of arc.

  99. Question 99Geodesy and Geodetic Surveying

    At latitude phi, the radius of curvature in the meridian M and the radius of curvature in the prime vertical N compare as follows:

    1. M is smaller than N except at the poles Correct answer.
    2. M is larger than N at every latitude
    3. M equals N at every latitude
    4. M is smaller than N except at the equator

    Explanation

    The prime-vertical radius is larger than the meridian radius at all latitudes between the equator and the poles because of the way the ellipsoid curves in the two directions. The two radii converge only at the poles, where both equal the polar radius of curvature. At the equator the difference is greatest.

  100. Question 100Geodesy and Geodetic Surveying

    For a geodetic triangle on the ellipsoid, the spherical excess in seconds of arc is computed as:

    1. epsilon = (M times N) divided by (Area times rho)
    2. epsilon = Area times rho divided by (M times N) Correct answer.
    3. epsilon = Area times rho times (M times N)
    4. epsilon = Area times rho divided by (M + N)

    Explanation

    The spherical excess equals the triangle area divided by the product of the two principal radii of curvature, converted from radians to seconds by the factor rho. It grows with the area of the triangle and with latitude. The excess must be removed before the angles are treated as plane angles.

  101. Question 101Geodesy and Geodetic Surveying

    In a Transverse Mercator projection, the convergence of meridians at a point is approximately:

    1. lambda0 times sin(phi)
    2. (lambda - lambda0) times cos(phi)
    3. (lambda - lambda0) times sin(phi) Correct answer.
    4. (phi - phi0) times sin(lambda)

    Explanation

    Grid convergence, the angle between grid north and true north, varies with the longitude difference from the central meridian and with latitude. The standard approximation is the longitude difference from the central meridian multiplied by the sine of the latitude. It is zero on the central meridian and grows toward the zone edges.

  102. Question 102Geodesy and Geodetic Surveying

    A geodetic network in which horizontal angles are observed and side lengths are then derived from a known baseline is called:

    1. traversing
    2. spirit levelling
    3. triangulation Correct answer.
    4. trilateration

    Explanation

    Triangulation measures angles in a chain of triangles and computes the side lengths by trigonometry starting from one measured baseline. Trilateration does the reverse, measuring the distances directly. Traversing follows a continuous line of measured angles and distances rather than a triangle network.

  103. Question 103Geodesy and Geodetic Surveying

    A satellite positioning receiver determines its position by:

    1. measuring the received signal strength from three satellites
    2. measuring the Doppler shift of signals from four satellites
    3. measuring the magnetic bearing to three satellites
    4. measuring the travel times of signals from at least four satellites Correct answer.

    Explanation

    The receiver compares the code or phase of the received signal with its own replica to obtain a range or pseudorange to each satellite. Four satellites are needed because each gives one range equation containing four unknowns: three coordinates and the receiver clock offset. Additional satellites improve the solution by least squares.

  104. Question 104Geodesy and Geodetic Surveying

    A horizontal distance measured at mean ellipsoidal height h above the ellipsoid is reduced to the ellipsoid by:

    1. multiplying it by (R + h) / R
    2. dividing it by the cosine of the vertical angle
    3. multiplying it by the grid scale factor
    4. multiplying it by R / (R + h) Correct answer.

    Explanation

    The reduction to the ellipsoid shortens the distance in proportion to the ratio R/(R + h), where R is the mean radius of curvature along the line. Distances at high elevation are reduced by a larger amount. The vertical angle must already have been removed before this step.

  105. Question 105Geodesy and Geodetic Surveying

    The geoid undulation N at a point is defined as:

    1. the height of the ellipsoid above mean sea level at the equator
    2. the ellipsoidal height minus the orthometric height, h - H Correct answer.
    3. the height of mean sea level above the ellipsoid at the pole
    4. the orthometric height minus the ellipsoidal height, H - h

    Explanation

    The geoid undulation is the separation of the geoid from the reference ellipsoid, counted positive when the geoid lies outside the ellipsoid. It equals the ellipsoidal height minus the orthometric height at the same point. Geoid models provide this quantity so that satellite heights can be converted to heights above sea level.

  106. Question 106Geodesy and Geodetic Surveying

    The Laplace condition applied at a geodetic station states that:

    1. the geodetic longitude must equal the astronomic longitude
    2. the geodetic azimuth equals the astronomic azimuth minus the longitude difference times the sine of the latitude Correct answer.
    3. the geodetic latitude must equal the astronomic latitude at the station
    4. the deflection of the vertical must be zero at the station

    Explanation

    The Laplace condition transfers the observed astronomic azimuth into the geodetic system by applying a correction built from the difference between astronomic and geodetic longitude and the sine of the latitude. This makes the geodetic network consistent with the ellipsoid. It is applied at Laplace stations, which control the orientation of the network.

  107. Question 107Geodesy and Geodetic Surveying

    For a point on the reference ellipsoid, the geocentric latitude psi is related to the geodetic latitude phi by:

    1. tan(psi) = tan(phi) divided by (1 - e squared)
    2. tan(psi) = (1 - e squared) times tan(phi) Correct answer.
    3. tan(psi) = the square root of (1 - e squared) times tan(phi)
    4. tan(psi) = (1 + e squared) times tan(phi)

    Explanation

    The geocentric latitude is always smaller in magnitude than the geodetic latitude away from the equator and the poles. The exact relation is that the tangent of the geocentric latitude equals (1 - e squared) times the tangent of the geodetic latitude. The maximum difference is about 11 minutes of arc at 45 degrees latitude.

  108. Question 108Geodesy and Geodetic Surveying

    Heights reckoned above the quasigeoid in the Molodensky height system are called:

    1. orthometric heights
    2. dynamic heights
    3. normal heights Correct answer.
    4. ellipsoidal heights

    Explanation

    Normal heights are measured from the quasigeoid, which is defined so that no hypothesis about the density of the crust is required. Orthometric heights, in contrast, require an assumption about mean gravity along the plumb line. Ellipsoidal heights are purely geometric and refer to the reference ellipsoid.

  109. Question 109Geodesy and Geodetic Surveying

    Orthometric heights are reckoned from:

    1. the quasigeoid
    2. the mean topographic surface
    3. the geoid Correct answer.
    4. the reference ellipsoid

    Explanation

    Orthometric height is the distance along the curved plumb line from a point down to the geoid. This makes it a physical height above mean sea level rather than a purely geometric one. Ellipsoidal heights, by contrast, are measured from the reference ellipsoid.

  110. Question 110Geodesy and Geodetic Surveying

    The standard seven-parameter Helmert transformation between two geocentric datums consists of:

    1. three translations, three rotations and a scale factor Correct answer.
    2. three translations and one rotation with no scale change
    3. three translations and three rotations only
    4. three translations only

    Explanation

    The Bursa-Wolf form of the Helmert transformation applies three translations of the origin, three small rotations about the axes and one scale difference. Together these seven parameters relate the coordinate sets realised on the two datums. A three-parameter transformation keeps only the translations.

  111. Question 111Geodesy and Geodetic Surveying

    Bruns' equation expresses the geoid undulation N in terms of the disturbing potential T and mean gravity gamma as:

    1. N = T minus gamma
    2. N = T times gamma
    3. N = T divided by gamma Correct answer.
    4. N = gamma divided by T

    Explanation

    Bruns' equation states that the geoid undulation equals the disturbing potential at the geoid divided by normal gravity. It provides the theoretical link between gravity field modelling and geoid determination. Disturbing potential and gravity must be expressed in consistent units.

  112. Question 112Surveying Calculations and Adjustments

    A closed traverse has six sides. What is the theoretical sum of its interior angles?

    1. 900°
    2. 1 080°
    3. 720° Correct answer.
    4. 540°

    Explanation

    The interior angles of a closed polygon sum to (n − 2) × 180°, where n is the number of sides. For n = 6 this gives 4 × 180° = 720°.

  113. Question 113Surveying Calculations and Adjustments

    What is the equivalent azimuth (measured clockwise from north) of a line whose bearing is N 32° E?

    1. 328°
    2. 58°
    3. 32° Correct answer.
    4. 148°

    Explanation

    In the northeast quadrant the bearing angle equals the azimuth directly, so N 32° E corresponds to an azimuth of 32°. Azimuths in other quadrants are obtained by combining the bearing angle with 180° or 360°.

  114. Question 114Surveying Calculations and Adjustments

    In traverse computations, the latitude of a course is obtained as:

    1. distance × sin(bearing angle)
    2. distance ÷ cos(bearing angle)
    3. distance × tan(bearing angle)
    4. distance × cos(bearing angle) Correct answer.

    Explanation

    Latitude is the northing component of a course, so it equals the horizontal distance multiplied by the cosine of the bearing angle. Departure, the easting component, uses the sine instead.

  115. Question 115Surveying Calculations and Adjustments

    In a closed traverse, the linear misclosure is best described as:

    1. The measured interior angle sum minus the theoretical sum
    2. The vector from the computed end point back to the start point Correct answer.
    3. The total length of all courses added together
    4. The average of all course latitudes and departures

    Explanation

    Linear misclosure is the vector discrepancy between where the traverse is computed to end and the point where it should end, usually expressed by its latitude and departure components. Its magnitude, divided by the perimeter, gives the relative precision.

  116. Question 116Surveying Calculations and Adjustments

    A benchmark has an elevation of 100.000 m. With the instrument set up, the backsight on the benchmark reads 1.500 m and the foresight on a point reads 0.800 m. What is the elevation of that point?

    1. 99.300 m
    2. 101.500 m
    3. 102.300 m
    4. 100.700 m Correct answer.

    Explanation

    The height of instrument is 100.000 + 1.500 = 101.500 m. The elevation of the foresight point is the height of instrument minus the foresight, 101.500 − 0.800 = 100.700 m.

  117. Question 117Surveying Calculations and Adjustments

    In metric units, the combined correction for curvature and refraction (in metres) for a sight distance K expressed in kilometres is:

    1. 0.0112 K²
    2. 0.0785 K²
    3. 0.0675 K² Correct answer.
    4. 0.0206 K²

    Explanation

    Curvature alone contributes about 0.0785 K² metres and refraction removes roughly one-seventh of that, leaving a combined correction of about 0.0675 K² metres. The correction is always subtracted from the rod reading.

  118. Question 118Surveying Calculations and Adjustments

    How is the relative precision of a closed traverse expressed?

    1. Angular misclosure divided by the number of angles
    2. Total traverse length divided by the number of courses
    3. Linear misclosure divided by the total traverse length Correct answer.
    4. Linear misclosure divided by the number of courses

    Explanation

    Relative precision compares the linear misclosure with the total length traversed, usually stated as a ratio such as 1:10 000. A smaller misclosure for the same perimeter indicates a more precise survey.

  119. Question 119Surveying Calculations and Adjustments

    Under the compass (Bowditch) rule, the correction applied to the latitude of a course is proportional to:

    1. An equal share assigned to every course
    2. The course length divided by the perimeter Correct answer.
    3. The magnitude of that course's latitude
    4. The magnitude of that course's departure

    Explanation

    The compass rule distributes the misclosure in proportion to course length relative to total traverse length, on the assumption that errors grow with distance measured. The same factor is applied to both latitudes and departures.

  120. Question 120Surveying Calculations and Adjustments

    The transit rule of traverse adjustment is generally preferred when:

    1. The traverse contains more than ten courses
    2. Only linear measurements were taken in the field
    3. The traverse is a link between two fixed points of known coordinates
    4. The angular measurements are more precise than the linear measurements Correct answer.

    Explanation

    The transit rule scales corrections to the size of each latitude and departure, which suits surveys in which angles are observed with higher precision than distances. When distances are relatively more reliable, the compass rule is preferred.

  121. Question 121Surveying Calculations and Adjustments

    The measured interior angles of a five-sided closed traverse sum to 540°01'30". If the misclosure is distributed equally, what is the correction per angle?

    1. +1'30"
    2. +18"
    3. −1'30"
    4. −18" Correct answer.

    Explanation

    The theoretical sum for five sides is 540°00'00", so the measured sum is 1'30" (90") too large. Distributing −90" equally over five angles gives a correction of −18" per angle.

  122. Question 122Surveying Calculations and Adjustments

    A line has an azimuth of 118°24'. What is its bearing?

    1. S 61°36' E Correct answer.
    2. N 61°36' W
    3. S 61°36' W
    4. N 61°36' E

    Explanation

    An azimuth between 90° and 180° lies in the southeast quadrant, where the bearing angle is 180° − azimuth. Here 180°00' − 118°24' = 61°36', giving S 61°36' E.

  123. Question 123Surveying Calculations and Adjustments

    Which relationship is the standard arithmetic check on a reduction of differential leveling notes?

    1. ΣBS + ΣFS = last RL − first RL
    2. ΣFS − ΣBS = last RL − first RL
    3. ΣBS − ΣFS = first RL − last RL
    4. ΣBS − ΣFS = last RL − first RL Correct answer.

    Explanation

    Each backsight raises the reduced level and each foresight lowers it, so the algebraic sum of backsights minus foresights must equal the change in reduced level from the first to the last station. Any disagreement signals an arithmetic error.

  124. Question 124Surveying Calculations and Adjustments

    Which statement is the standard arithmetic check on the rise-and-fall reduction of leveling notes?

    1. Σrise − Σfall = ΣBS + ΣFS
    2. Σfall − Σrise = last RL − first RL
    3. Σrise − Σfall = last RL − first RL Correct answer.
    4. Σrise + Σfall = ΣBS − ΣFS

    Explanation

    Rises increase and falls decrease the reduced level, so the net of rises minus falls must equal the difference between the last and first reduced levels. Both quantities must also equal ΣBS − ΣFS.

  125. Question 125Surveying Calculations and Adjustments

    A course of length 250.00 m runs N 30°00' E from a point with coordinates N 1 000.000, E 2 000.000. What are the coordinates of the next point?

    1. N 1 216.506, E 2 125.000 Correct answer.
    2. N 783.494, E 1 875.000
    3. N 1 225.000, E 2 216.506
    4. N 1 216.506, E 1 875.000

    Explanation

    The latitude is 250.00 × cos 30° = 216.506 m and the departure is 250.00 × sin 30° = 125.000 m. Adding these to the given coordinates gives N 1 216.506 and E 2 125.000.

  126. Question 126Surveying Calculations and Adjustments

    Point A is at E 500.000, N 500.000 and point B is at E 560.000, N 580.000. What are the length and bearing of AB?

    1. 100.000 m, S 36°52' W
    2. 140.000 m, N 36°52' E
    3. 100.000 m, N 36°52' E Correct answer.
    4. 100.000 m, N 53°08' E

    Explanation

    The departure is +60.000 m and the latitude is +80.000 m, so the length is √(60² + 80²) = 100.000 m. The bearing angle is arctan(60/80) = 36°52', and both components are positive, giving N 36°52' E.

  127. Question 127Surveying Calculations and Adjustments

    A quadrilateral has corners at (E 0, N 0), (E 200, N 0), (E 200, N 150) and (E 0, N 100). What is its area by the coordinate method?

    1. 30 000 m²
    2. 50 000 m²
    3. 25 000 m² Correct answer.
    4. 20 000 m²

    Explanation

    Applying the coordinate (shoelace) method gives a double area of 50 000 m², so the area is 25 000 m². The same result follows from treating the figure as a trapezoid with parallel sides 100 m and 150 m and width 200 m.

  128. Question 128Surveying Calculations and Adjustments

    A level circuit run with six instrument setups of equal length closes with a misclosure of −0.024 m. If the misclosure is distributed equally, what is the correction per setup?

    1. +0.006 m
    2. −0.004 m
    3. −0.144 m
    4. +0.004 m Correct answer.

    Explanation

    The correction is the opposite of the misclosure, so +0.024 m is spread over six equal setups. Each setup receives +0.004 m.

  129. Question 129Surveying Calculations and Adjustments

    A stadia interval of 1.20 m is observed on a rod with a sight inclined 10° from horizontal and an instrument factor of 100 with no additive constant. What is the horizontal distance?

    1. 118.18 m
    2. 116.38 m Correct answer.
    3. 109.20 m
    4. 120.00 m

    Explanation

    For an inclined sight the horizontal distance is K·s·cos²θ, which gives 100 × 1.20 × cos²10° = 116.38 m. The squared cosine is required because the interval itself is foreshortened by the tilt.

  130. Question 130Surveying Calculations and Adjustments

    The measured interior angles of a five-sided closed traverse total 539°58'00". After equal distribution of the misclosure, what is the adjusted value of an angle measured as 108°15'40"?

    1. 108°16'04" Correct answer.
    2. 108°15'40"
    3. 108°16'28"
    4. 108°15'16"

    Explanation

    The theoretical sum is 540°00'00", so the misclosure is −2'00" (120"). Equal distribution gives +24" per angle, and 108°15'40" + 24" = 108°16'04".

  131. Question 131Surveying Calculations and Adjustments

    A closed five-sided figure has corners at (E 0, N 0), (E 400, N 0), (E 400, N 300), (E 200, N 500) and (E 0, N 300). What is its area?

    1. 14.0 ha
    2. 12.0 ha
    3. 18.0 ha
    4. 16.0 ha Correct answer.

    Explanation

    The coordinate method gives a double area of 320 000 m², so the area is 160 000 m², or 16.0 ha. This agrees with a 400 m × 300 m rectangle plus a triangle of base 400 m and height 200 m.

  132. Question 132Surveying Calculations and Adjustments

    A closed traverse has a perimeter of 600.00 m with a total departure misclosure of +0.180 m. Using the compass rule, what is the adjusted departure of a 200.00 m course whose computed departure is +130.00 m?

    1. 129.820 m
    2. 130.060 m
    3. 129.760 m
    4. 129.940 m Correct answer.

    Explanation

    The compass-rule correction is the misclosure multiplied by the course length over the perimeter, with the opposite sign: −0.180 × (200.00/600.00) = −0.060 m. Adding this to +130.00 m gives 129.940 m.

  133. Question 133Surveying Calculations and Adjustments

    With the instrument set close to point A, rod readings are 1.500 m on A and 2.800 m on B. With the instrument set close to point B, readings are 2.900 m on B and 1.400 m on A. What is the most reliable difference in elevation between A and B?

    1. 1.400 m Correct answer.
    2. 1.500 m
    3. 1.450 m
    4. 1.300 m

    Explanation

    Reciprocal leveling averages the two observed differences so that curvature, refraction and residual instrument error largely cancel. The observations give 2.800 − 1.500 = 1.300 m and 2.900 − 1.400 = 1.500 m, whose mean is 1.400 m.

  134. Question 134Mapping and Platting

    How many acres are contained in one regular section of the Public Land Survey System?

    1. 640 acres Correct answer.
    2. 1,280 acres
    3. 320 acres
    4. 160 acres

    Explanation

    A regular PLSS section is one square mile, and one square mile equals 640 acres. Section boundaries are nominally 5,280 feet on each side.

  135. Question 135Mapping and Platting

    A parcel is described as the NE 1/4 of the SW 1/4 of a section. What is its area?

    1. 160 acres
    2. 80 acres
    3. 20 acres
    4. 40 acres Correct answer.

    Explanation

    Each quarter-quarter division reduces the area by a factor of four. The NE 1/4 of the SW 1/4 is 1/4 × 1/4 = 1/16 of a 640-acre section, or 40 acres.

  136. Question 136Mapping and Platting

    A deed calls for a boundary line to run to a marked stone, but the record distance falls short of the stone. Which element governs the boundary location?

    1. The record distance governs because it is more precise
    2. The physical monument governs the location Correct answer.
    3. The record bearing governs because it is a direction
    4. The stated area governs the boundary

    Explanation

    In boundary retracement, a natural or artificial monument called for in the description generally controls over courses, distances, and area. Distances and bearings yield to the monument when they conflict.

  137. Question 137Mapping and Platting

    A plat is drawn at a scale of 1 inch = 200 feet. A line on the plat measures 2.25 inches. What distance does it represent on the ground?

    1. 225 ft
    2. 425 ft
    3. 400 ft
    4. 450 ft Correct answer.

    Explanation

    Multiply the map measurement by the scale factor: 2.25 inches × 200 feet per inch = 450 feet.

  138. Question 138Mapping and Platting

    What is the primary purpose of the north arrow on a recorded plat?

    1. Identify the surveyor's seal
    2. Show record bearing orientation Correct answer.
    3. Mark the highest site elevation
    4. Show the map scale ratio

    Explanation

    The north arrow establishes the orientation of the bearings and lines shown on the plat. Bearings are referenced to a stated meridian or basis of bearing.

  139. Question 139Mapping and Platting

    Using the arc definition, what is the degree of curve for a circular curve with a radius of 500.00 feet?

    1. 22.92°
    2. 45.84°
    3. 11.46° Correct answer.
    4. 5.73°

    Explanation

    For the arc definition, D = 5,729.58 / R. Substituting R = 500.00 ft gives D ≈ 11.46°.

  140. Question 140Mapping and Platting

    A ground distance is 1,000.000 ft. The combined grid scale factor for the location is 0.99995. What is the grid distance?

    1. 999.95 ft Correct answer.
    2. 1,000.05 ft
    3. 999.90 ft
    4. 1,000.10 ft

    Explanation

    Grid distance equals ground distance multiplied by the combined factor. 1,000.000 × 0.99995 = 999.95 ft.

  141. Question 141Mapping and Platting

    After a subdivision plat has received required local approvals, what is the usual next step to make it a public record?

    1. Record it before final approval is signed
    2. Send it to the state land board for review
    3. Post it at the courthouse door for 30 days
    4. File it with the county recorder Correct answer.

    Explanation

    Approval authorizes recording; the plat becomes part of the public land records when filed with the county recorder or equivalent official. Recording gives constructive notice of the lot lines and dedications.

  142. Question 142Mapping and Platting

    How is a utility easement typically depicted on a subdivision plat?

    1. A circled lot number
    2. A shaded contour band
    3. A single solid boundary line
    4. Dashed parallel lines with a label Correct answer.

    Explanation

    Easements are shown by their boundary lines, often dashed, with a width and purpose note. The easement burdens the lots but does not change lot ownership lines.

  143. Question 143Mapping and Platting

    On a topographic map, the vertical distance between adjacent contour lines is called the:

    1. Scale factor
    2. Contour interval Correct answer.
    3. Hachure spacing
    4. Index contour

    Explanation

    The contour interval is the elevation difference represented from one contour line to the next. Index contours are heavier lines labeled with elevation.

  144. Question 144Mapping and Platting

    In the Public Land Survey System, what is the purpose of a meander line along a navigable body of water?

    1. The ordinary high water mark
    2. The legal boundary of the upland owner
    3. An area line for fractional lots Correct answer.
    4. The centerline of the water body

    Explanation

    Meander lines are run to determine the area of fractional lots bordering meandered water. They are generally not the legal boundary; the water boundary is commonly the ordinary high water mark or as defined by state law.

  145. Question 145Mapping and Platting

    Fractional lots created along a meandered water boundary in the PLSS are known as:

    1. Government lots Correct answer.
    2. Aliquot lots
    3. Section lots
    4. Donation lots

    Explanation

    Fractional lots bordering meandered water or reservation boundaries are called government lots and are numbered within the section. They are not regular aliquot parts.

  146. Question 146Mapping and Platting

    A bearing of S 45° E corresponds to which azimuth?

    1. 315°
    2. 135° Correct answer.
    3. 225°
    4. 45°

    Explanation

    Azimuths are measured clockwise from north. Starting at south, 180°, and turning 45° toward east gives 180° − 45° = 135°.

  147. Question 147Mapping and Platting

    In a metes and bounds description, the point at which the boundary traverse actually begins is called the:

    1. Basis of bearing
    2. Terminus
    3. Point of commencement
    4. Point of beginning Correct answer.

    Explanation

    The point of beginning is the corner where the described traverse starts and must close. A point of commencement may be an earlier reference point from which the surveyor travels to the point of beginning.

  148. Question 148Mapping and Platting

    In a recorded subdivision plat, how are lots ordinarily numbered?

    1. Sequentially by block Correct answer.
    2. In order of acreage
    3. By tax parcel number
    4. By owner surname

    Explanation

    Lots are conventionally numbered consecutively within each block, and blocks are numbered or lettered across the subdivision. This creates a unique lot-and-block identifier.

  149. Question 149Mapping and Platting

    A notation on a plat that land is dedicated to the public for street purposes generally constitutes:

    1. A zoning variance
    2. A lien on the lot
    3. A conveyance of fee title
    4. An offer of dedication Correct answer.

    Explanation

    Dedication is the donation of land for public use, and plat notation typically operates as an offer that is accepted by public use or formal action. It is not automatically a fee conveyance or a lien.

  150. Question 150Mapping and Platting

    Flood hazard zones for a property are most commonly shown on which map?

    1. A USGS quadrangle
    2. A PLSS plat
    3. An ALTA survey
    4. A FIRM Correct answer.

    Explanation

    A Flood Insurance Rate Map published by FEMA delineates special flood hazard areas and insurance zones. USGS quadrangles show topography but not regulatory flood zones.

  151. Question 151Mapping and Platting

    Contour lines with hachures pointing inward toward lower ground indicate:

    1. A depression Correct answer.
    2. A vertical cliff
    3. A saddle
    4. A ridge

    Explanation

    Hachured contours mark a depression; the hachures point downslope toward the lower elevation inside the closed contour. A ridge would show contours closing around higher ground.

  152. Question 152Mapping and Platting

    How wide is a single UTM zone in longitude?

    1. 3°
    2. 6° Correct answer.
    3. 4°
    4. 12°

    Explanation

    The Universal Transverse Mercator system divides the globe into 60 zones, each 6° of longitude wide. Zones are numbered from west to east starting at 180°.

  153. Question 153Mapping and Platting

    On a transverse Mercator projection such as a State Plane zone, the projection scale is exact along:

    1. The central meridian Correct answer.
    2. The standard parallels
    3. The equator
    4. The zone boundaries

    Explanation

    In a transverse Mercator projection, the central meridian is the line of zero distortion, and scale increases with distance from it. A combined scale factor accounts for this grid distortion and elevation.

  154. Question 154Mapping and Platting

    A metes and bounds traverse closes back on its point of beginning with a small misclosure. What should be done before the area is computed?

    1. Describe the parcel as an open traverse
    2. Rotate all bearings to magnetic north
    3. Accept it without any adjustment
    4. Adjust the traverse for the misclosure Correct answer.

    Explanation

    A closed boundary traverse should be adjusted to distribute the misclosure before coordinates and area are computed. Computing area from an unadjusted traverse propagates the error into the result.

  155. Question 155Mapping and Platting

    NAVD 88 is best described as:

    1. A coordinate system
    2. A vertical datum Correct answer.
    3. A horizontal datum
    4. A map projection

    Explanation

    NAVD 88 is the North American Vertical Datum of 1988, a vertical reference based on orthometric heights. Horizontal positions are referenced to datums such as NAD83.

  156. Question 156Construction Surveys

    In construction layout, what is the primary purpose of a grade stake?

    1. To mark the legal boundary corner for the public record
    2. To record the azimuth of the primary control traverse
    3. To establish the horizontal datum for the whole site
    4. To show the design elevation of the finished work Correct answer.

    Explanation

    A grade stake carries the design elevation at a specific location, usually written as a cut or fill so the crew can bring the work to the required level. Boundary corners, horizontal datums, and traverse azimuths are matters of control and property surveys, not grade stakes.

  157. Question 157Construction Surveys

    A point is staked with a cut of 1.2 m. What does this mean for the crew?

    1. The stake must be shifted 1.2 m horizontally
    2. The design grade is 1.2 m above the project datum
    3. Existing ground is 1.2 m below the design grade
    4. Existing ground is 1.2 m above the design grade Correct answer.

    Explanation

    A cut means the existing ground stands above the design grade and material must be removed down to it. A fill would be noted when the ground lies below the design grade and material must be added.

  158. Question 158Construction Surveys

    Batter boards are used in building layout mainly to:

    1. Establish the elevation of the finished floor level
    2. Hold offset lines that can be restrung after digging Correct answer.
    3. Support the excavation shoring along the trench
    4. Mark the centre of the proposed column footings

    Explanation

    Batter boards are set back from the excavation so nails or saw kerfs in them can carry string lines offset from the building lines. Because they stand outside the dig, the lines can be replaced by stringing between the same nails after excavation.

  159. Question 159Construction Surveys

    In construction surveying, a benchmark is best described as:

    1. A temporary point used for a single instrument setup
    2. A stable point of known elevation for levelling Correct answer.
    3. A point whose elevation is read from a contour map
    4. The highest point of the site's topographic survey

    Explanation

    A benchmark is a durable, identifiable point whose elevation has been determined to a stated accuracy, and it is the reference from which other elevations are carried. Temporary instrument points and contour-derived values do not serve that role.

  160. Question 160Construction Surveys

    Slope stakes are set in the field to:

    1. Locate where the finished slope meets the ground Correct answer.
    2. Establish the elevation of the drainage invert
    3. Mark the centreline of the proposed roadway only
    4. Record the as-built elevations of the subgrade

    Explanation

    Slope stakes mark the catch point, where the designed cut or fill slope intersects existing ground, and they also carry the cut or fill at that position. Centreline stakes and invert elevations are separate layout items.

  161. Question 161Construction Surveys

    When setting out points by coordinates with a total station, the minimum information needed at the setup is:

    1. Only the elevation of the instrument station
    2. The station coordinates and a backsight orientation Correct answer.
    3. A known azimuth to magnetic north from a compass
    4. A prism constant and the atmospheric correction

    Explanation

    Stakeout coordinates are transformed into angles and distances relative to the occupied station, so the instrument must know its own coordinates and be oriented to a known reference. Corrections such as prism constant and atmospheric values refine the result but do not establish orientation.

  162. Question 162Construction Surveys

    In construction layout, a hub with a tack is used to:

    1. Mark a point precisely with a nail in the stake top Correct answer.
    2. Hold the levelling rod in a vertical position
    3. Provide a permanent monument of the horizontal control
    4. Measure the depth of the trench during excavation

    Explanation

    A hub is a stout stake driven nearly flush with the ground and a tack is set in its top to define the exact point, so instruments and tapes can be plumbed over it. Hubs are temporary layout aids rather than permanent control monuments.

  163. Question 163Construction Surveys

    The instrument height of elevation (HI) is 104.00 m. A rod held on the ground at a station reads 1.85 m, and the design elevation there is 102.35 m. What is required at that point?

    1. 1.85 m cut
    2. 0.20 m fill Correct answer.
    3. 1.65 m fill
    4. 0.20 m cut

    Explanation

    Ground elevation equals HI minus the rod reading, 104.00 − 1.85 = 102.15 m. The ground is 0.20 m below the design elevation of 102.35 m, so fill is needed.

  164. Question 164Construction Surveys

    The height of instrument is 105.00 m and the design grade at a point is 103.20 m. What rod reading marks finished grade at that point?

    1. 1.80 m Correct answer.
    2. 0.80 m
    3. 1.20 m
    4. 2.20 m

    Explanation

    The grade rod is the height of instrument minus the design elevation: 105.00 − 103.20 = 1.80 m. When the rod is held on the subgrade and reads 1.80 m, the base of the rod is at the design grade.

  165. Question 165Construction Surveys

    A building corner is checked by the 3-4-5 method using 9.0 m along one line and 12.0 m along the other. Which diagonal distance confirms a right angle?

    1. 13.5 m
    2. 16.2 m
    3. 21.0 m
    4. 15.0 m Correct answer.

    Explanation

    The 3-4-5 ratio is scaled by a factor of three, giving sides of 9, 12 and 15 m. A diagonal of 15.0 m from the two measured points confirms the corner is square.

  166. Question 166Construction Surveys

    Because a sewer trench will be excavated on the pipe centreline, the line is staked 3.0 m away. How is that offset distance normally measured?

    1. Perpendicular to the centreline at the point Correct answer.
    2. Parallel to the centreline between two hubs
    3. Along the pipe invert measured from the manhole
    4. Vertically from the trench bottom to ground surface

    Explanation

    Offset stakes are placed on a line that is perpendicular to the work centreline, at a recorded distance, so the centreline can be re-established after excavation. The offset is a horizontal distance at right angles to the line being built.

  167. Question 167Construction Surveys

    An as-built survey of a completed construction project is performed mainly to:

    1. Compute the volumes of the remaining excavation
    2. Record actual positions of the completed work Correct answer.
    3. Set the grades for the next stage of construction
    4. Establish the original property boundary corners

    Explanation

    An as-built survey documents where the work was actually built, both in plan and in elevation, so it can be compared with the design and handed over for records. It is a record survey rather than a layout or boundary operation.

  168. Question 168Construction Surveys

    In slope staking, the catch point is the location where:

    1. the grade rod is held for the final elevation check
    2. the centreline crosses the finished shoulder break
    3. the daylit slope intersects original ground Correct answer.
    4. the slope ratio changes from cut to fill batter

    Explanation

    The catch point is the intersection of the designed slope surface with existing terrain, and it is where the slope stake is set. Its distance from centreline is found by trial, comparing a computed catch distance with a measured one.

  169. Question 169Construction Surveys

    GNSS and total station machine control for grading and paving typically relies on:

    1. Daily manual stakeout by a two-person crew
    2. A digital design model and blade-mounted sensors Correct answer.
    3. String lines and a rotating laser for each lift
    4. A single benchmark and a hand level on the blade

    Explanation

    Three-dimensional machine control compares the blade position, measured by positioning sensors, with a digital design model and adjusts the blade automatically. Stakes and string lines are thereby reduced or eliminated.

  170. Question 170Construction Surveys

    Pavement 0.25 m thick will be placed on the subgrade. The grade stake shows a cut of 1.05 m to finished grade. What cut should be set for the subgrade?

    1. 1.55 m
    2. 1.05 m
    3. 0.80 m
    4. 1.30 m Correct answer.

    Explanation

    The subgrade lies one pavement thickness below finished grade, so the two depths add: 1.05 + 0.25 = 1.30 m. Cutting to that depth leaves exactly the design thickness for the pavement.

  171. Question 171Construction Surveys

    A point on a baseline is at station 12+45.00. A second point lies 87.5 m ahead of it along the same line. What is the station of the second point?

    1. 13+32.50 Correct answer.
    2. 13+30.00
    3. 13+32.05
    4. 12+132.50

    Explanation

    Station 12+45.00 is 1245.00 m from the origin, and adding 87.50 m gives 1332.50 m, written as 13+32.50. Stations are expressed in full 100 m units plus the remaining metres.

  172. Question 172Construction Surveys

    In a level run used for construction control, a turning point must:

    1. coincide with a staked construction offset point
    2. be read on both a foresight and a backsight Correct answer.
    3. be the highest elevation in the levelling loop
    4. be re-observed only at the end of the project

    Explanation

    A turning point is a temporary point on which the rod is held for the foresight of one setup and the backsight of the next, which carries the elevation forward. It must therefore be firm and re-readable without moving.

  173. Question 173Construction Surveys

    The two-peg test performed on a level is used to check:

    1. whether the line of sight is truly horizontal Correct answer.
    2. the accuracy of the horizontal circle readings
    3. the verticality of the levelling rod bubble
    4. the optical plummet alignment over a point

    Explanation

    The two-peg test compares rod readings taken from two instrument positions between the same pegs to detect collimation error, that is, a line of sight that is not horizontal. The resulting difference is used to adjust or apply a correction.

  174. Question 174Construction Surveys

    A roadway in fill has a half-width of 5.0 m, a centreline fill of 1.5 m, and side slopes of 2:1 (horizontal to vertical). On level ground, what is the catch distance from the centreline?

    1. 6.5 m
    2. 5.0 m
    3. 8.0 m Correct answer.
    4. 11.0 m

    Explanation

    On level ground the slope runs out horizontally 2 m for every 1 m of fill, so the slope adds 2 × 1.5 = 3.0 m to the half-width. The catch distance is therefore 5.0 + 3.0 = 8.0 m.

  175. Question 175Construction Surveys

    A level loop 1.2 km long closes 0.024 m in error. The specified allowable misclosure is 8 mm times the square root of the length in kilometres. What is the correct conclusion?

    1. Acceptable; the allowance works out to 24 mm
    2. Acceptable; the allowance works out to 8.8 mm
    3. Rejected; it exceeds the 8.8 mm allowance Correct answer.
    4. Rejected; the loop tolerance is fixed at 5 mm

    Explanation

    The allowable misclosure is 8 mm × √1.2 ≈ 8.8 mm, while the measured misclosure is 24 mm. Since 24 mm exceeds the allowance, the loop fails and must be re-run or investigated.

  176. Question 176Construction Surveys

    When slope staking on sidehill terrain, the rod is moved laterally and re-read until:

    1. the computed and measured catch distances agree Correct answer.
    2. the instrument height matches the centreline cut
    3. the slope ratio becomes steeper than the design
    4. the rod reading equals the design slope elevation

    Explanation

    On sloping ground the ground elevation changes with the offset, so the catch distance must be computed from the rod reading at the trial position and compared with the measured distance. The rod is moved until the two distances match within tolerance.

  177. Question 177Construction Surveys

    Point B lies 30.000 m east and 40.000 m north of point A. What is the azimuth from A to B?

    1. 45°00'00"
    2. 53°07'48"
    3. 30°00'00"
    4. 36°52'12" Correct answer.

    Explanation

    The azimuth measured clockwise from north is the arctangent of the easting difference divided by the northing difference: arctan(30/40) = 36.87°, which is 36°52'12".

  178. Question 178Business and Professional Practice

    In the United States, the legal authority to grant and revoke a land surveyor's license rests with which of the following?

    1. The federal agency that publishes surveying standards
    2. The national council that prepares the licensing exams
    3. The licensing board of each state or territory Correct answer.
    4. The national professional society for surveying

    Explanation

    Licensure of land surveyors is a function of state government, exercised through each state's licensing board under its police power. National organizations influence standards and examination content but neither grant nor revoke licenses.

  179. Question 179Business and Professional Practice

    A surveyor's standard of care in a negligence claim is best described as:

    1. The level of care promised in the firm's marketing materials
    2. The highest accuracy attainable with current technology
    3. The minimum accuracy required by the client's written instructions
    4. The care a prudent surveyor would use under similar circumstances Correct answer.

    Explanation

    Professional negligence is measured against what a reasonably prudent practitioner would do in similar circumstances, not against perfection or advertising claims. A contract can raise the duty, but the baseline remains the ordinary standard of the profession.

  180. Question 180Business and Professional Practice

    Qualifications-based selection (QBS) for surveying services is a procurement method in which the firm is chosen primarily on the basis of:

    1. Its quoted fee for the described scope of work
    2. The lowest bid submitted in a sealed competitive process
    3. Its demonstrated competence and qualifications for the work Correct answer.
    4. The number of field crews it can commit to the project

    Explanation

    QBS ranks firms on competence, experience, and past performance, then negotiates a fair fee with the highest-ranked firm. It is required for federal architect-engineer procurements and is widely used by public agencies for survey work.

  181. Question 181Business and Professional Practice

    Which statement correctly describes a claims-made professional liability policy?

    1. It covers only claims arising from incidents that occur during the policy period
    2. It responds to claims first made and reported while the policy is in force Correct answer.
    3. It responds to claims whenever the act occurred, if reported after the policy expires
    4. It pays defense costs only after the deductible is exhausted by a judgment

    Explanation

    A claims-made policy is triggered by the date the claim is first made and reported, not solely by when the negligent act occurred. Coverage therefore depends on the policy period, the retroactive date, and any extended reporting period the firm purchases.

  182. Question 182Business and Professional Practice

    Which type of loss is covered by a typical commercial general liability (CGL) policy rather than by a professional liability policy?

    1. Damage to a neighbor's fence caused by the firm's truck Correct answer.
    2. An error in a boundary computation that causes a client's loan to fail
    3. A claim that a plat's building setback lines were misstated
    4. A claim that a survey omitted an easement from the drawing

    Explanation

    CGL policies respond to third-party bodily injury and property damage arising from the insured's premises and operations. Errors and omissions in the professional services themselves belong to professional liability coverage.

  183. Question 183Business and Professional Practice

    A state statute of repose for survey work differs from a statute of limitations mainly in that a statute of repose:

    1. Sets a fixed outer limit measured from substantial completion Correct answer.
    2. Applies only to claims brought by parties with a written contract
    3. May be extended by written agreement at any time before it runs
    4. Begins to run when the surveyor discovers the error

    Explanation

    A statute of limitations runs from accrual, which in some states occurs on discovery of the injury. A statute of repose instead bars claims after a fixed period measured from substantial completion, regardless of when the error is discovered.

  184. Question 184Business and Professional Practice

    Midway through a boundary survey, a client asks the surveyor to add a topographic survey of the parcel. The surveyor should:

    1. Complete the original scope first and then renegotiate from scratch
    2. Refuse, since the original contract defines the entire scope of work
    3. Issue a written amendment or change order defining scope and fee Correct answer.
    4. Perform the additional work and bill for it under the existing contract

    Explanation

    Work beyond the agreed scope should be authorized in writing before it is performed so that fee, schedule, and responsibilities are clear. Performing first and billing later invites disputes and can weaken the surveyor's claim to additional compensation.

  185. Question 185Business and Professional Practice

    A time-and-materials contract is most appropriate when:

    1. The scope of work is fully defined and competitive pricing is required
    2. The project must be awarded to the lowest responsible bidder
    3. The client requires a guaranteed maximum price before work begins
    4. The exact extent of the work cannot be determined in advance Correct answer.

    Explanation

    Time-and-materials pricing is used when the quantity of work is uncertain and the client accepts the risk of actual cost. Lump-sum pricing assumes a well-defined scope that bidders can price competitively.

  186. Question 186Business and Professional Practice

    A contract provides that the client will withhold 10 percent of each invoice until final acceptance. The withheld amount is properly called:

    1. Retainage Correct answer.
    2. A contingency
    3. A lien
    4. A retainer

    Explanation

    Retainage is a percentage withheld from progress payments as security for completion and is released after acceptance. A retainer, by contrast, is an advance payment made before any work is performed.

  187. Question 187Business and Professional Practice

    While preparing a fee proposal for a survey of a parcel with unrecorded occupation lines, a firm adds 8 percent to its estimated cost to cover unknowns. This addition is best described as:

    1. Profit
    2. Overhead
    3. Contingency Correct answer.
    4. Retainage

    Explanation

    A contingency is an allowance added to an estimate for unknowns that cannot be priced directly. Overhead covers indirect firm costs, while profit is a return on the work performed.

  188. Question 188Business and Professional Practice

    A firm's direct labor cost for a project is $20,000. Overhead is applied at 150 percent of direct labor, and profit is 10 percent of total cost (direct labor plus overhead). What fee should the firm propose?

    1. $55,000 Correct answer.
    2. $50,000
    3. $52,000
    4. $60,000

    Explanation

    Direct labor of $20,000 multiplied by a 2.5 factor (1.0 labor plus 1.5 overhead) gives $50,000 of total cost. Adding 10 percent profit to that cost yields a fee of $55,000.

  189. Question 189Business and Professional Practice

    Before sealing and delivering a final survey map, a two-person firm should:

    1. Have the client sign off on the field notes
    2. Have a qualified second surveyor review the work Correct answer.
    3. Submit the map to the state board for pre-approval
    4. Have the drafting technician seal the map as the preparer

    Explanation

    Quality control in a small firm typically uses an independent review by another qualified professional before the seal is applied. The seal certifies the professional's own work, so the reviewer must have both the competence and the authority to check it.

  190. Question 190Business and Professional Practice

    A prime surveyor hires a subcontractor to perform aerial mapping. A defect in the mapping harms the client. As between the client and the prime surveyor:

    1. The prime remains responsible to the client for the sub's work Correct answer.
    2. The subcontractor alone bears responsibility for its own work
    3. The client must pursue the subcontractor directly
    4. The prime is liable only for its own negligent acts

    Explanation

    The prime professional remains accountable to the client for all work performed under the prime contract, including work subcontracted out. The prime's remedy for a defective submittal is a claim against the subcontractor.

  191. Question 191Business and Professional Practice

    A surveyor is asked to perform work for a party whose interests conflict with those of an existing client. The surveyor should first:

    1. Proceed if the new client agrees to keep the relationship confidential
    2. Disclose the conflict in writing before accepting the work Correct answer.
    3. Accept the work, since both parties will pay the fee
    4. Decline all work for both parties permanently

    Explanation

    Potential conflicts must be disclosed and resolved before the assignment is accepted, typically in writing and with the client's informed consent. Proceeding quietly or refusing all related work are both improper responses.

  192. Question 192Business and Professional Practice

    Under most state board rules, a surveyor's fee may not be contingent on:

    1. The survey's outcome Correct answer.
    2. The number of hours actually worked
    3. The client's schedule for delivery
    4. The size of the parcel surveyed

    Explanation

    Fees contingent on a particular result compromise the surveyor's independence and objectivity and are prohibited by most board rules. Fees may be based on time, scope, or schedule so long as they do not turn on the findings.

  193. Question 193Business and Professional Practice

    Continuing education requirements for licensed land surveyors are established by:

    1. The firm's quality control manual
    2. The national professional society
    3. The state licensing board Correct answer.
    4. The client's contract terms

    Explanation

    Continuing education is a condition of license renewal set by the state board through its rules. Professional societies may offer qualifying courses, but they do not establish the requirement.

  194. Question 194Business and Professional Practice

    Most state boards require a surveyor to retain project records, field notes, and computations because:

    1. The records may be needed to defend or explain the work later Correct answer.
    2. The records are public documents any person may request to inspect
    3. The records must be filed with the licensing board at project closeout
    4. The records become the property of the client once the fee is paid

    Explanation

    Records are kept so the surveyor can reconstruct and defend the work if a boundary dispute, claim, or board inquiry arises. Board rules typically set a minimum retention period, and the records generally remain the surveyor's property.

  195. Question 195Business and Professional Practice

    As between the surveyor and the client, ownership of the surveyor's original field notes and working files is ordinarily:

    1. Retained by the surveyor unless the contract says otherwise Correct answer.
    2. Held jointly by the surveyor and the client
    3. Transferred to the client upon payment in full
    4. Determined by the state board at the end of the project

    Explanation

    Field notes and working files generally stay with the surveyor, who must retain them under board rules. The client typically receives the final deliverable and a license to use it for the intended purpose unless the contract transfers more.

  196. Question 196Business and Professional Practice

    A surveyor prepares a plat for a developer. A lender who was not a party to the contract relies on the plat and suffers a loss. The lender's recovery typically depends on whether:

    1. the surveyor knew the lender would rely on the plat Correct answer.
    2. the developer paid the survey fee in full before closing
    3. the surveyor held a current professional license
    4. the plat was recorded before the loan closed

    Explanation

    A duty to a non-client can arise when the surveyor knows the third party will rely on the work, as when a certified plat is furnished to a lender. Absent known reliance, the surveyor's duty generally runs only to the client.

  197. Question 197Business and Professional Practice

    A client asks a surveyor to certify a plat to a bank using the bank's own certification form, which contains statements the surveyor cannot verify. The surveyor should:

    1. Sign the form and attach a note that the certification is unverified
    2. Sign the form as written to keep the client's loan on schedule
    3. Refuse to deliver the plat until the bank withdraws the form
    4. Negotiate revised certification language that the surveyor can support Correct answer.

    Explanation

    A professional should certify only to matters within the scope of the work and supported by the record. Certifications are statements of professional opinion, so unverifiable language must be negotiated rather than signed or informally qualified.

  198. Question 198Business and Professional Practice

    A contract contains a termination-for-convenience clause. When the client invokes it, the surveyor is ordinarily entitled to:

    1. Payment for work performed plus reasonable termination costs Correct answer.
    2. Nothing beyond the cost of the work not yet started
    3. Lost profits for the entire remaining contract term
    4. The full contract fee as if the work had been completed

    Explanation

    Termination for convenience ends the contract without fault, and the surveyor recovers the value of work performed plus reasonable costs of demobilization or closeout. Profits on unperformed work are not ordinarily recoverable.

  199. Question 199Business and Professional Practice

    Some states give a surveyor who is unpaid for services on a land development project the right to record a claim against the property. This right is most closely related to:

    1. The recording act that governs deed priority
    2. The surveyor's professional liability policy
    3. Mechanic's lien statutes covering improvements to land Correct answer.
    4. The board's disciplinary authority over licensees

    Explanation

    Surveyor's lien statutes typically extend mechanic's lien principles to design and survey services that improve the property. The surveyor must usually record the lien and give notice within strict statutory deadlines.

  200. Question 200Business and Professional Practice

    Under the federal Occupational Safety and Health Act, the primary duty to provide a workplace free of recognized hazards rests with:

    1. The employer Correct answer.
    2. The state licensing board
    3. The property owner where the work is performed
    4. The individual field crew member

    Explanation

    OSHA places the general duty to furnish a workplace free of recognized hazards on the employer. The employer must also train employees and supply required protective equipment.

FS Surveying flashcards

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Peg test
A field procedure that checks a level's line of sight for parallelism to the bubble tube by comparing elevation differences taken with the instrument set up at unequal distances from two points.
Basis of bearing
The single line in a survey or plat whose direction is held fixed and from which all other directions are referenced, always stated explicitly on the drawing.
Right of entry
Permission from a property owner allowing survey crews to enter private land; without it, entry can be treated as trespass and create liability for the surveyor.
Utility locate request
A notice to the regional one-call center, generally required by law several working days before excavation, so buried utilities can be marked for crew and public safety.
Curvature and refraction
The combined correction of about 0.0675 K squared meters, with K in kilometers, applied in leveling because level surfaces and refracted lines of sight depart from horizontal.
Prism constant
An offset added to an EDM-measured distance to compensate for the difference between the electrical phase center of the instrument and the effective center of the prism assembly.
Face left and face right
Two telescope positions separated by 180 degrees, used to cancel collimation, trunnion-axis, and vertical-index errors when turning angles with a total station.
Angular closure
The difference between the measured sum of a closed polygon's interior angles and the theoretical sum of n minus two times 180 degrees used to detect angular misclosure.
Senior rights
The doctrine that an earlier conveyance prevails over a later one covering the same land, so the junior deed conveys only what the senior deed left.
Meander line
A traverse run along a water boundary to compute upland area; it is evidence of the water's position at survey time and not itself a boundary line.
Accretion and reliction
Gradual, imperceptible additions of land caused by water action, which belong to the riparian owner; a sudden change, avulsion, does not move the boundary.
Quarter-quarter section
A Public Land Survey System subdivision nominally 40 acres, formed by halving a section twice and bounded by monumented corners or, absent monuments, by proportionate measurement.
Photo scale
The ratio of lens focal length to flying height above ground, so a 6-inch lens flown 6,000 feet above ground produces a scale of 1:12,000.
Relief displacement
The radial shift of an elevated object's image on a vertical photograph, equal to r times h over H, and zero at the principal point directly below the lens.
Ground sample distance
The ground spacing between adjacent pixel centers in a digital image; smaller values indicate finer spatial resolution and allow detection of smaller features.
Digital surface model
A raster elevation model that includes the tops of vegetation, buildings, and other above-ground features, in contrast with a bare-earth terrain model.
Geoid undulation
The separation between the geoid and the reference ellipsoid at a location; ellipsoidal height equals orthometric height plus this value, symbolized capital N.
Combined factor
The product of grid scale factor and elevation factor, used to convert between ground distances and grid distances on a state plane or other projection.
UTM central meridian
The line of true origin at the center of each 6-degree UTM zone, where the grid scale factor is exactly 0.9996 and grid north equals true north.
Deflection of the vertical
The angle between the local plumb line and the normal to the reference ellipsoid; it separates astronomic from geodetic azimuths and affects zenith angles.
Bowditch rule
A traverse adjustment distributing latitude and departure misclosures in proportion to course length, also called the compass rule, suited to random errors in angles and distances.
Relative precision of closure
The linear error of closure divided by total traverse length, expressed as 1 to N; a larger N indicates a more precise traverse.
Degree of curve
Under the arc definition, the central angle subtended by a 100-foot arc; the radius equals 5,729.58 feet divided by the degree of curve.
Area by coordinates
A computation in which twice the enclosed area equals the sum of cross products of successive coordinate pairs minus the reverse sum, the shoelace formula.
Contour interval
The constant vertical distance between adjacent contour lines on a topographic map, selected from map scale, terrain relief, and the intended use.
Representative fraction
A map scale expressed as a dimensionless ratio such as 1:24,000, meaning one unit on the map equals 24,000 of the same units on the ground.
Plat curve data
Values tabulated along each curved boundary, including radius, arc length, chord bearing and distance, and central angle, so the parcel can be retraced.
Cut and fill
The vertical difference between design and existing ground elevation at a point; positive values indicate cut and negative values indicate fill.
Batter boards
Horizontal boards set outside an excavation at a known elevation and offset, from which stringlines locate building corners and grades are measured.
Slope stake
A stake placed where the design side slope intersects original ground, marked with cut or fill to guide excavation of a roadway or embankment.
Standard of care
The degree of skill and care ordinarily exercised by reputable surveyors under similar circumstances; a failure to meet it is the basis for a negligence claim.
Statute of repose
A law barring design and construction claims after a fixed period following substantial completion, regardless of when the injury is discovered.

FS Surveying study guide

Pre-Examination Activities

Scope, contract, and research before mobilizing

The exam treats pre-examination work as everything between award of the contract and the first instrument setup. Expect items on (1) defining scope, deliverables, and the applicable standard in writing, (2) records research, and (3) logistics - permits, right of entry, utility locates, traffic control, and safety planning.

Records research is the highest-yield topic. Pull the subject deed plus adjoining deeds, the subdivision plat, prior survey plats, highway or right-of-way plans, tax maps, and any original government field notes. Research the chain of title far enough back to resolve where the parcel came from; a common trap is a description that only fits the ground once you know the parent tract's senior/junior relationship. Another trap is assuming recorded bearings and distances govern - in a retracement they are the least persuasive evidence.

Equipment and control checks

Verify calibration before mobilizing: EDM baseline or prism-constant check, level collimation test, tribrach and optical plummet adjustment. Document the check in the file. Recover at least two, preferably three, existing control monuments so the work can be tied to the stated datum and held to record values.

Rule of thumb

Before field work, confirm four things in writing: the scope and standard (for example the ALTA/NSPS minimum standards), the datum and units, client-supplied records, and access/permits. Time spent on records research is almost never recovered later in the field.

A frequent exam trap is a question describing a request to survey a boundary with no title research; the correct answer is to obtain the record evidence first, or to limit the deliverable to what can actually be certified.

Surveying Instruments and Procedures

Angles and the total station

A total station combines a theodolite, an EDM, and a data collector. Understanding the error-cancelling procedures is the point of most questions. Turning a set with the telescope direct (face left) and reversed (face right) and averaging cancels horizontal collimation error and vertical-circle index error. Multiple sets, each advanced by a fraction of the circle, average out circle graduation errors. A backward/forward plunge or transit is not the same as a full set.

Distances, levels, and GNSS

EDM accuracy depends on the prism constant, atmospheric correction, and the instrument's specified accuracy (commonly ±(2 mm + 2 ppm)). The prism constant must be entered with the correct sign; a mismatch shows up as a short, consistent offset. Levels are run by the height-of-instrument method or rise-and-fall; a closed loop misclosure is distributed by distance, not uniformly, when the runs differ in length. GNSS surveying demands attention to initialization status, PDOP, multipath, and the stated accuracy of the base solution - RTK positions are relative to the base, not absolute.

Key trap: curvature and refraction

Long horizontal sights require a correction because the line of sight curves with refraction while the level surface curves away. Combined curvature and refraction is subtracted from the rod reading: 0.0206 × M² in feet, where M is the sight distance in hundreds of feet (0.0675 × K² in meters, K in km).

Worked example

A 500-ft sight: M = 5.00, so the correction is 0.0206 × 25 = 0.515 ft, subtracted from the rod reading. At 1000 ft the correction is 2.06 ft - which is why long shots are avoided for precise work.

Boundary and Cadastral Surveys

Evidence and the retracement hierarchy

A boundary survey retraces an existing boundary rather than creating a new one. The classic hierarchy of evidence is: natural monuments, artificial monuments, courses (bearings), distances, and finally area or quantity. Monuments called for in a deed control over the measurements that describe them, but only the monument actually called for - a stray pipe found nearby cannot be substituted for the one the deed names. Senior rights prevail: the parcel conveyed first is not diminished by a later conveyance from the same grantor.

Water boundaries

Accretion and reliction (gradual, imperceptible change) move the boundary; avulsion (a sudden change of channel) does not. Meander lines along a stream do not bound the parcel; they approximate the bank for area purposes, and the water itself is the boundary.

PLSS retracement

Townships are nominally 6 × 6 miles containing 36 sections; section 1 lies in the northeast corner and numbering serpentines so that section 6 is the southeast corner of the northeast section stack. Standard parallels (correction lines) close the system, and closing corners are set on them. A lost interior corner is restored by double proportion; a lost corner on a line between two accepted corners is restored by single proportion. Obliterated corners are re-established from remaining evidence and original record, not proportioned away.

Worked example

A deed calls for "to an iron pin, thence N 30° E 200.00 ft." If the pin is recovered but the distance measures 197.32 ft, record the pin and note the discrepancy; do not hold the recorded distance over the monument and do not move the pin.

Photogrammetry and Remote Sensing

Scale and flying height

The core relationships are simple and heavily tested. Photographic scale is focal length divided by flying height above ground: S = f/H, and for a photograph, S = photo distance / ground distance. If you need the flying height, H = f/S. Always confirm whether the height given is above mean ground, above the datum, or above sea level - using the wrong reference is the most common single error in these items.

Relief displacement, parallax, and stereo

The displacement of a point due to its height above the datum is d = r·h/H, where r is the radial distance from the principal point and h is the object height. Displacement is radial from the nadir/principal point and vanishes directly below the camera. Stereoscopic viewing uses parallax differences to recover elevations; the base-height ratio (B/H) governs vertical accuracy - a larger base gives better heights. Endlap (typically about 60%) and sidelap (typically about 30%) ensure continuous stereo coverage.

Products and platforms

Expect questions distinguishing orthophotos (displacement removed, measurable) from plain vertical photos, and DSM from DTM/DEM. LiDAR delivers dense elevation points and can penetrate light vegetation; satellite imagery is limited by GSD, revisit, and cloud cover. Ground control and aerial triangulation tie imagery to the datum.

Worked example

A camera with a 6-in (0.5 ft) focal length flying 5,000 ft above ground produces S = 0.5/5,000 = 1:10,000. On that photo, 1 in represents 10,000 in, or about 833 ft on the ground.

Geodesy and Geodetic Surveying

Reference surfaces and heights

Geodesy supplies the framework on which all surveys hang. The ellipsoid is a mathematical model (GRS80 for NAD83); the geoid is an equipotential surface approximating mean sea level. Heights relate by h = H + N, where h is ellipsoid height (GNSS-derived), H is orthometric height (what a level run produces), and N is the geoid undulation from a model such as GEOID18. Mixing h and H is a classic exam trap, and N varies with location - it is not a constant.

Datums and horizontal coordinates

NAD27 and NAD83 differ by hundreds of meters; a position cannot be shifted between them by a simple offset. WGS84 and ITRF are close to NAD83 but not identical. State Plane Coordinates divide states into zones with a defined projection and a scale factor that is exactly 1.0 only along the standard parallels (or the central meridian in a transverse Mercator). UTM uses 6° zones with a central-meridian scale factor of 0.9996.

Grid versus ground

Grid distance = ground distance × combined factor, where combined factor = scale factor × elevation factor, and elevation factor ≈ R/(R + h) using mean radius and average elevation above the ellipsoid. Grid azimuth differs from geodetic azimuth by the convergence angle. Sign errors here - applying the factor the wrong way, or adding instead of subtracting convergence - are a favorite distractor.

Worked example

Ground distance 1,000.000 ft, scale factor 0.99992, elevation factor 0.99997: combined factor = 0.99989, so grid distance = 999.890 ft.

Surveying Calculations and Adjustments

Traverse computation

Latitude = distance × cos(bearing); departure = distance × sin(bearing). North and east are positive. Sum the latitudes and departures around a closed traverse to get the misclosure; linear precision is closure divided into the perimeter, expressed as 1:N. The compass (Bowditch) rule distributes the latitude and departure errors in proportion to the length of each course; the transit rule distributes in proportion to the magnitude of the latitude or departure. Least squares distributes by the actual precision of each observation - the correct answer whenever a question specifies differing weights or standard deviations.

Angles and coordinates

Sum of interior angles of a closed polygon = (n − 2) × 180°. Angle misclosure is distributed equally unless weights are given. Area by coordinates uses the double-meridian-distance or the shoelace formula; double-meridian distances also compute area and check the adjustment.

Curves and levels

For a circular curve: T = R tan(Δ/2), L = RΔ(radians), and D = 5729.58/R for degree of curve by arc definition. A level loop misclosure is adjusted in proportion to distance run between benchmarks.

Worked example

A closed loop of course lengths 300, 400, and 500 ft has a closure of 0.060 ft. Precision = 0.060/1200 = 1/20,000. The compass rule correction applied to the 300-ft course is 0.060 × (300/1200) = 0.015 ft, split into latitude and departure components.

Mapping and Platting

Scale and map content

Every map question starts with scale. A representative fraction of 1:2,400 means 1 unit on the map equals 2,400 units on the ground; one inch equals 200 ft. Converting between engineer's scale (1 in = 50 ft), graphic scale, and representative fraction is routine. Remember that areas scale as the square of the linear factor: a parcel of 2 in² on a 1:1,200 map covers 2 × (100 ft)², not 2 × 100 ft.

Topographic maps

Contour interval is the vertical distance between adjacent contours; index contours are heavier and labeled. Contours never cross, are perpendicular to the direction of steepest slope, and form closed loops around hills or depressions (hachures mark depressions). A uniform spacing indicates a uniform slope; closely spaced contours indicate steep terrain. Spot elevations supplement contours.

Plats and legal descriptions

A record plat typically shows the boundary with bearings and distances, lot and block layout, dedication of right-of-way, curve data (radius, arc, chord, delta), bearings and distances of all lines, adjoining plats, north arrow, scale, legend, and the owner's certificate, surveyor's certificate and seal, and the approval block. Legal descriptions must close and be self-contained; metes and bounds versus lot-and-block versus aliquot-part descriptions each carry their own conventions. Deliverables must state the datum, units, and whether the file is a recordable plat or a working map.

Worked example

A map at 1:2,400 with 1 in = 200 ft: a measured map distance of 1.75 in corresponds to 350 ft on the ground.

Construction Surveys

Layout fundamentals

Construction surveying transfers design positions to the ground. Control is established first, then offsets, hubs, and stakes are set from that control. Stationing notation combines station and offset (for example 12+45.00, 25 ft left). A benchmark is the vertical reference; every stake has an elevation and an offset from a reference line.

Cut and fill

Grade is expressed as cut (dig) or fill (place). A typical grade stake reads "C 1.2" or "F 0.8" relative to the design elevation at that point. The arithmetic trap: cut is the amount the design grade is below existing ground; fill is the amount above. Slope stakes are set where the side slope intersects existing ground, using the catch distance derived from the design cross-section, offset, and depth.

Horizontals, verticals, and tolerances

Horizontal curve staking uses deflection angles and chords from the PC, with the PI, PT, and delta angle given. Vertical curves are parabolas; the high or low point occurs where the grade changes sign, at x = L·g₁/(g₁ − g₂) measured from the BVC. As-built surveys verify the constructed work against design, and machine control relies on the same 3D model with its own tolerance and calibration checks.

Worked example

Design elevation 104.20 ft, existing ground 105.50 ft at a stake: difference is 1.30 ft, and since the ground is higher than design, it is a cut of 1.30 ft. If the ground were 103.60 ft, it would be a fill of 0.60 ft.

Trap to watch

Stationing is not a coordinate and cannot be used interchangeably with a state plane value. Also watch sign conventions: a negative cut is a fill, not an error to report.

Business and Professional Practice

Licensure and the seal

Practice questions test the boundary between legal and ethical. The license is held by an individual, not a firm; only a licensed surveyor may seal and sign survey work, and the seal attests to personal responsibility for the work. Working outside one's competence - even if legal in a broad sense - is a violation. Aiding an unlicensed person in the unlicensed practice of surveying, or sealing work you did not direct and review, are the classic distractors.

Standard of care and negligence

Negligence is measured against the standard of care: what a reasonably prudent surveyor practicing in the same community would do. It is not perfection, and being right in hindsight does not cure a failure to follow the standard, nor does a good outcome cure a breach. Contracts, insurance (general liability and professional liability/E&O), and a clear scope of work are the primary risk-management tools. Limitation-of-liability clauses and indemnity language are commonly tested.

Contracts and fees

Contracts should specify scope, deliverables, schedule, payment terms, and the standard of care applied. Common fee methods are lump sum, hourly (time and materials), cost plus fixed fee, and percentage of construction cost. Change orders are necessary when scope changes. A surveyor may decline work outside the scope; a fee estimate is not a guarantee of the outcome.

Rule of thumb

When two answers look correct, pick the one that discloses the issue and defers to the client or board rather than the one that quietly resolves it. Records retention and file documentation are the best defense in any dispute.

Trap to watch

An answer that is technically legal but conflicts with the professional code - for example, accepting a boundary survey with no title research because the client asked for speed - is wrong.

FS Surveying cheat sheet

Quick reference

Pre-Examination Activities

  • Research sequence: gather subject deed and plat, adjoiner deeds, prior surveys, and public records first; written record evidence never outranks an original monument that the deed calls for.

  • Pre-mobilization instrument checks: peg test for level line of sight, plate/lircular bubble adjustment, optical plummet check, and EDM comparison against a calibrated baseline.

  • Collimation error by two-face observation: error = (reading FL − reading FR ± 180°)/2 for horizontal angles; the mean of faces cancels the error.

  • Coordinate metadata that must be identified before using any control: datum and realization, epoch, projection and zone, linear unit, and order/class of accuracy.

  • Control-network selection depends on required accuracy order: traverse for corridor work, static GNSS for long baselines and open sky, RTK/VRS where a single receiver must be positioned quickly.

  • In the United States, call 811 before any excavation or monument setting; most states require the locate request two to three working days before work begins.

  • Corner-record statutes typically require the monument material and dimensions, a cap stamped with the surveyor's license number, and filing of the record within a stated period.

  • Field safety controls: MUTCD-compliant traffic control, high-visibility apparel, fall protection above six feet, and hazard communication for fuels and herbicides.

  • Land-entry authority must be documented; a right-of-entry, permit, or written permission protects the surveyor against trespass claims and supports the final report.

Quick reference

Surveying Instruments and Procedures

  • Peg test: take the elevation difference between two points with the level set midway (true difference), then re-observe with the instrument near one point; the discrepancy is the collimation error for that sight length.

  • Curvature and refraction in leveling: combined correction ≈ 0.0675 K² meters with K in kilometers; refraction offsets roughly one-seventh of the curvature effect and is subtracted from the rod reading.

  • EDM accuracy is stated as ±(a mm + b ppm); atmospheric correction uses temperature, pressure, and humidity, with the correction changing roughly 1 ppm per 1 °C.

  • Total-station angles are turned clockwise from the set zero; a zenith angle of 90° is horizontal and 0° is directly overhead.

  • Direct and reverse (face left/face right) observations cancel horizontal collimation, trunnion-axis, and vertical-index errors; the mean of the two faces is the accepted value.

  • Traverse types: closed-loop returns to the starting point, closed-link begins and ends on known control, open traverse has no closure check and is avoided for boundary work.

  • Angular misclosure of an n-sided closed polygon = measured angle sum − (n − 2)(180°); distribute the misclosure equally or in proportion to instrument weights before computing coordinates.

  • Instrument error sources: residual level-bubble error, optical plummet misalignment, EDM zero and prism constant, and axis non-perpendicularity.

  • Natural error sources: atmospheric refraction, thermal expansion, wind-induced vibration, tripod settlement, and unstable instrument points.

Quick reference

Boundary and Cadastral Surveys

  • Evidence hierarchy: natural monuments outrank artificial monuments, which outrank courses and distances, which outrank area; quantity yields to quality.

  • Senior rights: an earlier conveyance prevails over a later one for the same land, so a junior deed conveys only what the senior deed left unconveyed.

  • Public Land Survey System: a township is 36 sections in a 6-by-6 arrangement, each section nominally one mile square and 640 acres; original government-set corners are controlling monuments.

  • Lost-corner reestablishment uses single proportionate measurement between the nearest existent corners on the same line unless the position can be restored from independent accepted evidence.

  • Tidal boundary waters are generally bounded by mean high water; non-tidal navigable waters are commonly bounded by the ordinary high water mark, with title extent set by state law.

  • Accretion and reliction are gradual and move the boundary with the water; avulsion is sudden and leaves the boundary where it was before the event.

  • Unwritten rights that can control a boundary include practical location, acquiescence, estoppel, and adverse possession, regardless of deed language.

  • Adverse possession elements: actual, open and notorious, exclusive, hostile, and continuous for the statutory period.

  • A meander line is evidence of the water's location at the time of survey; it is not a boundary line and does not limit the conveyance.

Quick reference

Photogrammetry and Remote Sensing

  • Photograph scale S = f / (H − h), with f the focal length, H the flying height above datum, and h terrain elevation; scale varies across a single vertical photo with relief.

  • Relief displacement d = r·h / H, where r is the radial distance from the principal point; displacement is zero at the nadir point and increases outward.

  • Parallax height equation: h = H·Δp / (P + Δp), with Δp the parallax difference between points and P the parallax at the reference elevation.

  • Air base between exposures B = (1 − endlap fraction) × ground coverage of one photograph along the flight line; side spacing = (1 − sidelap fraction) × ground width.

  • Ground sample distance = pixel size × (H / f), equivalently pixel size times the photo-scale denominator.

  • An orthophoto is differentially rectified to remove tilt and relief displacement, giving a uniform map scale suitable for measuring positions.

  • A DTM/DEM represents bare-earth elevations; a DSM includes buildings and vegetation; LiDAR classification separates ground returns from canopy and structures.

  • Airborne topographic LiDAR is specified by point density (points per square meter) and vertical accuracy as RMSEz, commonly 5–15 cm for modern sensors.

  • Representative satellite resolutions: Landsat multispectral 30 m, Sentinel-2 10 m, WorldView-3 panchromatic about 0.31 m.

Quick reference

Geodesy and Geodetic Surveying

  • Height relationship: h = H + N, where h is ellipsoidal height, H is orthometric height above the geoid, and N is the geoid undulation.

  • NAD83 is referenced to the GRS80 ellipsoid; NAD27 used the Clarke 1866 ellipsoid; NAVD88 provides orthometric heights derived from tide-gage observations.

  • Grid distance = ground distance × combined factor; combined factor = grid scale factor × elevation factor, with elevation factor ≈ R / (R + h).

  • Universal Transverse Mercator: 6°-wide zones, central-meridian scale factor 0.9996, false easting 500,000 m, zero false northing in the northern hemisphere.

  • Grid azimuth = geodetic azimuth − convergence angle, with convergence approximately Δλ · sin φ measured from the central meridian.

  • Datum transformation uses a similarity (Helmert) model with seven parameters: three translations, three rotations, and one scale factor.

  • Astronomic and geodetic azimuths differ by the Laplace correction, which depends on the deflection of the vertical.

  • Coordinates must carry a realization and epoch, for example NAD83(2011) at epoch 2010.00, because plate motion changes coordinates with time.

  • Spherical excess of a geodetic triangle equals its area divided by R² in radians and is applied to close triangles observed on the ellipsoid.

Quick reference

Surveying Calculations and Adjustments

  • Latitude = distance × cos(azimuth); departure = distance × sin(azimuth); azimuth is measured clockwise from north.

  • Linear error of closure = √[(Σlatitude)² + (Σdeparture)²]; relative precision = closure / total traverse length, stated as 1:N.

  • Bowditch (compass) rule distributes misclosure in proportion to course length; the transit rule distributes it in proportion to the absolute latitudes and departures.

  • Least squares minimizes Σv²; normal equations are N = AᵀWA and X = (AᵀWA)⁻¹AᵀWL, which also yield residuals, a variance factor, and error ellipses.

  • Weighted mean = Σ(wx)/Σw with weights w = 1/σ²; the weight of the mean equals the sum of the weights.

  • Error propagation for independent variables: σz² = (∂z/∂x)²σx² + (∂z/∂y)²σy².

  • Horizontal curve formulas: T = R tan(Δ/2); L = RΔ in radians; LC = 2R sin(Δ/2); M = R[1 − cos(Δ/2)]; E = R[sec(Δ/2) − 1].

  • Degree of curve, arc definition: R = 5729.578 / D; chord definition: R = 50 / sin(D/2).

  • Area by coordinates: 2A = Σ(Xi·Yi+1 − Xi+1·Yi), taken in order around the traverse; the sign indicates the direction of travel.

Quick reference

Mapping and Platting

  • Scale as a representative fraction is dimensionless: 1:1,200 means one map unit equals 1,200 ground units, and 1 in = 100 ft is the same as 1:1,200.

  • Contour interval is chosen so adjacent contours remain legible at the plotted scale and match the map's purpose; larger-scale maps support smaller intervals and finer terrain depiction.

  • Plat content: basis of bearing, bearings and distances, curve data (radius, arc, chord, central angle), area, monument descriptions, adjoiner names, and the surveyor's seal and signature.

  • Map accuracy is reported as RMSE under NSSDA/ASPRS-style standards; horizontal accuracy is tied to map scale and vertical accuracy to contour interval.

  • Maps on a projected grid show grid distances and grid north; ground distances must be converted using the combined factor before comparison.

  • Metes-and-bounds parcels must mathematically close; the misclosure and the area computed by coordinates are typically tabulated on the face of the plat.

  • Digital submissions should separate boundary, easement, improvement, and annotation layers and be georeferenced to the datum, realization, and epoch stated on the map.

  • Vertical information on a map requires contour lines, spot elevations, and benchmarks referenced to a stated vertical datum such as NAVD88.

  • Easements and rights-of-way are shown graphically and tabulated with bearings, distances, widths, and the document reference of record.

Quick reference

Construction Surveys

  • Cut/fill at a point = design elevation − existing ground elevation; a positive result is cut and a negative result is fill.

  • Grade stakes carry the cut or fill dimension at the stake; hubs with tacks mark the offset line and are referenced to a project benchmark.

  • Square a building corner with the 3-4-5 relationship and confirm by comparing diagonals, which must be equal for a true rectangle.

  • A temporary benchmark is set outside the construction influence zone and checked into existing vertical control before any layout.

  • Offsets from control lines to structure faces are set with batter boards or hubs placed clear of excavation and backfill.

  • Slope stakes require the catch point where the design side-slope plane intersects existing ground, found by trial computation along measured offsets.

  • As-built surveys compare constructed to designed positions; typical tolerances are about ±0.02–0.05 ft for structures and ±0.1 ft for earthwork.

  • Site GNSS RTK layout needs a local base or network correction and a site calibration to the project's local control and grid.

  • Earthwork volumes come from average end area, prismoidal, or cross-section methods and are compared to design quantities to support payment.

Quick reference

Business and Professional Practice

  • Common compensation structures: lump sum, time and materials, cost plus fixed fee, and unit price; scope, deliverables, and exclusions belong in writing.

  • Standard of care is the degree of skill and care ordinarily exercised by reputable surveyors under similar circumstances; failing it establishes negligence.

  • Responsible charge means the licensed surveyor who directs and controls the work; most jurisdictions require that person's seal and signature on final documents.

  • Indemnification and hold-harmless clauses for a party's own negligence are limited or void in many states, and anti-indemnity statutes may override contract language.

  • A statute of limitations runs from the injury or its discovery; a statute of repose bars claims after a fixed period regardless of when the injury is discovered.

  • Field notes, computations, and correspondence should be retained under contract and state requirements, commonly five to ten years or longer for boundary work.

  • Board rules generally prohibit contingent compensation tied to a boundary location opinion and require disclosure of conflicts of interest to clients.

  • Professional liability (errors and omissions) insurance covers negligent professional services; commercial general liability policies typically exclude them.

FS Surveying key terms

Datum

A reference surface or set of parameters against which positions or elevations are measured; horizontal datums define coordinates on an ellipsoid, and vertical datums define heights above a zero reference surface.

Related: Geoid, Ellipsoid, Benchmark
Geoid

The equipotential surface of the Earth's gravity field that best approximates mean sea level and is imagined to continue through the continents; it serves as the zero reference for vertical datums.

Related: Datum, Ellipsoid
Ellipsoid

A mathematically defined flattened sphere used as the reference surface for horizontal coordinates, with size and shape chosen to fit the geoid globally or over a region.

Related: Geoid, Datum
Benchmark

A relatively permanent, stable object whose elevation above a vertical datum has been determined by survey, used as a starting or checking point for leveling operations.

Related: Differential leveling, Height of instrument, Datum
Magnetic declination

The angular difference at a given place and time between magnetic north, as indicated by a compass, and true or geographic north; it varies with location and changes slowly over the years.

Related: Azimuth, Bearing
State Plane Coordinate System

A system of planar rectangular coordinates defined separately for each state or zone by map projection from the national horizontal datum, allowing surveyors to compute and record positions in feet or meters.

Related: Datum, Map scale
Total station

An electronic instrument that combines an electronic theodolite, an electromagnetic distance meter, and an onboard computer, so angles and distances to a target are measured and recorded from one setup.

Related: Theodolite, Traverse
Theodolite

An optical or electronic instrument for measuring horizontal and vertical angles precisely, consisting of a telescope rotating on horizontal and vertical axes fitted with graduated circles.

Related: Total station, Backsight
Backsight

A sight taken to a previously known point in order to orient the instrument, establish a reference direction, or determine the height of the instrument before other measurements are made.

Related: Foresight, Height of instrument
Foresight

A sight taken to a new point whose direction, position, or elevation is to be determined; in leveling it is the rod reading taken on a point ahead of the instrument.

Related: Backsight, Turning point
Turning point

A temporary point on which a leveling rod is held so the instrument can be moved and set up again while a leveling line continues, carrying the elevation forward.

Related: Foresight, Differential leveling
Height of instrument

The elevation of the line of sight of a leveling instrument above the chosen datum, obtained by adding the backsight rod reading to the known elevation of the point sighted.

Related: Backsight, Differential leveling
Differential leveling

The procedure of determining elevation differences between points by reading a graduated rod through a level from setups between them, accumulating backsight and foresight differences along the line.

Related: Benchmark, Turning point
Traverse

A survey in which the lengths and directions of a connected series of lines are measured so that the positions of the stations at the ends of those lines can be computed.

Related: Misclosure, Total station
Azimuth

The horizontal angle measured clockwise from a chosen reference meridian, usually north, to a given line, taking values from zero to 360 degrees.

Related: Bearing, Magnetic declination
Bearing

The acute horizontal angle between a reference meridian and a line, always stated with a quadrant label such as N 45 E or S 30 W.

Related: Azimuth, Magnetic declination
Latitude and departure

The northing and easting components of a traverse course, calculated as the course distance multiplied by the cosine and sine of its azimuth respectively.

Related: Traverse, Misclosure
Misclosure

The amount by which a survey fails to return to its known starting value or known point, such as the gap between the computed and known end positions of a closed traverse.

Related: Traverse, Least-squares adjustment
Least-squares adjustment

A method of distributing measurement errors by finding the coordinates or values that minimize the sum of the squares of the weighted residuals, yielding the most probable solution.

Related: Misclosure, Precision
Accuracy

How close a measured or computed value is to its true value; it is degraded mainly by systematic errors and is distinct from the scatter of repeated measurements.

Related: Precision, Least-squares adjustment
Precision

The degree of repeatability or consistency among repeated measurements of the same quantity, reflecting random scatter; a highly precise result can still be inaccurate.

Related: Accuracy, Misclosure
Metes and bounds

A method of describing land by giving the courses and distances of its boundary lines, usually beginning and ending at a known monument or point of reference.

Related: Monument, Retracement survey
Monument

A physical object, either natural or artificial, that is placed or accepted to mark a boundary corner or survey point and that controls the location described in a deed or plat.

Related: Metes and bounds, Retracement survey
Retracement survey

A survey performed to re-establish or verify the boundaries of an existing parcel as originally created, relying on record evidence and original monuments rather than establishing new lines.

Related: Monument, Metes and bounds
Public Land Survey System

The rectangular system used to subdivide public lands in the United States, laying out township and range lines at six-mile intervals and dividing townships into sections and aliquot parts.

Related: Monument, Plat
Easement

A right held by one party to use a defined portion of another person's land for a specific purpose, such as access or utilities, without owning that land.

Related: Riparian rights, Plat
Riparian rights

The rights belonging to owners of land bordering a stream, river, or lake to use and access the water and, under some rules, to land that gradually accretes.

Related: Easement
Adverse possession

A legal doctrine under which a person who openly, notoriously, exclusively, and continuously occupies another's land for the required statutory period may acquire title to it.

Related: Monument
Parallax

The apparent shift in an object's position relative to a reference when it is viewed from different locations; in photogrammetry this displacement lets distances and elevations be derived from overlapping photographs.

Related: Orthophoto, Ground control point
Orthophoto

A photograph that has been differentially rectified to remove displacements caused by camera tilt and terrain relief, giving it a uniform scale so it can be used like a map.

Related: Parallax, Map scale
Ground control point

A point on the ground whose horizontal position or elevation is known and which can be identified on imagery, used to orient, scale, and georeference photogrammetric or remotely sensed data.

Related: Orthophoto, LiDAR
LiDAR

A remote sensing technique that measures distances by timing laser pulses reflected from the ground or from objects, producing dense point clouds used for terrain models and mapping.

Related: Ground control point, Orthophoto
Contour line

A line drawn on a map or plat that connects points of equal elevation, so that the spacing and shape of the lines portray the steepness and form of the terrain.

Related: Map scale, Orthophoto
Plat

A map of a land parcel or subdivision showing boundary lines, dimensions, monuments, lots, streets, and any dedications, prepared for recording in the public land records.

Related: Monument, Map scale
Map scale

The relationship between a distance measured on a map and the corresponding distance on the ground, expressed as a ratio, an equivalence, or a graphic bar scale.

Related: Plat, Orthophoto
Vertical curve

A parabolic curve used to join two intersecting grades on a roadway or other alignment, providing a gradual change of slope that is safe and comfortable to travel.

Related: Stakeout
Cut and fill

The earthwork of excavating soil where existing ground lies above the design grade and placing it where ground lies below, bringing the terrain to the planned elevation.

Related: Stakeout, Contour line
Stakeout

The field operation of marking on the ground the horizontal positions and elevations of planned design elements, such as building corners, pipes, or roadway centerlines, for the construction crew.

Related: As-built survey, Cut and fill
As-built survey

A survey performed after construction to record the actual horizontal location and elevation of improvements as they were built, so results can be compared with the design drawings.

Related: Stakeout
Standard of care

The degree of care, skill, and diligence that a reasonably prudent surveyor, practicing in the same locality and under similar circumstances, would exercise in the same work.

FS Surveying study plan

8 weeks · About 7 hours per week

Week 1

Surveying Instruments and Procedures & Surveying Calculations and Adjustments

  • Sequence the setup, centering, leveling, and backsight procedures for a total station, an automatic level, and a GNSS rover, and name the specific error each step controls.

  • Convert slope distances to horizontal and vertical components, reduce angle sets, and compute elevation differences from 15 sets of raw field notes without consulting a reference.

  • Diagnose the standard instrumental error sources (collimation, index error, vertical-axis tilt, curvature and refraction, rod zero error) and match each to its field check or correction.

  • Solve 20 closure problems by hand across level loops and closed traverses, stating the allowable misclosure criterion used in each case.

Your checkpoint

A one-page field-procedure checklist per instrument plus a 20-problem worked closure portfolio scored at 85% or better.

Week 2

Surveying Calculations and Adjustments & Pre-Examination Activities

  • Propagate random error through a chain of measurements to state the uncertainty of a computed distance, angle, or area.

  • Adjust the same six-station traverse three ways (compass rule, transit rule, least squares) and compare the resulting coordinate residuals.

  • Assemble a complete pre-field package for a hypothetical boundary job: record search list, deed and title documents, horizontal and vertical control recovery plan, and utility locate and safety plan.

  • Write a scope of work, a task schedule, and a budget-hours estimate for that same job.

Your checkpoint

A pre-field survey package plus an adjustment workbook comparing the three adjustment methods on one traverse.

Week 3

Geodesy and Geodetic Surveying

  • Convert 25 points among geodetic coordinates, State Plane Coordinates, and UTM, showing the map projection scale factor and convergence of the meridian for each.

  • Compute geoid separation and ellipsoid-to-orthometric elevation differences for a stated project area.

  • Explain and apply datum transformations between historic and current horizontal and vertical datums, including the practical consequences of mixing them.

  • Calculate grid-to-ground distances and areas using the combined factor for two sites at different latitudes.

Your checkpoint

A 25-item coordinate conversion problem set with every scale factor and convergence computation shown and checked.

Week 4

Boundary and Cadastral Surveys

  • Interpret metes-and-bounds and lot-and-block deed descriptions and reduce each to a closed geometric figure with stated area.

  • Apply the rules of construction (monument over distance, senior rights, natural monuments over artificial) to resolve two deliberately conflicting deed scenarios.

  • Analyze a riparian and an easement boundary question and justify the boundary location in writing.

  • Complete an ALTA/NSPS-style table of optional items checklist for a commercial parcel and flag the items requiring client decisions.

Your checkpoint

A written boundary resolution memo for two conflicting-deed scenarios plus a completed mock ALTA checklist.

Week 5

Construction Surveys & Mapping and Platting

  • Compute and lay out horizontal curve elements (PC, PT, tangent, length, external, middle ordinate) and vertical curve elevations at stated stations.

  • Build a cut-and-fill stakeout sheet for a building pad and a gravity sewer line, including offsets, grades, and invert elevations.

  • Check a set of as-built measurements against design tolerances and document the deviations.

  • Draft a subdivision plat sheet that satisfies a stated checklist of scale, legend, adjacency, setback, and signature-block requirements.

Your checkpoint

A stakeout package for one building pad and one utility run, plus one plat sheet that scores 100% on the supplied checklist.

Week 6

Photogrammetry and Remote Sensing & Mapping and Platting

  • Compute photographic scale, ground sample distance, relief displacement, and object height from stereo parallax for 15 given problems.

  • Design a flight plan for a stated acreage: choose overlap, altitude, focal length, number of flight lines and photos, and ground control layout.

  • Compare photogrammetric, LiDAR, and UAS-derived surface products by accuracy, density, and typical use case.

  • Evaluate an orthophoto and a point cloud deliverable against a stated positional accuracy standard and list acceptance or rejection findings.

Your checkpoint

A complete flight plan with calculations for a site of stated size plus a 15-problem photogrammetry set with an accuracy review memo.

Week 7

Business and Professional Practice & Pre-Examination Activities

  • Review a sample professional services contract and identify the clauses governing scope, liability, indemnity, payment, and dispute resolution.

  • Prepare a fee estimate with assumptions and exclusions for a topographic survey of a stated acreage.

  • Apply the licensure and ethics rules governing responsible charge, sealing of work, and records retention to three short scenarios.

  • Update the pre-field package from Week 2 to reflect the contract and fee constraints identified.

Your checkpoint

A contract review checklist, a defensible fee estimate with assumptions and exclusions, and written answers to three ethics scenarios.

Week 8

Pre-Examination Activities & Surveying Instruments and Procedures & Boundary and Cadastral Surveys & Photogrammetry and Remote Sensing & Geodesy and Geodetic Surveying & Surveying Calculations and Adjustments & Mapping and Platting & Construction Surveys & Business and Professional Practice

  • Sit two full-length timed mock exams under exam conditions, one mid-week and one at week's end.

  • Build an error log and re-work every missed item to a correct, self-explained solution.

  • Consolidate all formulas, conversion factors, and adjustment procedures into a single final reference sheet.

  • Re-drill the two lowest-scoring domains until each reaches 85% or better on a fresh set of 20 items.

Your checkpoint

Two timed mock exams scored at 80% or better overall, with a completed error log showing every missed item re-worked and verified.

Milestones

Week 2: All nine domains mapped to a personal weakness list, and three traverse adjustments reconciled to the same final coordinates within stated tolerance.

Week 4: Boundary resolution memo defended in writing against the senior-rights and monument-over-distance rules; geodesy problem set at 80% or better.

Week 6: Construction stakeout, plat sheet, and flight plan all complete and self-checked; cumulative mock practice trending above 75%.

Week 8: Two timed mock exams at 80% or better overall with no single domain below 70%, and a final reference sheet in hand.

FS Surveying exam day

Your checklist

Government-issued photo ID

Bring an unexpired, government-issued photo ID with your signature. The first and last name must match your registration exactly. If your ID name differs from your registration (nickname, maiden name, suffix), resolve it with the provider before test day.

Appointment confirmation / eligibility record

Bring your scheduling confirmation or eligibility number if the provider issues one. Whether a printed copy is required varies - confirm with the provider whether digital or printed proof is accepted.

Approved calculator

Confirm your exact model appears on the provider's approved-calculator list, since unapproved models are typically confiscated or cause denial of entry. Bring a second approved unit or fresh batteries if allowed.

Knowledge of the provided reference material

Many surveying fundamentals exams supply an on-screen or provided reference handbook rather than allowing personal notes. Confirm with the provider what reference material is furnished and whether any printed material is permitted.

Travel and parking plan

Scout the test center location, parking, and transit in advance, and add buffer for traffic, security screening, and building navigation.

Arrival target time

Plan to arrive well before your appointment - commonly 30 minutes early. Confirm with the provider the exact check-in window, since late arrivals may be turned away without a refund.

Leave prohibited items behind

Phones, smartwatches, notes, and bags are almost universally banned from the testing room. Confirm with the provider whether a secure locker is provided or whether you must leave items in your vehicle.

Eyeglasses, medications, and personal necessities

Bring only what you genuinely need. Rules for medication and personal medical items vary - confirm with the provider in advance and request an accommodation if needed.

Break snack and water

Bring a light snack and water only if the provider permits access to them during breaks. Confirm with the provider where these items may be stored and accessed.

Backup alarm and a rest plan

Set two alarms and protect a full night's sleep in the 48 hours before the exam; fatigue costs more points than one extra hour of cramming gains.

Review of the candidate agreement

Read the provider's candidate/testing agreement before test day so you understand the conduct rules, confidentiality terms, and consequences of a violation.

Plan the day

Final 72 hours

Confirm your appointment date, time, and test center address. Verify your calculator model against the approved list and arrange a backup. Do a final pass over the exam content outline, then shift to timed practice sets and reviewing your own error log rather than starting new topics.

Final 24 hours

Pack your ID, confirmation, and calculator in one place. Lay out clothing and plan the route and departure time with a 30-minute buffer. Do light review only - skim summary sheets and formulas - and stop studying by early evening. Confirm with the provider any last details about check-in or permitted items.

Morning of

Eat a normal breakfast, avoid heavy caffeine if you are sensitive to it, and leave on schedule with buffer for traffic and screening. At the center, follow the administrator's check-in instructions, store prohibited items, and use the restroom before entering the room. Do not attempt new material in the waiting area.

First minutes in the room

Read the on-screen instructions and note how to flag questions, how to access the reference material, and how the break works. Confirm the timer behavior before you begin answering.

During the test

Work in passes: answer the straightforward questions first, flag anything that needs long calculation or a concept you need to reconsider, and return to flagged items. Budget your time per question from the total item count, keep an eye on the clock, and check units, bearings, and significant figures on every computation. Answer every question - verify with the provider whether unanswered items are scored as incorrect.

During a break

Stand up, hydrate, and eat something light. Avoid discussing exam content with other candidates and avoid deep-diving into a topic that will make you second-guess answers. Note whether the clock keeps running during breaks - confirm the provider's break policy before test day.

Rules to check

  • Bring a valid, unexpired government-issued photo ID with your signature, and ensure the name matches your registration exactly; confirm the name-match policy with the provider in advance.

  • Only approved calculators and permitted reference material may be used in the testing room. Confirm the current approved-calculator list with the provider, since an unapproved device can result in removal from the exam.

  • Electronic devices, notes, and personal belongings are generally prohibited in the testing room; confirm with the provider what storage is available and leave anything unnecessary at home.

  • Follow all instructions from the test center administrator. Disputes about seating, breaks, or timing should be raised with the provider afterward, not argued with staff during the exam.

  • Breaks are governed by the provider's policy - confirm in advance whether breaks are scheduled or optional and whether the exam clock continues to run during them.

  • Scoring methods, passing standards, and retake rules vary; confirm the current scoring and reporting policy with the provider rather than relying on secondhand information.

  • Treat all exam content as confidential. Do not copy, photograph, or discuss specific questions, and review the candidate agreement you accept at check-in.

  • If something goes wrong - an ID issue, a malfunctioning workstation, or an illness - notify the administrator immediately and document it, since timely reporting is typically required for any later remedy.

FS Surveying FAQ

How many FS Surveying practice questions are available?

The practice set has 200 FS Surveying questions. Each one includes the choices, the correct answer, and an explanation, and the set is free to read with no signup.

How many FS Surveying flashcards are available?

The flashcard set has 32 FS Surveying cards. Each card shows the term and its definition.

Which topics does the FS Surveying study material cover?

The FS Surveying study material has 9 sections, including Pre-Examination Activities, Surveying Instruments and Procedures, and Boundary and Cadastral Surveys.

What format facts does the catalog list for the FS Surveying exam?

The catalog lists a duration of 360 minutes and these item types: computer-based and multiple choice for the FS Surveying exam.